SlideShare una empresa de Scribd logo
1 de 40
Descargar para leer sin conexión
1. Onshore Pipeline Installation
2. Shore Approach Construction
3. Offshore Pipelaying
4. Riser Installation
5. Post-lay Trenching
Proposed Methodology (Preliminary)
TA B L E O F C O N T E N T S
1) BRIEF INTRODUCTION TO COMPANY’S KEY PERSONNEL
2) FIELD MAP AND PIPELINE ROUTE
3) SCOPE OF WORKS
4) PIPELINE CONSTRUCTION AND INSTALLATION OVERVIEW
5) PROJECT SCHEDULE AND DURATIONS
6) PROPOSED PROJECT MANAGEMENT TEAM (PMT)
7) PIPELAY BARGE ‘OMBAK BIRU SATU’
1) PIPELAY BARGE ‘OMBAK BIRU SATU’ SPECIFICATIONS AND BARGE LAYOUT
2) BARGE WELDING STATIONS AND BARGE ROLLER ARRANGEMENT
3) STINGER DETAILS
4) PIPELAY BARGE PHOTOS
8) ONSHORE PIPELINE INSTALLATION FROM LANDFALL POINT TO LANDFALL STATION
(APPROXIMATELY 5.3KM)
9) SHORE APPROACH & BEACHPULL METHODOLOGY AT LANDFALL POINT
10) SUBSEA PIPELAYING BY PIPELAY BARGE ‘OMBAK BIRU SATU 1 (APPROXIMATELY 12 KM)
1) ENGINEERING ANALYSIS
11) RISER INSTALLATION AT TBDP-A PLATFORM
12) PRE-COMMISSIONING METHODOLOGY
13) PRE AND POST TRENCHING WORKS SCOPE AND METHODOLOGY
14) SUMMARY OF MARINE SPREAD & MAJOR EQUIPMENT
15) PROJECT RELATED PHOTOS
Thai Binh-Ham Rong Gas Pipeline
LINEAR
WINCH AT
LANDFALL
POINT
PRE-TRENCH PRIOR TO PIPE PULLING FROM
KP11.0 TO KP13.03
SUBSEA PIPELINE= 13.03 km = 1,056 joints
KP0.00
KP13.03
LAYING DIRECTION
300 Linear
Winch
LAY BARGE
LINEAR WINCH
SUBSEA
SPOOL TIE-IN
LAUNCHER
AT TBDP-A
KP0.00
LAYING DIRECTION
Pulling Direction
KP5.283
LAND PIPE = 5.283 km
= 428 joints
SUBSEA PIPELINE
LANDFALL
STATION
(KP5.283)
LANDFALL
POINT
TBDP-A
EXCAVATION
USING
AMPHIBIOUS
EXCAVATOR
RECEIVER AT
LANDFALL
STATION
NO. DESIGNATION NO.OF PERSON
1 PROJECT MANAGER 1
2 CONSTRUCTION MANAGER (OCS) 1
3 OPERATION MANAGER 1
4 HEAD OF PLANNING AND COST CONTROL 1
5 HEAD OF PROCUREMENT AND SUB-CONTRACTING 1
6 HEAD OF MARINE AND LOGISTIC 1
7 LOGISTIC COORDINATOR 1
8 ENGINEERING MANAGER 1
9 FIELD ENGINEER 4
10 QA/QC COORDINATOR 1
11 SAFETY COORDINATOR 1
12 DRAUGHTMAN 1
13 DOCUMENT CONTROLLER 1
TOTAL OF PMT 16 PERSONS
ENGINEERING ANAYLSIS
- SHORE APPROACH - BEACH PULL CALCULATION
- SHORE APPROACH – COFFERDAM DESIGN ANALYSIS
- PIPELAY ANALYSIS ( START-UP, LAYING,LAYDOWN )
- RISER ANALYSIS
- MISCELLANEOUS CALCULATION ( ANCHOR CATENARY, LINEAR WINCH HOLD-BACK
TIE-IN DOWN DESIGN, PULLING HEAD DESIGN , ETC.)
OPERATION / INSTALLATION PROCEDURES
- PRE-LAY SURVEY ( HYDROGRAPHIC PROCEDURE )
- WELDING PROCEDURE SPECIFICATION ( WPS )
- PROJECT QUALITY PLAN ( PQP )
- SAFETY MANAGEMENT MANUAL
- ONSHORE PIPELINE PROCEDURE
- SUBSEA PIPELINE INSTALLATION PROCEDURE
- SHORE APPROACH - BEACH PULL PIPELINE PROCEDURE
- RISER INSTALLATION PROCEDURE
- SUBSEA SPOOL INSTALLATION PROCEDURE
- PRE-TRENCHING PROCEDURE
- PRE-COMMISSIONING PROCEDURE (PIGGING, HYDROTESTING, DEWATERING, AIR-DRYING &
NITROGEN PACKING)
- POST-TRENCHING PROCEDURE
- PROJECT CLOSED-OUT REPORT
Pipelay Barge Ombak Biru Satu
Barge Particulars :
- Length: 242ft ( 73.74m)
- Breadth : 80 ft (24.38m)
- Moulded Draft : 16ft (4.88m)
- Light Draft : 1.8m
- Operating Draft : 2.0m
- Accommodation : 52 pax
Mooring System :
- 8 point mooring winches with delta flipper anchor
- 800m Anchor Wire
- Anchor buoy : 12 nos
Pipe Laying Facilities :
- Pipe Conveyor
- Pipe Alignment System
- Tensioner : 60MT
- A&R Winch : 120MT
- Main Compressor : 900cfm
- Air Tugger : 10 MT
- Stinger Length – 25 m length
Pipelay Station :
- Cleaning and Bevelling
- Alignment/ Fit-up and Welding Station #1 ( Root & Hot Pass )
- Welding Station #2 ( Filling )
- Welding Station #3 ( Filling & Capping )
- Tensioner
- X-Ray and Repair Station
- Field Joint Coating ( Wrapping and In-Fill Coating )
General Layout of Pipelay Barge
Typical Beachpull
General Beach-pull Arrangement
Methodology:
Methodology:
Methodology:
9
14
125
102
-
PREPARATION WORKS :
- RIG-UP 300MT LINEAR WINCH AT SHORE APPROACH LOCATION
- RIG-UP LONG-ARMED EXCAVATOR ONBOARD PONTOON BARGE
SHORE APPROACH METHODOLOGY :
- SET-UP PIPELAY BARGE ( W.D = 5m at ACD )
- PASS PULLING CABLE TO BARGE ( MESSENGER LINE ) BY SPEED BOAT
- PIPELAY BARGE TO HEAVE UP PULLING CABLE
- PIPELAY BARGE TO CONNECT PULLING CABLE TO PULLING HEAD
( PULLING HEAD cum UNDERWATER RECEIVER FOR GAUGING )
- COMMENCE PULLING PIPE STRING WITH BUOYANCY TANKS
( OFF-BOTTOM PULL )
- MAXIMUM 150 MT CALCULATED TO PULL 2,500M (203 JTS)
Pre-Lay Survey & Post-Lay Survey Works
- Survey Boat
Shore Approach & Subsea Pipeline Installation Works
- Pipelay Barge – Ombak Biru Satu
- Anchor HandlingTug
- Crew Boat
Tow & Tie-in Pipe Strings at Mud Flat
- 2 x Flat-bottomed boats
Riser and Spool Installation Work at TBDP-A
- Pipelay Barge – Ombak Biru Satu
- Anchor HandlingTug
- Crew Boat
Pre- and Post-lay Trenching Works
- Long-armed Excavators onboard Steel Barge
- Jet-sled Trencher
Equipment & Vessels
Shore Approach at Con Vanh & Subsea Pipeline Installation
- Air Diving System
- 150MT crawler crane ( onboard pipelay barge )
- NDT Equipment & Spread
- Survey Equipment
- Field Joint Coating Equipment
- 300 MT Linear Winch
- Long Arm Excavator
Thai Binh-Ham Rong Gas Pipeline
POST-TRENCHING WORKS AT MUD-FLAT AREA USING
JET-SLED TRENCHING SYSTEM
TRENCHER
Water for ballasting
Air for deballasting
Previous contain material been
push out
POST-TRENCHING WORKS AT MUD-FLAT AREA USING
JET-SLED TRENCHING SYSTEM
POST-TRENCHING WORKS AT MUD-FLAT AREA USING
JET-SLED TRENCHING SYSTEM
APPROACHING COFFERDAM /STARTUP POINT
Thai Binh-Ham Rong Gas Pipeline
POST-TRENCHING WORKS AT MUD-FLAT AREA USING
JET-SLED TRENCHING SYSTEM
INITIAL POSITIONING OF TRENCHER BY DIVER
POST-TRENCHING WORKS AT MUD-FLAT AREA USING
JET-SLED TRENCHING SYSTEM
Our Experience :
Beach Pull Operation 1
Our Experience:
Typical Mid Point Tie-in Operation 1
Our Experience : Mid Point Tie-in Operation 2
Our Experience: Beach Pull Operation 2
Our Experience: Laying Through Sand Bank
Area
Our Experience:
Typical Water Master During Excavation Operation
Our Experience:
Typical Linear Winch For Beach Pull Operation
Our Experience:
Barge with Excavator for Pre-Trenching
1. Onshore Pipeline Installation
2. Shore Approach Construction
3. Offshore Pipelaying
4. Riser Installation
5. Post-lay Trenching
Proposed Methodology (Preliminary)

Más contenido relacionado

La actualidad más candente

495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docxSharad Naik
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and CommissioningWendy Soerachman
 
Basic whp presentation(1)
Basic whp presentation(1)Basic whp presentation(1)
Basic whp presentation(1)nguyen_uptorcem
 
(BASIC) Offshore pipeline operations and engineering
(BASIC) Offshore pipeline operations and engineering(BASIC) Offshore pipeline operations and engineering
(BASIC) Offshore pipeline operations and engineeringMohammed Alobaid
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002Minh Bui Si
 
Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.maqsood1459
 
Offshore platform-design
Offshore platform-designOffshore platform-design
Offshore platform-designRahul Ranakoti
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.pptMuhammed Sulfeek
 
Subsea Pipeline Engineering
Subsea Pipeline EngineeringSubsea Pipeline Engineering
Subsea Pipeline EngineeringpetroEDGE
 
38785106 api-tank-design
38785106 api-tank-design38785106 api-tank-design
38785106 api-tank-design141jdf
 

La actualidad más candente (20)

Jacket
JacketJacket
Jacket
 
Pipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case StudiesPipe Support Field Examples & Case Studies
Pipe Support Field Examples & Case Studies
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Introduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface FacilitiesIntroduction to Offshore Oil and Gas Surface Facilities
Introduction to Offshore Oil and Gas Surface Facilities
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
Basic whp presentation(1)
Basic whp presentation(1)Basic whp presentation(1)
Basic whp presentation(1)
 
Offshore packages
Offshore packagesOffshore packages
Offshore packages
 
(BASIC) Offshore pipeline operations and engineering
(BASIC) Offshore pipeline operations and engineering(BASIC) Offshore pipeline operations and engineering
(BASIC) Offshore pipeline operations and engineering
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.
 
Offshore platform-design
Offshore platform-designOffshore platform-design
Offshore platform-design
 
API 650 vs 620
API 650 vs 620API 650 vs 620
API 650 vs 620
 
Saudi Aramco Inspection Checklist (SAIC)
Saudi Aramco Inspection Checklist (SAIC)Saudi Aramco Inspection Checklist (SAIC)
Saudi Aramco Inspection Checklist (SAIC)
 
329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt329497121-Onshore-Pipeline.ppt
329497121-Onshore-Pipeline.ppt
 
Engineering & Design of Pipe Supports
Engineering & Design of Pipe SupportsEngineering & Design of Pipe Supports
Engineering & Design of Pipe Supports
 
Subsea Pipeline Engineering
Subsea Pipeline EngineeringSubsea Pipeline Engineering
Subsea Pipeline Engineering
 
38785106 api-tank-design
38785106 api-tank-design38785106 api-tank-design
38785106 api-tank-design
 
Offshore platforms
Offshore platformsOffshore platforms
Offshore platforms
 
Well test procedures manual
Well test procedures manualWell test procedures manual
Well test procedures manual
 
subsea
subseasubsea
subsea
 

Similar a Proposed Methodology Shore Approach

CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000daniel cobar
 
Site Surveys_Rig Safety-Link
Site Surveys_Rig Safety-LinkSite Surveys_Rig Safety-Link
Site Surveys_Rig Safety-LinkAbdul Rahim
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 
Demzy's Presentation on HDD
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDDDemzy George
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Hitesh Khanna
 
Indramayu Subsea Pipeline
Indramayu Subsea PipelineIndramayu Subsea Pipeline
Indramayu Subsea Pipelinearifsarwo
 
Foundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxFoundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxMailapalliJayaRaju
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling pptSuman Paul
 
Benjamin colbrandt | C-Power offshore windmolenpark
Benjamin colbrandt  | C-Power offshore windmolenparkBenjamin colbrandt  | C-Power offshore windmolenpark
Benjamin colbrandt | C-Power offshore windmolenparkGreenbridge nv
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.Emeka Ngwobia
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Nandan Shandilya
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdfRaviNobleseas
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 

Similar a Proposed Methodology Shore Approach (20)

CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000
 
Site Surveys_Rig Safety-Link
Site Surveys_Rig Safety-LinkSite Surveys_Rig Safety-Link
Site Surveys_Rig Safety-Link
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Demzy's Presentation on HDD
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDD
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
Indramayu Subsea Pipeline
Indramayu Subsea PipelineIndramayu Subsea Pipeline
Indramayu Subsea Pipeline
 
Foundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxFoundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptx
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling ppt
 
Benjamin colbrandt | C-Power offshore windmolenpark
Benjamin colbrandt  | C-Power offshore windmolenparkBenjamin colbrandt  | C-Power offshore windmolenpark
Benjamin colbrandt | C-Power offshore windmolenpark
 
Bridge construction methods aug 2007
Bridge construction methods aug 2007Bridge construction methods aug 2007
Bridge construction methods aug 2007
 
Project Monitoring
Project MonitoringProject Monitoring
Project Monitoring
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
DESIGN OF A MODEL HAULAGE TECHNIQUE FOR WATER FLOODING CAISSON ASSEMBLY.
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
 
930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf930DickWardTetraTechnologies.pdf
930DickWardTetraTechnologies.pdf
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Paper
PaperPaper
Paper
 

Proposed Methodology Shore Approach

  • 1. 1. Onshore Pipeline Installation 2. Shore Approach Construction 3. Offshore Pipelaying 4. Riser Installation 5. Post-lay Trenching Proposed Methodology (Preliminary)
  • 2. TA B L E O F C O N T E N T S 1) BRIEF INTRODUCTION TO COMPANY’S KEY PERSONNEL 2) FIELD MAP AND PIPELINE ROUTE 3) SCOPE OF WORKS 4) PIPELINE CONSTRUCTION AND INSTALLATION OVERVIEW 5) PROJECT SCHEDULE AND DURATIONS 6) PROPOSED PROJECT MANAGEMENT TEAM (PMT) 7) PIPELAY BARGE ‘OMBAK BIRU SATU’ 1) PIPELAY BARGE ‘OMBAK BIRU SATU’ SPECIFICATIONS AND BARGE LAYOUT 2) BARGE WELDING STATIONS AND BARGE ROLLER ARRANGEMENT 3) STINGER DETAILS 4) PIPELAY BARGE PHOTOS 8) ONSHORE PIPELINE INSTALLATION FROM LANDFALL POINT TO LANDFALL STATION (APPROXIMATELY 5.3KM) 9) SHORE APPROACH & BEACHPULL METHODOLOGY AT LANDFALL POINT 10) SUBSEA PIPELAYING BY PIPELAY BARGE ‘OMBAK BIRU SATU 1 (APPROXIMATELY 12 KM) 1) ENGINEERING ANALYSIS 11) RISER INSTALLATION AT TBDP-A PLATFORM 12) PRE-COMMISSIONING METHODOLOGY 13) PRE AND POST TRENCHING WORKS SCOPE AND METHODOLOGY 14) SUMMARY OF MARINE SPREAD & MAJOR EQUIPMENT 15) PROJECT RELATED PHOTOS Thai Binh-Ham Rong Gas Pipeline
  • 3. LINEAR WINCH AT LANDFALL POINT PRE-TRENCH PRIOR TO PIPE PULLING FROM KP11.0 TO KP13.03 SUBSEA PIPELINE= 13.03 km = 1,056 joints KP0.00 KP13.03 LAYING DIRECTION 300 Linear Winch LAY BARGE LINEAR WINCH SUBSEA SPOOL TIE-IN LAUNCHER AT TBDP-A KP0.00 LAYING DIRECTION Pulling Direction KP5.283 LAND PIPE = 5.283 km = 428 joints SUBSEA PIPELINE LANDFALL STATION (KP5.283) LANDFALL POINT TBDP-A EXCAVATION USING AMPHIBIOUS EXCAVATOR RECEIVER AT LANDFALL STATION
  • 4. NO. DESIGNATION NO.OF PERSON 1 PROJECT MANAGER 1 2 CONSTRUCTION MANAGER (OCS) 1 3 OPERATION MANAGER 1 4 HEAD OF PLANNING AND COST CONTROL 1 5 HEAD OF PROCUREMENT AND SUB-CONTRACTING 1 6 HEAD OF MARINE AND LOGISTIC 1 7 LOGISTIC COORDINATOR 1 8 ENGINEERING MANAGER 1 9 FIELD ENGINEER 4 10 QA/QC COORDINATOR 1 11 SAFETY COORDINATOR 1 12 DRAUGHTMAN 1 13 DOCUMENT CONTROLLER 1 TOTAL OF PMT 16 PERSONS
  • 5. ENGINEERING ANAYLSIS - SHORE APPROACH - BEACH PULL CALCULATION - SHORE APPROACH – COFFERDAM DESIGN ANALYSIS - PIPELAY ANALYSIS ( START-UP, LAYING,LAYDOWN ) - RISER ANALYSIS - MISCELLANEOUS CALCULATION ( ANCHOR CATENARY, LINEAR WINCH HOLD-BACK TIE-IN DOWN DESIGN, PULLING HEAD DESIGN , ETC.) OPERATION / INSTALLATION PROCEDURES - PRE-LAY SURVEY ( HYDROGRAPHIC PROCEDURE ) - WELDING PROCEDURE SPECIFICATION ( WPS ) - PROJECT QUALITY PLAN ( PQP ) - SAFETY MANAGEMENT MANUAL - ONSHORE PIPELINE PROCEDURE - SUBSEA PIPELINE INSTALLATION PROCEDURE - SHORE APPROACH - BEACH PULL PIPELINE PROCEDURE - RISER INSTALLATION PROCEDURE - SUBSEA SPOOL INSTALLATION PROCEDURE - PRE-TRENCHING PROCEDURE - PRE-COMMISSIONING PROCEDURE (PIGGING, HYDROTESTING, DEWATERING, AIR-DRYING & NITROGEN PACKING) - POST-TRENCHING PROCEDURE - PROJECT CLOSED-OUT REPORT
  • 7. Barge Particulars : - Length: 242ft ( 73.74m) - Breadth : 80 ft (24.38m) - Moulded Draft : 16ft (4.88m) - Light Draft : 1.8m - Operating Draft : 2.0m - Accommodation : 52 pax Mooring System : - 8 point mooring winches with delta flipper anchor - 800m Anchor Wire - Anchor buoy : 12 nos Pipe Laying Facilities : - Pipe Conveyor - Pipe Alignment System - Tensioner : 60MT - A&R Winch : 120MT - Main Compressor : 900cfm - Air Tugger : 10 MT - Stinger Length – 25 m length Pipelay Station : - Cleaning and Bevelling - Alignment/ Fit-up and Welding Station #1 ( Root & Hot Pass ) - Welding Station #2 ( Filling ) - Welding Station #3 ( Filling & Capping ) - Tensioner - X-Ray and Repair Station - Field Joint Coating ( Wrapping and In-Fill Coating )
  • 8. General Layout of Pipelay Barge
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 19.
  • 20.
  • 22. - PREPARATION WORKS : - RIG-UP 300MT LINEAR WINCH AT SHORE APPROACH LOCATION - RIG-UP LONG-ARMED EXCAVATOR ONBOARD PONTOON BARGE SHORE APPROACH METHODOLOGY : - SET-UP PIPELAY BARGE ( W.D = 5m at ACD ) - PASS PULLING CABLE TO BARGE ( MESSENGER LINE ) BY SPEED BOAT - PIPELAY BARGE TO HEAVE UP PULLING CABLE - PIPELAY BARGE TO CONNECT PULLING CABLE TO PULLING HEAD ( PULLING HEAD cum UNDERWATER RECEIVER FOR GAUGING ) - COMMENCE PULLING PIPE STRING WITH BUOYANCY TANKS ( OFF-BOTTOM PULL ) - MAXIMUM 150 MT CALCULATED TO PULL 2,500M (203 JTS)
  • 23. Pre-Lay Survey & Post-Lay Survey Works - Survey Boat Shore Approach & Subsea Pipeline Installation Works - Pipelay Barge – Ombak Biru Satu - Anchor HandlingTug - Crew Boat Tow & Tie-in Pipe Strings at Mud Flat - 2 x Flat-bottomed boats Riser and Spool Installation Work at TBDP-A - Pipelay Barge – Ombak Biru Satu - Anchor HandlingTug - Crew Boat Pre- and Post-lay Trenching Works - Long-armed Excavators onboard Steel Barge - Jet-sled Trencher Equipment & Vessels
  • 24. Shore Approach at Con Vanh & Subsea Pipeline Installation - Air Diving System - 150MT crawler crane ( onboard pipelay barge ) - NDT Equipment & Spread - Survey Equipment - Field Joint Coating Equipment - 300 MT Linear Winch - Long Arm Excavator
  • 25. Thai Binh-Ham Rong Gas Pipeline
  • 26.
  • 27. POST-TRENCHING WORKS AT MUD-FLAT AREA USING JET-SLED TRENCHING SYSTEM
  • 28. TRENCHER Water for ballasting Air for deballasting Previous contain material been push out POST-TRENCHING WORKS AT MUD-FLAT AREA USING JET-SLED TRENCHING SYSTEM
  • 29. POST-TRENCHING WORKS AT MUD-FLAT AREA USING JET-SLED TRENCHING SYSTEM
  • 30. APPROACHING COFFERDAM /STARTUP POINT Thai Binh-Ham Rong Gas Pipeline POST-TRENCHING WORKS AT MUD-FLAT AREA USING JET-SLED TRENCHING SYSTEM
  • 31. INITIAL POSITIONING OF TRENCHER BY DIVER POST-TRENCHING WORKS AT MUD-FLAT AREA USING JET-SLED TRENCHING SYSTEM
  • 32. Our Experience : Beach Pull Operation 1
  • 33. Our Experience: Typical Mid Point Tie-in Operation 1
  • 34. Our Experience : Mid Point Tie-in Operation 2
  • 35. Our Experience: Beach Pull Operation 2
  • 36. Our Experience: Laying Through Sand Bank Area
  • 37. Our Experience: Typical Water Master During Excavation Operation
  • 38. Our Experience: Typical Linear Winch For Beach Pull Operation
  • 39. Our Experience: Barge with Excavator for Pre-Trenching
  • 40. 1. Onshore Pipeline Installation 2. Shore Approach Construction 3. Offshore Pipelaying 4. Riser Installation 5. Post-lay Trenching Proposed Methodology (Preliminary)