Lean Project
Delivery
Group 7
Mohammad Jaseer – CE21M009
B. Chiranjeevi – CE21M108
Sourabh Kumar Singh – CE21M126
Tejaswini K – CE21M128
Site Locations
1. Sarayu Hostel
• Tour Based Work Sampling
• Process Mapping of Carpentry work
Site Locations
2. Open AirTheater
• Crew Balance Chart of Concreting of floor
• Crew Based Work Sampling of Concreting of floor
1. WORK SAMPLING
1.1Tour basedWork Sampling
• Location – Sarayu Hostel
• Date of sampling – 15th April 2022
• Time – 04:35 PM to 5:45 PM
• No. of workers – 53
• Type of sampling – Random
Category Nos.
VA 21
NVAN 12
NVA 20
Total 53
VA, 39.62%
NVAN,
22.64%
NVA,
37.74%
Percent Distribution ofVA, NVAN and NVA
VA
Finishing - applying Plaster
of Paris (PoP)
13
Finishing - Grinding 2
Carpentry 4
Electrical wiring 2
Total 21
NVAN
Scarping -waste cement 4
Brooming 3
Material shifting 5
Total 12
Carpentry
Scrapping and
Brooming
Material Shifting
Applying PoP
Grinding
NVA
Standing idle 6
Waiting for materials 4
Sleeping 1
Using mobile 2
Talking 5
Walking 2
Total 20
Waiting for
material
Walking
Sleeping
Standing idle
Talking
Using mobile
62%
9%
19%
10%
Value Added Activities
Finishing - applying Plaster of
Paris (PoP)
Finishing - Grinding
Carpentary
Electrical wiring
33%
25%
42%
NonValue Added but Necessary
Activities
Scarping -waste cement
Brooming
Material shifting
30%
20%
5%
10%
25%
10%
NonValue Added Activities
Standing idle
Waiting for materials
Sleeping
Using mobile
Talking
Walking
1.2 Crew basedWork Sampling
• Location – OAT
• Date of sampling – 15th April 2022
• Time – 10:20 PM
• No. of workers in the crew– 10
• Type of sampling – Random
• 75 samples taken from video
Work categorization for Masons
VA - Spreading and leveling concrete
NVAN - Minor leveling of concrete at the edge
NVA - Idling
Work categorization for Helpers
VA -Transporting, pouring, and spreading
concrete
NVAN - Cleaning and handing over tools
NVA - Idling
Worker’s
Identification
Crew – 10 Workers
3 Masons
7 Helpers
Crew 1 – Mason #1
Crew 2 – Mason #2
Crew 3 – Mason #3
Crew 7 – Helper #4
Crew 8 – Helper #5
Crew 5 – Helper #2
Crew 10 – Helper #7
Crew 4 – Hel
Crew 6 – Helper #3
Crew 9 – Helper #6
Levelling of concrete
Spreading of concrete
Transportation of
concrete
Pouring of concrete
Minor levelling
Idling
85%
8%
7%
Mason#1
69%
8%
23%
Mason#2
79%
7%
15%
Mason #3
VA - Spreading and leveling concrete
NVAN - Minor leveling of concrete at the edge
NVA - Idling
23%
33%
44%
Mason Helper#1
28%
19%
53%
Mason Helper#2
40%
32%
28%
Mason Helper#3
VA - Transporting, pouring, and
spreading concrete
NVAN - Cleaning and handing
over tools
NVA - Idling
100%
Mason Helper#4
49%
51%
Mason Helper#5
48%
52%
Mason Helper#6
47%
53%
Mason Helper#7
Summary ofVA, NVAN & NVA activities
32%
25%
43%
Percent Distribution of overallVA,
NVAN & NVA
VA NVAN NVA
78%
7%
15%
Distribution ofVA, NVAN & NVA
activities for all Masons
VA NVAN NVA
13%
33%
54%
Distribution ofVA, NVAN & NVA
activities for all Helpers
VA NVAN NVA
Observation Recommendation
Tour
based
WS
Standing idle and talking contributed 55% of NVA
activities as there was lack of supervisors.
Deployment of 2 supervisors.
Waiting for materials contributed 20% of NVA
activities.
To minimize waiting for materials,
preplanning of activities is required
by accessing daily and weekly
schedules.
Crew
based
WS
More workers were deployed that lead to 43% idle
time
Reduce the number of helpers.
Monitoring of productivity.
2. PROCESS MAPPING
2 Process Mapping
• Location – Sarayu Hostel
• Process– Carpentry work of wardrobe
doors and main doors of room
• Objective – optimize the flow
Process Chart – Current State
Location Symbol Activity
Location 1 Transfer of plywood fromTruck
Storage of plywood till the requirement at Ground
floor
Location 2
Transfer to the storage location of individual floor
storage room
Storage of plywood till the cutting operation
Location 3 Transportation to cutting, finishing workplace
Processing of plywood for fitting
Location 4 Transfer of finished plywood
Temporary storage till the rooms are ready for fitting
Location 5 Transfer of finished works for fitting location
Fitting and finishing operation
Process Chart – Future state
Location Symbol Activity
Location 1
(CentralWorkplace)
Transfer of plywood fromTruck
Storage of plywood til the requirement
Processing of plywood for fitting
Location 2 Transfer of finished plywood
TemporaryStorage of finished plywood
till the rooms are ready for fitting
Location 3
Transfer of finished works for fitting
location
Fitting and finishing operation
1. Temporary storage
in
Ground floor
2. Manual shifting of plywood to individual floors
3.Temporary storage
in
Individual floors
4. Processing of plywood for fitting 5.Temporary storage of finished plywood
6. Fitting Location 7. Central workshop area proposed.
Observation Recommendation
Process
mapping
The intermediate storage of plywood at
individual floor and operation location was
redundant
The single transfer of materials from central
work location to fitting location
The setting up of central work place at
courtyard wherein all carpentry work can be
streamlined
The workplace was distributed all over the
building
Inventory management issue as the plywood was
kept at so many locations
Comparison of Process Chart – Present vs Future state
Process A B Savings
Operation 2 2 0
Transporatation 5 3 2
Storage 3 2 1
10 7 3
3. CREW BALANCE CHART
Activity :- Concreting @ Open Air Auditorium
1 Cycle :- Completion of 1 section of concrete work
Cycle Time :- 7 min 28 sec (448 sec)
Manpower in as-in condition,
• No of masons :- 3
• No of helpers :- 7
Main Activities observed,
• Levelling
• Pouring
• Spreading
• Transporting
• Idling
• Waiting
Activity Details
Crew 1 – Mason #1
Crew 2 – Mason #2
Crew 3 – Mason #3
Crew 7 – Helper #4
Crew 8 – Helper #5
Crew 5 – Helper #2
Crew 10 – Helper #7
Crew 4 – Helper #
Crew 6 – Helper #3
Crew 9 – Helper #6
Crew based chart for as-is condition
Detection phase-
• The workers were idle most of the time (39% of total time) due to unclear
sequence of activities.
• The workers are not assigned with clear roles as evident from the CBC.
• The M4 is idle for most of the time.
• M9 & M10 were idle and waiting for most of the time.
Observation from As-Is Condition
• Workers were idle for almost 39% of the cycle time.
• From the table, it is observed that M4. M9 & M10 seem to be more idle, mostly waiting for the mixed
concrete.
Duration distribution of various activities in as-in condition
Observation from As-Is Condition
Crew based chart after 1st iteration
Improvement phase-
• The M4 was completely idle, hence he was removed.
• M9 & M10 whose major work was transporting was removed and assigned the same activity to M8.
• Clear roles has been assigned to Masons M6 & M7 in sequence to spread the Concrete.
• Masons M1, M2 & M5 starts levelling in a sequence after the spreading is done.
• The Pouring activity is completed with in seconds, so it was not considered in CBC.
After 1st iteration
Cost Improvement after 1st Iteration
Crew based chart after 2nd iteration Improvement phase-
• The works of Mason M1 was removed and the same activity was distributed to M2
& M5 in a sequence.
• The main activity of Mason M3 was spreading and the same activity was assigned to
M7 in continuous manner. in such a way that there is no idle time for M7.
After 2nd iteration
Cost Improvement after 2nd Iteration
Crew based chart after 1st iteration Crew based chart after 2nd iteration
Crew based chart for as-in condition
COST SAVED- 48%
COST SAVED - 27%
Crew Based Charts - Summary
THANK YOU.

Más contenido relacionado

La actualidad más candente

Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 

La actualidad más candente (10)

Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
 
Management consulting process
Management consulting process Management consulting process
Management consulting process
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Project scheduling and tracking
Project scheduling and  trackingProject scheduling and  tracking
Project scheduling and tracking
 
CMA Roadmap Deck (9).pdf
CMA Roadmap Deck (9).pdfCMA Roadmap Deck (9).pdf
CMA Roadmap Deck (9).pdf
 
Components of a monitoring and evaluation system
Components of a monitoring and evaluation system  Components of a monitoring and evaluation system
Components of a monitoring and evaluation system
 
Monotoring and evaluation principles and theories
Monotoring and evaluation  principles and theoriesMonotoring and evaluation  principles and theories
Monotoring and evaluation principles and theories
 
Practical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsPractical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex Projects
 
Use of Routine Data for Economic Evaluations
Use of Routine Data for Economic EvaluationsUse of Routine Data for Economic Evaluations
Use of Routine Data for Economic Evaluations
 
Value Stream Transformation: 10 Keys to Success
Value Stream Transformation: 10 Keys to SuccessValue Stream Transformation: 10 Keys to Success
Value Stream Transformation: 10 Keys to Success
 

Similar a Work Sampling, Process Mapping and Crew Balance Chart

Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout
Javier Siles
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
hlksd
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Crosstown TO
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
Minh Bui Si
 
Design of rigit pavement
Design of rigit pavementDesign of rigit pavement
Design of rigit pavement
TAHIR HUSEN
 
Laubsher cave mining handbook de beers version
Laubsher  cave mining handbook de beers versionLaubsher  cave mining handbook de beers version
Laubsher cave mining handbook de beers version
JULIO QUISPE
 
Chinook Projects-Geosteering and drilling optimization
Chinook Projects-Geosteering and drilling optimizationChinook Projects-Geosteering and drilling optimization
Chinook Projects-Geosteering and drilling optimization
Chinook Consulting Services
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Crosstown TO
 
Jaimin Hooper - Resume
Jaimin Hooper - ResumeJaimin Hooper - Resume
Jaimin Hooper - Resume
Jaimin Hooper
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...
Benoit Latapie
 
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGVVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
Indrani7
 

Similar a Work Sampling, Process Mapping and Crew Balance Chart (20)

Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout
 
Erosion Analysis of Subsea Equipment: A Case Study with High Solid Loading
Erosion Analysis of Subsea Equipment: A Case Study with High Solid LoadingErosion Analysis of Subsea Equipment: A Case Study with High Solid Loading
Erosion Analysis of Subsea Equipment: A Case Study with High Solid Loading
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
AH15019
AH15019AH15019
AH15019
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Design of rigit pavement
Design of rigit pavementDesign of rigit pavement
Design of rigit pavement
 
Laubsher cave mining handbook de beers version
Laubsher  cave mining handbook de beers versionLaubsher  cave mining handbook de beers version
Laubsher cave mining handbook de beers version
 
Column & beam
Column & beamColumn & beam
Column & beam
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposal
 
Chinook Projects-Geosteering and drilling optimization
Chinook Projects-Geosteering and drilling optimizationChinook Projects-Geosteering and drilling optimization
Chinook Projects-Geosteering and drilling optimization
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Tabnak Drilling Management
Tabnak Drilling ManagementTabnak Drilling Management
Tabnak Drilling Management
 
Jaimin Hooper - Resume
Jaimin Hooper - ResumeJaimin Hooper - Resume
Jaimin Hooper - Resume
 
Demolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David WoodDemolition of a former mine site - Luke Egan and David Wood
Demolition of a former mine site - Luke Egan and David Wood
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...151111 Exploring the challenges of underground construction in urban areas_Be...
151111 Exploring the challenges of underground construction in urban areas_Be...
 
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGVVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
 

Último

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

Último (20)

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 

Work Sampling, Process Mapping and Crew Balance Chart

  • 1. Lean Project Delivery Group 7 Mohammad Jaseer – CE21M009 B. Chiranjeevi – CE21M108 Sourabh Kumar Singh – CE21M126 Tejaswini K – CE21M128
  • 2. Site Locations 1. Sarayu Hostel • Tour Based Work Sampling • Process Mapping of Carpentry work
  • 3. Site Locations 2. Open AirTheater • Crew Balance Chart of Concreting of floor • Crew Based Work Sampling of Concreting of floor
  • 5. 1.1Tour basedWork Sampling • Location – Sarayu Hostel • Date of sampling – 15th April 2022 • Time – 04:35 PM to 5:45 PM • No. of workers – 53 • Type of sampling – Random Category Nos. VA 21 NVAN 12 NVA 20 Total 53 VA, 39.62% NVAN, 22.64% NVA, 37.74% Percent Distribution ofVA, NVAN and NVA
  • 6. VA Finishing - applying Plaster of Paris (PoP) 13 Finishing - Grinding 2 Carpentry 4 Electrical wiring 2 Total 21 NVAN Scarping -waste cement 4 Brooming 3 Material shifting 5 Total 12 Carpentry Scrapping and Brooming Material Shifting Applying PoP Grinding
  • 7. NVA Standing idle 6 Waiting for materials 4 Sleeping 1 Using mobile 2 Talking 5 Walking 2 Total 20 Waiting for material Walking Sleeping Standing idle Talking Using mobile
  • 8. 62% 9% 19% 10% Value Added Activities Finishing - applying Plaster of Paris (PoP) Finishing - Grinding Carpentary Electrical wiring 33% 25% 42% NonValue Added but Necessary Activities Scarping -waste cement Brooming Material shifting 30% 20% 5% 10% 25% 10% NonValue Added Activities Standing idle Waiting for materials Sleeping Using mobile Talking Walking
  • 9.
  • 10. 1.2 Crew basedWork Sampling • Location – OAT • Date of sampling – 15th April 2022 • Time – 10:20 PM • No. of workers in the crew– 10 • Type of sampling – Random • 75 samples taken from video Work categorization for Masons VA - Spreading and leveling concrete NVAN - Minor leveling of concrete at the edge NVA - Idling Work categorization for Helpers VA -Transporting, pouring, and spreading concrete NVAN - Cleaning and handing over tools NVA - Idling
  • 11. Worker’s Identification Crew – 10 Workers 3 Masons 7 Helpers Crew 1 – Mason #1 Crew 2 – Mason #2 Crew 3 – Mason #3 Crew 7 – Helper #4 Crew 8 – Helper #5 Crew 5 – Helper #2 Crew 10 – Helper #7 Crew 4 – Hel Crew 6 – Helper #3 Crew 9 – Helper #6
  • 12. Levelling of concrete Spreading of concrete Transportation of concrete Pouring of concrete Minor levelling Idling
  • 13. 85% 8% 7% Mason#1 69% 8% 23% Mason#2 79% 7% 15% Mason #3 VA - Spreading and leveling concrete NVAN - Minor leveling of concrete at the edge NVA - Idling
  • 14. 23% 33% 44% Mason Helper#1 28% 19% 53% Mason Helper#2 40% 32% 28% Mason Helper#3 VA - Transporting, pouring, and spreading concrete NVAN - Cleaning and handing over tools NVA - Idling 100% Mason Helper#4 49% 51% Mason Helper#5 48% 52% Mason Helper#6 47% 53% Mason Helper#7
  • 15. Summary ofVA, NVAN & NVA activities 32% 25% 43% Percent Distribution of overallVA, NVAN & NVA VA NVAN NVA 78% 7% 15% Distribution ofVA, NVAN & NVA activities for all Masons VA NVAN NVA 13% 33% 54% Distribution ofVA, NVAN & NVA activities for all Helpers VA NVAN NVA
  • 16.
  • 17. Observation Recommendation Tour based WS Standing idle and talking contributed 55% of NVA activities as there was lack of supervisors. Deployment of 2 supervisors. Waiting for materials contributed 20% of NVA activities. To minimize waiting for materials, preplanning of activities is required by accessing daily and weekly schedules. Crew based WS More workers were deployed that lead to 43% idle time Reduce the number of helpers. Monitoring of productivity.
  • 19. 2 Process Mapping • Location – Sarayu Hostel • Process– Carpentry work of wardrobe doors and main doors of room • Objective – optimize the flow
  • 20. Process Chart – Current State Location Symbol Activity Location 1 Transfer of plywood fromTruck Storage of plywood till the requirement at Ground floor Location 2 Transfer to the storage location of individual floor storage room Storage of plywood till the cutting operation Location 3 Transportation to cutting, finishing workplace Processing of plywood for fitting Location 4 Transfer of finished plywood Temporary storage till the rooms are ready for fitting Location 5 Transfer of finished works for fitting location Fitting and finishing operation
  • 21. Process Chart – Future state Location Symbol Activity Location 1 (CentralWorkplace) Transfer of plywood fromTruck Storage of plywood til the requirement Processing of plywood for fitting Location 2 Transfer of finished plywood TemporaryStorage of finished plywood till the rooms are ready for fitting Location 3 Transfer of finished works for fitting location Fitting and finishing operation
  • 22. 1. Temporary storage in Ground floor 2. Manual shifting of plywood to individual floors 3.Temporary storage in Individual floors
  • 23. 4. Processing of plywood for fitting 5.Temporary storage of finished plywood
  • 24. 6. Fitting Location 7. Central workshop area proposed.
  • 25. Observation Recommendation Process mapping The intermediate storage of plywood at individual floor and operation location was redundant The single transfer of materials from central work location to fitting location The setting up of central work place at courtyard wherein all carpentry work can be streamlined The workplace was distributed all over the building Inventory management issue as the plywood was kept at so many locations
  • 26. Comparison of Process Chart – Present vs Future state Process A B Savings Operation 2 2 0 Transporatation 5 3 2 Storage 3 2 1 10 7 3
  • 28. Activity :- Concreting @ Open Air Auditorium 1 Cycle :- Completion of 1 section of concrete work Cycle Time :- 7 min 28 sec (448 sec) Manpower in as-in condition, • No of masons :- 3 • No of helpers :- 7 Main Activities observed, • Levelling • Pouring • Spreading • Transporting • Idling • Waiting Activity Details Crew 1 – Mason #1 Crew 2 – Mason #2 Crew 3 – Mason #3 Crew 7 – Helper #4 Crew 8 – Helper #5 Crew 5 – Helper #2 Crew 10 – Helper #7 Crew 4 – Helper # Crew 6 – Helper #3 Crew 9 – Helper #6
  • 29. Crew based chart for as-is condition Detection phase- • The workers were idle most of the time (39% of total time) due to unclear sequence of activities. • The workers are not assigned with clear roles as evident from the CBC. • The M4 is idle for most of the time. • M9 & M10 were idle and waiting for most of the time. Observation from As-Is Condition
  • 30. • Workers were idle for almost 39% of the cycle time. • From the table, it is observed that M4. M9 & M10 seem to be more idle, mostly waiting for the mixed concrete. Duration distribution of various activities in as-in condition Observation from As-Is Condition
  • 31. Crew based chart after 1st iteration Improvement phase- • The M4 was completely idle, hence he was removed. • M9 & M10 whose major work was transporting was removed and assigned the same activity to M8. • Clear roles has been assigned to Masons M6 & M7 in sequence to spread the Concrete. • Masons M1, M2 & M5 starts levelling in a sequence after the spreading is done. • The Pouring activity is completed with in seconds, so it was not considered in CBC. After 1st iteration
  • 32. Cost Improvement after 1st Iteration
  • 33. Crew based chart after 2nd iteration Improvement phase- • The works of Mason M1 was removed and the same activity was distributed to M2 & M5 in a sequence. • The main activity of Mason M3 was spreading and the same activity was assigned to M7 in continuous manner. in such a way that there is no idle time for M7. After 2nd iteration
  • 34. Cost Improvement after 2nd Iteration
  • 35. Crew based chart after 1st iteration Crew based chart after 2nd iteration Crew based chart for as-in condition COST SAVED- 48% COST SAVED - 27% Crew Based Charts - Summary