SlideShare una empresa de Scribd logo
1 de 13
Descargar para leer sin conexión
Vlad MINEA MANOLACHI Pag. 1 of 13
NOTEWORTHY ACCOMPLISHMENTS @ CONDMAG SA
1- Cold weather welding preheater, welding enclosures, controlled cooling belts.
Idea description:
Welding is a major operation in the
Pipeline Contractor business and has to
be performed in the field, to form the
pipeline.
Weather conditions and temperatures are
a big factor in the quality of welding.
In the cold weather the material has to
be brought to a certain temperature
before welding, maintain the conditions
during the welding of the weld bead and
then have a controlled cooling process in
order to ensure a high quality weld
required for high pressure natural gas
pipelines.
Figure 1 - Pipeline welding area that
requires the special treatment. These pipe
are 3’ in diameter and have a wall
thickness of ½”
Figure 3 - Special enclosure that can be easily
placed over the pipeline, protects the welder
and the welding area from wind, rain and snow
and maintains the proper welding conditions.
Had to be dimensioned according to the health
and safety requirements
Figure 2 - Diesel Fuel flame heater. Using
diesel fuel and compressed air creates a
high temperature powerful flame that
allows and efficient and fast preheating
procedure.
Figure 1 - Controlled cooling belt. Thermal insulation was
applied over the fresh finished weld bead and maintained
there for a certain time depending on the outside
temperatures. Ease of installation is a major factor.
Vlad MINEA MANOLACHI Pag. 2 of 13
2- Designed an automatic welding device for segmented pipeline curves - awarded
with an innovation certificate in 1989.
Welding Head
Segmented curved pipe
Rotor body
Distance
D1
Angle
A1
Rotation
Axis
Welding Head
Segmented curved pipe
Rotor body
Distance
D2
Angle
A2
Position for
Weld 2
Position for
Weld 1
Welding path is
in a vertical plane
Welding path is
in a vertical plane
Protective Flux
Protective Flux
Rotation
Axis
Welding Head
Welding Head
Operators
Platform
Welding Head
Support Arm
Idea description:
Welding is a major
operation in the Pipeline
Contractor business but
some constructive
elements can be prebuilt
in factory environments
with higher efficiency
installations.
Due to the thickness of
the material of large
diameter pipelines,
submerged arc welding is
the desired process. The
process requires the weld
area to be covered by the
flux and that can happen
only in a condition in
which the gravity does
not remove the flux. This
is usually done by
rotating the pipe under
the welding head. The
joins of a segmented
curve are not round they
are elliptic, so this device
has to compensate for
the problems.
The rotating plan of the
weld had to be set
vertically.
Figure 1 - Diagram presenting the principle of mounting
and rotating a segmented curve so that the welding plane
is vertical during the process.
Figure 2 - Image of the installation functioning in factory
environment.
Figure 3 - Model presenting the
challenges of rotating a segmented
curve for welding purposes.
Vlad MINEA MANOLACHI Pag. 3 of 13
Welding Head
Motor wheel
Motor wheel
Support wheel
Protective Flux
Incline section
Rotary Plate
Pipe Holder
Pipe
Segment
Welding
Head
Rotary
Plate
Loading
Hook
Structure
Frame
Chain
Flux
Recycling
Container
Incline
Section
Idea description:
The process is sown for
half of the segmented
curve, after that the
curve is flipped in the
installation and the other
end is brought in the
welding area and the
whole procedure is
repeated.
Challenges of the project
were the sophisticated 3D
movement of very large
and heavy objects,
performed at controlled
speeds and zero
accelerations.
Project was finalized in
1989 and is still in use
today. Controls were
upgraded to
computerized systems
but the mechanics are
the same.
Figure 4 - Diagram with solutions of the challenges presented previously.
Figure 5 - Image of the installation performing
weld nr.2 as presented in the previous diagram.
Vlad MINEA MANOLACHI Pag. 4 of 13
3- Cable pulleys to resist tensions of 600,000 lb. for 2.5 inch diameter cables.
Idea description:
Undercrossing the river Danube was
done successfully twice in Romania with
this “pulling” solution. A critical element
of the solution were the pulleys that
were supposed to bear large forces
during the process.
Due to the powerful flow of the Danube
River the pulleys were subjected to
horizontal forces in addition to the
vertical ones.
Figure 3 - Engineering team at the site
photographed on the pipeline ready to start
the launching process. I am the one in the
middle.
Figure 1 - The pulleys before starting
the pull. Group of process
supervisors and the river Danube in
the back. 1986
Figure 4 - Disjoining the cable segments after
pulling stroke. Notice the dimension of the cable –
2.5" diameter.
Figure 5 - Diagram representing the process in a cross- section through the river in the
crossing area.
Figure 2 - Pulleys detail of the cross
section diagram.
Vlad MINEA MANOLACHI Pag. 5 of 13
Vlad MINEA MANOLACHI Pag. 6 of 13
Vlad MINEA MANOLACHI Pag. 7 of 13
Vlad MINEA MANOLACHI Pag. 8 of 13
Vlad MINEA MANOLACHI Pag. 9 of 13
First page:
ROMGAZ R.A. Medias
NATURAL GAS DISTRIBUTION BUCURESTI
GAS LICENSED PLUMBER LICENSE
Nr: 3979/ 1994
Second page:
Photo
Owner’s signature
Last Name: MINEA MANOLACHI
First Name: Vlad
Residence: BRASOV, Grivitei nr. 42
ID Series: B.T nr: 283530
Issued by: BRASOV
Third page:
Degree obtained through licensing
I - Design, manufacture and operation of all gas works. VOIDED
II - Design, execution and operation of utilization installations, operation and execution of all
works of distribution system – GRANTED.
Director: Illegible Signature Date of issuing: 12-07-94. Stamp.
III - Execution, operation and maintenance of all natural gas utilization installations. –
VOIDED
Forth page:
Annual visa
Year 1995 Director: Illegible Signature, Stamp
I certify hereby the concordance of this translation with the original document in Romanian
endorsed by me,
Translator: Vlad Minea Manolachi
Vlad MINEA MANOLACHI Pag. 10 of 13
Vlad MINEA MANOLACHI Pag. 11 of 13
SOCIALIST REPUBLIC OF ROMANIA
MINISTRY OF PETROLEUM
(Ministry or Central Body)
INNOVATOR CERTIFICATE
Number: 924
For innovation titled: AUTOMATIC FLUX CORED WELDING INSTALLATION FOR
SEGMENTED PIPE CURVES JOINS
Innovation was registered at the date: 1989
At: CGM-IAMCM Brasov
(Name of innovation registering company)
Acknowledges as author(s): ing. Minea Vlad
Through this certificate, granted under article 71 of the Law 62/1974, all privileges associated
with this accreditation are conferred upon the author(s).
Delivery date: 10.08.1989
Director: Ing. Val. Soare
Illegible signature
Stamp
I certify hereby the concordance of this translation with the original document in Romanian
endorsed by me,
Translator: Vlad Minea Manolachi
Vlad MINEA MANOLACHI Pag. 12 of 13
Vlad MINEA MANOLACHI Pag. 13 of 13
SOCIALIST REPUBLIC OF ROMANIA
MINISTRY OF PETROLEUM
(Ministry or Central Body)
INNOVATOR CERTIFICATE
Number: 558
For innovation titled: AUTOMATIC FLUX CORED WELDING INSTALLATION FOR
CIRCULAR AND ELIPTICAL JOINS AT METALLIC CONSTRUCTIONS AND PIPES
Innovation was registered at the date: 1984
At: Intreprinderea Antrepriza de Montaj conducte Magistrale Brasov
(Name of innovation registering company)
Acknowledges as author(s): CAPBATUT VASILE, PANAZAN TEODOR, MINEA VLAD,
KERTESZ PAVEL, NECULAE NECULAE, STOICA CONSTANTIN and COPOT ION
Through this certificate, granted under article 71 of the Law 62/1974, all privileges associated
with this accreditation are conferred upon the author(s).
Delivery date: 28.05.1985
Illegible signature
Stamp
I certify hereby the concordance of this translation with the original document in Romanian
endorsed by me,
Translator: Vlad Minea Manolachi

Más contenido relacionado

La actualidad más candente

Triathlon
Triathlon Triathlon
Triathlon
rgaskill
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
Minh Bui Si
 

La actualidad más candente (10)

Alumina ceramic-block
Alumina ceramic-blockAlumina ceramic-block
Alumina ceramic-block
 
Internship report with background
Internship report  with backgroundInternship report  with background
Internship report with background
 
MEKA K SERIES CONCRETE BATCHING PLANTS
MEKA K SERIES CONCRETE BATCHING PLANTSMEKA K SERIES CONCRETE BATCHING PLANTS
MEKA K SERIES CONCRETE BATCHING PLANTS
 
industrial training report on composite girder and aggregate testing
industrial  training report on composite girder and aggregate testingindustrial  training report on composite girder and aggregate testing
industrial training report on composite girder and aggregate testing
 
Concrete Batching Plant
Concrete Batching PlantConcrete Batching Plant
Concrete Batching Plant
 
CASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGECASE STUDY OF WAKOTA BRIDGE
CASE STUDY OF WAKOTA BRIDGE
 
Triathlon
Triathlon Triathlon
Triathlon
 
4 week summer training report
4 week summer training report4 week summer training report
4 week summer training report
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 

Similar a Vlad Minea - Condmag

AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCES
Carlo Avanzini
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
John Grover
 
Final project report
Final project reportFinal project report
Final project report
hedleymfb
 
PPT of final on Ultra low head turbine(crossflow)final.pptx
PPT of final on Ultra low head turbine(crossflow)final.pptxPPT of final on Ultra low head turbine(crossflow)final.pptx
PPT of final on Ultra low head turbine(crossflow)final.pptx
PawanSharma565262
 
ZSM-Connection_Brochure_english
ZSM-Connection_Brochure_englishZSM-Connection_Brochure_english
ZSM-Connection_Brochure_english
Chris Munnick
 
IPTC 16192 Manuscript
IPTC 16192 ManuscriptIPTC 16192 Manuscript
IPTC 16192 Manuscript
Nghi Nguyen
 
Belihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) Ltd
Belihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) LtdBelihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) Ltd
Belihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) Ltd
Sandeepa Edirisooriya
 

Similar a Vlad Minea - Condmag (20)

Underwater Welding techniques
Underwater Welding techniquesUnderwater Welding techniques
Underwater Welding techniques
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCES
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Final project report
Final project reportFinal project report
Final project report
 
report
reportreport
report
 
Design and Stress Analysis of High Pressure Accumulator
Design and Stress Analysis of High Pressure AccumulatorDesign and Stress Analysis of High Pressure Accumulator
Design and Stress Analysis of High Pressure Accumulator
 
IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...
IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...
IRJET- Design and Finite Element Analysis of Fabricated Panama Chock with 225...
 
Fabrication of Semi-Automatic Molten Metal Pouring System in Casting Industries.
Fabrication of Semi-Automatic Molten Metal Pouring System in Casting Industries.Fabrication of Semi-Automatic Molten Metal Pouring System in Casting Industries.
Fabrication of Semi-Automatic Molten Metal Pouring System in Casting Industries.
 
IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...
IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...
IRJET- Finite Element Analysis of Stempipe Used in Deepwater Pipeline Install...
 
Flat Rolling Process -A Review
Flat Rolling Process -A ReviewFlat Rolling Process -A Review
Flat Rolling Process -A Review
 
Km04 pneumatic based metal sheet cutter (wecompress)
Km04 pneumatic based  metal sheet cutter (wecompress)Km04 pneumatic based  metal sheet cutter (wecompress)
Km04 pneumatic based metal sheet cutter (wecompress)
 
Underwater Welding Techniques
Underwater Welding TechniquesUnderwater Welding Techniques
Underwater Welding Techniques
 
PPT of final on Ultra low head turbine(crossflow)final.pptx
PPT of final on Ultra low head turbine(crossflow)final.pptxPPT of final on Ultra low head turbine(crossflow)final.pptx
PPT of final on Ultra low head turbine(crossflow)final.pptx
 
ZSM-Connection_Brochure_english
ZSM-Connection_Brochure_englishZSM-Connection_Brochure_english
ZSM-Connection_Brochure_english
 
Submerged Arc Welding
Submerged Arc WeldingSubmerged Arc Welding
Submerged Arc Welding
 
IPTC 16192 Manuscript
IPTC 16192 ManuscriptIPTC 16192 Manuscript
IPTC 16192 Manuscript
 
Km06 pneumatic punching machine abstract (wecompress)
Km06 pneumatic punching machine abstract (wecompress)Km06 pneumatic punching machine abstract (wecompress)
Km06 pneumatic punching machine abstract (wecompress)
 
Design and analysis of ball mill inlet chute for roller press circuit in ceme...
Design and analysis of ball mill inlet chute for roller press circuit in ceme...Design and analysis of ball mill inlet chute for roller press circuit in ceme...
Design and analysis of ball mill inlet chute for roller press circuit in ceme...
 
Design and Analysis Of Hybrid Car Using Tubular Frame Chasis and Helium Gas
Design and Analysis Of Hybrid Car Using Tubular Frame Chasis and Helium GasDesign and Analysis Of Hybrid Car Using Tubular Frame Chasis and Helium Gas
Design and Analysis Of Hybrid Car Using Tubular Frame Chasis and Helium Gas
 
Belihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) Ltd
Belihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) LtdBelihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) Ltd
Belihul Oya Mini Hydropower Plant project under LTL holdings (Pvt) Ltd
 

Vlad Minea - Condmag

  • 1. Vlad MINEA MANOLACHI Pag. 1 of 13 NOTEWORTHY ACCOMPLISHMENTS @ CONDMAG SA 1- Cold weather welding preheater, welding enclosures, controlled cooling belts. Idea description: Welding is a major operation in the Pipeline Contractor business and has to be performed in the field, to form the pipeline. Weather conditions and temperatures are a big factor in the quality of welding. In the cold weather the material has to be brought to a certain temperature before welding, maintain the conditions during the welding of the weld bead and then have a controlled cooling process in order to ensure a high quality weld required for high pressure natural gas pipelines. Figure 1 - Pipeline welding area that requires the special treatment. These pipe are 3’ in diameter and have a wall thickness of ½” Figure 3 - Special enclosure that can be easily placed over the pipeline, protects the welder and the welding area from wind, rain and snow and maintains the proper welding conditions. Had to be dimensioned according to the health and safety requirements Figure 2 - Diesel Fuel flame heater. Using diesel fuel and compressed air creates a high temperature powerful flame that allows and efficient and fast preheating procedure. Figure 1 - Controlled cooling belt. Thermal insulation was applied over the fresh finished weld bead and maintained there for a certain time depending on the outside temperatures. Ease of installation is a major factor.
  • 2. Vlad MINEA MANOLACHI Pag. 2 of 13 2- Designed an automatic welding device for segmented pipeline curves - awarded with an innovation certificate in 1989. Welding Head Segmented curved pipe Rotor body Distance D1 Angle A1 Rotation Axis Welding Head Segmented curved pipe Rotor body Distance D2 Angle A2 Position for Weld 2 Position for Weld 1 Welding path is in a vertical plane Welding path is in a vertical plane Protective Flux Protective Flux Rotation Axis Welding Head Welding Head Operators Platform Welding Head Support Arm Idea description: Welding is a major operation in the Pipeline Contractor business but some constructive elements can be prebuilt in factory environments with higher efficiency installations. Due to the thickness of the material of large diameter pipelines, submerged arc welding is the desired process. The process requires the weld area to be covered by the flux and that can happen only in a condition in which the gravity does not remove the flux. This is usually done by rotating the pipe under the welding head. The joins of a segmented curve are not round they are elliptic, so this device has to compensate for the problems. The rotating plan of the weld had to be set vertically. Figure 1 - Diagram presenting the principle of mounting and rotating a segmented curve so that the welding plane is vertical during the process. Figure 2 - Image of the installation functioning in factory environment. Figure 3 - Model presenting the challenges of rotating a segmented curve for welding purposes.
  • 3. Vlad MINEA MANOLACHI Pag. 3 of 13 Welding Head Motor wheel Motor wheel Support wheel Protective Flux Incline section Rotary Plate Pipe Holder Pipe Segment Welding Head Rotary Plate Loading Hook Structure Frame Chain Flux Recycling Container Incline Section Idea description: The process is sown for half of the segmented curve, after that the curve is flipped in the installation and the other end is brought in the welding area and the whole procedure is repeated. Challenges of the project were the sophisticated 3D movement of very large and heavy objects, performed at controlled speeds and zero accelerations. Project was finalized in 1989 and is still in use today. Controls were upgraded to computerized systems but the mechanics are the same. Figure 4 - Diagram with solutions of the challenges presented previously. Figure 5 - Image of the installation performing weld nr.2 as presented in the previous diagram.
  • 4. Vlad MINEA MANOLACHI Pag. 4 of 13 3- Cable pulleys to resist tensions of 600,000 lb. for 2.5 inch diameter cables. Idea description: Undercrossing the river Danube was done successfully twice in Romania with this “pulling” solution. A critical element of the solution were the pulleys that were supposed to bear large forces during the process. Due to the powerful flow of the Danube River the pulleys were subjected to horizontal forces in addition to the vertical ones. Figure 3 - Engineering team at the site photographed on the pipeline ready to start the launching process. I am the one in the middle. Figure 1 - The pulleys before starting the pull. Group of process supervisors and the river Danube in the back. 1986 Figure 4 - Disjoining the cable segments after pulling stroke. Notice the dimension of the cable – 2.5" diameter. Figure 5 - Diagram representing the process in a cross- section through the river in the crossing area. Figure 2 - Pulleys detail of the cross section diagram.
  • 5. Vlad MINEA MANOLACHI Pag. 5 of 13
  • 6. Vlad MINEA MANOLACHI Pag. 6 of 13
  • 7. Vlad MINEA MANOLACHI Pag. 7 of 13
  • 8. Vlad MINEA MANOLACHI Pag. 8 of 13
  • 9. Vlad MINEA MANOLACHI Pag. 9 of 13 First page: ROMGAZ R.A. Medias NATURAL GAS DISTRIBUTION BUCURESTI GAS LICENSED PLUMBER LICENSE Nr: 3979/ 1994 Second page: Photo Owner’s signature Last Name: MINEA MANOLACHI First Name: Vlad Residence: BRASOV, Grivitei nr. 42 ID Series: B.T nr: 283530 Issued by: BRASOV Third page: Degree obtained through licensing I - Design, manufacture and operation of all gas works. VOIDED II - Design, execution and operation of utilization installations, operation and execution of all works of distribution system – GRANTED. Director: Illegible Signature Date of issuing: 12-07-94. Stamp. III - Execution, operation and maintenance of all natural gas utilization installations. – VOIDED Forth page: Annual visa Year 1995 Director: Illegible Signature, Stamp I certify hereby the concordance of this translation with the original document in Romanian endorsed by me, Translator: Vlad Minea Manolachi
  • 10. Vlad MINEA MANOLACHI Pag. 10 of 13
  • 11. Vlad MINEA MANOLACHI Pag. 11 of 13 SOCIALIST REPUBLIC OF ROMANIA MINISTRY OF PETROLEUM (Ministry or Central Body) INNOVATOR CERTIFICATE Number: 924 For innovation titled: AUTOMATIC FLUX CORED WELDING INSTALLATION FOR SEGMENTED PIPE CURVES JOINS Innovation was registered at the date: 1989 At: CGM-IAMCM Brasov (Name of innovation registering company) Acknowledges as author(s): ing. Minea Vlad Through this certificate, granted under article 71 of the Law 62/1974, all privileges associated with this accreditation are conferred upon the author(s). Delivery date: 10.08.1989 Director: Ing. Val. Soare Illegible signature Stamp I certify hereby the concordance of this translation with the original document in Romanian endorsed by me, Translator: Vlad Minea Manolachi
  • 12. Vlad MINEA MANOLACHI Pag. 12 of 13
  • 13. Vlad MINEA MANOLACHI Pag. 13 of 13 SOCIALIST REPUBLIC OF ROMANIA MINISTRY OF PETROLEUM (Ministry or Central Body) INNOVATOR CERTIFICATE Number: 558 For innovation titled: AUTOMATIC FLUX CORED WELDING INSTALLATION FOR CIRCULAR AND ELIPTICAL JOINS AT METALLIC CONSTRUCTIONS AND PIPES Innovation was registered at the date: 1984 At: Intreprinderea Antrepriza de Montaj conducte Magistrale Brasov (Name of innovation registering company) Acknowledges as author(s): CAPBATUT VASILE, PANAZAN TEODOR, MINEA VLAD, KERTESZ PAVEL, NECULAE NECULAE, STOICA CONSTANTIN and COPOT ION Through this certificate, granted under article 71 of the Law 62/1974, all privileges associated with this accreditation are conferred upon the author(s). Delivery date: 28.05.1985 Illegible signature Stamp I certify hereby the concordance of this translation with the original document in Romanian endorsed by me, Translator: Vlad Minea Manolachi