There are two types of lacing system.
1. Single lacing system
2. Double lacing system
 The compression member comprising two main components laced and tied should,
where practicable, have a radius of gyration about the axis perpendicular to the plane
of lacing not less than the radius of gyration at right angles to that axis.
 The lacing system should not be varied throughout the length of the strut as far as
practicable.
 Cross (except tie plates) should not be provided along the length of the column with
lacing system, unless all forces resulting from deformation of column members are
calculated and provided for in the lacing and its fastening.
 The single-laced systems on opposite sides of the main components should preferably
be in the same direction so that one system is the shadow of the other.
 Laced compression members should be provided with tie plates at the ends of the
lacing system and at points where the lacing system are interrupted. The tie plates
should be designed by the same method as followed for battens.
(1) Angle of inclination(θ): (cl. 7.6.4)
For single or double lacing system,
θ = 40 ͦͦ to 70 ͦ To the axis of the built up member
normally,=45 is taken
(2) Slendernes ratio(kL/r) : (cl. 7.6.5.1)
KL/r for each component of column, should not be gretear than 50.
or
kL/r not greater than 0.7 *most favourable slenderness ratio of the member as
a whole
The slenderness ratio of lacing shall not exceed 145 (cl. 7.6.6.3)
(3) effective length of lacing (le) :
For bolted connection :
For single lacing, le = L
For double lacing, le = 0.7 l
Where, L = distance between the inner end fastner
In welded connection :
Le = 0.7 * distance between the inner ends of welds
(4)width of lacing bars(b) :
minimum width of lacing bar, b = 3d
Where,
D = nominal diameter of bolt
(5) Thickness of lacing (t) : (cl. 7.6.3)
For single lacing, t > Le/40
For double lacing, t > Le/60
(6) Transvers shear (Vt) : (cl.
7.6.6.1)
Vt= 2.5% of the axial force in the
column.
This force shall be divided equally
among the lacing systems in
parallel
Planes.
For double lacing
F=Vt/4 sin
Where,
(7) Check for compressive strength
For lacing using Le/r min and fy = 250 Mpa
Find Fcd from IS: 800, table -9 (c)
For rectangular section buckling class is “c”.
Compressive load carrying capacity of lacing
Pd = (b * t) * fcd
If (b *t )* fcd > F(axial force n lacing) …. OK
b*t = area of lacing
i.e. pd > F …. OK
(8) check for tensile strength :
tensile strength of lacing flat is
Td = 0.9 (b-d)t fu /ϒ or fy.Ag/ ϒmo Which ever is less.
If Td > F…….Ok { Is: 800 cl.
6.3.1 pg 32 }
(9) End connection :
For case (a) : Resultant on force on bolt = R = F
No of bolt required = F/bolt value
For case (b) : Resultant on force on bolt = R =2Fcosθ
No of bolt required =
2𝐹 𝑐𝑜𝑠θ
𝑏𝑜𝑙𝑡 𝑣𝑎𝑙𝑢𝑒
For 16 dia. Bolt strength is single shear= 29 kN
For 20 dia. Bolt strength is single shear= 45.3 kN
Strength of bolt in bearing =2.5 kb.d.t.fu (cl.
10.3.4)
(10) Overlap:
In case of welded connection, the amount of overlap measured along either
edge of lacing bar shall not be less than , four times the thickness of the lacing
bar or the
thickness of the element of main member, whichever is less.
 Compression member can also be built up intermediate
horizontal connecting plates or angle connecting two or four
elements of column .these horizontal connecting plates are called
battens
 The battens shall be placed opposite to each other at each end
of the member and at point where the member is stayed in it
length and as for as practicable , be spaced and proportioned
uniformly throughout.
 The number of battens shall be such that the member is devided
into not less than three bays within its actual length
(IS : 800, cl. 7.2.2, P.51)
(1)The number of battens shall be
such that the member is divided into
not less than three bays.
(2) Battens shall be designed to resist
, simultaneous
 Longitudinal shear
Vb = Vt. C/Ns
And
 Moment
M=Vt.C/2N
Where,
Vt = transverse shear force
C = distance between centre to centre of battens longitudinally .
N = number of parallel planes of battens (2 usually)
S= Minimum transverse distance between the centroid of the bolt/
rivet group / welding.
(3) Slenderness ratio : (cl. 7.7.1.4)
the effective slenderness ratio (
𝑘𝐿
𝑟
)e of battenced column shall be taken as 1.1 times
the (
𝑘𝐿
𝑟
)o, the maximum actual slenderness ratio of the column, to account for shear
deformation effects.
(4) Spacing of battens (C) : (cl. 7.7.3)
For any component of column
(i)
𝑐
𝑟 𝑚𝑖𝑛
should not greater than 50
(ii)
𝑐
𝑟 𝑚𝑖𝑛
should not greater than 0.7 * kL/r of built up column (about z-z axis)
(5) Thickness of battens (t) : (cl. 7.7.2.4)
t >
𝐿𝑏
50
where Lb = Distance between the inner most connecting line of bolts, perpendicular
to the main member
(6) Effective Depth of battens (de) : (cl 7.7.2.3)
 de > 3/4 *a ……… for intermediate battens
 de > a,……. For end batten
 de > 2b , ………. For any battens
where
de = effective depth of battens
= distance between outermost bolts longitudinally
a = distance between centroid of the main member
b = width of one member
Overall depth of battens
 D = de + (2 * end distance)
(7) transverse shear (Vt) : (cl. 7.7.2.1)
Vt = 2.5 % of the factored axial column load
(8) Ovrlap (cl. 7.7.4.1)
for welded connection, the overlap shall be not less than four
times the thickness of the battens
It should be noted that the battens columns have least
resistance to shear compared to column with lacings
the minimum thickness of rectangular slab bases , supporting columns
under axial compression shall be
 ts =√(2.5 w (a2 - 0.3b2) ϒmo/fy) > tf
Where
ts = thickness of slab base
w = uniform pressure below the base
a,b = larger and smaller projection, respectively of slab base beyond
the column
tf = flange thickness of compression member
 Design a slab base foundation for a column ISHB 350 to carry a factored
axial load of 1200 KN. Assume fe 410 grade steel and M25 concrete. take
safe bearing capacity of soil as 200 kN/m2
Solution :
For steel fe 410 fy = 250 N/mm2
For m 25 concrete, fck = 25 N/mm2
FOR ISHB 350 COLUMN
h = 350 mm
Bf =250 mm
Tf = 11.6mm
Tw= 8.3 mm
(a) Area of base plate : {IS 800 -2007 CL. 7.4.1 P.46 }
pu = 120 kn ( factored load )
 bearing strength of concrete = 0.6 fck
= 0.6 * 25
= 15 N/mm
2
 area of base plate :
=
p
u
𝑏𝑒𝑎𝑟𝑖𝑛𝑔 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒
A =
1200∗103
15
= 80,000 mm2
size of built up column
b = 350 mm
d = bf =250 mm
( B ) THICKNESS OF BASE PLATE :
 a =larger projection
= 50 mm
 b = smaller projection
= 50 mm
 W = uniform pressure on base plate
=
1200 ∗103
450 ∗350
= 7.62 n/ mm2
thickness of base plate =t
provide 50 mm equal projection all around the column
 width of plate
 Bp = 350 + 50 + 50 = 450 mm
 Dp = 250 + 50 +50 = 350 mm
Use base plate of size 450 mm* 350 mm
 Gross area of base plate provided = 450 * 350 = 157500 mm2
(C) WELD CONNECTING COLUM TO BASE
PLATE :
 Use a 6 mm fillet weld all around the colum section to hold the base
plate in position
 total length available for welding along the periphery of ISHB 350 ,
there are 12 ends for ISHB
 DEDUCTION = 12* 2S
=12 * 2 * 6
= 144 mm
 effective length of weld available
= 1683.4 – 144
= 1539.4
 capacity of weld per mm length
= 0.7 s * fwd
= 0.7 * 6 * 189
= 793.8 n/mm
= 0.7938 KN/mm
 required length of weld
= 1200
0.7938
= 1512 mm < 1539.4 mm
6 mm weld is adequate .
(D) SIZE OF CONCRETE BLOCK :
 Axial load on column =120 kN(factored load)
 Working load =1200/1.5=800kN
 Add 10% as self weight of concrete block =80KN
 Total load =800+80=880 kN
 Area of concrete block required
=Total load /S.B.C. of soil
=880/200
=4.4m2
 Concrete block is designed for working
load
 Consider rectangular concrete block
with equal projection beyond base plate.
 Let, X= projection of concrete block
 Area of concrete block =L*B
4.4=(0.45+2x) *(0.35 + 2x)
4.4=0.1575 + 0.7x +0.9x + 4x2
4x2 + 1.6 x – 4.2425 = 0
Solving it, x=0.849 m
Using calculator , say x= 0.85 m
 L=0.45 + 2 * 0.85 = 2.15m
 B=0.35 + 2*0.85 = 2.05m
 Area of concrete block
provide = 2.15 * 2.05
=4.407m2
> 4..4 m2……OK
 Assumme angle of dispersion
=45°
 Depth of concrete block = d =
x
= 0.85 m
column splice:
A joint when provided in the length of column to get to required length
it I called column splice.
If a column is loaded axially, theoretically no splice is required.
Compression will be transmitted by direct bearing, and column sections
could be rested one on top of each other.
How ever , In practice the load on column is never truely axial and the
real column has to resist bending due to this eccentrically applied load.
In addition , the column may be subjected to bending moments.
Also, the bearing surface of the adjacent sections can never be
machined to perfection.
Design of column spices:
The steps inn the design of splices are:
1. Determine the nature of loads to which the splice is subjected. The splice
may be subjected to axial compressive load, bending moment and shear
force.
2. For axial compressive load the splice plates are provided on the flanges of
the two columns.
if the ends of columns are milled/machined, the splice is designed only to
keep the column in position and to carry tension due to the bending
moment. In this case splice plate is designed to carry 50% of the axial load
and tension due to B.M.
if the ends of column are not milled/machined, the splice and connections
are designed to resist the total axial load and tension, if any.
3. Load due to axial load for machined ends of column,
 Pul= load on splice due to axial factored load Pu on the column.
=
𝑃𝑢
4
(total load on splice plates =
𝑃𝑢
2
but load on each splice plate =
𝑃𝑢
2
)
For non-machined ends of column,
Pul =
𝑃𝑢
2
4. Load due to bending moment Pu2 =
𝑀𝑢
𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚
=
𝑀𝑢
𝑎
Where,
a = lever arm
= c/c distance of two splice plates.
5. Column splice plates are assumed to act as short column (with zero
slenderness). Hence, the plates will be subjected to yield stress (fy).
 fcd=
𝑓𝑦
1.10
6. The cross-sectional area of splice plaate(A)
 A=
𝑃𝑢
𝑓𝑐𝑑
Pu= Pul + Pu2
7. The width of splice plate is kept equal to the width of the column
flange.
 thickness of splice plate=
𝐴
𝑤𝑖𝑑𝑡ℎ 𝑜𝑓 𝑠𝑝𝑙𝑖𝑐𝑒 𝑝𝑙𝑎𝑡𝑒
For column exposed to weather , the thickness of splice should not
Be less than 6 mm.
8. Nominal diameter of bolts for connection is assumed.
 No. of bolts=
𝑇𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 𝑜𝑛 𝑠𝑝𝑙𝑖𝑐𝑒 𝑝𝑙𝑎𝑡𝑒
𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑏𝑜𝑙𝑡
9. When the bearing plates are to provided to join two columns of
unequal
sizes:
- The bearing plate may be assumed as short beam to transmit the axial load
to the lower column.
- Axial load of the column is assumed to be taken by flanges only.
shown in figure
Maximum B.M in bearing plate:
 M=
𝑃𝑢
2
*a1
The length and width of the bearing plates are kept
equal to the size of the lower
storey column.
Thickness of bearing plate,
 M= fbs * Z
Where ,
 fbs= design bending stress
=
𝑓𝑦
1.10
=
250
1.10
= 227.27 N/𝑚𝑚2
 Z =
𝑏𝑡2
6
10. The web splice plates are designed to resist maximum shear force.
11. If packing are provided between the splice plate and column flange
and more than 6mm in thickness, the design shear capacity of the
bolts is reduced as per cl. 10.3.3.3 of IS : 800-2007.
 A column section ISHB 250@ 500.3 N/m is carrying a factored load of 600
kN. Design a suitable column splice. Use 16 Ø 4.6 grade bolts and steel of
grade Fe 410.
Solution..
For 4.6 grade bolts,
Fub =400 N/mm2
For – fe 410 plate fu = 410 N/mm2
fy = 250 N/mm2
 For column ISHB 250 @ 50.3 N/m
bf = 250 mm
tf = 9.7 mm
 Assume ends of columns are miled /machined for complete bearing.
Therefore , splice plate are designed for 50 % of axial load of column .
load on each splice plate ,
 pu1 = 𝑝 𝑢
4
= 600
4
= 150 KN
 Fcd
𝑓 𝑦
ɣ 𝑚0
= 250
1.10
= 227.27 N/mm2
Area of splice plate requride = 150 ∗103
227.27
= 660 mm2
 width of splice plate should be equal to the width of the column flange .
b = 250 mm
 thickness of splice plate,
t = 𝑎𝑟𝑒𝑎
𝑏
= 660
250
= 2.54 mm
 provide 6 mm thick splice plate as colum may be exposed to weather .
For 16 mm dia , 4.6 grade bolts
strength of bolt in single shear = 29 KN
 Stength of bolt in bearing ( on 6 mm
plate )
= 2.5 kb . D .t .fu /ɣ𝑚𝑏
= 2.5 * 1* 16 * 6 * *400/1.25
= 76800 N
= 76.8 KN
bolt value = 29 KN
 N0 0f bolt required =150/29=5.17
say 6 nos.
 Provide 16 mm dia , 6 bolt on each
side of the splice (joint) in two
vertical raws to connect splice plate
with column flangers.
Minimum pitch = 2.5 d = 2.5* 16
= 40 mm
 Provide pitch = 50 mm
 Edge distance = 1.5 d0 =1.5 *18 =27 mm provide 30 mm
 Depth of splice plate
=(4 * 50) +(4*30)
=320 mm
 Provide splice plate 320*250*6mm 0n column flanges.
Lacing, battening

Más contenido relacionado

La actualidad más candente (20)

Tension members
Tension membersTension members
Tension members
 
Bearing capacity of soil
Bearing capacity of soilBearing capacity of soil
Bearing capacity of soil
 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
Design of tension members
Design of tension membersDesign of tension members
Design of tension members
 
Doubly R C Beam
Doubly R C BeamDoubly R C Beam
Doubly R C Beam
 
Circular slabs
Circular slabsCircular slabs
Circular slabs
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
 
DESIGN OF FLAT SLABS
DESIGN OF FLAT SLABSDESIGN OF FLAT SLABS
DESIGN OF FLAT SLABS
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Structural analysis 2
Structural analysis   2Structural analysis   2
Structural analysis 2
 
Design of rcc structures
Design of rcc structuresDesign of rcc structures
Design of rcc structures
 
Raft foundations
Raft foundationsRaft foundations
Raft foundations
 
Shear wall
Shear wallShear wall
Shear wall
 
Well foundation
Well foundationWell foundation
Well foundation
 
Working Stress Method v/s Limit State Method
Working Stress Method v/s Limit State MethodWorking Stress Method v/s Limit State Method
Working Stress Method v/s Limit State Method
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 

Similar a Lacing, battening

Esd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHODEsd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHODyasir Khan
 
lacing and battening .pptx
lacing and battening .pptxlacing and battening .pptx
lacing and battening .pptxmayur280524
 
Compression member
Compression memberCompression member
Compression memberVikas Mehta
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2saibabu48
 
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfDiv_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfLandelSmith1
 
Reinforced concrete II Hand out Chapter 5_PPT_Torsion.pdf
Reinforced concrete II Hand out Chapter 5_PPT_Torsion.pdfReinforced concrete II Hand out Chapter 5_PPT_Torsion.pdf
Reinforced concrete II Hand out Chapter 5_PPT_Torsion.pdfObsiNaanJedhani
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Hossam Shafiq II
 
Assignment shear and bending
Assignment shear and bendingAssignment shear and bending
Assignment shear and bendingYatin Singh
 
U3 design of connecting rod-(i section, big&amp;small eng, bolt, whipping str...
U3 design of connecting rod-(i section, big&amp;small eng, bolt, whipping str...U3 design of connecting rod-(i section, big&amp;small eng, bolt, whipping str...
U3 design of connecting rod-(i section, big&amp;small eng, bolt, whipping str...karuppusamy pitchai
 
Connection and Bracing
Connection and BracingConnection and Bracing
Connection and Bracingsuddal
 
Axially loaded columns
Axially loaded columnsAxially loaded columns
Axially loaded columnsYash Patel
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Hossam Shafiq II
 

Similar a Lacing, battening (20)

Esd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHODEsd ppt 150180106093,111,160183106008 GECDAHOD
Esd ppt 150180106093,111,160183106008 GECDAHOD
 
lacing and battening .pptx
lacing and battening .pptxlacing and battening .pptx
lacing and battening .pptx
 
Compression member
Compression memberCompression member
Compression member
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
 
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfDiv_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
 
Composite construction
Composite constructionComposite construction
Composite construction
 
Reinforced concrete II Hand out Chapter 5_PPT_Torsion.pdf
Reinforced concrete II Hand out Chapter 5_PPT_Torsion.pdfReinforced concrete II Hand out Chapter 5_PPT_Torsion.pdf
Reinforced concrete II Hand out Chapter 5_PPT_Torsion.pdf
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
 
Fmd riveted joints
Fmd riveted jointsFmd riveted joints
Fmd riveted joints
 
Assignment shear and bending
Assignment shear and bendingAssignment shear and bending
Assignment shear and bending
 
Design of connections
Design of connectionsDesign of connections
Design of connections
 
0 ne way slab
0 ne way slab0 ne way slab
0 ne way slab
 
U3 design of connecting rod-(i section, big&amp;small eng, bolt, whipping str...
U3 design of connecting rod-(i section, big&amp;small eng, bolt, whipping str...U3 design of connecting rod-(i section, big&amp;small eng, bolt, whipping str...
U3 design of connecting rod-(i section, big&amp;small eng, bolt, whipping str...
 
Connection and Bracing
Connection and BracingConnection and Bracing
Connection and Bracing
 
Lecture note on column design
Lecture note on column designLecture note on column design
Lecture note on column design
 
Design of One-Way Slab
Design of One-Way SlabDesign of One-Way Slab
Design of One-Way Slab
 
Reinforced concrete column
Reinforced concrete columnReinforced concrete column
Reinforced concrete column
 
Reinforced column design
Reinforced column design Reinforced column design
Reinforced column design
 
Axially loaded columns
Axially loaded columnsAxially loaded columns
Axially loaded columns
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
 

Más de Yash Patel

statue of unity
statue of unitystatue of unity
statue of unityYash Patel
 
RETAINING WALL
RETAINING WALLRETAINING WALL
RETAINING WALLYash Patel
 
Famous places in India
Famous places in IndiaFamous places in India
Famous places in IndiaYash Patel
 
Deduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingDeduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingYash Patel
 
Canal Regulation Work
Canal Regulation WorkCanal Regulation Work
Canal Regulation WorkYash Patel
 
Street lighting
Street lightingStreet lighting
Street lightingYash Patel
 
Formwork for Bridge and Centering Of Arch
Formwork for Bridge and Centering Of ArchFormwork for Bridge and Centering Of Arch
Formwork for Bridge and Centering Of ArchYash Patel
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam Yash Patel
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its typeYash Patel
 
Separation of boundary layer
Separation of boundary layerSeparation of boundary layer
Separation of boundary layerYash Patel
 
Physical Unit Operation- Screening, Grit Removal, Equalization
Physical Unit Operation-Screening, Grit Removal,EqualizationPhysical Unit Operation-Screening, Grit Removal,Equalization
Physical Unit Operation- Screening, Grit Removal, EqualizationYash Patel
 
Drought management and water harvesting
Drought management and water harvesting Drought management and water harvesting
Drought management and water harvesting Yash Patel
 
Environment Engineering
Environment EngineeringEnvironment Engineering
Environment EngineeringYash Patel
 

Más de Yash Patel (14)

statue of unity
statue of unitystatue of unity
statue of unity
 
RETAINING WALL
RETAINING WALLRETAINING WALL
RETAINING WALL
 
Famous places in India
Famous places in IndiaFamous places in India
Famous places in India
 
Deduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingDeduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending Scheduling
 
Canal Regulation Work
Canal Regulation WorkCanal Regulation Work
Canal Regulation Work
 
Street lighting
Street lightingStreet lighting
Street lighting
 
Formwork for Bridge and Centering Of Arch
Formwork for Bridge and Centering Of ArchFormwork for Bridge and Centering Of Arch
Formwork for Bridge and Centering Of Arch
 
Ventilation
VentilationVentilation
Ventilation
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its type
 
Separation of boundary layer
Separation of boundary layerSeparation of boundary layer
Separation of boundary layer
 
Physical Unit Operation- Screening, Grit Removal, Equalization
Physical Unit Operation-Screening, Grit Removal,EqualizationPhysical Unit Operation-Screening, Grit Removal,Equalization
Physical Unit Operation- Screening, Grit Removal, Equalization
 
Drought management and water harvesting
Drought management and water harvesting Drought management and water harvesting
Drought management and water harvesting
 
Environment Engineering
Environment EngineeringEnvironment Engineering
Environment Engineering
 

Último

Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 

Último (20)

Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 

Lacing, battening

  • 1. GUIDED BY: Prof. Sunil Jaganiya Prof. Pritesh Rathod Sub : Elementary Structural Design NAME ENROLL NO. Patel Jimi 131100106029 Patel Milind 131100106035 Patel Nirmal 131100106036 Patel Viraj 131100106040 Patel Yash 131100106042 Shah Ashit 131100106051
  • 2.
  • 3.
  • 4. There are two types of lacing system. 1. Single lacing system 2. Double lacing system
  • 5.  The compression member comprising two main components laced and tied should, where practicable, have a radius of gyration about the axis perpendicular to the plane of lacing not less than the radius of gyration at right angles to that axis.  The lacing system should not be varied throughout the length of the strut as far as practicable.  Cross (except tie plates) should not be provided along the length of the column with lacing system, unless all forces resulting from deformation of column members are calculated and provided for in the lacing and its fastening.  The single-laced systems on opposite sides of the main components should preferably be in the same direction so that one system is the shadow of the other.  Laced compression members should be provided with tie plates at the ends of the lacing system and at points where the lacing system are interrupted. The tie plates should be designed by the same method as followed for battens.
  • 6. (1) Angle of inclination(θ): (cl. 7.6.4) For single or double lacing system, θ = 40 ͦͦ to 70 ͦ To the axis of the built up member normally,=45 is taken (2) Slendernes ratio(kL/r) : (cl. 7.6.5.1) KL/r for each component of column, should not be gretear than 50. or kL/r not greater than 0.7 *most favourable slenderness ratio of the member as a whole The slenderness ratio of lacing shall not exceed 145 (cl. 7.6.6.3)
  • 7. (3) effective length of lacing (le) : For bolted connection : For single lacing, le = L For double lacing, le = 0.7 l Where, L = distance between the inner end fastner In welded connection : Le = 0.7 * distance between the inner ends of welds (4)width of lacing bars(b) : minimum width of lacing bar, b = 3d Where, D = nominal diameter of bolt
  • 8. (5) Thickness of lacing (t) : (cl. 7.6.3) For single lacing, t > Le/40 For double lacing, t > Le/60 (6) Transvers shear (Vt) : (cl. 7.6.6.1) Vt= 2.5% of the axial force in the column. This force shall be divided equally among the lacing systems in parallel Planes. For double lacing F=Vt/4 sin Where,
  • 9. (7) Check for compressive strength For lacing using Le/r min and fy = 250 Mpa Find Fcd from IS: 800, table -9 (c) For rectangular section buckling class is “c”. Compressive load carrying capacity of lacing Pd = (b * t) * fcd If (b *t )* fcd > F(axial force n lacing) …. OK b*t = area of lacing i.e. pd > F …. OK
  • 10. (8) check for tensile strength : tensile strength of lacing flat is Td = 0.9 (b-d)t fu /ϒ or fy.Ag/ ϒmo Which ever is less. If Td > F…….Ok { Is: 800 cl. 6.3.1 pg 32 } (9) End connection : For case (a) : Resultant on force on bolt = R = F No of bolt required = F/bolt value For case (b) : Resultant on force on bolt = R =2Fcosθ No of bolt required = 2𝐹 𝑐𝑜𝑠θ 𝑏𝑜𝑙𝑡 𝑣𝑎𝑙𝑢𝑒 For 16 dia. Bolt strength is single shear= 29 kN For 20 dia. Bolt strength is single shear= 45.3 kN Strength of bolt in bearing =2.5 kb.d.t.fu (cl. 10.3.4)
  • 11. (10) Overlap: In case of welded connection, the amount of overlap measured along either edge of lacing bar shall not be less than , four times the thickness of the lacing bar or the thickness of the element of main member, whichever is less.
  • 12.  Compression member can also be built up intermediate horizontal connecting plates or angle connecting two or four elements of column .these horizontal connecting plates are called battens  The battens shall be placed opposite to each other at each end of the member and at point where the member is stayed in it length and as for as practicable , be spaced and proportioned uniformly throughout.  The number of battens shall be such that the member is devided into not less than three bays within its actual length
  • 13. (IS : 800, cl. 7.2.2, P.51) (1)The number of battens shall be such that the member is divided into not less than three bays. (2) Battens shall be designed to resist , simultaneous
  • 14.  Longitudinal shear Vb = Vt. C/Ns And  Moment M=Vt.C/2N Where, Vt = transverse shear force C = distance between centre to centre of battens longitudinally . N = number of parallel planes of battens (2 usually) S= Minimum transverse distance between the centroid of the bolt/ rivet group / welding.
  • 15. (3) Slenderness ratio : (cl. 7.7.1.4) the effective slenderness ratio ( 𝑘𝐿 𝑟 )e of battenced column shall be taken as 1.1 times the ( 𝑘𝐿 𝑟 )o, the maximum actual slenderness ratio of the column, to account for shear deformation effects. (4) Spacing of battens (C) : (cl. 7.7.3) For any component of column (i) 𝑐 𝑟 𝑚𝑖𝑛 should not greater than 50 (ii) 𝑐 𝑟 𝑚𝑖𝑛 should not greater than 0.7 * kL/r of built up column (about z-z axis) (5) Thickness of battens (t) : (cl. 7.7.2.4) t > 𝐿𝑏 50 where Lb = Distance between the inner most connecting line of bolts, perpendicular to the main member
  • 16. (6) Effective Depth of battens (de) : (cl 7.7.2.3)  de > 3/4 *a ……… for intermediate battens  de > a,……. For end batten  de > 2b , ………. For any battens where de = effective depth of battens = distance between outermost bolts longitudinally a = distance between centroid of the main member b = width of one member Overall depth of battens  D = de + (2 * end distance)
  • 17. (7) transverse shear (Vt) : (cl. 7.7.2.1) Vt = 2.5 % of the factored axial column load (8) Ovrlap (cl. 7.7.4.1) for welded connection, the overlap shall be not less than four times the thickness of the battens It should be noted that the battens columns have least resistance to shear compared to column with lacings
  • 18. the minimum thickness of rectangular slab bases , supporting columns under axial compression shall be  ts =√(2.5 w (a2 - 0.3b2) ϒmo/fy) > tf Where ts = thickness of slab base w = uniform pressure below the base a,b = larger and smaller projection, respectively of slab base beyond the column tf = flange thickness of compression member
  • 19.  Design a slab base foundation for a column ISHB 350 to carry a factored axial load of 1200 KN. Assume fe 410 grade steel and M25 concrete. take safe bearing capacity of soil as 200 kN/m2 Solution : For steel fe 410 fy = 250 N/mm2 For m 25 concrete, fck = 25 N/mm2 FOR ISHB 350 COLUMN h = 350 mm Bf =250 mm Tf = 11.6mm Tw= 8.3 mm
  • 20. (a) Area of base plate : {IS 800 -2007 CL. 7.4.1 P.46 } pu = 120 kn ( factored load )  bearing strength of concrete = 0.6 fck = 0.6 * 25 = 15 N/mm 2  area of base plate : = p u 𝑏𝑒𝑎𝑟𝑖𝑛𝑔 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑐𝑜𝑛𝑐𝑟𝑒𝑡𝑒 A = 1200∗103 15 = 80,000 mm2 size of built up column b = 350 mm d = bf =250 mm
  • 21. ( B ) THICKNESS OF BASE PLATE :  a =larger projection = 50 mm  b = smaller projection = 50 mm  W = uniform pressure on base plate = 1200 ∗103 450 ∗350 = 7.62 n/ mm2 thickness of base plate =t provide 50 mm equal projection all around the column  width of plate  Bp = 350 + 50 + 50 = 450 mm  Dp = 250 + 50 +50 = 350 mm Use base plate of size 450 mm* 350 mm  Gross area of base plate provided = 450 * 350 = 157500 mm2
  • 22. (C) WELD CONNECTING COLUM TO BASE PLATE :  Use a 6 mm fillet weld all around the colum section to hold the base plate in position  total length available for welding along the periphery of ISHB 350 , there are 12 ends for ISHB  DEDUCTION = 12* 2S =12 * 2 * 6 = 144 mm  effective length of weld available = 1683.4 – 144 = 1539.4
  • 23.  capacity of weld per mm length = 0.7 s * fwd = 0.7 * 6 * 189 = 793.8 n/mm = 0.7938 KN/mm  required length of weld = 1200 0.7938 = 1512 mm < 1539.4 mm 6 mm weld is adequate .
  • 24. (D) SIZE OF CONCRETE BLOCK :  Axial load on column =120 kN(factored load)  Working load =1200/1.5=800kN  Add 10% as self weight of concrete block =80KN  Total load =800+80=880 kN  Area of concrete block required =Total load /S.B.C. of soil =880/200 =4.4m2
  • 25.  Concrete block is designed for working load  Consider rectangular concrete block with equal projection beyond base plate.  Let, X= projection of concrete block  Area of concrete block =L*B 4.4=(0.45+2x) *(0.35 + 2x) 4.4=0.1575 + 0.7x +0.9x + 4x2 4x2 + 1.6 x – 4.2425 = 0 Solving it, x=0.849 m Using calculator , say x= 0.85 m
  • 26.  L=0.45 + 2 * 0.85 = 2.15m  B=0.35 + 2*0.85 = 2.05m  Area of concrete block provide = 2.15 * 2.05 =4.407m2 > 4..4 m2……OK  Assumme angle of dispersion =45°  Depth of concrete block = d = x = 0.85 m
  • 27. column splice: A joint when provided in the length of column to get to required length it I called column splice. If a column is loaded axially, theoretically no splice is required. Compression will be transmitted by direct bearing, and column sections could be rested one on top of each other. How ever , In practice the load on column is never truely axial and the real column has to resist bending due to this eccentrically applied load. In addition , the column may be subjected to bending moments. Also, the bearing surface of the adjacent sections can never be machined to perfection.
  • 28. Design of column spices: The steps inn the design of splices are: 1. Determine the nature of loads to which the splice is subjected. The splice may be subjected to axial compressive load, bending moment and shear force. 2. For axial compressive load the splice plates are provided on the flanges of the two columns. if the ends of columns are milled/machined, the splice is designed only to keep the column in position and to carry tension due to the bending moment. In this case splice plate is designed to carry 50% of the axial load and tension due to B.M. if the ends of column are not milled/machined, the splice and connections are designed to resist the total axial load and tension, if any.
  • 29. 3. Load due to axial load for machined ends of column,  Pul= load on splice due to axial factored load Pu on the column. = 𝑃𝑢 4 (total load on splice plates = 𝑃𝑢 2 but load on each splice plate = 𝑃𝑢 2 ) For non-machined ends of column, Pul = 𝑃𝑢 2 4. Load due to bending moment Pu2 = 𝑀𝑢 𝑙𝑒𝑣𝑒𝑟 𝑎𝑟𝑚 = 𝑀𝑢 𝑎 Where, a = lever arm = c/c distance of two splice plates.
  • 30. 5. Column splice plates are assumed to act as short column (with zero slenderness). Hence, the plates will be subjected to yield stress (fy).  fcd= 𝑓𝑦 1.10 6. The cross-sectional area of splice plaate(A)  A= 𝑃𝑢 𝑓𝑐𝑑 Pu= Pul + Pu2 7. The width of splice plate is kept equal to the width of the column flange.  thickness of splice plate= 𝐴 𝑤𝑖𝑑𝑡ℎ 𝑜𝑓 𝑠𝑝𝑙𝑖𝑐𝑒 𝑝𝑙𝑎𝑡𝑒 For column exposed to weather , the thickness of splice should not Be less than 6 mm.
  • 31. 8. Nominal diameter of bolts for connection is assumed.  No. of bolts= 𝑇𝑜𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 𝑜𝑛 𝑠𝑝𝑙𝑖𝑐𝑒 𝑝𝑙𝑎𝑡𝑒 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑜𝑛𝑒 𝑏𝑜𝑙𝑡 9. When the bearing plates are to provided to join two columns of unequal sizes: - The bearing plate may be assumed as short beam to transmit the axial load to the lower column. - Axial load of the column is assumed to be taken by flanges only. shown in figure Maximum B.M in bearing plate:  M= 𝑃𝑢 2 *a1
  • 32. The length and width of the bearing plates are kept equal to the size of the lower storey column. Thickness of bearing plate,  M= fbs * Z Where ,  fbs= design bending stress = 𝑓𝑦 1.10 = 250 1.10 = 227.27 N/𝑚𝑚2  Z = 𝑏𝑡2 6
  • 33. 10. The web splice plates are designed to resist maximum shear force. 11. If packing are provided between the splice plate and column flange and more than 6mm in thickness, the design shear capacity of the bolts is reduced as per cl. 10.3.3.3 of IS : 800-2007.
  • 34.  A column section ISHB 250@ 500.3 N/m is carrying a factored load of 600 kN. Design a suitable column splice. Use 16 Ø 4.6 grade bolts and steel of grade Fe 410. Solution.. For 4.6 grade bolts, Fub =400 N/mm2 For – fe 410 plate fu = 410 N/mm2 fy = 250 N/mm2  For column ISHB 250 @ 50.3 N/m bf = 250 mm tf = 9.7 mm
  • 35.  Assume ends of columns are miled /machined for complete bearing. Therefore , splice plate are designed for 50 % of axial load of column . load on each splice plate ,  pu1 = 𝑝 𝑢 4 = 600 4 = 150 KN  Fcd 𝑓 𝑦 ɣ 𝑚0 = 250 1.10 = 227.27 N/mm2
  • 36. Area of splice plate requride = 150 ∗103 227.27 = 660 mm2  width of splice plate should be equal to the width of the column flange . b = 250 mm  thickness of splice plate, t = 𝑎𝑟𝑒𝑎 𝑏 = 660 250 = 2.54 mm  provide 6 mm thick splice plate as colum may be exposed to weather . For 16 mm dia , 4.6 grade bolts strength of bolt in single shear = 29 KN
  • 37.  Stength of bolt in bearing ( on 6 mm plate ) = 2.5 kb . D .t .fu /ɣ𝑚𝑏 = 2.5 * 1* 16 * 6 * *400/1.25 = 76800 N = 76.8 KN bolt value = 29 KN  N0 0f bolt required =150/29=5.17 say 6 nos.  Provide 16 mm dia , 6 bolt on each side of the splice (joint) in two vertical raws to connect splice plate with column flangers. Minimum pitch = 2.5 d = 2.5* 16 = 40 mm
  • 38.  Provide pitch = 50 mm  Edge distance = 1.5 d0 =1.5 *18 =27 mm provide 30 mm  Depth of splice plate =(4 * 50) +(4*30) =320 mm  Provide splice plate 320*250*6mm 0n column flanges.