SlideShare una empresa de Scribd logo
1 de 27
Steps of Site Identification
&
Project Pre-Feasibility
 Identification of site
 Solar insolation and shadow assessment
 Geological due diligence
 Social audit of the site
 Power Evacuation Feasibility and
accessibility
 Technology and supplier selection
 Financial Pre Feasibility
 Land shall be plain and Red soil with
proper rain water drainage provision .
 Near to 33KV SS
 Motor able road
 Following land is not suitable :
 Black Cotton Soil
 Site located near mountain ,Larger Water
Bodies & Shadow over land .
• No of sunny days / sunny hours
• No of Cloudy days & Rainy days
• Relative Humidity & Temperature @ Site
• Direction of Sun Rays falling on the Panel
• Following land is not suitable :
• More dusty Area
• Site located near mountain ,Larger Water
Bodies & Shadow over land .
• As land orientation should preferably be flat,
considerations while identifying site must
include;
• Degree of levelization,
• A drainage system,
• Dust percentage in air
• Land/soil capacity to hold structures.
• Soil Testing Experts/ Geotechnical Engineers
having understanding of soil and land
mechanics.
Review issues related to:-
 Security of the project and the systems,
 Possible threats in terms of security of
employees,
 Availability of labor & local support for the
project.
Review issues related to:-
• Availability of substation for power evacuation
(Nearest- 11/33 KV )
• Availability / provision for Additional Bay @ SS
• Evacuation capacity of the sub-station- to be
checked with distribution  utility.
• Feasibility study of Power Evacuation line of 33
KV from site to SS ( Pole compensation cost)
• Grid to be constructed as per IEGC .
Selection of Solar PV Technology based on -
• Past performance record, Available global
radiation(GHI), Climatic conditions- Specially
temperature and Wind velocity, Cost of technology
(capital and O&M), Projected conversion
efficiency/’s and Consequent projected CUF’s, Risks
associated with the technologies
• Solar Panels – Type
• Mono crystalline , Poly crystalline or Thin film
technology .
• Battery Banks , inverters , PV – DC Cable
connectors , etc .
• Use of specific PV DC cables
• Land & Development Cost
• Construction Cost
• Engineering Cost
• Equipment Cost
• Operational Cost
• Revenue
• Benefits/Incentives
• Funds Availability
• Cash Flow
• Returns
 Radiation at Site
 Losses in PV System
(Invertors ,Cabling, Soiling (Dust), Module
Mismatch , MPPT losses & Transformer)
 Temperature and Climatic condition
 Design Parameters of the Solar Plant
 Inverter efficiency
 Module degradation due to ageing .
 Grid Availability
 Direct Method –
Pyrheliometer & Pyronometer instruments used
@ site to estimate the Solar Radiation
 InDirect method –
Satelite data , NASA ,
Indian Metrological Department ,
 World Radition Data Centre ( WRDC) &
 RET Screen Canadian software - Free of
cost
 Reflection losses due to Sun Path, - Solar rays should
fall perpendicular to panel for higher efficiency – But
actually it may have wider incidence angle due to sun
path – 1 % loss expected .
 Soiling losses due to dust , SNOW etc – 1 % loss
 Mis Match effect losses- due to interconnection of Solar
Panels in series & parallel – Good quality panel to be
procured .
 MPPT ( Max Power Point Tracking) Losses - due to
Changes in direction of sun , changes in solar
insolations level with varying Temp
 Inverter Efficiency depends upon Conversion of DC to
AC – 96 to 98.5% .
 Cabling losses due to improper joints etc .
 Transformer losses.
 Proper selection of Modules
 Optimum angle of tilt
 Minimisation of Ohmic losess with proper
selection of conductors .
 Selection of Efficient Transformers & Inverters
Energy output depends upon
- Temperature of the module decrease the output
- Intensity of lights
- Sun lights reflection on the surface but not on
the modules
- Defuse light - Changes in Sun spectrum in the
day/ year , due to clouds, smoky, fogs etc
- Materials used in Modules – Amorphous Silicon
performance changes with aging
 Mounting position of modules & Air circluation
 Inclination Angle - Tilting position of modules –
Fixed type- Non Tracking system
 Performance changes with aging .
 Temp Co Efficient –Changes in power out put
with Different Temp
 Typical value of Temp co efficient
Y( P mpp) Crystaline Modules -0.4 to 0.45 % K
Y( P mpp) Amorphous Modules -0.2 to 0.23 % K
Y( P mpp) CdTe Modules -0.24 to 0.25 % K
Thin film modules can give higher performance
@ Elevated Temp compare to Crystaline silicon.
 Module degradation occurs to Sun light
 - Slow Breakdown of Module encapsulant
( Ethelene Vinyl Acetate EVA & Back sheet
Polyvinyl Flouride Films )
 Moisture ingress leads to corrosion formation on
Cable connectors and decreased voltage outputs
 UV rays breaks down the EVA layer between
Module Front Glass and silicon cells – Silicon cells
outputs gets affected .
 Discoloration of Panels .
 Degradation of silicon cells – Metastable Dangling
bonds – 15 to 20 % reduction in efficiency .
Sl No Description Life in
Years
Remarks
1 Module 30
2 Inverter 15 Small plant
30 10% Parts replacement 2 Every 10
years
3 Structure 30 Roof Top
30 to 60 Ground mounted fixed in metal
4 Cabling 30
After 10 years – 90 % & After 20 Years -80 % efficiency noticed in modules
First 03 years of Operations No reduction in designed power output and then
Yearly reduction of power output is 0.5 %
 Software available –
RETScreen (Free of cost), PVSyst23, Homer
 Following analysis can be done :-
-Energy Analysis
-Emission Analysis
-Cost Analysis
-Financial Analysis
-Sensitivity / risk Analysis
 Performance of CUF depends upon :-
 Solar Radiation
 Temperature
 Air velocity
 Module type and materials used
 Quality of Module & cable joints etc
 Efficiency of Inverter &Transformer
 Thin Film Modules most suitable higher ambient
temp area . ( CUF around 19 to 20%)
 To compensate degradation loss after 3 years add
5 KW module / MW in every year.
Sl No Description Cost In Crore % of Cost
1 Solar PV Modules 4.51 58.2687339
2 Solar Invertors 1.166 15.0645995
3 Transformers 0.294 3.79844961
4 Protective devices 0.12 1.5503876
5 Wire/cables 0.1 1.29198966
6 SCADA/RMS 0.1 1.29198966
7 Project Execution & Comm 0.2 2.58397933
8 Construction cost 0.4 5.16795866
9
Grid Evacuation
@ 15 L /Km x 5 KM 0.75 9.68992248
10 Other official works 0.1 1.29198966
7.74 100
Loan amount @ 70 % of project cost 5.418 crore
Annual EMI (Including Principle + Interest @12PA= Rs
8,76,105 Lakhs / Month)
1,05,13,320 Crore
Annual OMS Charge & Staff Pay + Admin cost 20,00,000 Lakhs
Total Expense / year 1,25,00,000 Crore
Revenue Details
Net Energy Produced in MWH 1655 MWH
PLF ( 1x24x365= 8760 MWH) / Year 18.8926%
PPA @ 7.50 KWH Cost 1,24,12,500 crore
Revenune due to sale of REC @12000 /MWH 1,97,59,180 crore
Net Cash Flow ( NCF) = ( PPA + REC cost ) 3,22,72,500 Crore
Net Balance Amount = ( NCF- Net Expense / Year) 1,97,59,180 Crore
Break even
7.74 / 1.97 crore
( Total Project cost /Net Balance amount/ year)
3.92 years
Net Amount at the end of the 7 th year 13,83,14,260 crore
Net Amount at the end of the 10th year 19,75,91,800 Crore
Solar Power Plant cash flow model
Solar Power Plant cash flow model
Solar Power Plant cash flow model

Más contenido relacionado

La actualidad más candente

Better efficiency of eletrostatic precipitator
Better efficiency of eletrostatic precipitatorBetter efficiency of eletrostatic precipitator
Better efficiency of eletrostatic precipitatorIRS srl
 
Case Study of Energy Audit
Case Study of Energy Audit Case Study of Energy Audit
Case Study of Energy Audit Darshan Vithani
 
Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptD.Pawan Kumar
 
Fbc fluidized bed combustion
Fbc fluidized bed combustionFbc fluidized bed combustion
Fbc fluidized bed combustionGulab Siraskar
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power PlantMd. Rimon Mia
 
An introduction to Energy Saving Opportunities in Pumping Systems
An introduction to Energy Saving Opportunities in Pumping Systems An introduction to Energy Saving Opportunities in Pumping Systems
An introduction to Energy Saving Opportunities in Pumping Systems Leonardo ENERGY
 
Tips for energy conservation for industries
Tips for energy conservation for industriesTips for energy conservation for industries
Tips for energy conservation for industriesKamlesh Hariyani
 
Wind farm grid issues
Wind farm grid issuesWind farm grid issues
Wind farm grid issuesRohil Kumar
 
Solar energy opportunities in Uzbekistan
Solar energy opportunities in UzbekistanSolar energy opportunities in Uzbekistan
Solar energy opportunities in UzbekistanMurod Khusanov
 
Energy management & audit
Energy management & auditEnergy management & audit
Energy management & auditPINAKI ROY
 
Direct energy conversion v
Direct energy conversion vDirect energy conversion v
Direct energy conversion vSARAN RAJ I
 
Photovoltaic modules & sizing of pv system
Photovoltaic modules & sizing of pv systemPhotovoltaic modules & sizing of pv system
Photovoltaic modules & sizing of pv systemEr Madhuri More
 
Ppt on design of solar photovoltaic generation for residential building
Ppt on design of solar photovoltaic generation for residential buildingPpt on design of solar photovoltaic generation for residential building
Ppt on design of solar photovoltaic generation for residential buildingSiya Agarwal
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystsolpowerpeople
 
Photovoltaic Systems: System Design Tools
Photovoltaic Systems: System Design ToolsPhotovoltaic Systems: System Design Tools
Photovoltaic Systems: System Design ToolsGavin Harper
 
Solar Radiation Geometry
Solar Radiation GeometrySolar Radiation Geometry
Solar Radiation GeometryVanita Thakkar
 
Project Proposal For Solar Panel Installation PowerPoint Presentation Slides
Project Proposal For Solar Panel Installation PowerPoint Presentation SlidesProject Proposal For Solar Panel Installation PowerPoint Presentation Slides
Project Proposal For Solar Panel Installation PowerPoint Presentation SlidesSlideTeam
 
Energy Conservation Act 2001
Energy Conservation Act 2001Energy Conservation Act 2001
Energy Conservation Act 2001Darshan Vithani
 
Efficiency and Heat Rate in cogenerative power system
Efficiency and Heat Rate in cogenerative power systemEfficiency and Heat Rate in cogenerative power system
Efficiency and Heat Rate in cogenerative power systemHashim Hasnain Hadi
 

La actualidad más candente (20)

Better efficiency of eletrostatic precipitator
Better efficiency of eletrostatic precipitatorBetter efficiency of eletrostatic precipitator
Better efficiency of eletrostatic precipitator
 
Case Study of Energy Audit
Case Study of Energy Audit Case Study of Energy Audit
Case Study of Energy Audit
 
Jakson_report_Final
Jakson_report_FinalJakson_report_Final
Jakson_report_Final
 
Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans ppt
 
Fbc fluidized bed combustion
Fbc fluidized bed combustionFbc fluidized bed combustion
Fbc fluidized bed combustion
 
Combined Cycle Power Plant
Combined Cycle Power PlantCombined Cycle Power Plant
Combined Cycle Power Plant
 
An introduction to Energy Saving Opportunities in Pumping Systems
An introduction to Energy Saving Opportunities in Pumping Systems An introduction to Energy Saving Opportunities in Pumping Systems
An introduction to Energy Saving Opportunities in Pumping Systems
 
Tips for energy conservation for industries
Tips for energy conservation for industriesTips for energy conservation for industries
Tips for energy conservation for industries
 
Wind farm grid issues
Wind farm grid issuesWind farm grid issues
Wind farm grid issues
 
Solar energy opportunities in Uzbekistan
Solar energy opportunities in UzbekistanSolar energy opportunities in Uzbekistan
Solar energy opportunities in Uzbekistan
 
Energy management & audit
Energy management & auditEnergy management & audit
Energy management & audit
 
Direct energy conversion v
Direct energy conversion vDirect energy conversion v
Direct energy conversion v
 
Photovoltaic modules & sizing of pv system
Photovoltaic modules & sizing of pv systemPhotovoltaic modules & sizing of pv system
Photovoltaic modules & sizing of pv system
 
Ppt on design of solar photovoltaic generation for residential building
Ppt on design of solar photovoltaic generation for residential buildingPpt on design of solar photovoltaic generation for residential building
Ppt on design of solar photovoltaic generation for residential building
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsyst
 
Photovoltaic Systems: System Design Tools
Photovoltaic Systems: System Design ToolsPhotovoltaic Systems: System Design Tools
Photovoltaic Systems: System Design Tools
 
Solar Radiation Geometry
Solar Radiation GeometrySolar Radiation Geometry
Solar Radiation Geometry
 
Project Proposal For Solar Panel Installation PowerPoint Presentation Slides
Project Proposal For Solar Panel Installation PowerPoint Presentation SlidesProject Proposal For Solar Panel Installation PowerPoint Presentation Slides
Project Proposal For Solar Panel Installation PowerPoint Presentation Slides
 
Energy Conservation Act 2001
Energy Conservation Act 2001Energy Conservation Act 2001
Energy Conservation Act 2001
 
Efficiency and Heat Rate in cogenerative power system
Efficiency and Heat Rate in cogenerative power systemEfficiency and Heat Rate in cogenerative power system
Efficiency and Heat Rate in cogenerative power system
 

Destacado

Financial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaFinancial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaAkash Jauhari
 
Solar mango corporate presentation
Solar mango   corporate presentationSolar mango   corporate presentation
Solar mango corporate presentationAnjali Khandelwal
 
Accurately measuring pv soiling losses using module power measurements
Accurately measuring pv soiling losses using module power measurementsAccurately measuring pv soiling losses using module power measurements
Accurately measuring pv soiling losses using module power measurementsMichael Gostein
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1Murugappa Group
 
1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic SystemManthan Thakkar
 
PPT on Mini Water Supply Scheme
PPT on Mini Water Supply SchemePPT on Mini Water Supply Scheme
PPT on Mini Water Supply SchemeArvind kumar
 
Consulting toolkit structuring the problem
Consulting toolkit   structuring the problemConsulting toolkit   structuring the problem
Consulting toolkit structuring the problemchrisdoran
 
Will risks-derail-the-modest-recovery-oecd-interim-economic-outlook-march-2017
Will risks-derail-the-modest-recovery-oecd-interim-economic-outlook-march-2017Will risks-derail-the-modest-recovery-oecd-interim-economic-outlook-march-2017
Will risks-derail-the-modest-recovery-oecd-interim-economic-outlook-march-2017OECD, Economics Department
 
Thermal Power Plant - Manual
Thermal Power Plant - ManualThermal Power Plant - Manual
Thermal Power Plant - ManualSheel Shah
 
10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, DesignVignesh Sekar
 
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...sdchrosis
 
A project report on cash and fund flow analysis and ratio analysis of dksskn,...
A project report on cash and fund flow analysis and ratio analysis of dksskn,...A project report on cash and fund flow analysis and ratio analysis of dksskn,...
A project report on cash and fund flow analysis and ratio analysis of dksskn,...Babasab Patil
 
Optimizing Operation & Maintenance Practices for Solar Power Plant
Optimizing Operation & Maintenance Practices for Solar Power PlantOptimizing Operation & Maintenance Practices for Solar Power Plant
Optimizing Operation & Maintenance Practices for Solar Power PlantGensol Engineering Limited
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantVignesh Sekar
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsGensol Engineering Limited
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
 
Eai corporate presentation
Eai   corporate presentationEai   corporate presentation
Eai corporate presentationEAI
 

Destacado (19)

Financial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in IndiaFinancial Feasibility of Solar Power Plant in India
Financial Feasibility of Solar Power Plant in India
 
Solar mango corporate presentation
Solar mango   corporate presentationSolar mango   corporate presentation
Solar mango corporate presentation
 
Accurately measuring pv soiling losses using module power measurements
Accurately measuring pv soiling losses using module power measurementsAccurately measuring pv soiling losses using module power measurements
Accurately measuring pv soiling losses using module power measurements
 
Influence of artificial soiling on the power losses of different PV technologies
Influence of artificial soiling on the power losses of different PV technologiesInfluence of artificial soiling on the power losses of different PV technologies
Influence of artificial soiling on the power losses of different PV technologies
 
Soiling monitoring solution & field test results in MENA regions
Soiling monitoring solution & field test results in MENA regionsSoiling monitoring solution & field test results in MENA regions
Soiling monitoring solution & field test results in MENA regions
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1
 
1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System1 KW Solar Photovoltaic System
1 KW Solar Photovoltaic System
 
PPT on Mini Water Supply Scheme
PPT on Mini Water Supply SchemePPT on Mini Water Supply Scheme
PPT on Mini Water Supply Scheme
 
Consulting toolkit structuring the problem
Consulting toolkit   structuring the problemConsulting toolkit   structuring the problem
Consulting toolkit structuring the problem
 
Will risks-derail-the-modest-recovery-oecd-interim-economic-outlook-march-2017
Will risks-derail-the-modest-recovery-oecd-interim-economic-outlook-march-2017Will risks-derail-the-modest-recovery-oecd-interim-economic-outlook-march-2017
Will risks-derail-the-modest-recovery-oecd-interim-economic-outlook-march-2017
 
Thermal Power Plant - Manual
Thermal Power Plant - ManualThermal Power Plant - Manual
Thermal Power Plant - Manual
 
10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design10 MW Solar PV power Plant - CPM & PERT, Design
10 MW Solar PV power Plant - CPM & PERT, Design
 
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
REACH Solar Consultants - Presentation at Intersolar India 2013 | Learnings f...
 
A project report on cash and fund flow analysis and ratio analysis of dksskn,...
A project report on cash and fund flow analysis and ratio analysis of dksskn,...A project report on cash and fund flow analysis and ratio analysis of dksskn,...
A project report on cash and fund flow analysis and ratio analysis of dksskn,...
 
Optimizing Operation & Maintenance Practices for Solar Power Plant
Optimizing Operation & Maintenance Practices for Solar Power PlantOptimizing Operation & Maintenance Practices for Solar Power Plant
Optimizing Operation & Maintenance Practices for Solar Power Plant
 
Project Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power PlantProject Proposal on 10 MW Solar PV Power Plant
Project Proposal on 10 MW Solar PV Power Plant
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar Projects
 
Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best Practices
 
Eai corporate presentation
Eai   corporate presentationEai   corporate presentation
Eai corporate presentation
 

Similar a Solar Power Plant cash flow model

Mrs. Wilma EERENSTEIN - Desert Proof Modules
Mrs. Wilma EERENSTEIN - Desert Proof ModulesMrs. Wilma EERENSTEIN - Desert Proof Modules
Mrs. Wilma EERENSTEIN - Desert Proof ModulesMouhcine Benmeziane
 
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...Ashish Verma
 
ompresentation-intersolar2013ver3-131115095204-phpapp02.pdf
ompresentation-intersolar2013ver3-131115095204-phpapp02.pdfompresentation-intersolar2013ver3-131115095204-phpapp02.pdf
ompresentation-intersolar2013ver3-131115095204-phpapp02.pdfhanadi40
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.Saurabh Biswas
 
5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contextsLeNS_slide
 
Conference Presentation: Quantifying Sources of Mismatch
Conference Presentation: Quantifying Sources of MismatchConference Presentation: Quantifying Sources of Mismatch
Conference Presentation: Quantifying Sources of MismatchEvan Sarkisian
 
Solar Cells: when will they become economically feasible
Solar Cells: when will they become economically feasibleSolar Cells: when will they become economically feasible
Solar Cells: when will they become economically feasibleJeffrey Funk
 
Next105 Ases Power Point Presentation Internal Final
Next105 Ases Power Point Presentation Internal FinalNext105 Ases Power Point Presentation Internal Final
Next105 Ases Power Point Presentation Internal FinalNextronex Inc
 
Automatic sun tracking system
Automatic sun tracking systemAutomatic sun tracking system
Automatic sun tracking systemSreekanth Shastry
 
Conducting a Site Assessment and PV System Field Survey
Conducting a Site Assessment and   PV System Field SurveyConducting a Site Assessment and   PV System Field Survey
Conducting a Site Assessment and PV System Field SurveyEyad Adnan
 
March9 2009-workshop-slides
March9 2009-workshop-slidesMarch9 2009-workshop-slides
March9 2009-workshop-slidesSWITCHOntario
 
Slideshare presentation
Slideshare presentationSlideshare presentation
Slideshare presentationNextronex Inc
 
16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf
16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf
16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdfMohamed Salah
 
List Of Solar Technologies
List Of Solar TechnologiesList Of Solar Technologies
List Of Solar Technologiesfirstgreen
 
List of solar technologies
List of solar technologiesList of solar technologies
List of solar technologiesfirstgreen
 

Similar a Solar Power Plant cash flow model (20)

Mrs. Wilma EERENSTEIN - Desert Proof Modules
Mrs. Wilma EERENSTEIN - Desert Proof ModulesMrs. Wilma EERENSTEIN - Desert Proof Modules
Mrs. Wilma EERENSTEIN - Desert Proof Modules
 
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...Solar power sector: Technology, BoS, Pre Feasbility and  phase of project dev...
Solar power sector: Technology, BoS, Pre Feasbility and phase of project dev...
 
ompresentation-intersolar2013ver3-131115095204-phpapp02.pdf
ompresentation-intersolar2013ver3-131115095204-phpapp02.pdfompresentation-intersolar2013ver3-131115095204-phpapp02.pdf
ompresentation-intersolar2013ver3-131115095204-phpapp02.pdf
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.
 
5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts5.5 off main-grid technologies for power generation in rural contexts
5.5 off main-grid technologies for power generation in rural contexts
 
Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
Conference Presentation: Quantifying Sources of Mismatch
Conference Presentation: Quantifying Sources of MismatchConference Presentation: Quantifying Sources of Mismatch
Conference Presentation: Quantifying Sources of Mismatch
 
Solar Cells: when will they become economically feasible
Solar Cells: when will they become economically feasibleSolar Cells: when will they become economically feasible
Solar Cells: when will they become economically feasible
 
Next105 Ases Power Point Presentation Internal Final
Next105 Ases Power Point Presentation Internal FinalNext105 Ases Power Point Presentation Internal Final
Next105 Ases Power Point Presentation Internal Final
 
Automatic sun tracking system
Automatic sun tracking systemAutomatic sun tracking system
Automatic sun tracking system
 
Solar Barge
Solar BargeSolar Barge
Solar Barge
 
Conducting a Site Assessment and PV System Field Survey
Conducting a Site Assessment and   PV System Field SurveyConducting a Site Assessment and   PV System Field Survey
Conducting a Site Assessment and PV System Field Survey
 
Solar ppt
Solar pptSolar ppt
Solar ppt
 
March9 2009-workshop-slides
March9 2009-workshop-slidesMarch9 2009-workshop-slides
March9 2009-workshop-slides
 
Solar PV DC Concepts
Solar PV DC ConceptsSolar PV DC Concepts
Solar PV DC Concepts
 
Slideshare presentation
Slideshare presentationSlideshare presentation
Slideshare presentation
 
16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf
16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf
16_Economic_assessment_of_PV_and_wind_for_energy_planning_Cairo_Egypt.pdf
 
List Of Solar Technologies
List Of Solar TechnologiesList Of Solar Technologies
List Of Solar Technologies
 
List of solar technologies
List of solar technologiesList of solar technologies
List of solar technologies
 

Más de Vijay Kannan

IJSETR-VOL-2-ISSUE-7-1526-1530
IJSETR-VOL-2-ISSUE-7-1526-1530IJSETR-VOL-2-ISSUE-7-1526-1530
IJSETR-VOL-2-ISSUE-7-1526-1530Vijay Kannan
 
Wind Turbine Financials
Wind Turbine FinancialsWind Turbine Financials
Wind Turbine FinancialsVijay Kannan
 
IMPACT_OF_MENTAL_WELLNESS_ON_THE_NATION 12th Jan 2014
IMPACT_OF_MENTAL_WELLNESS_ON_THE_NATION 12th Jan 2014IMPACT_OF_MENTAL_WELLNESS_ON_THE_NATION 12th Jan 2014
IMPACT_OF_MENTAL_WELLNESS_ON_THE_NATION 12th Jan 2014Vijay Kannan
 

Más de Vijay Kannan (9)

cv summary
cv summarycv summary
cv summary
 
Renge - Deck
Renge - DeckRenge - Deck
Renge - Deck
 
IJSETR-VOL-2-ISSUE-7-1526-1530
IJSETR-VOL-2-ISSUE-7-1526-1530IJSETR-VOL-2-ISSUE-7-1526-1530
IJSETR-VOL-2-ISSUE-7-1526-1530
 
9-Energy
9-Energy9-Energy
9-Energy
 
Getwell Summary
Getwell SummaryGetwell Summary
Getwell Summary
 
getwell 2 (1)
getwell 2 (1)getwell 2 (1)
getwell 2 (1)
 
getwell ppt (1)
getwell ppt (1)getwell ppt (1)
getwell ppt (1)
 
Wind Turbine Financials
Wind Turbine FinancialsWind Turbine Financials
Wind Turbine Financials
 
IMPACT_OF_MENTAL_WELLNESS_ON_THE_NATION 12th Jan 2014
IMPACT_OF_MENTAL_WELLNESS_ON_THE_NATION 12th Jan 2014IMPACT_OF_MENTAL_WELLNESS_ON_THE_NATION 12th Jan 2014
IMPACT_OF_MENTAL_WELLNESS_ON_THE_NATION 12th Jan 2014
 

Solar Power Plant cash flow model

  • 1. Steps of Site Identification & Project Pre-Feasibility
  • 2.
  • 3.
  • 4.
  • 5.  Identification of site  Solar insolation and shadow assessment  Geological due diligence  Social audit of the site  Power Evacuation Feasibility and accessibility  Technology and supplier selection  Financial Pre Feasibility
  • 6.  Land shall be plain and Red soil with proper rain water drainage provision .  Near to 33KV SS  Motor able road  Following land is not suitable :  Black Cotton Soil  Site located near mountain ,Larger Water Bodies & Shadow over land .
  • 7. • No of sunny days / sunny hours • No of Cloudy days & Rainy days • Relative Humidity & Temperature @ Site • Direction of Sun Rays falling on the Panel • Following land is not suitable : • More dusty Area • Site located near mountain ,Larger Water Bodies & Shadow over land .
  • 8. • As land orientation should preferably be flat, considerations while identifying site must include; • Degree of levelization, • A drainage system, • Dust percentage in air • Land/soil capacity to hold structures. • Soil Testing Experts/ Geotechnical Engineers having understanding of soil and land mechanics.
  • 9. Review issues related to:-  Security of the project and the systems,  Possible threats in terms of security of employees,  Availability of labor & local support for the project.
  • 10. Review issues related to:- • Availability of substation for power evacuation (Nearest- 11/33 KV ) • Availability / provision for Additional Bay @ SS • Evacuation capacity of the sub-station- to be checked with distribution  utility. • Feasibility study of Power Evacuation line of 33 KV from site to SS ( Pole compensation cost) • Grid to be constructed as per IEGC .
  • 11. Selection of Solar PV Technology based on - • Past performance record, Available global radiation(GHI), Climatic conditions- Specially temperature and Wind velocity, Cost of technology (capital and O&M), Projected conversion efficiency/’s and Consequent projected CUF’s, Risks associated with the technologies • Solar Panels – Type • Mono crystalline , Poly crystalline or Thin film technology . • Battery Banks , inverters , PV – DC Cable connectors , etc . • Use of specific PV DC cables
  • 12. • Land & Development Cost • Construction Cost • Engineering Cost • Equipment Cost • Operational Cost • Revenue • Benefits/Incentives • Funds Availability • Cash Flow • Returns
  • 13.  Radiation at Site  Losses in PV System (Invertors ,Cabling, Soiling (Dust), Module Mismatch , MPPT losses & Transformer)  Temperature and Climatic condition  Design Parameters of the Solar Plant  Inverter efficiency  Module degradation due to ageing .  Grid Availability
  • 14.  Direct Method – Pyrheliometer & Pyronometer instruments used @ site to estimate the Solar Radiation  InDirect method – Satelite data , NASA , Indian Metrological Department ,  World Radition Data Centre ( WRDC) &  RET Screen Canadian software - Free of cost
  • 15.  Reflection losses due to Sun Path, - Solar rays should fall perpendicular to panel for higher efficiency – But actually it may have wider incidence angle due to sun path – 1 % loss expected .  Soiling losses due to dust , SNOW etc – 1 % loss  Mis Match effect losses- due to interconnection of Solar Panels in series & parallel – Good quality panel to be procured .  MPPT ( Max Power Point Tracking) Losses - due to Changes in direction of sun , changes in solar insolations level with varying Temp  Inverter Efficiency depends upon Conversion of DC to AC – 96 to 98.5% .  Cabling losses due to improper joints etc .  Transformer losses.
  • 16.  Proper selection of Modules  Optimum angle of tilt  Minimisation of Ohmic losess with proper selection of conductors .  Selection of Efficient Transformers & Inverters Energy output depends upon - Temperature of the module decrease the output - Intensity of lights - Sun lights reflection on the surface but not on the modules - Defuse light - Changes in Sun spectrum in the day/ year , due to clouds, smoky, fogs etc - Materials used in Modules – Amorphous Silicon performance changes with aging
  • 17.  Mounting position of modules & Air circluation  Inclination Angle - Tilting position of modules – Fixed type- Non Tracking system  Performance changes with aging .  Temp Co Efficient –Changes in power out put with Different Temp  Typical value of Temp co efficient Y( P mpp) Crystaline Modules -0.4 to 0.45 % K Y( P mpp) Amorphous Modules -0.2 to 0.23 % K Y( P mpp) CdTe Modules -0.24 to 0.25 % K Thin film modules can give higher performance @ Elevated Temp compare to Crystaline silicon.
  • 18.  Module degradation occurs to Sun light  - Slow Breakdown of Module encapsulant ( Ethelene Vinyl Acetate EVA & Back sheet Polyvinyl Flouride Films )  Moisture ingress leads to corrosion formation on Cable connectors and decreased voltage outputs  UV rays breaks down the EVA layer between Module Front Glass and silicon cells – Silicon cells outputs gets affected .  Discoloration of Panels .  Degradation of silicon cells – Metastable Dangling bonds – 15 to 20 % reduction in efficiency .
  • 19. Sl No Description Life in Years Remarks 1 Module 30 2 Inverter 15 Small plant 30 10% Parts replacement 2 Every 10 years 3 Structure 30 Roof Top 30 to 60 Ground mounted fixed in metal 4 Cabling 30 After 10 years – 90 % & After 20 Years -80 % efficiency noticed in modules First 03 years of Operations No reduction in designed power output and then Yearly reduction of power output is 0.5 %
  • 20.  Software available – RETScreen (Free of cost), PVSyst23, Homer  Following analysis can be done :- -Energy Analysis -Emission Analysis -Cost Analysis -Financial Analysis -Sensitivity / risk Analysis
  • 21.  Performance of CUF depends upon :-  Solar Radiation  Temperature  Air velocity  Module type and materials used  Quality of Module & cable joints etc  Efficiency of Inverter &Transformer  Thin Film Modules most suitable higher ambient temp area . ( CUF around 19 to 20%)  To compensate degradation loss after 3 years add 5 KW module / MW in every year.
  • 22. Sl No Description Cost In Crore % of Cost 1 Solar PV Modules 4.51 58.2687339 2 Solar Invertors 1.166 15.0645995 3 Transformers 0.294 3.79844961 4 Protective devices 0.12 1.5503876 5 Wire/cables 0.1 1.29198966 6 SCADA/RMS 0.1 1.29198966 7 Project Execution & Comm 0.2 2.58397933 8 Construction cost 0.4 5.16795866 9 Grid Evacuation @ 15 L /Km x 5 KM 0.75 9.68992248 10 Other official works 0.1 1.29198966 7.74 100
  • 23. Loan amount @ 70 % of project cost 5.418 crore Annual EMI (Including Principle + Interest @12PA= Rs 8,76,105 Lakhs / Month) 1,05,13,320 Crore Annual OMS Charge & Staff Pay + Admin cost 20,00,000 Lakhs Total Expense / year 1,25,00,000 Crore Revenue Details Net Energy Produced in MWH 1655 MWH PLF ( 1x24x365= 8760 MWH) / Year 18.8926% PPA @ 7.50 KWH Cost 1,24,12,500 crore Revenune due to sale of REC @12000 /MWH 1,97,59,180 crore Net Cash Flow ( NCF) = ( PPA + REC cost ) 3,22,72,500 Crore Net Balance Amount = ( NCF- Net Expense / Year) 1,97,59,180 Crore
  • 24. Break even 7.74 / 1.97 crore ( Total Project cost /Net Balance amount/ year) 3.92 years Net Amount at the end of the 7 th year 13,83,14,260 crore Net Amount at the end of the 10th year 19,75,91,800 Crore