Coal Combustion Residuals: Regulatory,
Litigation, and Enforcement Update
May Wall & Averil Edwards
January 16, 2014

Brought to you by Winston & Strawn’s
Environmental Practice Group
Today’s eLunch Presenters

May Wall
Environmental Practice Group
Washington, DC

Environmental Practice Group
Chicago, IL

mwall@winston.com

© 2014 Winston & Strawn LLP

Averil Edwards

aedwards@winston.com

2
Today’s Presentation
• EPA’s Regulatory Process and Status of CCR Rules
– Coal Combustion Residuals Proposals
– Power Plant Effluent Limitations Guidelines

• Federal Legislative Initiatives on CCR Management
– House of Representatives
– Senate

• Key CCR Litigation and Enforcement Proceedings
–
–
–
–

Appalachian Voices v. McCarthy
GenOn Consent Decree
Midwest Generation
Duke Energy

• Conclusions

© 2014 Winston & Strawn LLP

3
Regulatory Background
• 1980 – Bevill Amendment excludes coal ash from regulation as hazardous
waste under RCRA Subtitle C
– Bevill Amendment directed EPA to study whether regulation of coal ash under
Subtitle C was warranted

• 2000 – EPA issued a “regulatory determination” concluding that CCRs did not
warrant regulation under RCRA Subtitle C
– CCRs should be regulated under RCRA Subtitle D as solid waste by establishing
minimum nationwide standards for CCR disposal, but delayed issuance of the
regulations

• Following the December 2008 TVA Kingston TN impoundment release, EPA
decided to revisit coal ash regulation
• On June 21, 2010, EPA published its proposal to regulate CCRs under
RCRA

© 2014 Winston & Strawn LLP

4
2010 Proposed Rule
• Three options for regulation of CCRs:
– As “special waste” under RCRA Subtitle C, when the CCRs are destined for
disposal in landfills or surface impoundments (effectively phase out wet handling
and disposal in surface impoundments in 5 years); direct federal enforcement
– As non-hazardous waste under RCRA Subtitle D by establishing national
minimum criteria to be implemented and enforced by the states (wet handling
could continue if existing impoundments retrofitted)
– Subtitle D prime – less costly regulation as non-hazardous waste (e.g. no
composite liner requirements for existing impoundments)

• Dam safety requirements for surface impoundment under each option
• Beneficial uses of coal combustion products will remain exempt from
hazardous waste regulations—with some exceptions
• Main differences involve implementation and enforcement; each option will
increase compliance costs and litigation risks
• 450,000 comments; spurred multiple notices of data availability and
additional requests for comment

© 2014 Winston & Strawn LLP

5
Notices of Data Availability
• In October 2010, EPA published a NODA consisting of electric utility responses to
requests for information on CCR surface impoundments and the site assessments
EPA had conducted
• In October 2011, EPA published a NODA on additional information regarding:
–
–
–
–
–

Chemical constituent data from CCRs
Facility and waste management unit data
Information on additional alleged damage cases
Adequacy of State programs
Beneficial use

• In August 2013, EPA published a NODA regarding:
– Industry responses to EPA's questionnaire for the power plant ELGs, which contain technical
information regarding wastewater generation and treatment, and economic information such as
costs of wastewater treatment technologies
– Information relevant to developing appropriate criteria or otherwise defining what constitutes largescale fill, such as data on the size of structural fills that have resulted in damage cases
– Updating CCR leaching data using new algorithms
– Additional fish bio-concentration factors and other chemical-specific data for hazardous constituents
– EPA assessment reports on the structural integrity of hundreds of surface impoundments

© 2014 Winston & Strawn LLP

6
Legal Issues
•
•
•
•

Authority to overturn Bevill Determination
Retroactive application of management standards
Defects in Risk Assessment
Authority to mandate state permits, approve state permit programs, and to
impose and enforce criteria
• Mandatory 3-year review for regulations
• Environmental group comments
– New toxicity data mandates characterizing coal ash as hazardous
– CCR disposal under-regulated or not regulated at all by the states

• Industry group comments
– RCRA provides the statutory basis for EPA to develop Subtitle D rules for CCR

• Lawsuits kept pressure on EPA for issuing both the ELG and CCR rules;
• ELG expected sometime this year; CCR by end of year

© 2014 Winston & Strawn LLP

7
Proposed Effluent Limitations Guidelines (“ELGs”)
• Defenders of Wildlife v. Jackson – case filed in 2010 alleging EPA violated
Clean Water Act Section 304(b) by failing to annually revise, if appropriate,
the effluent limitations guidelines for steam electric power plants
• Proposed rule published on June 7, 2013; comment period ended September
20, 2013
• Eight options (including four preferred options) of effluent limitation guidelines
(ELG) for numerous wastestreams, including fly ash wastewater, bottom ash
wastewater, FGD wastewater, and leachate from CCR landfills and surface
impoundments
• ELGs would apply on a date determined by the permitting authority that is as
soon as possible within the next NPDES permit cycle beginning July 1, 2017

© 2014 Winston & Strawn LLP

8
Proposed ELGs at a Glance
Technology basis for the main BAT/NSPS/PSES/PSNS regulatory options

Wastestreams
1

Gasification Wastewater

Nonchemical Metal
Cleaning
Wastes

3

4a

4

5

Dry handling

Impoundment (Equal
to BPT).

Dry handling

Impoundment
(Equal to
BPT).

Impoundment (Equal
to BPT).

Impoundment (Equal to
BPT).

Impoundment
(Equal to
BPT).

Impoundment
(Equal to
BPT).

Impoundment (Equal
to BPT).

Impoundment
(Equal to BPT).

Impoundment
(Equal to
BPT).

Impoundment
(Equal to
BPT).

Chemical Precipitation.

Impoundment
(Equal to BPT).

Dry handling

Impoundment (Equal
to BPT).

Dry handling

Dry handling

Dry handling

Dry handling

Dry handling

Evaporation

Evaporation

Evaporation

Evaporation.

Evaporation

Evaporation

Evaporation

Evaporation

Chemical Precipitation.

Chemical Precipitation.

Chemical Precipitation.

Chemical Precipitation.

Chemical Precipitation.

Chemical Precipitation.

Chemical Precipitation.

Chemical Precipitation

Impoundment
(Equal to BPT).

FGMC Wastewater

3b

Chemical Precipitation +
Biological
Treatment.

Fly Ash Transport
Water.

Combustion Residual
Leachate.

2

BPJ Determination.

Chemical
Precipitation.

Bottom Ash Transport
Water.

3a

Chemical PreChemical Precipitation + Biological
cipitation +
Treatment for units
Biological
at a fa-cility with a
Treatment.
total wet- scrubbed
capacity of 2,000
MW and more; BPJ
determination for
<2,000 MW.

FGD Wastewater

Impoundment
(Equal to BPT).

Impoundment
(Equal to BPT).

© 2014 Winston & Strawn LLP

9

Dry handling

Chemical Precipitation +
Biological
Treatment.

Chemical Precipitation +
Biological
Treatment.

Dry handling

Dry handling

Dry handling/
Closed loop
(for units
>400 MW);
Impoundment
(Equal to
BPT)(for units
≤400
MW).

Dry handling/
Closed loop.

Chemical Precipitation +
Evaporation

Dry handling

Dry handling/
Closed loop

Chemical Precipitation
Proposed ELGs, cont’d.
• In preamble to proposed ELG rule, EPA suggested it is leaning towards
regulating CCRs as solid wastes under Subtitle D instead of as special wastes
under Subtitle C and coordinating the CCR rule with the final ELG rule
– Significant new data obtained from 495 power plants as part of 2010 Information Collection
Request
– Proposed CCR rule relied upon a 1995 industry report and a number of significant
assumptions in the risk assessment that supported the proposed CCR rule
– Data shows impoundments are generally smaller than the impoundments included in data
used to support the proposed CCR rule
– Updated risk assessment not yet completed, but the data “may have the potential to lower the
CCR rule risk assessment results by as much as an order of magnitude”

• EPA confirmed it is coordinating the proposed ELG regulation with the proposed
CCR rule, focusing on areas where the two rules would regulate the same type of
unit
– E.g., coordinating implementation of the two rules to allow facilities to determine the
operational changes needed to comply with the ELG regulation before they would have to
decide whether to close or retrofit surface impoundments under the CCR rule

© 2014 Winston & Strawn LLP

10
Proposed ELGs: Best Management Practices (“BMPs”) for
Surface Impoundments and Voluntary Incentive Program
• EPA is considering establishing BMP requirements that would apply to CCR
surface impoundments
– Would be established as part of the ELGs and implemented through NPDES permits
– Plant operators to conduct weekly inspections of active and inactive surface impoundments,
look for signs of structural instability and other hazardous conditions, and to take immediate
corrective actions where warranted
• Similar to the structural integrity inspection and corrective action requirements proposed in the CCR
rule, but would not include closure requirements

– Requirements that facilities submit to EPA or authorized state, plans for the design,
construction, and maintenance of existing impoundments, closure plans, periodic inspections,
and an annual certification
• Similar to the Mine Safety and Health Administration (“MSHA”), BMP rules applicable to coal slurry
impoundments

• EPA is also considering a voluntary program that would give existing power
plants an additional two years to comply with the ELG rules if they:
– Convert ash handling systems to dry handling or closed-loop tank-based systems, and
convert FGD wastewater treatment to tank-based systems
– Dewater, close, and cap all CCR surface impoundments (except CCR leachate
impoundments, which could continue to operate if CCR leachate is the only type of CCR
contained in the impoundment)

© 2014 Winston & Strawn LLP

11
Proposed ELGs, cont’d.
• Industry comments:
– Supportive of EPA’s intent to coordinate the two rules
– Subtitle D prime option should be selected because it is most compatible with the
proposed ELG rule
• Under Subtitle D prime, unlined surface impoundments can continue to operate; under
Subtitle C plants would be required to close all wet surface impoundments, which
contradicts some of the more lenient options of the ELG rule that allow wastewater to be
treated via impoundment

– Updated data should lower the CCR rule's original risk assessment

• Environmental organization comments:
– ELGs do not eliminate the need for a stringent CCR rule to address potentially
leaking and unstable CCR impoundments, groundwater cleanup, dust issues, and
siting and construction of engineered landfills

• Under the consent decree, EPA is required to finalize the ELG rule by May
22, 2014
• December 16, 2013 status update to Court – EPA in discussions with
plaintiffs to agree upon a modification to the consent decree for an extension

© 2014 Winston & Strawn LLP

12
Federal Legislative Proposals
• H.R. 2218, Coal Residuals Reuse and Management Act of 2013 – Passed the House
on July 25, 2013
• Would amend Subtitle D of RCRA under which coal ash regulated as solid waste
rather than hazardous waste
• States would be allowed to establish a coal ash permitting program with EPA oversight
authority
• If states decline, EPA would step in
• Coal ash permits would be required no later than seven years after enactment
• Sets forth minimum requirements that must be required by a state-issued CCR permit
– Certification by an independent professional engineer that the design of structures including
surface impoundments is in accordance with acceptable engineering practices and the
construction and maintenance of the structure will ensure dam stability
– Annual inspections by an independent professional engineer
– State agency authority to close deficient structures
– Location restrictions
– Wind dispersal of dust to be prevented

• Latest action: Placed on Senate Legislative Calendar on July 30 but unlikely to be
considered by the Senate

© 2014 Winston & Strawn LLP

13
Federal Legislative Proposals, cont’d.
• H.R. 2279, Reducing Excessive Deadline Obligations Act of 2013 –
Introduced in the House of Representatives on June 6, 2013, and referred to
the Committees on Energy and Commerce and Transportation and
Infrastructure
– Introduced by Rep. Cory Gardner (R-CO)
– Would amend Section 2002(b) of RCRA to eliminate the requirement to review
and revise, as necessary, regulations promulgated under RCRA at least every
three years
– EPA Administrator would be required to review and revise the regulations as he or
she determines is appropriate
– Passed the House on January 9, 2014, by a vote of 225 to 188, with five
Democrats voting for the bill and four Republicans voting against
– Currently before the Senate’s Committee on Environment and Public Works, but
unlikely to be passed by the Senate

© 2014 Winston & Strawn LLP

14
Legislative Prospects
• Senate action very unlikely
– Procedural rules place high hurdle (unanimous consent or cloture motion to
bypass committee)
– Not a Reid priority

© 2014 Winston & Strawn LLP

15
CCR Litigation and Enforcement Cases
• Appalachian Voices v. McCarthy: Lawsuits filed April 2012 by numerous
environmental groups (Appalachian Voices, Sierra Club, Environmental
Integrity Project, and others) and CCR recyclers Headwaters Resources, Inc.
and Boral Material Technologies Inc.
• Environmental organization complaint
– Section 2002(b) of RCRA requires EPA to review each RCRA regulation and
revise as necessary, at least every three years
– EPA has not reviewed and revised the CCR regulations since 1981 and “lost
pace” with industry developments
– EPA has failed to review its regulation exempting CCR from hazardous waste
regulation
– EPA has failed to revise and update the Subtitle D regulations for the
management of CCR in landfills and surface impoundments
• Existing Subtitle D regulations inadequate for protecting groundwater and surface water
from CCR disposal

– EPA has not revised the Toxicity Characteristic Leaching Procedure (“TCLP”), a
test for determining whether a solid waste is toxic, and therefore, hazardous,
since 2002, and has never revised the regulations to address CCR

© 2014 Winston & Strawn LLP

16
Appalachian Voices v. McCarthy, cont’d.
• Headwaters Resources, Inc. and Boral Material Technologies Inc. complaints
– Delay in determining whether to revise the Subtitle D regulations is creating
uncertainty in the beneficial use market
– EPA has violated Section 2002(b) of RCRA by failing to review the Subtitle D
regulations and revise them as necessary, at least every three years

• Summary Judgment Memorandum Opinion and Order
– Issued October 29, 2013
– Denied the environmental organizations’ request for an order directing EPA to
review and if necessary, revise the Subtitle D regulations concerning coal ash
within six months
– Denied the recyclers’ request to order EPA to announce its regulatory direction
and authority for the regulation within three months
– Ordered EPA to file a written submission with the court setting forth a proposed
deadline for compliance with the obligation to review and revise if necessary, the
Subtitle D regulations concerning CCR within 60 days of the court's order (by
December 30)

© 2014 Winston & Strawn LLP

17
Appalachian Voices v. McCarthy, cont’d.
• EPA filed an unopposed motion for a 30-day extension of time to submit its
proposed deadline submission
• Parties have reached “an agreement in principle on a deadline for EPA to
comply with its obligation to review, and revise if necessary, its Subtitle D
regulations”; working on finalizing a proposed consent decree, which could
be approved by the EPA and the DOJ within 30 days
• Proposed deadline submission is now due by January 29
• Consent decree will likely require EPA to complete the rulemaking by the end
of 2014

© 2014 Winston & Strawn LLP

18
CCR Lawsuits and Enforcement Actions
• GenOn Consent Decree
– Notice of Intent to sue filed by a group of environmental organizations; subsequently the State
filed a federal lawsuit
– Consent decree entered in May 2013 in Maryland district court
– GenOn agreed to pay the Maryland Department of the Environment a $1.9 million civil penalty
for groundwater and surface water contamination claims, investigate and remediate
contamination, install liner systems on leachate and stormwater collection ponds, cap all
closed CCR ponds

• Lawsuit against Midwest Generation
– Filed before the Illinois Pollution Control Board (Board) by the Sierra Club and other
environmental groups in October 2012
– Alleging groundwater contamination from CCR ponds at four Midwest Generation facilities
– On October 3, 2013, the Board denied Midwest Generation’s motion to dismiss the complaint
as frivolous or duplicative based upon the existence of Compliance Commitment Agreements
between Midwest Generation and the Illinois Environmental Protection Agency

• Lawsuits against Duke Energy
– On September 12, 2013, the SELC and other environmental groups sued Duke Energy
Progress in federal court under the Clean Water Act for alleged CCR pollution from its Sutton
plant
– SELC and the NCDENR have pending lawsuits against other Duke facilities

© 2014 Winston & Strawn LLP

19
CCR Lawsuits and Enforcement Actions, cont’d.
• Winyah Rivers Foundation v. S.C. Public Service Authority (D.S.C.)
– Complaint filed April 29, 2013, citing violations of the Clean Water Act
• Lawsuit also filed in state court alleging violations of the S.C. Pollution Control Act

– Grainger Station closed due to the lawsuits
– In November 2013, the parties reached a settlement agreement resolving both
lawsuits, under which S.C. Public Service Authority agreed to remove 1.3 million
tons of CCR stored in unlined ponds beside the Waccamaw River within 7-10
years

• Anderson v. FirstEnergy Corporation (D.W.V.)
– Complaint filed October 10, 2013, by more than 50 West Virginia residents
– Common law claims of negligence, private nuisance, and trespass
– Alleging contamination of plaintiffs' properties from the unlined Little Blue Run
impoundment at FirstEnergy's Bruce Mansfield Plant
– FirstEnergy previously settled a PADEP action in a December 2012 consent
decree that required FirstEnergy to submit a closure plan for the impoundment by
March 31, 2013
– Complaint alleges that closure under FirstEnergy's proposed closure plan won't
begin in 2017 and won’t end until 2032

© 2014 Winston & Strawn LLP

20
CCR Lawsuits and Enforcement Actions, cont’d.
• TVA Ash Spill Litigation (E.D. Tenn.)
– 60 consolidated cases involving more than 800 plaintiffs
– Bifurcation (Phase I v. Phase II)
– Phase I August 23, 2012 liability decision
• Dismissed claims: negligence per se, recklessness, strict liability, and public nuisance
• TVA liable for negligence, trespass and private nuisance
• Cited (1) selection of location of dike, (2) designs of dike, and (3) failure to adequately
inform employees of applicable policies and procedures
• “Had TVA followed its own mandatory policies, procedures and practices, the subsurface
issues underlying the failure of the North Dike would have been investigated, addressed,
and potentially remedied before the catastrophic failure on December 22, 2008.”

– Phase II: Individualized evidentiary proceedings on damages
•
•
•
•

November 20, 2012 order referred Phase II of the litigation to mediation
Litigation proceedings currently stayed pending mediation
Three extensions of the deadline for the conclusion of mediation
October 24, 2013 order extended mediation for an additional 105 days

© 2014 Winston & Strawn LLP

21
Conclusions
• Continued push for RCRA Subtitle C regulation by environmental
organizations
• Momentum appears to be leaning towards a Subtitle-D-type program that is
coordinated with the power plant effluent limitations guidelines
• Legislative prospects unlikely but the House remains active
• Litigation against operators of CCR impoundments and landfills continues
• Lawsuits largely driven by environmental organizations
– Demands
• Phase-out of wet CCR storage
• Retrofit with covers, liners and leachate collection
• Investigation and remediation of groundwater contamination

© 2014 Winston & Strawn LLP

22
Questions?
Thank You.
Contact Information

May Wall

Averil Edwards

Environmental Practice Group
Washington, D.C.
(202) 282-5962
mwall@winston.com

Environmental Practice Group
Chicago
(312) 558-8310
aedwards@winston.com

© 2014 Winston & Strawn LLP

25

Más contenido relacionado

La actualidad más candente

Grand Canyon Trust - Opportunity for Transition
Grand Canyon Trust - Opportunity for TransitionGrand Canyon Trust - Opportunity for Transition
Grand Canyon Trust - Opportunity for Transition
en3pro
 
Island states - Renewable Energy Policy Pioneers
Island states - Renewable Energy Policy PioneersIsland states - Renewable Energy Policy Pioneers
Island states - Renewable Energy Policy Pioneers
Leonardo ENERGY
 
Fracking - AWMA Presentation
Fracking  - AWMA PresentationFracking  - AWMA Presentation
Fracking - AWMA Presentation
kwtght
 

La actualidad más candente (20)

Master Plan EIR CAP Presentation - March 27, 2014
Master Plan EIR CAP Presentation - March 27, 2014Master Plan EIR CAP Presentation - March 27, 2014
Master Plan EIR CAP Presentation - March 27, 2014
 
Climate Action Plan Update Sept 12 2013 Special Board Mtg
Climate Action Plan Update Sept 12 2013 Special Board MtgClimate Action Plan Update Sept 12 2013 Special Board Mtg
Climate Action Plan Update Sept 12 2013 Special Board Mtg
 
EPA's Clean Power Plan: Basics and Implications of the Proposed CO2 Emissions...
EPA's Clean Power Plan: Basics and Implications of the Proposed CO2 Emissions...EPA's Clean Power Plan: Basics and Implications of the Proposed CO2 Emissions...
EPA's Clean Power Plan: Basics and Implications of the Proposed CO2 Emissions...
 
Wp final climate action plan oct 24 2013
Wp   final climate action plan oct 24 2013Wp   final climate action plan oct 24 2013
Wp final climate action plan oct 24 2013
 
A Survey of the Generation Landscape
A Survey of the Generation LandscapeA Survey of the Generation Landscape
A Survey of the Generation Landscape
 
Grand Canyon Trust - Opportunity for Transition
Grand Canyon Trust - Opportunity for TransitionGrand Canyon Trust - Opportunity for Transition
Grand Canyon Trust - Opportunity for Transition
 
Philippine Geothermal Industry: Current Status and Perspectives
Philippine Geothermal Industry: Current Status and Perspectives�Philippine Geothermal Industry: Current Status and Perspectives�
Philippine Geothermal Industry: Current Status and Perspectives
 
Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”
Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”
Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”
 
Environmental Issues in Federal Permitting for Energy Projects
Environmental Issues in Federal Permitting for Energy ProjectsEnvironmental Issues in Federal Permitting for Energy Projects
Environmental Issues in Federal Permitting for Energy Projects
 
ScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden's 51st State Roadmap
ScottMadden's 51st State Roadmap
 
LNG Facility GHG Mitigation Options - Government of Nova Scotia
LNG Facility GHG Mitigation Options - Government of Nova ScotiaLNG Facility GHG Mitigation Options - Government of Nova Scotia
LNG Facility GHG Mitigation Options - Government of Nova Scotia
 
Island states - Renewable Energy Policy Pioneers
Island states - Renewable Energy Policy PioneersIsland states - Renewable Energy Policy Pioneers
Island states - Renewable Energy Policy Pioneers
 
1. Addressing Ireland's Water challenges, the National Response - Feargal O C...
1. Addressing Ireland's Water challenges, the National Response - Feargal O C...1. Addressing Ireland's Water challenges, the National Response - Feargal O C...
1. Addressing Ireland's Water challenges, the National Response - Feargal O C...
 
Fracking - AWMA Presentation
Fracking  - AWMA PresentationFracking  - AWMA Presentation
Fracking - AWMA Presentation
 
Update on ERCOT Activities
Update on ERCOT ActivitiesUpdate on ERCOT Activities
Update on ERCOT Activities
 
Master Plan Public Hearing Presentation - January 9, 2014
Master Plan Public Hearing Presentation - January 9, 2014Master Plan Public Hearing Presentation - January 9, 2014
Master Plan Public Hearing Presentation - January 9, 2014
 
EDPP Legislative Update by Jeremy Browner
EDPP Legislative Update by Jeremy BrownerEDPP Legislative Update by Jeremy Browner
EDPP Legislative Update by Jeremy Browner
 
Geothermal Presentation, March 14, 2013, Madrid/ Spain
Geothermal Presentation, March 14, 2013, Madrid/ SpainGeothermal Presentation, March 14, 2013, Madrid/ Spain
Geothermal Presentation, March 14, 2013, Madrid/ Spain
 
Regulation of Landfill in Ireland
Regulation of Landfill in IrelandRegulation of Landfill in Ireland
Regulation of Landfill in Ireland
 
San Antonio Vista Ridge Project
San Antonio Vista Ridge ProjectSan Antonio Vista Ridge Project
San Antonio Vista Ridge Project
 

Destacado (7)

World of Coal Ash 2013 bijoy
World of Coal Ash 2013 bijoyWorld of Coal Ash 2013 bijoy
World of Coal Ash 2013 bijoy
 
Gas turbine co propulsion power plant for marine system ije - copy
Gas turbine co propulsion power plant for marine system  ije - copyGas turbine co propulsion power plant for marine system  ije - copy
Gas turbine co propulsion power plant for marine system ije - copy
 
Slidshere
SlidshereSlidshere
Slidshere
 
Exercise and Training
Exercise and TrainingExercise and Training
Exercise and Training
 
CV Helmar 05.03.2015
CV Helmar 05.03.2015CV Helmar 05.03.2015
CV Helmar 05.03.2015
 
New Solutions for NPP Robustness Improvement
New Solutions for NPP Robustness ImprovementNew Solutions for NPP Robustness Improvement
New Solutions for NPP Robustness Improvement
 
1727092 634985076667011250
1727092 6349850766670112501727092 634985076667011250
1727092 634985076667011250
 

Similar a Coal Combustion Residuals: Regulatory, Litigation, and Enforcement Update

Including Electricity Imports in California’s Cap-and-Trade Program: A Case S...
Including Electricity Imports in California’s Cap-and-Trade Program: A Case S...Including Electricity Imports in California’s Cap-and-Trade Program: A Case S...
Including Electricity Imports in California’s Cap-and-Trade Program: A Case S...
Stefan U. Pauer, PhD
 
Greenhouse Gas Limits on New Electric Generating Units
Greenhouse Gas Limits on New Electric Generating UnitsGreenhouse Gas Limits on New Electric Generating Units
Greenhouse Gas Limits on New Electric Generating Units
Andrew Shroads
 
2023 Air Quality in California: What You Need to Know
2023 Air Quality in California: What You Need to Know2023 Air Quality in California: What You Need to Know
2023 Air Quality in California: What You Need to Know
BlueScape
 

Similar a Coal Combustion Residuals: Regulatory, Litigation, and Enforcement Update (20)

BlueScape Air Quality in 2015: What You Need to Know Webinar 2-10-15
BlueScape Air Quality in 2015: What You Need to Know Webinar 2-10-15BlueScape Air Quality in 2015: What You Need to Know Webinar 2-10-15
BlueScape Air Quality in 2015: What You Need to Know Webinar 2-10-15
 
Hieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland Park
Hieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland ParkHieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland Park
Hieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland Park
 
An Update on Changes to Missouri Environmental Regulations at 2013 Mid Americ...
An Update on Changes to Missouri Environmental Regulations at 2013 Mid Americ...An Update on Changes to Missouri Environmental Regulations at 2013 Mid Americ...
An Update on Changes to Missouri Environmental Regulations at 2013 Mid Americ...
 
Trends in Energy Regulatory Law
Trends in Energy Regulatory LawTrends in Energy Regulatory Law
Trends in Energy Regulatory Law
 
Including Electricity Imports in California’s Cap-and-Trade Program: A Case S...
Including Electricity Imports in California’s Cap-and-Trade Program: A Case S...Including Electricity Imports in California’s Cap-and-Trade Program: A Case S...
Including Electricity Imports in California’s Cap-and-Trade Program: A Case S...
 
The Carbon Nexus - Boilers, Power Plants, and Strategic Energy Management
The Carbon Nexus - Boilers, Power Plants, and Strategic Energy ManagementThe Carbon Nexus - Boilers, Power Plants, and Strategic Energy Management
The Carbon Nexus - Boilers, Power Plants, and Strategic Energy Management
 
Patchwork Blue - Survey of US RWH Laws - ARCSA Conference - Oct 2017
Patchwork Blue - Survey of US RWH Laws - ARCSA Conference - Oct 2017Patchwork Blue - Survey of US RWH Laws - ARCSA Conference - Oct 2017
Patchwork Blue - Survey of US RWH Laws - ARCSA Conference - Oct 2017
 
New Developments in the Natural Gas Industry
New Developments in the Natural Gas IndustryNew Developments in the Natural Gas Industry
New Developments in the Natural Gas Industry
 
Analyzing the Hazardous Waste Generator Improvements Rule
Analyzing the Hazardous Waste Generator Improvements RuleAnalyzing the Hazardous Waste Generator Improvements Rule
Analyzing the Hazardous Waste Generator Improvements Rule
 
Jeffery Pope, PE, Burns & McDonnell, Coal Ash Rule: Impact on Utilities and C...
Jeffery Pope, PE, Burns & McDonnell, Coal Ash Rule: Impact on Utilities and C...Jeffery Pope, PE, Burns & McDonnell, Coal Ash Rule: Impact on Utilities and C...
Jeffery Pope, PE, Burns & McDonnell, Coal Ash Rule: Impact on Utilities and C...
 
Communicating Environmental Regulations: It's Good Business
Communicating Environmental Regulations: It's Good BusinessCommunicating Environmental Regulations: It's Good Business
Communicating Environmental Regulations: It's Good Business
 
Greenhouse Gas Limits on New Electric Generating Units
Greenhouse Gas Limits on New Electric Generating UnitsGreenhouse Gas Limits on New Electric Generating Units
Greenhouse Gas Limits on New Electric Generating Units
 
Applying federal environmental laws to co2 enhanced oil recovery ppt
Applying federal environmental laws to co2 enhanced oil recovery pptApplying federal environmental laws to co2 enhanced oil recovery ppt
Applying federal environmental laws to co2 enhanced oil recovery ppt
 
Chris Wieberg, MDNR, Central Office Permitting Update, Missouri Water Seminar...
Chris Wieberg, MDNR, Central Office Permitting Update, Missouri Water Seminar...Chris Wieberg, MDNR, Central Office Permitting Update, Missouri Water Seminar...
Chris Wieberg, MDNR, Central Office Permitting Update, Missouri Water Seminar...
 
Pendergrass, Gary, GeoEngineers Inc., USEPA Coal Combustion Residuals Rule, I...
Pendergrass, Gary, GeoEngineers Inc., USEPA Coal Combustion Residuals Rule, I...Pendergrass, Gary, GeoEngineers Inc., USEPA Coal Combustion Residuals Rule, I...
Pendergrass, Gary, GeoEngineers Inc., USEPA Coal Combustion Residuals Rule, I...
 
EPA's Clean Power Plan – An Update
EPA's Clean Power Plan – An UpdateEPA's Clean Power Plan – An Update
EPA's Clean Power Plan – An Update
 
J Daniels US CCS Policy
J Daniels US CCS PolicyJ Daniels US CCS Policy
J Daniels US CCS Policy
 
2023 Air Quality in California: What You Need to Know
2023 Air Quality in California: What You Need to Know2023 Air Quality in California: What You Need to Know
2023 Air Quality in California: What You Need to Know
 
The Hazardous Waste Generator Improvements Rule Proposal
The Hazardous Waste Generator Improvements Rule ProposalThe Hazardous Waste Generator Improvements Rule Proposal
The Hazardous Waste Generator Improvements Rule Proposal
 
Marcia Willhite, Illinois EPA, Chloride Issue in the Chicago Area Waterway Sy...
Marcia Willhite, Illinois EPA, Chloride Issue in the Chicago Area Waterway Sy...Marcia Willhite, Illinois EPA, Chloride Issue in the Chicago Area Waterway Sy...
Marcia Willhite, Illinois EPA, Chloride Issue in the Chicago Area Waterway Sy...
 

Más de Winston & Strawn LLP

Solutions to Section 301 Tariffs on Products from China—Managing the Shock of...
Solutions to Section 301 Tariffs on Products from China—Managing the Shock of...Solutions to Section 301 Tariffs on Products from China—Managing the Shock of...
Solutions to Section 301 Tariffs on Products from China—Managing the Shock of...
Winston & Strawn LLP
 

Más de Winston & Strawn LLP (20)

The Nordic Sessions: Avoiding Employment Law Landmines
The Nordic Sessions: Avoiding Employment Law LandminesThe Nordic Sessions: Avoiding Employment Law Landmines
The Nordic Sessions: Avoiding Employment Law Landmines
 
Latest Developments Regarding Arbitration in Hong Kong and Mainland China
Latest Developments Regarding Arbitration in Hong Kong and Mainland ChinaLatest Developments Regarding Arbitration in Hong Kong and Mainland China
Latest Developments Regarding Arbitration in Hong Kong and Mainland China
 
Recent Trends in Regulatory Actions Impacting Banks and Financial Institutions
Recent Trends in Regulatory Actions Impacting Banks and Financial InstitutionsRecent Trends in Regulatory Actions Impacting Banks and Financial Institutions
Recent Trends in Regulatory Actions Impacting Banks and Financial Institutions
 
Computer Forensics – What Every Lawyer Needs to Know
Computer Forensics – What Every Lawyer Needs to KnowComputer Forensics – What Every Lawyer Needs to Know
Computer Forensics – What Every Lawyer Needs to Know
 
Maximizing Deductions in Light of the Section 162(m) Guidance
Maximizing Deductions in Light of the Section 162(m) GuidanceMaximizing Deductions in Light of the Section 162(m) Guidance
Maximizing Deductions in Light of the Section 162(m) Guidance
 
Regulators on the Move – Recent Treasury and Comptroller Actions: How They Af...
Regulators on the Move – Recent Treasury and Comptroller Actions: How They Af...Regulators on the Move – Recent Treasury and Comptroller Actions: How They Af...
Regulators on the Move – Recent Treasury and Comptroller Actions: How They Af...
 
IRS and DOL Audit Issues for Retirement Plans
IRS and DOL Audit Issues for Retirement PlansIRS and DOL Audit Issues for Retirement Plans
IRS and DOL Audit Issues for Retirement Plans
 
Solutions to Section 301 Tariffs on Products from China—Managing the Shock of...
Solutions to Section 301 Tariffs on Products from China—Managing the Shock of...Solutions to Section 301 Tariffs on Products from China—Managing the Shock of...
Solutions to Section 301 Tariffs on Products from China—Managing the Shock of...
 
Best Practices for Anti-Bribery and Anti-Corruption (ABAC) Compliance
Best Practices for Anti-Bribery and Anti-Corruption (ABAC) ComplianceBest Practices for Anti-Bribery and Anti-Corruption (ABAC) Compliance
Best Practices for Anti-Bribery and Anti-Corruption (ABAC) Compliance
 
International Transactions Program
International Transactions ProgramInternational Transactions Program
International Transactions Program
 
Recent Legislation Impacting Dodd-Frank Requirements: What Financial Institut...
Recent Legislation Impacting Dodd-Frank Requirements: What Financial Institut...Recent Legislation Impacting Dodd-Frank Requirements: What Financial Institut...
Recent Legislation Impacting Dodd-Frank Requirements: What Financial Institut...
 
Trade Secret Protection: Practical Advice on Protecting and Defending Your Or...
Trade Secret Protection: Practical Advice on Protecting and Defending Your Or...Trade Secret Protection: Practical Advice on Protecting and Defending Your Or...
Trade Secret Protection: Practical Advice on Protecting and Defending Your Or...
 
Cryptocurrency Crackdown: What You Need to Know about Enhanced IRS/Government...
Cryptocurrency Crackdown: What You Need to Know about Enhanced IRS/Government...Cryptocurrency Crackdown: What You Need to Know about Enhanced IRS/Government...
Cryptocurrency Crackdown: What You Need to Know about Enhanced IRS/Government...
 
Sanctions & Export Controls: Focus on Medical Devices
Sanctions & Export Controls: Focus on Medical DevicesSanctions & Export Controls: Focus on Medical Devices
Sanctions & Export Controls: Focus on Medical Devices
 
The Equal Rights Amendment: Legal Issues and Implications
The Equal Rights Amendment: Legal Issues and ImplicationsThe Equal Rights Amendment: Legal Issues and Implications
The Equal Rights Amendment: Legal Issues and Implications
 
Under New Management: What to Expect from a Trump NLRB
Under New Management: What to Expect from a Trump NLRBUnder New Management: What to Expect from a Trump NLRB
Under New Management: What to Expect from a Trump NLRB
 
2018 Hot Topics for Health & Welfare Plans, Fringe Benefits, and Withholding ...
2018 Hot Topics for Health & Welfare Plans, Fringe Benefits, and Withholding ...2018 Hot Topics for Health & Welfare Plans, Fringe Benefits, and Withholding ...
2018 Hot Topics for Health & Welfare Plans, Fringe Benefits, and Withholding ...
 
The Real Deal Webinar Series: Delaware Law Developments/Recent Judicial Decis...
The Real Deal Webinar Series: Delaware Law Developments/Recent Judicial Decis...The Real Deal Webinar Series: Delaware Law Developments/Recent Judicial Decis...
The Real Deal Webinar Series: Delaware Law Developments/Recent Judicial Decis...
 
GDPR is Coming, Five Things You Can Do Now To Prepare
GDPR is Coming, Five Things You Can Do Now To PrepareGDPR is Coming, Five Things You Can Do Now To Prepare
GDPR is Coming, Five Things You Can Do Now To Prepare
 
The Real Deal Webinar Series: Practical Advice from a Former Chief Compliance...
The Real Deal Webinar Series: Practical Advice from a Former Chief Compliance...The Real Deal Webinar Series: Practical Advice from a Former Chief Compliance...
The Real Deal Webinar Series: Practical Advice from a Former Chief Compliance...
 

Último

1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
ssuserdda66b
 

Último (20)

How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 

Coal Combustion Residuals: Regulatory, Litigation, and Enforcement Update

  • 1. Coal Combustion Residuals: Regulatory, Litigation, and Enforcement Update May Wall & Averil Edwards January 16, 2014 Brought to you by Winston & Strawn’s Environmental Practice Group
  • 2. Today’s eLunch Presenters May Wall Environmental Practice Group Washington, DC Environmental Practice Group Chicago, IL mwall@winston.com © 2014 Winston & Strawn LLP Averil Edwards aedwards@winston.com 2
  • 3. Today’s Presentation • EPA’s Regulatory Process and Status of CCR Rules – Coal Combustion Residuals Proposals – Power Plant Effluent Limitations Guidelines • Federal Legislative Initiatives on CCR Management – House of Representatives – Senate • Key CCR Litigation and Enforcement Proceedings – – – – Appalachian Voices v. McCarthy GenOn Consent Decree Midwest Generation Duke Energy • Conclusions © 2014 Winston & Strawn LLP 3
  • 4. Regulatory Background • 1980 – Bevill Amendment excludes coal ash from regulation as hazardous waste under RCRA Subtitle C – Bevill Amendment directed EPA to study whether regulation of coal ash under Subtitle C was warranted • 2000 – EPA issued a “regulatory determination” concluding that CCRs did not warrant regulation under RCRA Subtitle C – CCRs should be regulated under RCRA Subtitle D as solid waste by establishing minimum nationwide standards for CCR disposal, but delayed issuance of the regulations • Following the December 2008 TVA Kingston TN impoundment release, EPA decided to revisit coal ash regulation • On June 21, 2010, EPA published its proposal to regulate CCRs under RCRA © 2014 Winston & Strawn LLP 4
  • 5. 2010 Proposed Rule • Three options for regulation of CCRs: – As “special waste” under RCRA Subtitle C, when the CCRs are destined for disposal in landfills or surface impoundments (effectively phase out wet handling and disposal in surface impoundments in 5 years); direct federal enforcement – As non-hazardous waste under RCRA Subtitle D by establishing national minimum criteria to be implemented and enforced by the states (wet handling could continue if existing impoundments retrofitted) – Subtitle D prime – less costly regulation as non-hazardous waste (e.g. no composite liner requirements for existing impoundments) • Dam safety requirements for surface impoundment under each option • Beneficial uses of coal combustion products will remain exempt from hazardous waste regulations—with some exceptions • Main differences involve implementation and enforcement; each option will increase compliance costs and litigation risks • 450,000 comments; spurred multiple notices of data availability and additional requests for comment © 2014 Winston & Strawn LLP 5
  • 6. Notices of Data Availability • In October 2010, EPA published a NODA consisting of electric utility responses to requests for information on CCR surface impoundments and the site assessments EPA had conducted • In October 2011, EPA published a NODA on additional information regarding: – – – – – Chemical constituent data from CCRs Facility and waste management unit data Information on additional alleged damage cases Adequacy of State programs Beneficial use • In August 2013, EPA published a NODA regarding: – Industry responses to EPA's questionnaire for the power plant ELGs, which contain technical information regarding wastewater generation and treatment, and economic information such as costs of wastewater treatment technologies – Information relevant to developing appropriate criteria or otherwise defining what constitutes largescale fill, such as data on the size of structural fills that have resulted in damage cases – Updating CCR leaching data using new algorithms – Additional fish bio-concentration factors and other chemical-specific data for hazardous constituents – EPA assessment reports on the structural integrity of hundreds of surface impoundments © 2014 Winston & Strawn LLP 6
  • 7. Legal Issues • • • • Authority to overturn Bevill Determination Retroactive application of management standards Defects in Risk Assessment Authority to mandate state permits, approve state permit programs, and to impose and enforce criteria • Mandatory 3-year review for regulations • Environmental group comments – New toxicity data mandates characterizing coal ash as hazardous – CCR disposal under-regulated or not regulated at all by the states • Industry group comments – RCRA provides the statutory basis for EPA to develop Subtitle D rules for CCR • Lawsuits kept pressure on EPA for issuing both the ELG and CCR rules; • ELG expected sometime this year; CCR by end of year © 2014 Winston & Strawn LLP 7
  • 8. Proposed Effluent Limitations Guidelines (“ELGs”) • Defenders of Wildlife v. Jackson – case filed in 2010 alleging EPA violated Clean Water Act Section 304(b) by failing to annually revise, if appropriate, the effluent limitations guidelines for steam electric power plants • Proposed rule published on June 7, 2013; comment period ended September 20, 2013 • Eight options (including four preferred options) of effluent limitation guidelines (ELG) for numerous wastestreams, including fly ash wastewater, bottom ash wastewater, FGD wastewater, and leachate from CCR landfills and surface impoundments • ELGs would apply on a date determined by the permitting authority that is as soon as possible within the next NPDES permit cycle beginning July 1, 2017 © 2014 Winston & Strawn LLP 8
  • 9. Proposed ELGs at a Glance Technology basis for the main BAT/NSPS/PSES/PSNS regulatory options Wastestreams 1 Gasification Wastewater Nonchemical Metal Cleaning Wastes 3 4a 4 5 Dry handling Impoundment (Equal to BPT). Dry handling Impoundment (Equal to BPT). Impoundment (Equal to BPT). Impoundment (Equal to BPT). Impoundment (Equal to BPT). Impoundment (Equal to BPT). Impoundment (Equal to BPT). Impoundment (Equal to BPT). Impoundment (Equal to BPT). Impoundment (Equal to BPT). Chemical Precipitation. Impoundment (Equal to BPT). Dry handling Impoundment (Equal to BPT). Dry handling Dry handling Dry handling Dry handling Dry handling Evaporation Evaporation Evaporation Evaporation. Evaporation Evaporation Evaporation Evaporation Chemical Precipitation. Chemical Precipitation. Chemical Precipitation. Chemical Precipitation. Chemical Precipitation. Chemical Precipitation. Chemical Precipitation. Chemical Precipitation Impoundment (Equal to BPT). FGMC Wastewater 3b Chemical Precipitation + Biological Treatment. Fly Ash Transport Water. Combustion Residual Leachate. 2 BPJ Determination. Chemical Precipitation. Bottom Ash Transport Water. 3a Chemical PreChemical Precipitation + Biological cipitation + Treatment for units Biological at a fa-cility with a Treatment. total wet- scrubbed capacity of 2,000 MW and more; BPJ determination for <2,000 MW. FGD Wastewater Impoundment (Equal to BPT). Impoundment (Equal to BPT). © 2014 Winston & Strawn LLP 9 Dry handling Chemical Precipitation + Biological Treatment. Chemical Precipitation + Biological Treatment. Dry handling Dry handling Dry handling/ Closed loop (for units >400 MW); Impoundment (Equal to BPT)(for units ≤400 MW). Dry handling/ Closed loop. Chemical Precipitation + Evaporation Dry handling Dry handling/ Closed loop Chemical Precipitation
  • 10. Proposed ELGs, cont’d. • In preamble to proposed ELG rule, EPA suggested it is leaning towards regulating CCRs as solid wastes under Subtitle D instead of as special wastes under Subtitle C and coordinating the CCR rule with the final ELG rule – Significant new data obtained from 495 power plants as part of 2010 Information Collection Request – Proposed CCR rule relied upon a 1995 industry report and a number of significant assumptions in the risk assessment that supported the proposed CCR rule – Data shows impoundments are generally smaller than the impoundments included in data used to support the proposed CCR rule – Updated risk assessment not yet completed, but the data “may have the potential to lower the CCR rule risk assessment results by as much as an order of magnitude” • EPA confirmed it is coordinating the proposed ELG regulation with the proposed CCR rule, focusing on areas where the two rules would regulate the same type of unit – E.g., coordinating implementation of the two rules to allow facilities to determine the operational changes needed to comply with the ELG regulation before they would have to decide whether to close or retrofit surface impoundments under the CCR rule © 2014 Winston & Strawn LLP 10
  • 11. Proposed ELGs: Best Management Practices (“BMPs”) for Surface Impoundments and Voluntary Incentive Program • EPA is considering establishing BMP requirements that would apply to CCR surface impoundments – Would be established as part of the ELGs and implemented through NPDES permits – Plant operators to conduct weekly inspections of active and inactive surface impoundments, look for signs of structural instability and other hazardous conditions, and to take immediate corrective actions where warranted • Similar to the structural integrity inspection and corrective action requirements proposed in the CCR rule, but would not include closure requirements – Requirements that facilities submit to EPA or authorized state, plans for the design, construction, and maintenance of existing impoundments, closure plans, periodic inspections, and an annual certification • Similar to the Mine Safety and Health Administration (“MSHA”), BMP rules applicable to coal slurry impoundments • EPA is also considering a voluntary program that would give existing power plants an additional two years to comply with the ELG rules if they: – Convert ash handling systems to dry handling or closed-loop tank-based systems, and convert FGD wastewater treatment to tank-based systems – Dewater, close, and cap all CCR surface impoundments (except CCR leachate impoundments, which could continue to operate if CCR leachate is the only type of CCR contained in the impoundment) © 2014 Winston & Strawn LLP 11
  • 12. Proposed ELGs, cont’d. • Industry comments: – Supportive of EPA’s intent to coordinate the two rules – Subtitle D prime option should be selected because it is most compatible with the proposed ELG rule • Under Subtitle D prime, unlined surface impoundments can continue to operate; under Subtitle C plants would be required to close all wet surface impoundments, which contradicts some of the more lenient options of the ELG rule that allow wastewater to be treated via impoundment – Updated data should lower the CCR rule's original risk assessment • Environmental organization comments: – ELGs do not eliminate the need for a stringent CCR rule to address potentially leaking and unstable CCR impoundments, groundwater cleanup, dust issues, and siting and construction of engineered landfills • Under the consent decree, EPA is required to finalize the ELG rule by May 22, 2014 • December 16, 2013 status update to Court – EPA in discussions with plaintiffs to agree upon a modification to the consent decree for an extension © 2014 Winston & Strawn LLP 12
  • 13. Federal Legislative Proposals • H.R. 2218, Coal Residuals Reuse and Management Act of 2013 – Passed the House on July 25, 2013 • Would amend Subtitle D of RCRA under which coal ash regulated as solid waste rather than hazardous waste • States would be allowed to establish a coal ash permitting program with EPA oversight authority • If states decline, EPA would step in • Coal ash permits would be required no later than seven years after enactment • Sets forth minimum requirements that must be required by a state-issued CCR permit – Certification by an independent professional engineer that the design of structures including surface impoundments is in accordance with acceptable engineering practices and the construction and maintenance of the structure will ensure dam stability – Annual inspections by an independent professional engineer – State agency authority to close deficient structures – Location restrictions – Wind dispersal of dust to be prevented • Latest action: Placed on Senate Legislative Calendar on July 30 but unlikely to be considered by the Senate © 2014 Winston & Strawn LLP 13
  • 14. Federal Legislative Proposals, cont’d. • H.R. 2279, Reducing Excessive Deadline Obligations Act of 2013 – Introduced in the House of Representatives on June 6, 2013, and referred to the Committees on Energy and Commerce and Transportation and Infrastructure – Introduced by Rep. Cory Gardner (R-CO) – Would amend Section 2002(b) of RCRA to eliminate the requirement to review and revise, as necessary, regulations promulgated under RCRA at least every three years – EPA Administrator would be required to review and revise the regulations as he or she determines is appropriate – Passed the House on January 9, 2014, by a vote of 225 to 188, with five Democrats voting for the bill and four Republicans voting against – Currently before the Senate’s Committee on Environment and Public Works, but unlikely to be passed by the Senate © 2014 Winston & Strawn LLP 14
  • 15. Legislative Prospects • Senate action very unlikely – Procedural rules place high hurdle (unanimous consent or cloture motion to bypass committee) – Not a Reid priority © 2014 Winston & Strawn LLP 15
  • 16. CCR Litigation and Enforcement Cases • Appalachian Voices v. McCarthy: Lawsuits filed April 2012 by numerous environmental groups (Appalachian Voices, Sierra Club, Environmental Integrity Project, and others) and CCR recyclers Headwaters Resources, Inc. and Boral Material Technologies Inc. • Environmental organization complaint – Section 2002(b) of RCRA requires EPA to review each RCRA regulation and revise as necessary, at least every three years – EPA has not reviewed and revised the CCR regulations since 1981 and “lost pace” with industry developments – EPA has failed to review its regulation exempting CCR from hazardous waste regulation – EPA has failed to revise and update the Subtitle D regulations for the management of CCR in landfills and surface impoundments • Existing Subtitle D regulations inadequate for protecting groundwater and surface water from CCR disposal – EPA has not revised the Toxicity Characteristic Leaching Procedure (“TCLP”), a test for determining whether a solid waste is toxic, and therefore, hazardous, since 2002, and has never revised the regulations to address CCR © 2014 Winston & Strawn LLP 16
  • 17. Appalachian Voices v. McCarthy, cont’d. • Headwaters Resources, Inc. and Boral Material Technologies Inc. complaints – Delay in determining whether to revise the Subtitle D regulations is creating uncertainty in the beneficial use market – EPA has violated Section 2002(b) of RCRA by failing to review the Subtitle D regulations and revise them as necessary, at least every three years • Summary Judgment Memorandum Opinion and Order – Issued October 29, 2013 – Denied the environmental organizations’ request for an order directing EPA to review and if necessary, revise the Subtitle D regulations concerning coal ash within six months – Denied the recyclers’ request to order EPA to announce its regulatory direction and authority for the regulation within three months – Ordered EPA to file a written submission with the court setting forth a proposed deadline for compliance with the obligation to review and revise if necessary, the Subtitle D regulations concerning CCR within 60 days of the court's order (by December 30) © 2014 Winston & Strawn LLP 17
  • 18. Appalachian Voices v. McCarthy, cont’d. • EPA filed an unopposed motion for a 30-day extension of time to submit its proposed deadline submission • Parties have reached “an agreement in principle on a deadline for EPA to comply with its obligation to review, and revise if necessary, its Subtitle D regulations”; working on finalizing a proposed consent decree, which could be approved by the EPA and the DOJ within 30 days • Proposed deadline submission is now due by January 29 • Consent decree will likely require EPA to complete the rulemaking by the end of 2014 © 2014 Winston & Strawn LLP 18
  • 19. CCR Lawsuits and Enforcement Actions • GenOn Consent Decree – Notice of Intent to sue filed by a group of environmental organizations; subsequently the State filed a federal lawsuit – Consent decree entered in May 2013 in Maryland district court – GenOn agreed to pay the Maryland Department of the Environment a $1.9 million civil penalty for groundwater and surface water contamination claims, investigate and remediate contamination, install liner systems on leachate and stormwater collection ponds, cap all closed CCR ponds • Lawsuit against Midwest Generation – Filed before the Illinois Pollution Control Board (Board) by the Sierra Club and other environmental groups in October 2012 – Alleging groundwater contamination from CCR ponds at four Midwest Generation facilities – On October 3, 2013, the Board denied Midwest Generation’s motion to dismiss the complaint as frivolous or duplicative based upon the existence of Compliance Commitment Agreements between Midwest Generation and the Illinois Environmental Protection Agency • Lawsuits against Duke Energy – On September 12, 2013, the SELC and other environmental groups sued Duke Energy Progress in federal court under the Clean Water Act for alleged CCR pollution from its Sutton plant – SELC and the NCDENR have pending lawsuits against other Duke facilities © 2014 Winston & Strawn LLP 19
  • 20. CCR Lawsuits and Enforcement Actions, cont’d. • Winyah Rivers Foundation v. S.C. Public Service Authority (D.S.C.) – Complaint filed April 29, 2013, citing violations of the Clean Water Act • Lawsuit also filed in state court alleging violations of the S.C. Pollution Control Act – Grainger Station closed due to the lawsuits – In November 2013, the parties reached a settlement agreement resolving both lawsuits, under which S.C. Public Service Authority agreed to remove 1.3 million tons of CCR stored in unlined ponds beside the Waccamaw River within 7-10 years • Anderson v. FirstEnergy Corporation (D.W.V.) – Complaint filed October 10, 2013, by more than 50 West Virginia residents – Common law claims of negligence, private nuisance, and trespass – Alleging contamination of plaintiffs' properties from the unlined Little Blue Run impoundment at FirstEnergy's Bruce Mansfield Plant – FirstEnergy previously settled a PADEP action in a December 2012 consent decree that required FirstEnergy to submit a closure plan for the impoundment by March 31, 2013 – Complaint alleges that closure under FirstEnergy's proposed closure plan won't begin in 2017 and won’t end until 2032 © 2014 Winston & Strawn LLP 20
  • 21. CCR Lawsuits and Enforcement Actions, cont’d. • TVA Ash Spill Litigation (E.D. Tenn.) – 60 consolidated cases involving more than 800 plaintiffs – Bifurcation (Phase I v. Phase II) – Phase I August 23, 2012 liability decision • Dismissed claims: negligence per se, recklessness, strict liability, and public nuisance • TVA liable for negligence, trespass and private nuisance • Cited (1) selection of location of dike, (2) designs of dike, and (3) failure to adequately inform employees of applicable policies and procedures • “Had TVA followed its own mandatory policies, procedures and practices, the subsurface issues underlying the failure of the North Dike would have been investigated, addressed, and potentially remedied before the catastrophic failure on December 22, 2008.” – Phase II: Individualized evidentiary proceedings on damages • • • • November 20, 2012 order referred Phase II of the litigation to mediation Litigation proceedings currently stayed pending mediation Three extensions of the deadline for the conclusion of mediation October 24, 2013 order extended mediation for an additional 105 days © 2014 Winston & Strawn LLP 21
  • 22. Conclusions • Continued push for RCRA Subtitle C regulation by environmental organizations • Momentum appears to be leaning towards a Subtitle-D-type program that is coordinated with the power plant effluent limitations guidelines • Legislative prospects unlikely but the House remains active • Litigation against operators of CCR impoundments and landfills continues • Lawsuits largely driven by environmental organizations – Demands • Phase-out of wet CCR storage • Retrofit with covers, liners and leachate collection • Investigation and remediation of groundwater contamination © 2014 Winston & Strawn LLP 22