2. Introducing Waste Concern
Waste Concern Group is a Social Business
Enterprise (SBE) with the motto “Waste is a
Resource”
Waste handling capacity 700 ton/day
and 50,000 ton fertilizer/year
Serve the municipality with alternative
waste disposal
Provide quality compost
Want to ensure the easiest and secured
communication and transection with
customers
3. Current Situation
Communication Transection
Transection is done by
Through its website
an authorised person
Through phone
physically going to the
Through postal mail bank
Contact in person Most people/customers
do not have private
bank account
Company can not reach to the mass people, loosing
opportunities
4. Proposal
In June, 2011 bank offers the easiest, secured
& affordable mobile banking services.
So we can
Introduce M-commerce
Provide product ordering service through
mobile SMS options
Offer transection by mobile banking
5. Product Ordering Service
1. Fixed SMS number will be assigned for the
industry from mobile service provider
2. Industry and consumer will able to
communicate directly through the fixed
number with SMS and reply options under
unique server
3. Business account will be created for
mobile banking transaction
6. Working process
Transfer money
• A mobile • Industry reply
banking user • Choose an a
option confirmation
sms
Sends sms to the
Transection
industry provided
completed
number
7. SWOT Analysis
Strength Opportunity
1. 99% mobile network coverage 1. Can reach to most mobile users
2.Most private banks offer m- 2. Can transform bank customers
banking to consumers
3. Less server space 3. Negligible cost
4. No competitor 4. Larger market
5. Eco friendly , more versatile than 5. Huge return over investment
any other energy source
8. SWOT Analysis
Weakness Threat
1. % of organic waste decreasing 1. Longevity uncertain
2.Theoretically huge prospects. 2. Unknown threats
Practically not tested in this way
3. Unauthorized mobile user 3.Server overloaded
4. Government owned public 4.Corresponding customers will be
banks are not involved skipped
5.Competitive but non co- 5. Collaborative decision making
operative environment will be vulnerable
9. Financial Situation at the Initial
Stage 3.45
2.38
2.05
in Million CAD
Fixed Cost Operational Income/Year
Cost/Year
Pay back period of the investment was 23 months
10. Estimated Cost
Fixed cost Amount Sales in Profit (in Million)
Million
Computer equipment $2600
Yearly Operational Cost
Webhosting $308
SMS servicing $4800
Maintenance
Operator Payroll 2 X 12 X$180 $4320
IT Payroll 2X 12X $330 $7920
Subtotal $12240
Total cost $20000
Yearly Interest Rate 18% $3600
1st Year total cost (with interest) $23600 $4.45 $-0.02683
2nd Year total cost (with interest) $21596 $4.45
$2.021622
3rd Year total cost (No Interest) $17348 $4.45 $2.052700
11. Cost-Income Analysis
$4.45
Fixed $3.45
Cost Opt.
0% Cost/Yr
1%
Before After
Yearly income in Million
CAD
Income increases 28%
12. Net Profit for 3 Years
$2.02 $2.05
$-0.03
1st yr 2nd yr 3rd yr
Net profit in Million CAD
13. Promotional Strategy
Before starting this service we can
Advertise in our website
Inform about the service to the customers
by face to face contact
Promote the Banks and Mobile service
providers to inform their customers
14. Snapshot of opportunities
Electricity: 1 m3 biogas gives
about 2 kWh of useable
electricity
Biogas:1 ton organic waste
gives 20 m3 to 800 m3 of
biogas (depends on waste
quality, design)
Fertilizer:1 ton organic waste
gives ¼ ton compost
• 16 times larger than present lacking
By 2025: 1692 • A nuclear power plant by 2018 will
MWh electricity generate 2000 MWh.
17. Milestones of the project
Managing Waste from the Dhaka City Corporation
(DCC) area = 700 tons/day;
Production of Compost = 50,000 tons/year;
Reduction of Green House Gas = 89,000 tons of
CO2
Job Creation for the Urban Poor = 800 nos.;
Project Cost = 12 million Euro.(16.62 million CAD)
Clean Dhaka Ward Contest Award 2009
Environment Award 2007
Global Tech Museum Award 2003
UNDP The 2002 'Race against Poverty' Award