AUSENCO 04-Nov-2022.pptx
1. AGENDA 04-Nov-2022
1. PMS-1 technical input is awaited from JSW.
2. Geotech Survey report already shared with ASENCO for Kolmang, others ISP Paradeep and Valve Station to be expedited.
3. AUSENCO issued pipeline standard drawing are hold by JSW for minor correction [Dwg. No.:- JSW-ES-06-ODSP-401 to 414,
Rev C]
4. JSW has updated the crossing list according to revised route along with plan and elevation for reference of Alignment
Sheet, JSW waiting the approve copy of Alignment Sheet (AFC) for construction site.
5. AUSENCO shall made the correction of thickness of HOT Bend in MR and shall issue the revised MR with Priority.
6. Query of HOT Bend Manufacturer –The material properties of the qualification bend shall be verified by testing after
bending and after any post bend heat treatment.
Vendor Responses- Heat treatment facilities is not available. They will fabricate the bend under control process parameters
and PQT shall be performed for each thickness. Destructive test also be performed on production test.
JSW would expected AUSENCO feedback.
7. JSW has shared the latest crossing list vetted by Mr. Alan, and proposed the thickness of line pipes for each crossings
according to their characteristic and further requested to AUSECO to give their approval for the same. So that JSW can
handed over that sheet to Contractors for construction work.