Presented By
Steve Gladstone
steve.gladstone@spg-solutions.com
Presentation Roadmap
 What is Microsoft Project (MSP)?
 Setting Up The Project Plan
 Set Project Start/End Dates
 Define Tasks And Dependencies
 Assign Resources and Costs
 “Baseline” The Plan
 Verify The Project Plan Is Viable
 Identify Resource Over-Allocations
 “Level” Project, If Necessary
 Execute And Manage The Plan
 Periodically Update Plan With Actual Work Done
 Compare Actual Against Baseline Plan
 Re-Plan and Re-Baseline, If Required
 Use The Plan To Balance And Communicate Scope, Time, And Resource Issues
 Wrap-Up: Review And Q&A
 Please Complete & Submit Feedback Forms
What Is Microsoft Project?
 Microsoft Project (or MSP)
 Project management software program developed and sold by Microsoft which is designed to
assist project managers in developing plans, assigning resources to tasks, tracking progress,
managing budgets and analyzing workloads.
 Microsoft Project Server
 Microsoft extends the capabilities of Microsoft Project with Project Server and Web Access.
Microsoft Project Server stores project information in a central database, protected from
unauthorized access and corruption. A Project Administrator can control security defining users
and access rights.
 The Project Center supports reports across an organization at the project level. Managers can
drill down into project details.
 The project manager needs to communicate project plans and to distribute task assignments to
team members. The assignment of tasks can be distributed to team member home pages in Web
Access. They need to communicate status and changes to keep the project manager up to date.
Project Server supports electronic communication over the web via Web Access.
 Resource workloads can be analyzed by project and by resource with the Resource Center,
allowing organizations to forecast future resource requirements and make more efficient use of
resources.
 The view definition is easier to understand and more robust with Web Access than with
Microsoft Project. Views can be protected to assist standardization. Project Server stores custom
calendars, views, tables, filters, and fields, in an Enterprise Global area where users have access to
the latest version every time they restart Microsoft Project.
Setting Up The Project Plan
 Set Up Project Start Date, Calendars, etc.
 -> Project --> Project Information
Setting Up The Project Plan
 Use Gantt Chart View to Define Project Tasks
There are four major types of tasks:
Summary tasks - contain subtasks
and their related properties
Subtasks - are smaller tasks that are
a part of a summary task
Recurring tasks - are tasks that
occur at regular intervals
Milestones - are tasks that are set to
zero duration and are like interim
goals in the project
Setting Up The Project Plan
 Use Gantt Chart View to Define Tasks Dependencies
 The Four Task Dependency Types
Setting Up The Project Plan
 Use Resource Sheet View to Define Resources and Resource Costs
Setting Up The Project Plan
 Baseline the Project Plan for Later Comparison
 -> Tools --> Tracking ---> Set Baseline
 You Can Clear or Re-Baseline
Verify The Project Plan Is Viable
 Use Resource Sheet, Task Usage, and Resource Graph Views to Identify
Resource Over-Allocations
 You Can Mitigate Resource Over-Allocations By “Leveling”
 -> Tools --> Level Resources
 Generally, Expands Schedule So That Resources Are Not Over-Allocated
 Leveling Is Not Always Effective In Practice
Execute And Manage The Plan
 Track Tasks As They Progress
 Simplest method is By “% Complete” on Gantt Chart View
 Alternatively, Use Tracking Gantt View
Execute And Manage The Plan
 Use Project Statistics To Track Project Progress
 Compare Actual Project versus Baseline Project
 View Realized Task Durations, Work, and Costs
 Periodically Communicate Progress and Issues To Project Team and Management
 Use Microsoft Project to Balance the Golden Triangle (Scope, Time, and Cost)
 Always Remember: MS Project is NOT Project Management
Wrap-Up: Review And Q&A
 What is Microsoft Project (MSP)?
 Setting Up The Project Plan
 Set Project Start/End Dates
 Define Tasks And Dependencies
 Assign Resources and Costs
 “Baseline” The Plan
 Verify The Project Plan Is Viable
 Identify Resource Over-Allocations
 “Level” Project, If Necessary
 Execute And Manage The Plan
 Periodically Update Plan With Actual Work Done
 Compare Actual Against Baseline Plan
 Re-Plan and Re-Baseline, If Required
 Use The Plan To Balance And Communicate Scope, Time, And Resource Issues
 Wrap-Up: Review And Q&A
 Please Complete & Submit Feedback Forms

Más contenido relacionado

La actualidad más candente

Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sAbhik Tushar Das
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Rajeev Sharma
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Agus Suhanto
 
projec kickoff presentation template
 projec kickoff presentation template projec kickoff presentation template
projec kickoff presentation templatedadiiskandar4
 
Primavera P6 User guide.pdf
Primavera P6 User guide.pdfPrimavera P6 User guide.pdf
Primavera P6 User guide.pdfssuseraaebbd
 
The Role of Project Manager in Modern Agile Projects
The Role of Project Manager in Modern Agile ProjectsThe Role of Project Manager in Modern Agile Projects
The Role of Project Manager in Modern Agile ProjectsVersionOne
 
Project Human Resource Management.pptx
Project Human Resource Management.pptxProject Human Resource Management.pptx
Project Human Resource Management.pptxIkram192675
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 

La actualidad más candente (20)

Microsoft Project 2013
Microsoft Project 2013Microsoft Project 2013
Microsoft Project 2013
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Project Mangement
Project MangementProject Mangement
Project Mangement
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
International Delay Analysis Approaches
International Delay Analysis ApproachesInternational Delay Analysis Approaches
International Delay Analysis Approaches
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
projec kickoff presentation template
 projec kickoff presentation template projec kickoff presentation template
projec kickoff presentation template
 
Primavera P6 User guide.pdf
Primavera P6 User guide.pdfPrimavera P6 User guide.pdf
Primavera P6 User guide.pdf
 
MS Project
MS ProjectMS Project
MS Project
 
The Role of Project Manager in Modern Agile Projects
The Role of Project Manager in Modern Agile ProjectsThe Role of Project Manager in Modern Agile Projects
The Role of Project Manager in Modern Agile Projects
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Project Human Resource Management.pptx
Project Human Resource Management.pptxProject Human Resource Management.pptx
Project Human Resource Management.pptx
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 

Similar a Practical Use of Microsoft Project for Project Managers

Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0niict
 
Primavara
PrimavaraPrimavara
Primavaradanabl
 
Mastering Microsoft Project_ A Comprehensive Guide.pptx
Mastering Microsoft Project_ A Comprehensive Guide.pptxMastering Microsoft Project_ A Comprehensive Guide.pptx
Mastering Microsoft Project_ A Comprehensive Guide.pptxkarenbelloc23
 
Using Rational Requisite Pro to Manage Projects
Using Rational Requisite Pro to Manage ProjectsUsing Rational Requisite Pro to Manage Projects
Using Rational Requisite Pro to Manage Projectsmlevine
 
Ms project literature to read
Ms project   literature to readMs project   literature to read
Ms project literature to readChetan vadodariya
 
]project-open[ OSS Project Mangement
]project-open[ OSS Project Mangement]project-open[ OSS Project Mangement
]project-open[ OSS Project MangementKlaus Hofeditz
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpmission_vishvas
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpvishvasyadav45
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpcmmaao
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmppmicmmaao
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpvishvasyadav676
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9Ian Sommerville
 
IBM Rational Team Concert at Landmap
IBM Rational Team Concert at LandmapIBM Rational Team Concert at Landmap
IBM Rational Team Concert at LandmapBharti Gupta
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software EngineeringMuhammad Yousuf Abdul Qadir
 
CORTAC PPC General
CORTAC PPC GeneralCORTAC PPC General
CORTAC PPC GeneralDerek Regan
 
Chapter7 database management system.pptx
Chapter7 database management system.pptxChapter7 database management system.pptx
Chapter7 database management system.pptxMohammedNouh7
 
Comparison and Analysis of Project Management software
Comparison and Analysis of Project Management softwareComparison and Analysis of Project Management software
Comparison and Analysis of Project Management softwareKonstantin Prokhorov, MBA, MSc
 

Similar a Practical Use of Microsoft Project for Project Managers (20)

Primavera6.0
Primavera6.0Primavera6.0
Primavera6.0
 
Primavara
PrimavaraPrimavara
Primavara
 
Mastering Microsoft Project_ A Comprehensive Guide.pptx
Mastering Microsoft Project_ A Comprehensive Guide.pptxMastering Microsoft Project_ A Comprehensive Guide.pptx
Mastering Microsoft Project_ A Comprehensive Guide.pptx
 
Using Rational Requisite Pro to Manage Projects
Using Rational Requisite Pro to Manage ProjectsUsing Rational Requisite Pro to Manage Projects
Using Rational Requisite Pro to Manage Projects
 
Ms project literature to read
Ms project   literature to readMs project   literature to read
Ms project literature to read
 
Microsoft Project Syllabus
Microsoft Project SyllabusMicrosoft Project Syllabus
Microsoft Project Syllabus
 
]project-open[ OSS Project Mangement
]project-open[ OSS Project Mangement]project-open[ OSS Project Mangement
]project-open[ OSS Project Mangement
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmp
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmp
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmp
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmp
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmp
 
Cmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmpCmmaao resource-assignment-matrix-pmi-pmp
Cmmaao resource-assignment-matrix-pmi-pmp
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9
 
IBM Rational Team Concert at Landmap
IBM Rational Team Concert at LandmapIBM Rational Team Concert at Landmap
IBM Rational Team Concert at Landmap
 
ERP Project Management.pdf
ERP Project Management.pdfERP Project Management.pdf
ERP Project Management.pdf
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software Engineering
 
CORTAC PPC General
CORTAC PPC GeneralCORTAC PPC General
CORTAC PPC General
 
Chapter7 database management system.pptx
Chapter7 database management system.pptxChapter7 database management system.pptx
Chapter7 database management system.pptx
 
Comparison and Analysis of Project Management software
Comparison and Analysis of Project Management softwareComparison and Analysis of Project Management software
Comparison and Analysis of Project Management software
 

Último

Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGSujit Pal
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 

Último (20)

Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAG
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 

Practical Use of Microsoft Project for Project Managers

  • 2. Presentation Roadmap  What is Microsoft Project (MSP)?  Setting Up The Project Plan  Set Project Start/End Dates  Define Tasks And Dependencies  Assign Resources and Costs  “Baseline” The Plan  Verify The Project Plan Is Viable  Identify Resource Over-Allocations  “Level” Project, If Necessary  Execute And Manage The Plan  Periodically Update Plan With Actual Work Done  Compare Actual Against Baseline Plan  Re-Plan and Re-Baseline, If Required  Use The Plan To Balance And Communicate Scope, Time, And Resource Issues  Wrap-Up: Review And Q&A  Please Complete & Submit Feedback Forms
  • 3. What Is Microsoft Project?  Microsoft Project (or MSP)  Project management software program developed and sold by Microsoft which is designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets and analyzing workloads.  Microsoft Project Server  Microsoft extends the capabilities of Microsoft Project with Project Server and Web Access. Microsoft Project Server stores project information in a central database, protected from unauthorized access and corruption. A Project Administrator can control security defining users and access rights.  The Project Center supports reports across an organization at the project level. Managers can drill down into project details.  The project manager needs to communicate project plans and to distribute task assignments to team members. The assignment of tasks can be distributed to team member home pages in Web Access. They need to communicate status and changes to keep the project manager up to date. Project Server supports electronic communication over the web via Web Access.  Resource workloads can be analyzed by project and by resource with the Resource Center, allowing organizations to forecast future resource requirements and make more efficient use of resources.  The view definition is easier to understand and more robust with Web Access than with Microsoft Project. Views can be protected to assist standardization. Project Server stores custom calendars, views, tables, filters, and fields, in an Enterprise Global area where users have access to the latest version every time they restart Microsoft Project.
  • 4. Setting Up The Project Plan  Set Up Project Start Date, Calendars, etc.  -> Project --> Project Information
  • 5. Setting Up The Project Plan  Use Gantt Chart View to Define Project Tasks There are four major types of tasks: Summary tasks - contain subtasks and their related properties Subtasks - are smaller tasks that are a part of a summary task Recurring tasks - are tasks that occur at regular intervals Milestones - are tasks that are set to zero duration and are like interim goals in the project
  • 6. Setting Up The Project Plan  Use Gantt Chart View to Define Tasks Dependencies  The Four Task Dependency Types
  • 7. Setting Up The Project Plan  Use Resource Sheet View to Define Resources and Resource Costs
  • 8. Setting Up The Project Plan  Baseline the Project Plan for Later Comparison  -> Tools --> Tracking ---> Set Baseline  You Can Clear or Re-Baseline
  • 9. Verify The Project Plan Is Viable  Use Resource Sheet, Task Usage, and Resource Graph Views to Identify Resource Over-Allocations  You Can Mitigate Resource Over-Allocations By “Leveling”  -> Tools --> Level Resources  Generally, Expands Schedule So That Resources Are Not Over-Allocated  Leveling Is Not Always Effective In Practice
  • 10. Execute And Manage The Plan  Track Tasks As They Progress  Simplest method is By “% Complete” on Gantt Chart View  Alternatively, Use Tracking Gantt View
  • 11. Execute And Manage The Plan  Use Project Statistics To Track Project Progress  Compare Actual Project versus Baseline Project  View Realized Task Durations, Work, and Costs  Periodically Communicate Progress and Issues To Project Team and Management  Use Microsoft Project to Balance the Golden Triangle (Scope, Time, and Cost)  Always Remember: MS Project is NOT Project Management
  • 12. Wrap-Up: Review And Q&A  What is Microsoft Project (MSP)?  Setting Up The Project Plan  Set Project Start/End Dates  Define Tasks And Dependencies  Assign Resources and Costs  “Baseline” The Plan  Verify The Project Plan Is Viable  Identify Resource Over-Allocations  “Level” Project, If Necessary  Execute And Manage The Plan  Periodically Update Plan With Actual Work Done  Compare Actual Against Baseline Plan  Re-Plan and Re-Baseline, If Required  Use The Plan To Balance And Communicate Scope, Time, And Resource Issues  Wrap-Up: Review And Q&A  Please Complete & Submit Feedback Forms