Module: Project Management
Code: PMNM101
PART TWO: PROJECT COSTS AND SCHEDULES
Learning Outcomes
a) Estimate a Project time and cost
b)Use chart and network techniques to schedule a project:
- Draw a GANTT chart
- Construct an AON network (PERT)
- Calculate activity times
- Determine the critical path and time
- Determine the float (slack)
c) Analyse changes in project constraints and the cost of making
adjustments.
Estimate a Project Time and Cost
Time and cost are the two of the three major project constraints.
The three constraints or dimensions have serious effect on the
success of a project.
This section will explore different scheduling techniques used in
project management from small to complex projects.
It will further analyse the project resource requirements: project cost
and cashflow.
SCHEDULING
 After the WBS process, scheduling the work elements is the most
important step in planning as it becomes the basis for:
Allocating resources
Executing work
Tracking project performance
Finishing on time
 Schedules show the timing for work elements and when specific
events and project milestone should take place.
SCHEDULING Cont’d
Events and Milestones:
• Events represent the start or finish of something.
• Event signifies a moment in time, an instant when something happens.
In projects there are two kinds of events: Interface and milestone.
• An interface event is the completion of one task and simultaneous start of
one or more subsequent tasks.
• A milestone event signifies a major project occurrence such as completion
of a phase or several critical or difficult tasks, approval of something
important, or availability of crucial resources.
• It signifies progress, therefore it measures performance
Kinds of Schedules
There are two kinds of schedules: project schedule and task schedule
• A project schedule (or project master schedule) plans and reviews the entire
project.
• It shows the major project activities without much details about each.
• Top managers develop project master schedule.
• A task schedule shows the specific activities necessary to complete a work
package.
• A task schedule is created for people working on a specific task and enables
lower level managers or supervisors to focus on the task and not to be
distracted by other tasks with which they have no interactions. Task
schedules are prepared by functional managers or sub-contractors.
NB: Task and project schedules are displayed in many ways including Gantt
charts and project networks.
PROJECT SCHEDULE: TIME MANAGEMENT
The project needs to be completed on time. It then consists of five major
processes:
1. Activity definition: specify the activity to be accomplished
2. Activity sequencing: Identify dependencies among activities
3. Duration estimation: Estimate the time needed to complete each
activity
4. Schedule development: Analyse activities sequences and durations,
and resource availability to develop a realistic and achievable
schedule.
5. Schedule control: maintain the project schedule
PROJECT SCHEDULE: TIME MANAGEMENT Cont’d
Activity sequencing
An activity-on-node network may have four types of logical
relationships:
 Finish-to-start
 Finish-to-finish
 Start-to-start
 Start-to-finish
A project critical path is the network path with the longest duration. It
determines the shortest total duration of a project. Any delay on critical
path will delay the project completion time.
CHART AND DIAGRAM USED IN PROJECT SCHEDULING
Chart and diagram mostly used in project scheduling:
 Gantt chart: simplest to use and display activities plotted as bars or lines
on a timeline. It cannot show logical relationships between activities.
 PERT (programme evaluation and review techniques): complex
Determination of the critical path
 EF=ES+AD
 LS=LF-AD
 A slack is the time that an activity may delay without delaying the project’
s end date.
 Slack= LF-EF or LS-ES
GANTT CHARTS
The simplest and most commonly used scheduling technique is the
Gantt chart (or bar chart) developed by Henry Gantt.
It was easily adopted in industry and today it is used in a variety of
ways.
The Gantt chart consists of a horizontal scale divided into time units
(days, weeks, months, etc.)
and vertical schedule showing project work elements (task, activities,
or work packages).
The preparation of the Gantt chart comes after a WBS analysis and
identification of work packages or other tasks.
Gantt chart and Calendar
The following must be considered before presenting the Gantt
chart:
Workdays
Rest days
Holidays
Training
Number of calendars
Milestone Gantt Chart
Gantt Chart
Advantages and Disadvantage of Gantt Chart
Advantages:
• it is often maintained manually, and better for small project, but a burden
and disadvantage in large project.
• It requires a software for a large project in its creation and update:
assuming input data is accurate and updated, computer-generated Gantt
charts can be updated frequently to display progress.
Disadvantages:
• The Gantt chart does not necessary show the relationships among work
elements
• It does not reveal the effect of a work element falling behind schedule on
other work elements as certain work elements must be completed by a
specific date for the project to be completed on target.
Program Evaluation and Review Techniques:
Networks Diagrams
• Network methods show interdependencies and what happens to
the project when resources change or individual activities are
delayed.
• A network diagram shows a group of activities or tasks and their
logical relationships. e.g.: precedence relationship or dependency.
• It describes a project in terms of sequences of activities and events.
Two common methods for constructing network diagrams are:
activity-on-node (AON) also called precedence programming
method (PDM) and activity-on-arrow (AOA)
EXERCISE
Construct the activity-on-the-node project network diagrams for the project
defined below:
ACTIVITY PRECEDING (FROM)
ACTIVITY
SUCCEEDING (TO) ACTIVITY
A _ C,E
B _ D
C A D
D B,C F
E A,G F
F D,E _
G _ E
ESTIMATED DURATION
(WORK-DAYS)
3
5
3
10
8
14
7
Critical path
Network
CP=A+C+D+F
= 3+3+10+14
Critical path may change
Network: assume I is preceding by E and will take 16 to complete
CP=G+E+I
=7+8+16
EXERCISE CONT’D
• CRITCAL PATH
ACTIVITY DURATION
(WORK-DAYS)
EARLY
START
EARLY FINISH=
EARLY
START+DURATION
LATE START=
LATE FINISH-
DURATION
LATE
FINISH
SLACK= LATE
FINISH-EARLY
FINISH OR LATE
START-EARLY START
K 2 0 2 0 2 0
L 2 2 4 2 4 0
M 2 4 6 4 6 0
N 4 0 4 1 5 1
P 1 4 5 5 6 1
Build a network for this manufacturing project:
Calculate and comment on the critical path
ACTIVITY IMMEDIATE PREDECESSORS DURATION (Weeks)
A - 3
B - 4
C A,B 3
D A,B 5
E C,D 5
F C 4
G D,E 6
H F,G 3
Introduction to Project Resources
Resources include (information, human, physical and financial):
• Skilled workers
• Machinery
• Equipment
• Working capital
These resources dictate whether activities will be completed on
time or delayed.
Allocation of Resources
1. Identifying and assigning resources to activities so that the
project is undertaken using appropriate levels of resources and
within an acceptable duration.
2. Usage and availability of resources are the major problem areas
for managers.
3. The project resource schedule is important because it serves as
time baseline of the project.
4. Resource allocation, smoothing (don’t go beyond resource
requirement), levelling and scheduling are techniques used to
determine and manage appropriate levels of resources.’
Allocation of resources Cont’d
Two cases where the project schedule must accommodate
resources: resource levelling in time constrained and resource
constrained project.
• Resource levelling: there is enough resource to complete the
project on time, but the amount of resource needed fluctuates
drastically. The objective is to balance or level the resource
needed throughout the project.
• Resource constrained project: there is no enough resource to
do multiple activities at once in adjusting the schedule to
accommodate the constraint.

Más contenido relacionado

Similar a PMNM101 Lesson 2 2022.pptx

Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalAMIT PAYAL
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 pptahsanrabbani
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxMdSabujHossen2
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 

Similar a PMNM101 Lesson 2 2022.pptx (20)

Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
programmed evaluation and review technique,
programmed evaluation and review technique,programmed evaluation and review technique,
programmed evaluation and review technique,
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Unit II.pptx
Unit II.pptxUnit II.pptx
Unit II.pptx
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 

Más de SydneyJaydeanKhanyil

Lecture notes.pdfhdhdhshsgdjshsjssjsjsgihhs
Lecture notes.pdfhdhdhshsgdjshsjssjsjsgihhsLecture notes.pdfhdhdhshsgdjshsjssjsjsgihhs
Lecture notes.pdfhdhdhshsgdjshsjssjsjsgihhsSydneyJaydeanKhanyil
 
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudskoCHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudskoSydneyJaydeanKhanyil
 
CHAPTER 6.pdfjdjdjdjdjdkdjkdhdjdudkdudkdjdj
CHAPTER 6.pdfjdjdjdjdjdkdjkdhdjdudkdudkdjdjCHAPTER 6.pdfjdjdjdjdjdkdjkdhdjdudkdudkdjdj
CHAPTER 6.pdfjdjdjdjdjdkdjkdhdjdudkdudkdjdjSydneyJaydeanKhanyil
 
Chapter 1 The Environment in which Technical People Work PCPM101.pptx
Chapter 1 The Environment in which Technical People Work PCPM101.pptxChapter 1 The Environment in which Technical People Work PCPM101.pptx
Chapter 1 The Environment in which Technical People Work PCPM101.pptxSydneyJaydeanKhanyil
 
Chapter 7 Managing Technology and Innovation.pptx
Chapter 7 Managing Technology and Innovation.pptxChapter 7 Managing Technology and Innovation.pptx
Chapter 7 Managing Technology and Innovation.pptxSydneyJaydeanKhanyil
 

Más de SydneyJaydeanKhanyil (6)

Lecture notes.pdfhdhdhshsgdjshsjssjsjsgihhs
Lecture notes.pdfhdhdhshsgdjshsjssjsjsgihhsLecture notes.pdfhdhdhshsgdjshsjssjsjsgihhs
Lecture notes.pdfhdhdhshsgdjshsjssjsjsgihhs
 
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudskoCHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
 
CHAPTER 6.pdfjdjdjdjdjdkdjkdhdjdudkdudkdjdj
CHAPTER 6.pdfjdjdjdjdjdkdjkdhdjdudkdudkdjdjCHAPTER 6.pdfjdjdjdjdjdkdjkdhdjdudkdudkdjdj
CHAPTER 6.pdfjdjdjdjdjdkdjkdhdjdudkdudkdjdj
 
CEDB201 REBOILER DESIGN_2022.pptx
CEDB201 REBOILER DESIGN_2022.pptxCEDB201 REBOILER DESIGN_2022.pptx
CEDB201 REBOILER DESIGN_2022.pptx
 
Chapter 1 The Environment in which Technical People Work PCPM101.pptx
Chapter 1 The Environment in which Technical People Work PCPM101.pptxChapter 1 The Environment in which Technical People Work PCPM101.pptx
Chapter 1 The Environment in which Technical People Work PCPM101.pptx
 
Chapter 7 Managing Technology and Innovation.pptx
Chapter 7 Managing Technology and Innovation.pptxChapter 7 Managing Technology and Innovation.pptx
Chapter 7 Managing Technology and Innovation.pptx
 

Último

The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 

Último (20)

The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 

PMNM101 Lesson 2 2022.pptx

  • 2. PART TWO: PROJECT COSTS AND SCHEDULES
  • 3. Learning Outcomes a) Estimate a Project time and cost b)Use chart and network techniques to schedule a project: - Draw a GANTT chart - Construct an AON network (PERT) - Calculate activity times - Determine the critical path and time - Determine the float (slack) c) Analyse changes in project constraints and the cost of making adjustments.
  • 4. Estimate a Project Time and Cost Time and cost are the two of the three major project constraints. The three constraints or dimensions have serious effect on the success of a project. This section will explore different scheduling techniques used in project management from small to complex projects. It will further analyse the project resource requirements: project cost and cashflow.
  • 5. SCHEDULING  After the WBS process, scheduling the work elements is the most important step in planning as it becomes the basis for: Allocating resources Executing work Tracking project performance Finishing on time  Schedules show the timing for work elements and when specific events and project milestone should take place.
  • 6. SCHEDULING Cont’d Events and Milestones: • Events represent the start or finish of something. • Event signifies a moment in time, an instant when something happens. In projects there are two kinds of events: Interface and milestone. • An interface event is the completion of one task and simultaneous start of one or more subsequent tasks. • A milestone event signifies a major project occurrence such as completion of a phase or several critical or difficult tasks, approval of something important, or availability of crucial resources. • It signifies progress, therefore it measures performance
  • 7. Kinds of Schedules There are two kinds of schedules: project schedule and task schedule • A project schedule (or project master schedule) plans and reviews the entire project. • It shows the major project activities without much details about each. • Top managers develop project master schedule. • A task schedule shows the specific activities necessary to complete a work package. • A task schedule is created for people working on a specific task and enables lower level managers or supervisors to focus on the task and not to be distracted by other tasks with which they have no interactions. Task schedules are prepared by functional managers or sub-contractors. NB: Task and project schedules are displayed in many ways including Gantt charts and project networks.
  • 8. PROJECT SCHEDULE: TIME MANAGEMENT The project needs to be completed on time. It then consists of five major processes: 1. Activity definition: specify the activity to be accomplished 2. Activity sequencing: Identify dependencies among activities 3. Duration estimation: Estimate the time needed to complete each activity 4. Schedule development: Analyse activities sequences and durations, and resource availability to develop a realistic and achievable schedule. 5. Schedule control: maintain the project schedule
  • 9. PROJECT SCHEDULE: TIME MANAGEMENT Cont’d Activity sequencing An activity-on-node network may have four types of logical relationships:  Finish-to-start  Finish-to-finish  Start-to-start  Start-to-finish A project critical path is the network path with the longest duration. It determines the shortest total duration of a project. Any delay on critical path will delay the project completion time.
  • 10. CHART AND DIAGRAM USED IN PROJECT SCHEDULING Chart and diagram mostly used in project scheduling:  Gantt chart: simplest to use and display activities plotted as bars or lines on a timeline. It cannot show logical relationships between activities.  PERT (programme evaluation and review techniques): complex Determination of the critical path  EF=ES+AD  LS=LF-AD  A slack is the time that an activity may delay without delaying the project’ s end date.  Slack= LF-EF or LS-ES
  • 11. GANTT CHARTS The simplest and most commonly used scheduling technique is the Gantt chart (or bar chart) developed by Henry Gantt. It was easily adopted in industry and today it is used in a variety of ways. The Gantt chart consists of a horizontal scale divided into time units (days, weeks, months, etc.) and vertical schedule showing project work elements (task, activities, or work packages). The preparation of the Gantt chart comes after a WBS analysis and identification of work packages or other tasks.
  • 12. Gantt chart and Calendar The following must be considered before presenting the Gantt chart: Workdays Rest days Holidays Training Number of calendars
  • 14. Advantages and Disadvantage of Gantt Chart Advantages: • it is often maintained manually, and better for small project, but a burden and disadvantage in large project. • It requires a software for a large project in its creation and update: assuming input data is accurate and updated, computer-generated Gantt charts can be updated frequently to display progress. Disadvantages: • The Gantt chart does not necessary show the relationships among work elements • It does not reveal the effect of a work element falling behind schedule on other work elements as certain work elements must be completed by a specific date for the project to be completed on target.
  • 15. Program Evaluation and Review Techniques: Networks Diagrams • Network methods show interdependencies and what happens to the project when resources change or individual activities are delayed. • A network diagram shows a group of activities or tasks and their logical relationships. e.g.: precedence relationship or dependency. • It describes a project in terms of sequences of activities and events. Two common methods for constructing network diagrams are: activity-on-node (AON) also called precedence programming method (PDM) and activity-on-arrow (AOA)
  • 16. EXERCISE Construct the activity-on-the-node project network diagrams for the project defined below: ACTIVITY PRECEDING (FROM) ACTIVITY SUCCEEDING (TO) ACTIVITY A _ C,E B _ D C A D D B,C F E A,G F F D,E _ G _ E ESTIMATED DURATION (WORK-DAYS) 3 5 3 10 8 14 7
  • 18. Critical path may change Network: assume I is preceding by E and will take 16 to complete CP=G+E+I =7+8+16
  • 19. EXERCISE CONT’D • CRITCAL PATH ACTIVITY DURATION (WORK-DAYS) EARLY START EARLY FINISH= EARLY START+DURATION LATE START= LATE FINISH- DURATION LATE FINISH SLACK= LATE FINISH-EARLY FINISH OR LATE START-EARLY START K 2 0 2 0 2 0 L 2 2 4 2 4 0 M 2 4 6 4 6 0 N 4 0 4 1 5 1 P 1 4 5 5 6 1
  • 20. Build a network for this manufacturing project: Calculate and comment on the critical path ACTIVITY IMMEDIATE PREDECESSORS DURATION (Weeks) A - 3 B - 4 C A,B 3 D A,B 5 E C,D 5 F C 4 G D,E 6 H F,G 3
  • 21. Introduction to Project Resources Resources include (information, human, physical and financial): • Skilled workers • Machinery • Equipment • Working capital These resources dictate whether activities will be completed on time or delayed.
  • 22. Allocation of Resources 1. Identifying and assigning resources to activities so that the project is undertaken using appropriate levels of resources and within an acceptable duration. 2. Usage and availability of resources are the major problem areas for managers. 3. The project resource schedule is important because it serves as time baseline of the project. 4. Resource allocation, smoothing (don’t go beyond resource requirement), levelling and scheduling are techniques used to determine and manage appropriate levels of resources.’
  • 23. Allocation of resources Cont’d Two cases where the project schedule must accommodate resources: resource levelling in time constrained and resource constrained project. • Resource levelling: there is enough resource to complete the project on time, but the amount of resource needed fluctuates drastically. The objective is to balance or level the resource needed throughout the project. • Resource constrained project: there is no enough resource to do multiple activities at once in adjusting the schedule to accommodate the constraint.