Introduction to Earned Value Management
10 Minute “Get Started” Tutorial
Kim Koster
Project Management Evangelist, Unanet
© Unanet
Why Organizations Need Earned Value
“9.9% of every dollar is wasted due to
poor project performance—that’s $99
million for every $1 billion invested”.
(Source: 2018 Pulse of the Profession®)
“Scaled to encompass total global capital
investment, around $1 million is wasted
every 20 seconds—or $2 trillion every year”.
(Source: Brightline Initiative™)
© Unanet
Project Reality
0
20
40
60
80
100
120
Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19
%Complete
Time Line
Plan Reality
4) Result - late and over budget project
1 – It all starts with a plan
2 – A surprise occurs
3 – Recovery Impossible
© Unanet
EVM For Project Success
• EVM encourages detailed realistic plans to be used from the start of a project.
• EVM requires disciplined and integrated planning that will help achieve early
detection of issues to course correct.
• Provides a common set of guidelines for measuring technical, schedule, and cost
performance throughout the life of a project.
• EV provides objective indicators as to performance during the life of a project.
© Unanet
EVM For Project Success
• EVM implementation can be tailored based on complexity of the project.
• EVM and project management aims to have an achievable program plan.
• EV provides an accurate forecast (EAC) of the total funds required for project
completion.
• EVM provides metrics based on actual performance data.
• Provides a signal in time for the project manager to take corrective action.
© Unanet
Benefits of EVM
• All project sizes will benefit
• Measure accomplishments
• Accurately forecast project completion and final cost
• Early warning to delays or overruns
© Unanet
• Provide schedule and cost variances
• Minimize scope creep that can result in overruns
• Improve the control of project performance
• Provides a competitive advantage and delights customers
Benefits of EVM
© Unanet
1 2 3
Tasks “earn”
value as work
is completed.
Earned Value (EV) can then
be compared to actuals and
budget for current status and
to predict the future.
Progress is measured in
dollars and hours, so schedule
and cost performance can be
analyzed in the same units.
EVM is the Answer
Earned Value Management (EVM) is a project management methodology that combines schedule
and cost performance to answer the question, What work was done for the money spent?
© Unanet
The Big 3 – Common for All Types of Projects
Cost
Scope – What is the product (Goods or Services)?
Schedule – When will the products be delivered?
Cost – How much will it cost to deliver the product?
EVM provides a structured process to manage all 3!
© Unanet
Organize
the Work
Define Control
Accounts
Plan
Resources
Scope
Comprehension
Establish an
Org Structure
Schedule
Tasks
Establish a Baseline
(cost and schedule)
EVM Roadmap
It all starts with a
great proposal
© Unanet
It all Starts with a GREAT Proposal
Steps for completing the proposal estimate:
▪ Understand the scope, scope comprehension is the key to accurate estimating
▪ Utilize the project template to clone or populate the project information, the past estimates, and the timelines for the tasks
▪ Establish a work breakdown structure (WBS)
▪ Estimate the resources needed to complete the work
▪ Understand the timing of needed resources
▪ Include all materials, services, and travel required
▪ Time phase the estimates
▪ Ensure that the right skill set is available when you need them
▪ Use To Be Determined (TBDs) if the name of the resource is not yet available
▪ Gain buy-in from the proposal team and the functional departments before submission to the customer
At contract award the proposal is the starting point for the project plans!
© Unanet
Scope Comprehension
IMP
PWS
SOW
The
Project
• Statement of Work (SOW) – description
of what is to be delivered to the
customer.
• Performance Work Statements (PWS) –
summary of the work that needs to be
done for a contract
• Integrated Master Plan – event driven
plan that documents the
accomplishments needed to complete
the scope of work and relates each
accomplishment to a project event.
© Unanet
Establish a Work Breakdown Structure (WBS)
Definition
A WBS is a hierarchical
decomposition of the work to be
accomplished on a project. It is
typically outcome or product based
and should make the management
of scope, schedule, and cost much
easier.
© Unanet
Organizational (Department) Breakdown Structure
Enterprise
Quality Project MgmtEngineering
Mechanical Electrical Inspection Reliability PMO Proj Controls
Responsible Organizations - A functional organization is a common type of
organizational structure in which the organization is divided into smaller groups
based on specialized functional areas, such as Engineering, Quality, or Project
Management.
© Unanet
Engineering
Control
Account
Control
Account
Quality
Control
Account
Control
Account
Control
Account
Control
Account
Project
Management
Control
Account
System
Integration
Control
Account
Management
Casing
Electronics
Monitor
Final
Assembly
Super
Computer
Control
Account
Define Control Accounts
Responsibility Assignment Matrix (RAM) - a graphic representation that reflects the integration of project participants such
as work teams, subcontractors, and internal organizations with individual project Work Breakdown Structure elements to
form Control Accounts (CA).
© Unanet
Schedule Tasks
Task 1
Task 4
Task 3
Task 5
Task 6
Task 7
Task 8
Task 9
Task 10
Task 2
Plan your tasks with start and stop dates
© Unanet
Plan and Manage Your Resources
Look for availability and skills to complete your project
© Unanet
Plan and Manage Your Resources
Resource Management:
1) Skills library
2) Enterprise availability
3) Planning grid
4) Visual notification
5) Available to all
stakeholders
© Unanet
Create a Cost Plan (Budget)
Characteristics of a good budget:
1. All scope is included
2. Time-phased
3. Meets the contract cost and
schedule
4. Includes all the resources
needed
5. Aligns with the WBS
6. Basis for comparison to
actuals and EV
https://www.unanet.com/blog/8-tips-budgeting-project-based-organizations
© Unanet
Execute the Project
Execution:
1. Time charged to tasks
2. Status % complete on
each task
3. Explain schedule and
cost variances
4. Update to go forecast
5. Look at metrics for
current issues and
potential future issues
© Unanet
GET S.M.A.R.T.
Specific - Target a specific area for improvement
Measure - quantify or at least suggest an indicator of progress
Attainable - specify who will do it
Realistic - state the results that can be achieved realistically,
given available resources.
Time-frame – when can the results be achieved?
Are Your KPIs SMART?
© Unanet
Additional Tips for Picking the Right KPIs
• Very clear purpose (what matters most)
• Common business language
• Align with your current processes if possible
• Holistic approach (think through the unintended consequences)
• Drive the desired behavior (Encourage and reward)
• Define tolerances (red, yellow, green, blue)
• Have a mechanism to display the KPIs to all stakeholders
(dashboards)
I – Important
P – Potential Improvement
A – Authority
IPA Rule
© Unanet
Define the KPIs That Help Drive Your Strategy
Project Enterprise/Portfolio
- On Schedule and Budget - Compounded Annual Growth
(CAGR)
- Profitability - Profitability
- Revenue - Revenue
- Labor Utilization - Booking
- Skillset Usage - Backlog
- Spend Variance - Bid to Win
- % Spent - Pipeline Snapshot
- Estimate to Complete (ETC) - Annual Billable Utilization
- Cost per Person - Rate Analysis
- Bill rate - Targets by Region, Customer,
Portfolio, etc.
© Unanet
EV Metrics –
help manage
current
status and
gives you a
window into
the future!
© Unanet
Myth Reality
EVM is only for huge government
projects
EVM is a basic project mgmt discipline –
scope, schedule, and cost regardless of
project size
EVM is expensive to implement
All of the base data is in the system
already…merely status % complete
EVM is looking only in the rearview
mirror
EVM provides metrics based on current
performance to predict the future
EVM is old and outdated
Good project management practices
never go out of date
EVM Myths
© Unanet
If you are ready to jump
into the Earned Value Pond
and take control of your
projects please contact us
at:
Unanet.com

Más contenido relacionado

La actualidad más candente

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVAAhmed Bamasdoos
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)Unanet
 
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...Association for Project Management
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)Joshua Render
 
A review of advanced linear repetitive scheduling methods and techniques
A review of advanced linear repetitive scheduling methods and techniquesA review of advanced linear repetitive scheduling methods and techniques
A review of advanced linear repetitive scheduling methods and techniquesAsadullah Malik
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value AnalysisDavidMcLachlan1
 

La actualidad más candente (20)

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
Why Do Projects Fail? Getting Ready for EIA 748 – Earned Value Management (EVM)
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
The Real Reason That Projects Fail and How to Fix it - An Introduction to Cri...
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Earned value
Earned valueEarned value
Earned value
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Methodologies of Project Progress Measurement
Methodologies of Project Progress MeasurementMethodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
 
Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
Earned value
Earned value Earned value
Earned value
 
A review of advanced linear repetitive scheduling methods and techniques
A review of advanced linear repetitive scheduling methods and techniquesA review of advanced linear repetitive scheduling methods and techniques
A review of advanced linear repetitive scheduling methods and techniques
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 

Similar a Introduction to Earned Value Management

The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of ProjectsUnanet
 
PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesRicardo Leite
 
Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...Unanet
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Contract Administrator Aew_Sanmai_RV10.2.16
Contract Administrator Aew_Sanmai_RV10.2.16Contract Administrator Aew_Sanmai_RV10.2.16
Contract Administrator Aew_Sanmai_RV10.2.16Aew Sanmai
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1ghulam MUSTAFA
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
8 Signs You’ve Outgrown Quickbooks!
8 Signs You’ve Outgrown Quickbooks!8 Signs You’ve Outgrown Quickbooks!
8 Signs You’ve Outgrown Quickbooks!Unanet
 
ecosys-brochure-digital
ecosys-brochure-digitalecosys-brochure-digital
ecosys-brochure-digitalZoe MacDonald
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxMariaNambahu
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 

Similar a Introduction to Earned Value Management (20)

The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of Projects
 
PMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best PracticesPMBok Processes with CCPM Best Practices
PMBok Processes with CCPM Best Practices
 
Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Contract Administrator Aew_Sanmai_RV10.2.16
Contract Administrator Aew_Sanmai_RV10.2.16Contract Administrator Aew_Sanmai_RV10.2.16
Contract Administrator Aew_Sanmai_RV10.2.16
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
8 Signs You’ve Outgrown Quickbooks!
8 Signs You’ve Outgrown Quickbooks!8 Signs You’ve Outgrown Quickbooks!
8 Signs You’ve Outgrown Quickbooks!
 
ecosys-brochure-digital
ecosys-brochure-digitalecosys-brochure-digital
ecosys-brochure-digital
 
Business Case _ PM.pptx
Business Case _ PM.pptxBusiness Case _ PM.pptx
Business Case _ PM.pptx
 
Quantim - Best Project Management Software
Quantim - Best Project Management SoftwareQuantim - Best Project Management Software
Quantim - Best Project Management Software
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
T24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning PresentationT24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning Presentation
 

Más de Unanet

Huntsville GovCon Growth Summit 2020 - Summit 7 - Cybersecurity Maturity Mode...
Huntsville GovCon Growth Summit 2020 - Summit 7 - Cybersecurity Maturity Mode...Huntsville GovCon Growth Summit 2020 - Summit 7 - Cybersecurity Maturity Mode...
Huntsville GovCon Growth Summit 2020 - Summit 7 - Cybersecurity Maturity Mode...Unanet
 
What is Going on in the GovCon Market? Benchmarks and Trends for Government C...
What is Going on in the GovCon Market? Benchmarks and Trends for Government C...What is Going on in the GovCon Market? Benchmarks and Trends for Government C...
What is Going on in the GovCon Market? Benchmarks and Trends for Government C...Unanet
 
The CMMC Has Arrived. Are You Ready?
The CMMC Has Arrived. Are You Ready?The CMMC Has Arrived. Are You Ready?
The CMMC Has Arrived. Are You Ready?Unanet
 
Project Forecasting from the Perspective of an EVMA and EIA-748
Project Forecasting from the Perspective of an EVMA and EIA-748Project Forecasting from the Perspective of an EVMA and EIA-748
Project Forecasting from the Perspective of an EVMA and EIA-748Unanet
 
DCAA Compliant Time & Expense Reporting Automation
DCAA Compliant Time & Expense Reporting AutomationDCAA Compliant Time & Expense Reporting Automation
DCAA Compliant Time & Expense Reporting AutomationUnanet
 
Control the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastControl the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastUnanet
 
The Project Life Cycle Through the Lens of a Project Based ERP
The Project Life Cycle Through the Lens of a Project Based ERPThe Project Life Cycle Through the Lens of a Project Based ERP
The Project Life Cycle Through the Lens of a Project Based ERPUnanet
 
Control the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastControl the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastUnanet
 
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)Unanet
 
Control the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastControl the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastUnanet
 
The Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionThe Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionUnanet
 
Indirect Rates - What Strategy is Right for your Organization
Indirect Rates - What Strategy is Right for your OrganizationIndirect Rates - What Strategy is Right for your Organization
Indirect Rates - What Strategy is Right for your OrganizationUnanet
 
Project Billing and Revenue Recognition
Project Billing and Revenue RecognitionProject Billing and Revenue Recognition
Project Billing and Revenue RecognitionUnanet
 
Top Reasons to Make Managing Your Pipeline a Priority
Top Reasons to Make Managing Your Pipeline a PriorityTop Reasons to Make Managing Your Pipeline a Priority
Top Reasons to Make Managing Your Pipeline a PriorityUnanet
 
Top Signs You May Have Outgrown Your Legacy ERP System
Top Signs You May Have Outgrown Your Legacy ERP SystemTop Signs You May Have Outgrown Your Legacy ERP System
Top Signs You May Have Outgrown Your Legacy ERP SystemUnanet
 
Government Contract Foundations – Understanding Indirect Rates
Government Contract Foundations – Understanding Indirect RatesGovernment Contract Foundations – Understanding Indirect Rates
Government Contract Foundations – Understanding Indirect RatesUnanet
 
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last CallCybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last CallUnanet
 
Improve Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type ContractsImprove Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type ContractsUnanet
 
NIST Cybersecurity Requirements for Government Contractors
NIST Cybersecurity Requirements for Government ContractorsNIST Cybersecurity Requirements for Government Contractors
NIST Cybersecurity Requirements for Government ContractorsUnanet
 
DCAA Audits Without Tears
DCAA Audits Without TearsDCAA Audits Without Tears
DCAA Audits Without TearsUnanet
 

Más de Unanet (20)

Huntsville GovCon Growth Summit 2020 - Summit 7 - Cybersecurity Maturity Mode...
Huntsville GovCon Growth Summit 2020 - Summit 7 - Cybersecurity Maturity Mode...Huntsville GovCon Growth Summit 2020 - Summit 7 - Cybersecurity Maturity Mode...
Huntsville GovCon Growth Summit 2020 - Summit 7 - Cybersecurity Maturity Mode...
 
What is Going on in the GovCon Market? Benchmarks and Trends for Government C...
What is Going on in the GovCon Market? Benchmarks and Trends for Government C...What is Going on in the GovCon Market? Benchmarks and Trends for Government C...
What is Going on in the GovCon Market? Benchmarks and Trends for Government C...
 
The CMMC Has Arrived. Are You Ready?
The CMMC Has Arrived. Are You Ready?The CMMC Has Arrived. Are You Ready?
The CMMC Has Arrived. Are You Ready?
 
Project Forecasting from the Perspective of an EVMA and EIA-748
Project Forecasting from the Perspective of an EVMA and EIA-748Project Forecasting from the Perspective of an EVMA and EIA-748
Project Forecasting from the Perspective of an EVMA and EIA-748
 
DCAA Compliant Time & Expense Reporting Automation
DCAA Compliant Time & Expense Reporting AutomationDCAA Compliant Time & Expense Reporting Automation
DCAA Compliant Time & Expense Reporting Automation
 
Control the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastControl the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & Forecast
 
The Project Life Cycle Through the Lens of a Project Based ERP
The Project Life Cycle Through the Lens of a Project Based ERPThe Project Life Cycle Through the Lens of a Project Based ERP
The Project Life Cycle Through the Lens of a Project Based ERP
 
Control the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastControl the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & Forecast
 
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
Win Your Next Defense Opportunity - Seaport Next Generation (NxG)
 
Control the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & ForecastControl the Future - Budget, Plan & Forecast
Control the Future - Budget, Plan & Forecast
 
The Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionThe Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost Submission
 
Indirect Rates - What Strategy is Right for your Organization
Indirect Rates - What Strategy is Right for your OrganizationIndirect Rates - What Strategy is Right for your Organization
Indirect Rates - What Strategy is Right for your Organization
 
Project Billing and Revenue Recognition
Project Billing and Revenue RecognitionProject Billing and Revenue Recognition
Project Billing and Revenue Recognition
 
Top Reasons to Make Managing Your Pipeline a Priority
Top Reasons to Make Managing Your Pipeline a PriorityTop Reasons to Make Managing Your Pipeline a Priority
Top Reasons to Make Managing Your Pipeline a Priority
 
Top Signs You May Have Outgrown Your Legacy ERP System
Top Signs You May Have Outgrown Your Legacy ERP SystemTop Signs You May Have Outgrown Your Legacy ERP System
Top Signs You May Have Outgrown Your Legacy ERP System
 
Government Contract Foundations – Understanding Indirect Rates
Government Contract Foundations – Understanding Indirect RatesGovernment Contract Foundations – Understanding Indirect Rates
Government Contract Foundations – Understanding Indirect Rates
 
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last CallCybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
Cybersecurity for GovCons - DFARS 252.204-7012 Latest Updates and Last Call
 
Improve Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type ContractsImprove Your Outcomes on Cost Type Contracts
Improve Your Outcomes on Cost Type Contracts
 
NIST Cybersecurity Requirements for Government Contractors
NIST Cybersecurity Requirements for Government ContractorsNIST Cybersecurity Requirements for Government Contractors
NIST Cybersecurity Requirements for Government Contractors
 
DCAA Audits Without Tears
DCAA Audits Without TearsDCAA Audits Without Tears
DCAA Audits Without Tears
 

Último

WSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With SimplicityWSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With SimplicityWSO2
 
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...masabamasaba
 
Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...
Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...
Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...SelfMade bd
 
WSO2Con204 - Hard Rock Presentation - Keynote
WSO2Con204 - Hard Rock Presentation - KeynoteWSO2Con204 - Hard Rock Presentation - Keynote
WSO2Con204 - Hard Rock Presentation - KeynoteWSO2
 
Direct Style Effect Systems - The Print[A] Example - A Comprehension Aid
Direct Style Effect Systems -The Print[A] Example- A Comprehension AidDirect Style Effect Systems -The Print[A] Example- A Comprehension Aid
Direct Style Effect Systems - The Print[A] Example - A Comprehension AidPhilip Schwarz
 
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...masabamasaba
 
WSO2CON 2024 - How to Run a Security Program
WSO2CON 2024 - How to Run a Security ProgramWSO2CON 2024 - How to Run a Security Program
WSO2CON 2024 - How to Run a Security ProgramWSO2
 
WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...
WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...
WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...WSO2
 
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park %in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park masabamasaba
 
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open SourceWSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open SourceWSO2
 
%+27788225528 love spells in new york Psychic Readings, Attraction spells,Bri...
%+27788225528 love spells in new york Psychic Readings, Attraction spells,Bri...%+27788225528 love spells in new york Psychic Readings, Attraction spells,Bri...
%+27788225528 love spells in new york Psychic Readings, Attraction spells,Bri...masabamasaba
 
%in Benoni+277-882-255-28 abortion pills for sale in Benoni
%in Benoni+277-882-255-28 abortion pills for sale in Benoni%in Benoni+277-882-255-28 abortion pills for sale in Benoni
%in Benoni+277-882-255-28 abortion pills for sale in Benonimasabamasaba
 
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...WSO2
 
AI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplateAI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplatePresentation.STUDIO
 
%in Soweto+277-882-255-28 abortion pills for sale in soweto
%in Soweto+277-882-255-28 abortion pills for sale in soweto%in Soweto+277-882-255-28 abortion pills for sale in soweto
%in Soweto+277-882-255-28 abortion pills for sale in sowetomasabamasaba
 
WSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaSWSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaSWSO2
 
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...WSO2
 
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital TransformationWSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital TransformationWSO2
 
%in tembisa+277-882-255-28 abortion pills for sale in tembisa
%in tembisa+277-882-255-28 abortion pills for sale in tembisa%in tembisa+277-882-255-28 abortion pills for sale in tembisa
%in tembisa+277-882-255-28 abortion pills for sale in tembisamasabamasaba
 
%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrand%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrandmasabamasaba
 

Último (20)

WSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With SimplicityWSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
WSO2Con2024 - Enabling Transactional System's Exponential Growth With Simplicity
 
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
 
Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...
Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...
Crypto Cloud Review - How To Earn Up To $500 Per DAY Of Bitcoin 100% On AutoP...
 
WSO2Con204 - Hard Rock Presentation - Keynote
WSO2Con204 - Hard Rock Presentation - KeynoteWSO2Con204 - Hard Rock Presentation - Keynote
WSO2Con204 - Hard Rock Presentation - Keynote
 
Direct Style Effect Systems - The Print[A] Example - A Comprehension Aid
Direct Style Effect Systems -The Print[A] Example- A Comprehension AidDirect Style Effect Systems -The Print[A] Example- A Comprehension Aid
Direct Style Effect Systems - The Print[A] Example - A Comprehension Aid
 
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
%+27788225528 love spells in Toronto Psychic Readings, Attraction spells,Brin...
 
WSO2CON 2024 - How to Run a Security Program
WSO2CON 2024 - How to Run a Security ProgramWSO2CON 2024 - How to Run a Security Program
WSO2CON 2024 - How to Run a Security Program
 
WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...
WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...
WSO2CON 2024 - API Management Usage at La Poste and Its Impact on Business an...
 
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park %in ivory park+277-882-255-28 abortion pills for sale in ivory park
%in ivory park+277-882-255-28 abortion pills for sale in ivory park
 
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open SourceWSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
WSO2CON 2024 - Freedom First—Unleashing Developer Potential with Open Source
 
%+27788225528 love spells in new york Psychic Readings, Attraction spells,Bri...
%+27788225528 love spells in new york Psychic Readings, Attraction spells,Bri...%+27788225528 love spells in new york Psychic Readings, Attraction spells,Bri...
%+27788225528 love spells in new york Psychic Readings, Attraction spells,Bri...
 
%in Benoni+277-882-255-28 abortion pills for sale in Benoni
%in Benoni+277-882-255-28 abortion pills for sale in Benoni%in Benoni+277-882-255-28 abortion pills for sale in Benoni
%in Benoni+277-882-255-28 abortion pills for sale in Benoni
 
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
 
AI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplateAI & Machine Learning Presentation Template
AI & Machine Learning Presentation Template
 
%in Soweto+277-882-255-28 abortion pills for sale in soweto
%in Soweto+277-882-255-28 abortion pills for sale in soweto%in Soweto+277-882-255-28 abortion pills for sale in soweto
%in Soweto+277-882-255-28 abortion pills for sale in soweto
 
WSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaSWSO2CON 2024 Slides - Open Source to SaaS
WSO2CON 2024 Slides - Open Source to SaaS
 
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
 
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital TransformationWSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
 
%in tembisa+277-882-255-28 abortion pills for sale in tembisa
%in tembisa+277-882-255-28 abortion pills for sale in tembisa%in tembisa+277-882-255-28 abortion pills for sale in tembisa
%in tembisa+277-882-255-28 abortion pills for sale in tembisa
 
%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrand%in Midrand+277-882-255-28 abortion pills for sale in midrand
%in Midrand+277-882-255-28 abortion pills for sale in midrand
 

Introduction to Earned Value Management

  • 1. © Unanet Introduction to Earned Value Management 10 Minute “Get Started” Tutorial Kim Koster Project Management Evangelist, Unanet
  • 2. © Unanet Why Organizations Need Earned Value “9.9% of every dollar is wasted due to poor project performance—that’s $99 million for every $1 billion invested”. (Source: 2018 Pulse of the Profession®) “Scaled to encompass total global capital investment, around $1 million is wasted every 20 seconds—or $2 trillion every year”. (Source: Brightline Initiative™)
  • 3. © Unanet Project Reality 0 20 40 60 80 100 120 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 %Complete Time Line Plan Reality 4) Result - late and over budget project 1 – It all starts with a plan 2 – A surprise occurs 3 – Recovery Impossible
  • 4. © Unanet EVM For Project Success • EVM encourages detailed realistic plans to be used from the start of a project. • EVM requires disciplined and integrated planning that will help achieve early detection of issues to course correct. • Provides a common set of guidelines for measuring technical, schedule, and cost performance throughout the life of a project. • EV provides objective indicators as to performance during the life of a project.
  • 5. © Unanet EVM For Project Success • EVM implementation can be tailored based on complexity of the project. • EVM and project management aims to have an achievable program plan. • EV provides an accurate forecast (EAC) of the total funds required for project completion. • EVM provides metrics based on actual performance data. • Provides a signal in time for the project manager to take corrective action.
  • 6. © Unanet Benefits of EVM • All project sizes will benefit • Measure accomplishments • Accurately forecast project completion and final cost • Early warning to delays or overruns
  • 7. © Unanet • Provide schedule and cost variances • Minimize scope creep that can result in overruns • Improve the control of project performance • Provides a competitive advantage and delights customers Benefits of EVM
  • 8. © Unanet 1 2 3 Tasks “earn” value as work is completed. Earned Value (EV) can then be compared to actuals and budget for current status and to predict the future. Progress is measured in dollars and hours, so schedule and cost performance can be analyzed in the same units. EVM is the Answer Earned Value Management (EVM) is a project management methodology that combines schedule and cost performance to answer the question, What work was done for the money spent?
  • 9. © Unanet The Big 3 – Common for All Types of Projects Cost Scope – What is the product (Goods or Services)? Schedule – When will the products be delivered? Cost – How much will it cost to deliver the product? EVM provides a structured process to manage all 3!
  • 10. © Unanet Organize the Work Define Control Accounts Plan Resources Scope Comprehension Establish an Org Structure Schedule Tasks Establish a Baseline (cost and schedule) EVM Roadmap It all starts with a great proposal
  • 11. © Unanet It all Starts with a GREAT Proposal Steps for completing the proposal estimate: ▪ Understand the scope, scope comprehension is the key to accurate estimating ▪ Utilize the project template to clone or populate the project information, the past estimates, and the timelines for the tasks ▪ Establish a work breakdown structure (WBS) ▪ Estimate the resources needed to complete the work ▪ Understand the timing of needed resources ▪ Include all materials, services, and travel required ▪ Time phase the estimates ▪ Ensure that the right skill set is available when you need them ▪ Use To Be Determined (TBDs) if the name of the resource is not yet available ▪ Gain buy-in from the proposal team and the functional departments before submission to the customer At contract award the proposal is the starting point for the project plans!
  • 12. © Unanet Scope Comprehension IMP PWS SOW The Project • Statement of Work (SOW) – description of what is to be delivered to the customer. • Performance Work Statements (PWS) – summary of the work that needs to be done for a contract • Integrated Master Plan – event driven plan that documents the accomplishments needed to complete the scope of work and relates each accomplishment to a project event.
  • 13. © Unanet Establish a Work Breakdown Structure (WBS) Definition A WBS is a hierarchical decomposition of the work to be accomplished on a project. It is typically outcome or product based and should make the management of scope, schedule, and cost much easier.
  • 14. © Unanet Organizational (Department) Breakdown Structure Enterprise Quality Project MgmtEngineering Mechanical Electrical Inspection Reliability PMO Proj Controls Responsible Organizations - A functional organization is a common type of organizational structure in which the organization is divided into smaller groups based on specialized functional areas, such as Engineering, Quality, or Project Management.
  • 15. © Unanet Engineering Control Account Control Account Quality Control Account Control Account Control Account Control Account Project Management Control Account System Integration Control Account Management Casing Electronics Monitor Final Assembly Super Computer Control Account Define Control Accounts Responsibility Assignment Matrix (RAM) - a graphic representation that reflects the integration of project participants such as work teams, subcontractors, and internal organizations with individual project Work Breakdown Structure elements to form Control Accounts (CA).
  • 16. © Unanet Schedule Tasks Task 1 Task 4 Task 3 Task 5 Task 6 Task 7 Task 8 Task 9 Task 10 Task 2 Plan your tasks with start and stop dates
  • 17. © Unanet Plan and Manage Your Resources Look for availability and skills to complete your project
  • 18. © Unanet Plan and Manage Your Resources Resource Management: 1) Skills library 2) Enterprise availability 3) Planning grid 4) Visual notification 5) Available to all stakeholders
  • 19. © Unanet Create a Cost Plan (Budget) Characteristics of a good budget: 1. All scope is included 2. Time-phased 3. Meets the contract cost and schedule 4. Includes all the resources needed 5. Aligns with the WBS 6. Basis for comparison to actuals and EV https://www.unanet.com/blog/8-tips-budgeting-project-based-organizations
  • 20. © Unanet Execute the Project Execution: 1. Time charged to tasks 2. Status % complete on each task 3. Explain schedule and cost variances 4. Update to go forecast 5. Look at metrics for current issues and potential future issues
  • 21. © Unanet GET S.M.A.R.T. Specific - Target a specific area for improvement Measure - quantify or at least suggest an indicator of progress Attainable - specify who will do it Realistic - state the results that can be achieved realistically, given available resources. Time-frame – when can the results be achieved? Are Your KPIs SMART?
  • 22. © Unanet Additional Tips for Picking the Right KPIs • Very clear purpose (what matters most) • Common business language • Align with your current processes if possible • Holistic approach (think through the unintended consequences) • Drive the desired behavior (Encourage and reward) • Define tolerances (red, yellow, green, blue) • Have a mechanism to display the KPIs to all stakeholders (dashboards) I – Important P – Potential Improvement A – Authority IPA Rule
  • 23. © Unanet Define the KPIs That Help Drive Your Strategy Project Enterprise/Portfolio - On Schedule and Budget - Compounded Annual Growth (CAGR) - Profitability - Profitability - Revenue - Revenue - Labor Utilization - Booking - Skillset Usage - Backlog - Spend Variance - Bid to Win - % Spent - Pipeline Snapshot - Estimate to Complete (ETC) - Annual Billable Utilization - Cost per Person - Rate Analysis - Bill rate - Targets by Region, Customer, Portfolio, etc.
  • 24. © Unanet EV Metrics – help manage current status and gives you a window into the future!
  • 25. © Unanet Myth Reality EVM is only for huge government projects EVM is a basic project mgmt discipline – scope, schedule, and cost regardless of project size EVM is expensive to implement All of the base data is in the system already…merely status % complete EVM is looking only in the rearview mirror EVM provides metrics based on current performance to predict the future EVM is old and outdated Good project management practices never go out of date EVM Myths
  • 26. © Unanet If you are ready to jump into the Earned Value Pond and take control of your projects please contact us at: Unanet.com