Presented by:
Vladimir Vujović, PMP
PMI Certification Preparation: PMP / CAPM
- Project Procurement Management -
Project Management Institute, Inc. All rights reserved.
December 2017
• Presenter
• Participants: profile, background, expectations
• Session: structure, approach and benefits
Introduction to the session
1. Integration management
2. Scope management
3. Time management
4. Cost management
5. Quality management
6. Human resources management
7. Communications management
8. Risk management
9. Procurement management
10. Stakeholder management
Project Management Knowledge Areas
PMI PMBOK 5th edition
1. Plan Procurement Management
2. Conduct Procurements
3. Control Procurements
4. Close Procurements
Project Procurement Management Processes:
Plan Procurement Management
Inputs
• Project management plan
• Requirements
documentation
• Risk register
• Activity resource
requirements
• Project schedule
• Activity cost estimates
• Stakeholder register
• Enterprise environmental
factors
• Organizational process assets
Tools and Techniques
• Make-or-buy analysis
• Expert judgment
• Market research
• Meetings
Outputs
• Procurement management
plan
• Procurement statement of
work
• Procurement documents
• Source selection criteria
• Make-or-buy decisions
• Change requests
• Project document updates
Plan Procurement Management: Data Flow
Plan
Procurement
Management
Close
Procurements
Identify Risks
Enterprise /
Organization
Project Procurement Management
• Activity cost
estimates
• OPA
• EEF
Identify
Stakeholders
Identify Risks
• Stakeholder
register
Project documents• Project
documents
updates
Control
Procurements
Conduct
Procurements
Estimate Costs
Develop
Schedule
Estimate
Activity
Resources
Collect
Requirements
Develop Project
Management
Plan
Perform
Integrated
Change Control
Identify
Stakeholders• Project schedule
• Activity resource
requirements
• Risk register
• Project
management
plan
• Requirements
documentation
• Make-or-buy
decisions
• Procurement
management plan
• Procurement
statement of work
• Source selection
criteria
•Procurementdocuments
• Procurement
documents
• Procurement
documents
• Change
requests
• Fixed-price contracts
• Cost-reimbursable contracts
• Time and Material contracts (T&M)
Types of contracts
• Firm Fixed Price Contracts (FFP)
• Fixed Price Incentive Fee Contracts (FPIF)
• Fixed Price with Economic Price Adjustment Contracts (FP-EPA)
Fixed-price contracts
• Cost Plus Fixed Fee Contracts (CPFF)
• Cost Plus Incentive Fee Contracts (CPIF)
• Cost Plus Award Fee Contracts (CPAF)
Cost-reimbursable contracts
• Understanding of need
• Overall or life-cycle cost
• Technical capability
• Risk
• Management approach
• Technical approach
• Warranty
• Financial capacity
• Production capacity and interest
• Business size and type
• Past performance of sellers
• References
• Intellectual property rights
• Proprietary rights
Source selection criteria
Conduct Procurements
Inputs
• Procurement management
plan
• Procurement documents
• Source selection criteria
• Seller proposals
• Project documents
• Make-or-buy decisions
• Procurement statement of
work
• Organizational process assets
Tools and Techniques
• Bidder conference
• Proposal evaluation
techniques
• Independent estimates
• Expert judgment
• Advertising
• Analytical techniques
• Procurement negotiations
Outputs
• Selected sellers
• Agreements
• Resource calendars
• Change requests
• Project management plan
updates
• Project documents updates
Conduct Procurements: Data Flow
Conduct
Procurements
Plan
Procurement
Management
Develop Project
Management
Plan
Enterprise /
Organization
Project Procurement Management
• OPA
Control
Procurements
Project documents
• Agreements
• Resource calendars
• Project
documents
• Seller proposals
Estimate
Activity
Resources
Estimate
Activity
Durations
Develop
Schedule
Determine
Budget
Develop Project
Team
Perform
Integrated
Change Control
Develop Project
Charter
Project documents
Sellers
• Selected sellers
• Procurement management plan
• Procurement documents
• Source selection criteria
• Make-or-buy decisions
• Procurement statement of work
• Project documents
updates
• Project management
plan updates
• Resource calendars
• Resource calendars
• Resource calendars
• Resource calendars
• Change requests
• Agreements
Risk to Buyer and Seller According to Contract Types
100%
Risk
0%
Buyer
Seller
CPPC CPAF T&M FPIF
CPFF CPIF FPEPA FP
CPPC: Cost Plus Percentage of Costs
CPFF: Cost Plus Fixed Fee
CPAF: Cost Plus Award Fee
CPIF: Cost Plus Incentive Fee
T&M: Time and Material
FPEPA: Fixed Price Economic Price Adjustment
FPIF: Fixed Price Incentive Fee
FP: Fixed Price
Control Procurements
Inputs
• Project management plan
• Procurement documents
• Agreements
• Approved change requests
• Work performance reports
• Work performance data
Tools and Techniques
• Contract change control
system
• Procurement performance
reviews
• Inspections and audits
• Performance reporting
• Payment systems
• Claims administration
• Records management system
Outputs
• Work performance
information
• Change requests
• Project management plan
updates
• Project documents updates
• Organizational process assets
updates
Control Procurements: Data Flow
Control
Procurements
Plan
Procurement
Management
Perform
Integrated
Change Control
Project Procurement Management
• Project communications
• Work performance
reports
Perform
Integrated
Change Control
Direct and
Manage Project
Work
Develop Project
Management
Plan
Project documents
• Work performance
data
• Project
Management Plan
• OPA updates
• Project documents
updates
• Change requests
• Approved change
requests
• Work performance information
Monitor and
Control Project
Work
Conduct
Procurements
Enterprise /
Organization
• Project Management Plan updates
• Procurement documents
• Agreements
Close Procurements
Inputs
• Project management plan
• Procurement documents
Tools and Techniques
• Procurement audits
• Procurement negotiations
• Records management system
Outputs
• Closed procurements
• Organizational process assets
updates
Close Procurements: Data Flow
Close
Procurements
Plan
Procurement
Management
Enterprise /
Organization
Project Procurement Management
• Procurement documents
Develop Project
Management
Plan
• Project
Management
Plan
• Closed
procurements
• OPA updates
• The risk shared between the buyer and the seller is determined by
which of the following?
A. The Scope of Work
B. The Teaming Agreement
C. The Contract Type
D. The Project Charter
Sample question #1
• The risk shared between the buyer and the seller is determined by
which of the following?
A. The Scope of Work
B. The Teaming Agreement
C. The Contract Type
D. The Project Charter
Sample question #1
• You are trying to decide whether to lease or buy an item for your
project. The daily lease cost is $120. To purchase the item, the
investment cost is $1,000 and the daily maintenance cost is $20. How
long will it take for the lease cost to be the same as the purchase cost?
A. 10 days
B. 12 days
C. 120 days
D. 100 days
Sample question #2
• You are trying to decide whether to lease or buy an item for your
project. The daily lease cost is $120. To purchase the item, the
investment cost is $1,000 and the daily maintenance cost is $20. How
long will it take for the lease cost to be the same as the purchase cost?
A. 10 days
B. 12 days
C. 120 days
D. 100 days
Sample question #2
• You are managing a complex project and some of the project work needs to be
outsourced. You have prepared a procurement statement of work document and
you are about to advertise the job to obtain vendor proposals. However, you need
to have a benchmark document against which you can later compare the vendor
proposals. Your primary focus for this activity is to have control over the quoted
prices. You will also need this document later to compare whether or not your
vendors properly understood the scope of the work required. Which technique
should you use to develop this benchmark document?
A. Bidder Conferences
B. Independent Estimates
C. Internet Search
D. Procurement Negotiations
Sample question #3
• You are managing a complex project and some of the project work needs to be
outsourced. You have prepared a procurement statement of work document and
you are about to advertise the job to obtain vendor proposals. However, you need
to have a benchmark document against which you can later compare the vendor
proposals. Your primary focus for this activity is to have control over the quoted
prices. You will also need this document later to compare whether or not your
vendors properly understood the scope of the work required. Which technique
should you use to develop this benchmark document?
A. Bidder Conferences
B. Independent Estimates
C. Internet Search
D. Procurement Negotiations
Sample question #3
• The project team is arguing about the prospective sellers who have
submitted proposals. One team member argues for a certain seller
while another team member wants the project to be awarded to a
different seller. The best thing the project manager should remind the
team to focus on in order to make a selection is the:
A. Procurement documents
B. Procurement audits
C. Source selection criteria
D. Procurement management plan
Sample question #4
• The project team is arguing about the prospective sellers who have
submitted proposals. One team member argues for a certain seller
while another team member wants the project to be awarded to a
different seller. The best thing the project manager should remind the
team to focus on in order to make a selection is the:
A. Procurement documents
B. Procurement audits
C. Source selection criteria
D. Procurement management plan
Sample question #4
• During which procurement processes does procurement negotiation
occur?
A. Plan Procurement Management and Close Procurements
B. Control Procurements and Close Procurements
C. Conduct Procurements and Control Procurements
D. Conduct Procurements and Close Procurements
Sample question #5
• During which procurement processes does procurement negotiation
occur?
A. Plan Procurement Management and Close Procurements
B. Control Procurements and Close Procurements
C. Conduct Procurements and Control Procurements
D. Conduct Procurements and Close Procurements
Sample question #5
• Your program manager has come to you, the project manager, for help
with a bid for her newest project. You want to protect your company
from financial risk, and you have limited scope definition. What is the
best type of contract to choose?
A. Fixed Price (FP)
B. Cost Plus Percentage of Cost (CPPC)
C. Time and Material (T&M)
D. Cost Plus Fixed Fee (CPFF)
Sample question #6
• Your program manager has come to you, the project manager, for help
with a bid for her newest project. You want to protect your company
from financial risk, and you have limited scope definition. What is the
best type of contract to choose?
A. Fixed Price (FP)
B. Cost Plus Percentage of Cost (CPPC)
C. Time and Material (T&M)
D. Cost Plus Fixed Fee (CPFF)
Sample question #6
• Close procurements is different from Close Project or Phase in that
Close Procurements
A. Occurs before Close Project or Phase
B. Is the only one to involve the customer
C. Includes the return of property
D. May be done more than once for each contract
Sample question #7
• Close procurements is different from Close Project or Phase in that
Close Procurements
A. Occurs before Close Project or Phase
B. Is the only one to involve the customer
C. Includes the return of property
D. May be done more than once for each contract
Sample question #7
• A new project manager is about to begin creating the procurement statement of
work. One stakeholder wants to add many items to the procurement statement of
work. Another stakeholder only wants to describe the functional requirements.
The project is important for the project manager’s company, but a seller will do
the work. How would you advise the project manager?
A. The procurement statement of work should be general to allow the seller to make
their own decisions
B. The procurement statement of work should be general to allow for clarification later
C. The procurement statement of work should be detailed to allow for clarification later
D. The procurement statement of work should be as detailed as necessary for the type of
project
Sample question #8
• A new project manager is about to begin creating the procurement statement of
work. One stakeholder wants to add many items to the procurement statement of
work. Another stakeholder only wants to describe the functional requirements.
The project is important for the project manager’s company, but a seller will do
the work. How would you advise the project manager?
A. The procurement statement of work should be general to allow the seller to make
their own decisions
B. The procurement statement of work should be general to allow for clarification later
C. The procurement statement of work should be detailed to allow for clarification later
D. The procurement statement of work should be as detailed as necessary for the type of
project
Sample question #8
• What type of contract do you NOT want to use if you do not have
enough labor to audit invoices?
A. Cost plus fixed fee (CPFF)
B. Time & Material (T&M)
C. Fixed Price (FP)
D. Fixed Price Incentive Fee (FPIF)
Sample question #9
• What type of contract do you NOT want to use if you do not have
enough labor to audit invoices?
A. Cost plus fixed fee (CPFF)
B. Time & Material (T&M)
C. Fixed Price (FP)
D. Fixed Price Incentive Fee (FPIF)
Sample question #9
• In a fixed-price (FP) contract, the fee or profit is:
A. Unknown
B. Part of the negotiation involved in paying every invoice
C. Applied as a line item to every invoice
D. Determined with the other party at the end of the project
Sample question #10
• In a fixed-price (FP) contract, the fee or profit is:
A. Unknown
B. Part of the negotiation involved in paying every invoice
C. Applied as a line item to every invoice
D. Determined with the other party at the end of the project
Sample question #10
Vladimir VUJOVIĆ, PMP E-mail: vladimir.vujovic@gmail.com
PMO and BCM Manager
Delhaize Serbia
Sources used:
PMBOK Guide, 5th Edition
Rita Mulcahy’s PMP Exam Prep, 8th Edition
Good Luck!

Más contenido relacionado

La actualidad más candente

La actualidad más candente (20)

12 project procurement management
12 project procurement management12 project procurement management
12 project procurement management
 
Procurement management
Procurement managementProcurement management
Procurement management
 
Project scope management
Project scope managementProject scope management
Project scope management
 
PMP_Project Procurement Management
PMP_Project Procurement ManagementPMP_Project Procurement Management
PMP_Project Procurement Management
 
Procurement- Contract Management
Procurement- Contract ManagementProcurement- Contract Management
Procurement- Contract Management
 
11- PMP Training - Procurement Management
11- PMP Training - Procurement Management 11- PMP Training - Procurement Management
11- PMP Training - Procurement Management
 
Project Procurement Management
Project Procurement ManagementProject Procurement Management
Project Procurement Management
 
Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpoint
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and Process
 
Project management
Project managementProject management
Project management
 
Project Integration Management - PMP Preparation
Project Integration Management - PMP PreparationProject Integration Management - PMP Preparation
Project Integration Management - PMP Preparation
 
Procurement contract management
Procurement contract managementProcurement contract management
Procurement contract management
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
Contract Risks
Contract RisksContract Risks
Contract Risks
 
Overview to contract management
Overview to contract managementOverview to contract management
Overview to contract management
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
Contract management
Contract managementContract management
Contract management
 
2.project lifecycle
2.project lifecycle2.project lifecycle
2.project lifecycle
 
4-0 PROJECT EXECUTION AND CONTROL
4-0 PROJECT EXECUTION AND CONTROL4-0 PROJECT EXECUTION AND CONTROL
4-0 PROJECT EXECUTION AND CONTROL
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
 

Similar a Project Procurement Management - PMP preparation course

SLA LMD webinar - Art & Science of Negotiating and Managing Contracts May 2014
SLA LMD webinar - Art & Science of Negotiating and Managing Contracts May 2014SLA LMD webinar - Art & Science of Negotiating and Managing Contracts May 2014
SLA LMD webinar - Art & Science of Negotiating and Managing Contracts May 2014
lmd_presentations
 
Aptude's IT Managed Services Webinar
Aptude's IT Managed Services WebinarAptude's IT Managed Services Webinar
Aptude's IT Managed Services Webinar
aptude01
 

Similar a Project Procurement Management - PMP preparation course (20)

12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
Pmp session 6
Pmp session 6Pmp session 6
Pmp session 6
 
Project Procurement Planning
Project Procurement PlanningProject Procurement Planning
Project Procurement Planning
 
Executing the Project (1).pdf
Executing the Project (1).pdfExecuting the Project (1).pdf
Executing the Project (1).pdf
 
CIPS NC1.pptx
CIPS NC1.pptxCIPS NC1.pptx
CIPS NC1.pptx
 
SLA LMD webinar - Art & Science of Negotiating and Managing Contracts May 2014
SLA LMD webinar - Art & Science of Negotiating and Managing Contracts May 2014SLA LMD webinar - Art & Science of Negotiating and Managing Contracts May 2014
SLA LMD webinar - Art & Science of Negotiating and Managing Contracts May 2014
 
13. Project Procurement Management
13. Project Procurement Management13. Project Procurement Management
13. Project Procurement Management
 
Session 20 4th edition PMP
Session 20 4th edition PMPSession 20 4th edition PMP
Session 20 4th edition PMP
 
FAID DAOUD Updated Rsume FEB 2023.docx
FAID DAOUD Updated Rsume FEB 2023.docxFAID DAOUD Updated Rsume FEB 2023.docx
FAID DAOUD Updated Rsume FEB 2023.docx
 
Resume.Shahbaz
Resume.ShahbazResume.Shahbaz
Resume.Shahbaz
 
Fundamentals of Contractor Qualification
Fundamentals of Contractor QualificationFundamentals of Contractor Qualification
Fundamentals of Contractor Qualification
 
Aptude's IT Managed Services Webinar
Aptude's IT Managed Services WebinarAptude's IT Managed Services Webinar
Aptude's IT Managed Services Webinar
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
Pm 10 procurement
Pm 10 procurementPm 10 procurement
Pm 10 procurement
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
Measure everything - but make NPS the Key
Measure everything - but make NPS the Key Measure everything - but make NPS the Key
Measure everything - but make NPS the Key
 
Collaborating to Achieve Seamless Source to Pay in 2017
Collaborating to Achieve Seamless Source to Pay in 2017Collaborating to Achieve Seamless Source to Pay in 2017
Collaborating to Achieve Seamless Source to Pay in 2017
 
Collaborating to Achieve Seamless Source to Pay in 2017
Collaborating to Achieve Seamless Source to Pay in 2017Collaborating to Achieve Seamless Source to Pay in 2017
Collaborating to Achieve Seamless Source to Pay in 2017
 

Último

The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 

Último (20)

SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTSJAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR  ESCORTS
JAJPUR CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN JAJPUR ESCORTS
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
 

Project Procurement Management - PMP preparation course

  • 1. Presented by: Vladimir Vujović, PMP PMI Certification Preparation: PMP / CAPM - Project Procurement Management - Project Management Institute, Inc. All rights reserved. December 2017
  • 2. • Presenter • Participants: profile, background, expectations • Session: structure, approach and benefits Introduction to the session
  • 3. 1. Integration management 2. Scope management 3. Time management 4. Cost management 5. Quality management 6. Human resources management 7. Communications management 8. Risk management 9. Procurement management 10. Stakeholder management Project Management Knowledge Areas PMI PMBOK 5th edition
  • 4. 1. Plan Procurement Management 2. Conduct Procurements 3. Control Procurements 4. Close Procurements Project Procurement Management Processes:
  • 5. Plan Procurement Management Inputs • Project management plan • Requirements documentation • Risk register • Activity resource requirements • Project schedule • Activity cost estimates • Stakeholder register • Enterprise environmental factors • Organizational process assets Tools and Techniques • Make-or-buy analysis • Expert judgment • Market research • Meetings Outputs • Procurement management plan • Procurement statement of work • Procurement documents • Source selection criteria • Make-or-buy decisions • Change requests • Project document updates
  • 6. Plan Procurement Management: Data Flow Plan Procurement Management Close Procurements Identify Risks Enterprise / Organization Project Procurement Management • Activity cost estimates • OPA • EEF Identify Stakeholders Identify Risks • Stakeholder register Project documents• Project documents updates Control Procurements Conduct Procurements Estimate Costs Develop Schedule Estimate Activity Resources Collect Requirements Develop Project Management Plan Perform Integrated Change Control Identify Stakeholders• Project schedule • Activity resource requirements • Risk register • Project management plan • Requirements documentation • Make-or-buy decisions • Procurement management plan • Procurement statement of work • Source selection criteria •Procurementdocuments • Procurement documents • Procurement documents • Change requests
  • 7. • Fixed-price contracts • Cost-reimbursable contracts • Time and Material contracts (T&M) Types of contracts
  • 8. • Firm Fixed Price Contracts (FFP) • Fixed Price Incentive Fee Contracts (FPIF) • Fixed Price with Economic Price Adjustment Contracts (FP-EPA) Fixed-price contracts
  • 9. • Cost Plus Fixed Fee Contracts (CPFF) • Cost Plus Incentive Fee Contracts (CPIF) • Cost Plus Award Fee Contracts (CPAF) Cost-reimbursable contracts
  • 10. • Understanding of need • Overall or life-cycle cost • Technical capability • Risk • Management approach • Technical approach • Warranty • Financial capacity • Production capacity and interest • Business size and type • Past performance of sellers • References • Intellectual property rights • Proprietary rights Source selection criteria
  • 11. Conduct Procurements Inputs • Procurement management plan • Procurement documents • Source selection criteria • Seller proposals • Project documents • Make-or-buy decisions • Procurement statement of work • Organizational process assets Tools and Techniques • Bidder conference • Proposal evaluation techniques • Independent estimates • Expert judgment • Advertising • Analytical techniques • Procurement negotiations Outputs • Selected sellers • Agreements • Resource calendars • Change requests • Project management plan updates • Project documents updates
  • 12. Conduct Procurements: Data Flow Conduct Procurements Plan Procurement Management Develop Project Management Plan Enterprise / Organization Project Procurement Management • OPA Control Procurements Project documents • Agreements • Resource calendars • Project documents • Seller proposals Estimate Activity Resources Estimate Activity Durations Develop Schedule Determine Budget Develop Project Team Perform Integrated Change Control Develop Project Charter Project documents Sellers • Selected sellers • Procurement management plan • Procurement documents • Source selection criteria • Make-or-buy decisions • Procurement statement of work • Project documents updates • Project management plan updates • Resource calendars • Resource calendars • Resource calendars • Resource calendars • Change requests • Agreements
  • 13. Risk to Buyer and Seller According to Contract Types 100% Risk 0% Buyer Seller CPPC CPAF T&M FPIF CPFF CPIF FPEPA FP CPPC: Cost Plus Percentage of Costs CPFF: Cost Plus Fixed Fee CPAF: Cost Plus Award Fee CPIF: Cost Plus Incentive Fee T&M: Time and Material FPEPA: Fixed Price Economic Price Adjustment FPIF: Fixed Price Incentive Fee FP: Fixed Price
  • 14. Control Procurements Inputs • Project management plan • Procurement documents • Agreements • Approved change requests • Work performance reports • Work performance data Tools and Techniques • Contract change control system • Procurement performance reviews • Inspections and audits • Performance reporting • Payment systems • Claims administration • Records management system Outputs • Work performance information • Change requests • Project management plan updates • Project documents updates • Organizational process assets updates
  • 15. Control Procurements: Data Flow Control Procurements Plan Procurement Management Perform Integrated Change Control Project Procurement Management • Project communications • Work performance reports Perform Integrated Change Control Direct and Manage Project Work Develop Project Management Plan Project documents • Work performance data • Project Management Plan • OPA updates • Project documents updates • Change requests • Approved change requests • Work performance information Monitor and Control Project Work Conduct Procurements Enterprise / Organization • Project Management Plan updates • Procurement documents • Agreements
  • 16. Close Procurements Inputs • Project management plan • Procurement documents Tools and Techniques • Procurement audits • Procurement negotiations • Records management system Outputs • Closed procurements • Organizational process assets updates
  • 17. Close Procurements: Data Flow Close Procurements Plan Procurement Management Enterprise / Organization Project Procurement Management • Procurement documents Develop Project Management Plan • Project Management Plan • Closed procurements • OPA updates
  • 18. • The risk shared between the buyer and the seller is determined by which of the following? A. The Scope of Work B. The Teaming Agreement C. The Contract Type D. The Project Charter Sample question #1
  • 19. • The risk shared between the buyer and the seller is determined by which of the following? A. The Scope of Work B. The Teaming Agreement C. The Contract Type D. The Project Charter Sample question #1
  • 20. • You are trying to decide whether to lease or buy an item for your project. The daily lease cost is $120. To purchase the item, the investment cost is $1,000 and the daily maintenance cost is $20. How long will it take for the lease cost to be the same as the purchase cost? A. 10 days B. 12 days C. 120 days D. 100 days Sample question #2
  • 21. • You are trying to decide whether to lease or buy an item for your project. The daily lease cost is $120. To purchase the item, the investment cost is $1,000 and the daily maintenance cost is $20. How long will it take for the lease cost to be the same as the purchase cost? A. 10 days B. 12 days C. 120 days D. 100 days Sample question #2
  • 22. • You are managing a complex project and some of the project work needs to be outsourced. You have prepared a procurement statement of work document and you are about to advertise the job to obtain vendor proposals. However, you need to have a benchmark document against which you can later compare the vendor proposals. Your primary focus for this activity is to have control over the quoted prices. You will also need this document later to compare whether or not your vendors properly understood the scope of the work required. Which technique should you use to develop this benchmark document? A. Bidder Conferences B. Independent Estimates C. Internet Search D. Procurement Negotiations Sample question #3
  • 23. • You are managing a complex project and some of the project work needs to be outsourced. You have prepared a procurement statement of work document and you are about to advertise the job to obtain vendor proposals. However, you need to have a benchmark document against which you can later compare the vendor proposals. Your primary focus for this activity is to have control over the quoted prices. You will also need this document later to compare whether or not your vendors properly understood the scope of the work required. Which technique should you use to develop this benchmark document? A. Bidder Conferences B. Independent Estimates C. Internet Search D. Procurement Negotiations Sample question #3
  • 24. • The project team is arguing about the prospective sellers who have submitted proposals. One team member argues for a certain seller while another team member wants the project to be awarded to a different seller. The best thing the project manager should remind the team to focus on in order to make a selection is the: A. Procurement documents B. Procurement audits C. Source selection criteria D. Procurement management plan Sample question #4
  • 25. • The project team is arguing about the prospective sellers who have submitted proposals. One team member argues for a certain seller while another team member wants the project to be awarded to a different seller. The best thing the project manager should remind the team to focus on in order to make a selection is the: A. Procurement documents B. Procurement audits C. Source selection criteria D. Procurement management plan Sample question #4
  • 26. • During which procurement processes does procurement negotiation occur? A. Plan Procurement Management and Close Procurements B. Control Procurements and Close Procurements C. Conduct Procurements and Control Procurements D. Conduct Procurements and Close Procurements Sample question #5
  • 27. • During which procurement processes does procurement negotiation occur? A. Plan Procurement Management and Close Procurements B. Control Procurements and Close Procurements C. Conduct Procurements and Control Procurements D. Conduct Procurements and Close Procurements Sample question #5
  • 28. • Your program manager has come to you, the project manager, for help with a bid for her newest project. You want to protect your company from financial risk, and you have limited scope definition. What is the best type of contract to choose? A. Fixed Price (FP) B. Cost Plus Percentage of Cost (CPPC) C. Time and Material (T&M) D. Cost Plus Fixed Fee (CPFF) Sample question #6
  • 29. • Your program manager has come to you, the project manager, for help with a bid for her newest project. You want to protect your company from financial risk, and you have limited scope definition. What is the best type of contract to choose? A. Fixed Price (FP) B. Cost Plus Percentage of Cost (CPPC) C. Time and Material (T&M) D. Cost Plus Fixed Fee (CPFF) Sample question #6
  • 30. • Close procurements is different from Close Project or Phase in that Close Procurements A. Occurs before Close Project or Phase B. Is the only one to involve the customer C. Includes the return of property D. May be done more than once for each contract Sample question #7
  • 31. • Close procurements is different from Close Project or Phase in that Close Procurements A. Occurs before Close Project or Phase B. Is the only one to involve the customer C. Includes the return of property D. May be done more than once for each contract Sample question #7
  • 32. • A new project manager is about to begin creating the procurement statement of work. One stakeholder wants to add many items to the procurement statement of work. Another stakeholder only wants to describe the functional requirements. The project is important for the project manager’s company, but a seller will do the work. How would you advise the project manager? A. The procurement statement of work should be general to allow the seller to make their own decisions B. The procurement statement of work should be general to allow for clarification later C. The procurement statement of work should be detailed to allow for clarification later D. The procurement statement of work should be as detailed as necessary for the type of project Sample question #8
  • 33. • A new project manager is about to begin creating the procurement statement of work. One stakeholder wants to add many items to the procurement statement of work. Another stakeholder only wants to describe the functional requirements. The project is important for the project manager’s company, but a seller will do the work. How would you advise the project manager? A. The procurement statement of work should be general to allow the seller to make their own decisions B. The procurement statement of work should be general to allow for clarification later C. The procurement statement of work should be detailed to allow for clarification later D. The procurement statement of work should be as detailed as necessary for the type of project Sample question #8
  • 34. • What type of contract do you NOT want to use if you do not have enough labor to audit invoices? A. Cost plus fixed fee (CPFF) B. Time & Material (T&M) C. Fixed Price (FP) D. Fixed Price Incentive Fee (FPIF) Sample question #9
  • 35. • What type of contract do you NOT want to use if you do not have enough labor to audit invoices? A. Cost plus fixed fee (CPFF) B. Time & Material (T&M) C. Fixed Price (FP) D. Fixed Price Incentive Fee (FPIF) Sample question #9
  • 36. • In a fixed-price (FP) contract, the fee or profit is: A. Unknown B. Part of the negotiation involved in paying every invoice C. Applied as a line item to every invoice D. Determined with the other party at the end of the project Sample question #10
  • 37. • In a fixed-price (FP) contract, the fee or profit is: A. Unknown B. Part of the negotiation involved in paying every invoice C. Applied as a line item to every invoice D. Determined with the other party at the end of the project Sample question #10
  • 38. Vladimir VUJOVIĆ, PMP E-mail: vladimir.vujovic@gmail.com PMO and BCM Manager Delhaize Serbia Sources used: PMBOK Guide, 5th Edition Rita Mulcahy’s PMP Exam Prep, 8th Edition Good Luck!