Earned Value Analysis
Final 6-1
Syed Saqib Raza RizviSyed Saqib Raza Rizvi
Earned Value - What
is it?
•Simply, it is a project monitoring and
measurement system that:
1. Establishes a clear relationship between plannedplanned
accomplishments and actualactual accomplishments
2.2. ReinforcesReinforces and rewards Good planningGood planning practices
2
Earned Value - What is
it?
•Basic concepts of Earned Value Management (EVM)
•Each task in a project earns value as planned workplanned work is
completed
•For example (perhaps), if you were paid on this basis,
you would earnearn $$ at key milestones based on the
value of what you have completed (Earned value)
•Earned value can be compared to actual cost and
budgeted cost to determine variance and predict
future performance
3
Earned Value - What is
it?
•The budgeted costbudgeted cost (e.g., dollars, person-hours,
person-days, etc.) in terms of your baselinebaseline
plan/budgetplan/budget of the work performed up to a
specified point in time
• Also known as Budgeted Cost of Work Performed (BCWPBCWP)
•Each task in the Work Breakdown Structure (WBS)
is assigned a BCWP based on its individual cost.
• Project BCWP is total of BCWP for all tasks required to
complete the project
4
Earned Value
Components•Planned Value
• How much work (person-hours) you planned to have
accomplished at a given point in time (this is from the WBS in
your plan)
•Actual Cost
• How much work (person-hours) you have actually spent at a
given point in time
•Earned Value
• The value (person-hours) in terms of your base budget of what
you have accomplished at a given point in time (or, % complete
X Planned Value)
5
Earned Value:
Example
On Day X:
• PLANNED VALUEPLANNED VALUE (Budgeted cost of the work scheduled, BCWS) =
18 + 10 + 16 + 6 = 50
• EARNED VALUEEARNED VALUE (Budgeted cost of the work performed, BCWP) =
18 + 8 + 14 + 0 = 40
• ACTUAL COSTACTUAL COST (of the work performed , ACWP) =
45 (from your project tracking - not evident in above chart)
6
18
8
14
Today
Earned Value:
Example
7
Cost(Person-Hours)
Time (Date)
Planned ValuePlanned Value: what your
plan called for sending on
the tasks planned to be
completed by this date.
Today
Earned ValueEarned Value: value
(cost) of what you have
accomplished to date, per
the base plan.
Actual CostActual Cost: what you
have actually spent to
this point in time.
Budgeted (Planned) Spending
Budgeted (Planned) Spending
Actual Spending
Actual Spending
Earned Value
Earned Value
Earned Value:
Example
8
Cost(Person-Hours)
Time (Date)
Today
Budgeted (Planned) Spending
Budgeted (Planned) Spending
Actual Spending
Actual Spending
Earned Value
Earned Value
BehindBehind
ScheduleSchedule
OverOver
BudgetBudget
Variance
•Any schedule or costschedule or cost deviationdeviation from a specific plan.
•Used within an organization to verify the budget and
schedule for a project
•Frequently used as a key component of plan reviewsplan reviews
andand performance measurementperformance measurement
9
Variance
•Must compare scheduling and budget variance at the
same time
• Schedule varianceSchedule variance: deviations from work planned
• Cost varianceCost variance: deviations from the
budget
10
Performance Indices
•Cost Performance Index
• CPICPI = BCWP/ACWP
•Schedule Performance Index
• SPISPI = BCWP/BCWS
•Analysis
•CPI > 1.0  exceptional performance
•CPI < 1.0  poor performance
11
Earned Value & Variance:
Example
On Day X:
• PLANNED VALUE (BCWS) = 18 + 10 + 16 + 6 = 50
• EARNED VALUE (BCWP) = 18 + 8 + 14 + 0 = 40
• ACTUAL COST (ACWP) = 45 (from your project tracking)
Therefore:
• Schedule VarianceSchedule Variance = BCWP – BCWS = 40 - 50 = -10 (behind schedule)
• Schedule Performance IndexSchedule Performance Index = 40 / 50 = 0.8, or 80% of plan
• Cost VarianceCost Variance = BCWP - ACWP = 40 - 45 = -5
• Cost Performance IndexCost Performance Index = 40/45 = .89, or you’re getting an 89¢ return on every
$1.00 (or, person-hour) spent on this project 12
18
8
14
Another Example
Project
•Plans to spend $100K in each of first 4 weeks
(baseline budget, per documented planper documented plan)
•Actuals, at end of week 4 show: $325K spent
•BCWS = $400K ($100K x 4)
•ACWP = $325K
•What conclusions can you draw?
•Under budget?
•Is project on schedule?
13
Earned Value
Management
•How can you use this information?
• Careful analysis of variance and trends
• Resetting schedule or budget, when appropriate
•Variance Analysis Questions
• What is the problem causing the variance?
• What is the impact on time, cost and performance?
• What is the impact on other efforts, if any?
• What corrective action is planned or under way?
• What are the expected results of the corrective action?
14
Earned Value
Management
•Extraordinary variance or alarming trends may be
cause for reset or cancellation ofreset or cancellation of a project, but where
do you draw the line?
•How much variance to allow depends on a number of
factors:
• Life-cycle phase
• Length of life-cycle phase
• Length of project
• Type of estimate
• Accuracy of estimate
15
Summary
•Cost, in the form of Earned Value or BCWP, can be
used to analyze progressanalyze progress of a project
•Using Earned Value data to make critical project
decisions must be based on careful analysiscareful analysis of
data, variances and trends
16
•Thank You
17

Más contenido relacionado

La actualidad más candente

Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVAAhmed Bamasdoos
 
Earned value
Earned valueEarned value
Earned valueOliver
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.pptPedadaSaikumar
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentationProPM Academy
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptTecnicoItca
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Editionpankajsh10
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 

La actualidad más candente (20)

Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
 
Earned value
Earned valueEarned value
Earned value
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.pptChapter-5-Scheduling-and-Resource-Allocation.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Cost management
Cost managementCost management
Cost management
 

Destacado

Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis trainingPaul King
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examManish Purwar
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy piecesGlen Alleman
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueGlen Alleman
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPJustAcademy
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 

Destacado (20)

Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Earned value in five easy pieces
Earned value in five easy piecesEarned value in five easy pieces
Earned value in five easy pieces
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 

Similar a Earned Value Analysis

Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptAsBali1
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptvitumbikokhoswe1
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptBetshaTizazu1
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureJohn Carter
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6HARDIK PARIKH
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptyogeshagrawal84
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value AnalysisSimonRobertson
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptxAhmedKayed6
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptadabotor7
 

Similar a Earned Value Analysis (20)

Earned value
Earned valueEarned value
Earned value
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
EARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.pptEARNED VALUE MANAGEMENT ANALYS 1.ppt
EARNED VALUE MANAGEMENT ANALYS 1.ppt
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
What Is Earned Value Analysis
What Is Earned Value AnalysisWhat Is Earned Value Analysis
What Is Earned Value Analysis
 
day 3-2 PMP.pptx
day 3-2 PMP.pptxday 3-2 PMP.pptx
day 3-2 PMP.pptx
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 

Más de Saqib Raza

The Design and Analysis of Algorithms.pdf
The Design and Analysis of Algorithms.pdfThe Design and Analysis of Algorithms.pdf
The Design and Analysis of Algorithms.pdfSaqib Raza
 
An Introduction to the Analysis of Algorithms (2nd_Edition_Robert_Sedgewick,_...
An Introduction to the Analysis of Algorithms (2nd_Edition_Robert_Sedgewick,_...An Introduction to the Analysis of Algorithms (2nd_Edition_Robert_Sedgewick,_...
An Introduction to the Analysis of Algorithms (2nd_Edition_Robert_Sedgewick,_...Saqib Raza
 
Data_Mining: Practical Machine Learning Tools and Techniques 2ndEd.pdf
Data_Mining: Practical Machine Learning Tools and Techniques 2ndEd.pdfData_Mining: Practical Machine Learning Tools and Techniques 2ndEd.pdf
Data_Mining: Practical Machine Learning Tools and Techniques 2ndEd.pdfSaqib Raza
 
Social Impacts of Artificial intelligence
Social Impacts of Artificial intelligenceSocial Impacts of Artificial intelligence
Social Impacts of Artificial intelligenceSaqib Raza
 
Professional Practice Course Outline
Professional Practice Course OutlineProfessional Practice Course Outline
Professional Practice Course OutlineSaqib Raza
 
Ethical hacking
Ethical hackingEthical hacking
Ethical hackingSaqib Raza
 
12 security policies
12 security policies12 security policies
12 security policiesSaqib Raza
 
11 Computer Privacy
11 Computer Privacy11 Computer Privacy
11 Computer PrivacySaqib Raza
 
Software Engineering Code Of Ethics And Professional Practice
Software Engineering Code Of Ethics And Professional PracticeSoftware Engineering Code Of Ethics And Professional Practice
Software Engineering Code Of Ethics And Professional Practice Saqib Raza
 
7 Engineering Profession
7 Engineering Profession7 Engineering Profession
7 Engineering ProfessionSaqib Raza
 
6 software contracts
6 software contracts6 software contracts
6 software contractsSaqib Raza
 
Introduction to Intellectual Property
Introduction to Intellectual PropertyIntroduction to Intellectual Property
Introduction to Intellectual PropertySaqib Raza
 
Itroduction to Business Ethics
Itroduction to Business EthicsItroduction to Business Ethics
Itroduction to Business EthicsSaqib Raza
 
Types of Ethics
Types of EthicsTypes of Ethics
Types of EthicsSaqib Raza
 
Introduction to ethics
Introduction to ethicsIntroduction to ethics
Introduction to ethicsSaqib Raza
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management ConceptsSaqib Raza
 
Software Re-Engineering
Software Re-EngineeringSoftware Re-Engineering
Software Re-EngineeringSaqib Raza
 
Software Quality Assurance
Software Quality AssuranceSoftware Quality Assurance
Software Quality AssuranceSaqib Raza
 
User Interface Analysis and Design
User Interface Analysis and DesignUser Interface Analysis and Design
User Interface Analysis and Design Saqib Raza
 
Architecture Design
Architecture DesignArchitecture Design
Architecture DesignSaqib Raza
 

Más de Saqib Raza (20)

The Design and Analysis of Algorithms.pdf
The Design and Analysis of Algorithms.pdfThe Design and Analysis of Algorithms.pdf
The Design and Analysis of Algorithms.pdf
 
An Introduction to the Analysis of Algorithms (2nd_Edition_Robert_Sedgewick,_...
An Introduction to the Analysis of Algorithms (2nd_Edition_Robert_Sedgewick,_...An Introduction to the Analysis of Algorithms (2nd_Edition_Robert_Sedgewick,_...
An Introduction to the Analysis of Algorithms (2nd_Edition_Robert_Sedgewick,_...
 
Data_Mining: Practical Machine Learning Tools and Techniques 2ndEd.pdf
Data_Mining: Practical Machine Learning Tools and Techniques 2ndEd.pdfData_Mining: Practical Machine Learning Tools and Techniques 2ndEd.pdf
Data_Mining: Practical Machine Learning Tools and Techniques 2ndEd.pdf
 
Social Impacts of Artificial intelligence
Social Impacts of Artificial intelligenceSocial Impacts of Artificial intelligence
Social Impacts of Artificial intelligence
 
Professional Practice Course Outline
Professional Practice Course OutlineProfessional Practice Course Outline
Professional Practice Course Outline
 
Ethical hacking
Ethical hackingEthical hacking
Ethical hacking
 
12 security policies
12 security policies12 security policies
12 security policies
 
11 Computer Privacy
11 Computer Privacy11 Computer Privacy
11 Computer Privacy
 
Software Engineering Code Of Ethics And Professional Practice
Software Engineering Code Of Ethics And Professional PracticeSoftware Engineering Code Of Ethics And Professional Practice
Software Engineering Code Of Ethics And Professional Practice
 
7 Engineering Profession
7 Engineering Profession7 Engineering Profession
7 Engineering Profession
 
6 software contracts
6 software contracts6 software contracts
6 software contracts
 
Introduction to Intellectual Property
Introduction to Intellectual PropertyIntroduction to Intellectual Property
Introduction to Intellectual Property
 
Itroduction to Business Ethics
Itroduction to Business EthicsItroduction to Business Ethics
Itroduction to Business Ethics
 
Types of Ethics
Types of EthicsTypes of Ethics
Types of Ethics
 
Introduction to ethics
Introduction to ethicsIntroduction to ethics
Introduction to ethics
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Software Re-Engineering
Software Re-EngineeringSoftware Re-Engineering
Software Re-Engineering
 
Software Quality Assurance
Software Quality AssuranceSoftware Quality Assurance
Software Quality Assurance
 
User Interface Analysis and Design
User Interface Analysis and DesignUser Interface Analysis and Design
User Interface Analysis and Design
 
Architecture Design
Architecture DesignArchitecture Design
Architecture Design
 

Último

%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...masabamasaba
 
VTU technical seminar 8Th Sem on Scikit-learn
VTU technical seminar 8Th Sem on Scikit-learnVTU technical seminar 8Th Sem on Scikit-learn
VTU technical seminar 8Th Sem on Scikit-learnAmarnathKambale
 
Right Money Management App For Your Financial Goals
Right Money Management App For Your Financial GoalsRight Money Management App For Your Financial Goals
Right Money Management App For Your Financial GoalsJhone kinadey
 
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...masabamasaba
 
%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein
%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein
%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfonteinmasabamasaba
 
Software Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsSoftware Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsArshad QA
 
WSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With SimplicityWSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With SimplicityWSO2
 
Announcing Codolex 2.0 from GDK Software
Announcing Codolex 2.0 from GDK SoftwareAnnouncing Codolex 2.0 from GDK Software
Announcing Codolex 2.0 from GDK SoftwareJim McKeeth
 
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...masabamasaba
 
Introducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) SolutionIntroducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) SolutionOnePlan Solutions
 
%in kaalfontein+277-882-255-28 abortion pills for sale in kaalfontein
%in kaalfontein+277-882-255-28 abortion pills for sale in kaalfontein%in kaalfontein+277-882-255-28 abortion pills for sale in kaalfontein
%in kaalfontein+277-882-255-28 abortion pills for sale in kaalfonteinmasabamasaba
 
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...Jittipong Loespradit
 
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...masabamasaba
 
Direct Style Effect Systems - The Print[A] Example - A Comprehension Aid
Direct Style Effect Systems -The Print[A] Example- A Comprehension AidDirect Style Effect Systems -The Print[A] Example- A Comprehension Aid
Direct Style Effect Systems - The Print[A] Example - A Comprehension AidPhilip Schwarz
 
Architecture decision records - How not to get lost in the past
Architecture decision records - How not to get lost in the pastArchitecture decision records - How not to get lost in the past
Architecture decision records - How not to get lost in the pastPapp Krisztián
 
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...Bert Jan Schrijver
 
WSO2CON 2024 - Does Open Source Still Matter?
WSO2CON 2024 - Does Open Source Still Matter?WSO2CON 2024 - Does Open Source Still Matter?
WSO2CON 2024 - Does Open Source Still Matter?WSO2
 
Harnessing ChatGPT - Elevating Productivity in Today's Agile Environment
Harnessing ChatGPT  - Elevating Productivity in Today's Agile EnvironmentHarnessing ChatGPT  - Elevating Productivity in Today's Agile Environment
Harnessing ChatGPT - Elevating Productivity in Today's Agile EnvironmentVictorSzoltysek
 
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital TransformationWSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital TransformationWSO2
 

Último (20)

%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
 
VTU technical seminar 8Th Sem on Scikit-learn
VTU technical seminar 8Th Sem on Scikit-learnVTU technical seminar 8Th Sem on Scikit-learn
VTU technical seminar 8Th Sem on Scikit-learn
 
Right Money Management App For Your Financial Goals
Right Money Management App For Your Financial GoalsRight Money Management App For Your Financial Goals
Right Money Management App For Your Financial Goals
 
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Atlanta Psychic Readings, Attraction spells,Brin...
 
%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein
%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein
%in Stilfontein+277-882-255-28 abortion pills for sale in Stilfontein
 
Software Quality Assurance Interview Questions
Software Quality Assurance Interview QuestionsSoftware Quality Assurance Interview Questions
Software Quality Assurance Interview Questions
 
WSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With SimplicityWSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
 
Announcing Codolex 2.0 from GDK Software
Announcing Codolex 2.0 from GDK SoftwareAnnouncing Codolex 2.0 from GDK Software
Announcing Codolex 2.0 from GDK Software
 
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
%+27788225528 love spells in Knoxville Psychic Readings, Attraction spells,Br...
 
Introducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) SolutionIntroducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) Solution
 
%in kaalfontein+277-882-255-28 abortion pills for sale in kaalfontein
%in kaalfontein+277-882-255-28 abortion pills for sale in kaalfontein%in kaalfontein+277-882-255-28 abortion pills for sale in kaalfontein
%in kaalfontein+277-882-255-28 abortion pills for sale in kaalfontein
 
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
 
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
 
Direct Style Effect Systems - The Print[A] Example - A Comprehension Aid
Direct Style Effect Systems -The Print[A] Example- A Comprehension AidDirect Style Effect Systems -The Print[A] Example- A Comprehension Aid
Direct Style Effect Systems - The Print[A] Example - A Comprehension Aid
 
Architecture decision records - How not to get lost in the past
Architecture decision records - How not to get lost in the pastArchitecture decision records - How not to get lost in the past
Architecture decision records - How not to get lost in the past
 
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICECHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Pushp Vihar (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
 
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
 
WSO2CON 2024 - Does Open Source Still Matter?
WSO2CON 2024 - Does Open Source Still Matter?WSO2CON 2024 - Does Open Source Still Matter?
WSO2CON 2024 - Does Open Source Still Matter?
 
Harnessing ChatGPT - Elevating Productivity in Today's Agile Environment
Harnessing ChatGPT  - Elevating Productivity in Today's Agile EnvironmentHarnessing ChatGPT  - Elevating Productivity in Today's Agile Environment
Harnessing ChatGPT - Elevating Productivity in Today's Agile Environment
 
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital TransformationWSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
 

Earned Value Analysis

  • 1. Earned Value Analysis Final 6-1 Syed Saqib Raza RizviSyed Saqib Raza Rizvi
  • 2. Earned Value - What is it? •Simply, it is a project monitoring and measurement system that: 1. Establishes a clear relationship between plannedplanned accomplishments and actualactual accomplishments 2.2. ReinforcesReinforces and rewards Good planningGood planning practices 2
  • 3. Earned Value - What is it? •Basic concepts of Earned Value Management (EVM) •Each task in a project earns value as planned workplanned work is completed •For example (perhaps), if you were paid on this basis, you would earnearn $$ at key milestones based on the value of what you have completed (Earned value) •Earned value can be compared to actual cost and budgeted cost to determine variance and predict future performance 3
  • 4. Earned Value - What is it? •The budgeted costbudgeted cost (e.g., dollars, person-hours, person-days, etc.) in terms of your baselinebaseline plan/budgetplan/budget of the work performed up to a specified point in time • Also known as Budgeted Cost of Work Performed (BCWPBCWP) •Each task in the Work Breakdown Structure (WBS) is assigned a BCWP based on its individual cost. • Project BCWP is total of BCWP for all tasks required to complete the project 4
  • 5. Earned Value Components•Planned Value • How much work (person-hours) you planned to have accomplished at a given point in time (this is from the WBS in your plan) •Actual Cost • How much work (person-hours) you have actually spent at a given point in time •Earned Value • The value (person-hours) in terms of your base budget of what you have accomplished at a given point in time (or, % complete X Planned Value) 5
  • 6. Earned Value: Example On Day X: • PLANNED VALUEPLANNED VALUE (Budgeted cost of the work scheduled, BCWS) = 18 + 10 + 16 + 6 = 50 • EARNED VALUEEARNED VALUE (Budgeted cost of the work performed, BCWP) = 18 + 8 + 14 + 0 = 40 • ACTUAL COSTACTUAL COST (of the work performed , ACWP) = 45 (from your project tracking - not evident in above chart) 6 18 8 14 Today
  • 7. Earned Value: Example 7 Cost(Person-Hours) Time (Date) Planned ValuePlanned Value: what your plan called for sending on the tasks planned to be completed by this date. Today Earned ValueEarned Value: value (cost) of what you have accomplished to date, per the base plan. Actual CostActual Cost: what you have actually spent to this point in time. Budgeted (Planned) Spending Budgeted (Planned) Spending Actual Spending Actual Spending Earned Value Earned Value
  • 8. Earned Value: Example 8 Cost(Person-Hours) Time (Date) Today Budgeted (Planned) Spending Budgeted (Planned) Spending Actual Spending Actual Spending Earned Value Earned Value BehindBehind ScheduleSchedule OverOver BudgetBudget
  • 9. Variance •Any schedule or costschedule or cost deviationdeviation from a specific plan. •Used within an organization to verify the budget and schedule for a project •Frequently used as a key component of plan reviewsplan reviews andand performance measurementperformance measurement 9
  • 10. Variance •Must compare scheduling and budget variance at the same time • Schedule varianceSchedule variance: deviations from work planned • Cost varianceCost variance: deviations from the budget 10
  • 11. Performance Indices •Cost Performance Index • CPICPI = BCWP/ACWP •Schedule Performance Index • SPISPI = BCWP/BCWS •Analysis •CPI > 1.0  exceptional performance •CPI < 1.0  poor performance 11
  • 12. Earned Value & Variance: Example On Day X: • PLANNED VALUE (BCWS) = 18 + 10 + 16 + 6 = 50 • EARNED VALUE (BCWP) = 18 + 8 + 14 + 0 = 40 • ACTUAL COST (ACWP) = 45 (from your project tracking) Therefore: • Schedule VarianceSchedule Variance = BCWP – BCWS = 40 - 50 = -10 (behind schedule) • Schedule Performance IndexSchedule Performance Index = 40 / 50 = 0.8, or 80% of plan • Cost VarianceCost Variance = BCWP - ACWP = 40 - 45 = -5 • Cost Performance IndexCost Performance Index = 40/45 = .89, or you’re getting an 89¢ return on every $1.00 (or, person-hour) spent on this project 12 18 8 14
  • 13. Another Example Project •Plans to spend $100K in each of first 4 weeks (baseline budget, per documented planper documented plan) •Actuals, at end of week 4 show: $325K spent •BCWS = $400K ($100K x 4) •ACWP = $325K •What conclusions can you draw? •Under budget? •Is project on schedule? 13
  • 14. Earned Value Management •How can you use this information? • Careful analysis of variance and trends • Resetting schedule or budget, when appropriate •Variance Analysis Questions • What is the problem causing the variance? • What is the impact on time, cost and performance? • What is the impact on other efforts, if any? • What corrective action is planned or under way? • What are the expected results of the corrective action? 14
  • 15. Earned Value Management •Extraordinary variance or alarming trends may be cause for reset or cancellation ofreset or cancellation of a project, but where do you draw the line? •How much variance to allow depends on a number of factors: • Life-cycle phase • Length of life-cycle phase • Length of project • Type of estimate • Accuracy of estimate 15
  • 16. Summary •Cost, in the form of Earned Value or BCWP, can be used to analyze progressanalyze progress of a project •Using Earned Value data to make critical project decisions must be based on careful analysiscareful analysis of data, variances and trends 16