SEMINAR FOR FINANCIAL ANALYSTS
Financing the water sector
Lorenzo Bardelli
Director
Water System Directorate
12th October 2015
FIRST REGULATORY PERIOD
Authority approach to Water regulation
Piecemeal activity within a comprehensive strategy
Local decision making process
Empowerment: self determination at decentralized level
Coherency
Cost reimbursement rules
Constraints on Operating Costs (endogenous vs. exogenous)
Priority to Investments
Price Cap and Full Cost Recovery
Pricing to end-users
Tariff multiplier
Reorganise tariff structure applied to consumers
Rebalancing past disequilibria
Past credit billing
Investigation on above-the-cap proposals
Measures to avoid default
Urgent equalisation
MTI REGULATORY PROCESS
4
PHASE 1 AEEGSI defines the tariff rules (2 or 3 consultations before the final
decision)
PHASE 2 Local Authorities
(Ato)
approve the tariff proposal (specific regulatory scheme),
composed of investment plan and related financial plan, in
agreement with the operators
PHASE 3 AEEGSI collects all the proposal and all the other relevant data
PHASE 4 AEEGSI investigates and verifies one-by-one the collected proposals,
asking for further information, if necessary
PHASE 5 AEEGSI approves – with or without modification or prescription, the
proposal
IDLE ATO Local Operator can communicate the proposal to AEEGSI
(approves/modifies); otherwise AEEGSI takes the final
decision (with penalization of 10% on the tariff)
COST REIMBURSEMENT RULES DEPEND ON
REGULATORY SCHEMES FOR THE YEARS 2014-2015
OPERATING COSTS
NO VARIATIONS IN THE OPERATOR’S
OBJECTIVES OR ACTIVITIES
PRESENCE OF VARIATIONS IN THE
OPERATOR’S OBJECTIVES OR ACTIVITIES
INVESTMENTS
SCHEME I – ordinary case
Opex: more push on operating
efficiency through a rolling cap,
assuming the invariance over the
period
Capex recognised ex post using
technical lives
SCHEME II
Opex: possibility to cover more opex
motivating the request (and taking in
consideration scale economies)
Capex: same as ordinary case
SCHEME III
Opex: same as ordinary case
Capex: more accelerated
depreciation admitted, together
with (limited) anticipation on
investments
SCHEME IV
Opex: possibility to cover more opex
motivating the request (and taking in
consideration scale economies)
Capex: more accelerated
depreciation admitted, together with
(limited) anticipation on investments
Ordinary
case is
sufficient to
finance
investments
Ordinary
case not
sufficient to
finance
investments
5,0
exp3
≤
∑
+
MTT
t
t
t
RAB
PI
5,0
exp3
>
∑
+
MTT
t
t
t
RAB
PI
not a constraint,
but a way to
evaluate the
most appropriate
regulatory option
More
investments
More activities
5
DEFINITION OF THE COST COMPONENTS IN MTI (2014-2015)
[1] [2] [3] [4] [5]
[1] IMMOBILIZATION COSTS
[2] COMPONENT IN SUPPORT OF SPECIFIC OBJECTIVES
[3] OPERATING COSTS
[4] COMPONENT TO COVER ENVIRONMENTAL AND RESOURCE COSTS
[5] COMPONENT TO BALANCE THE REVENUES LIMIT FOR THE OPERATOR IN THE PREVIOUS YEARS
aaaaa
CUITOFiscOFAMMCapex ∆+++=
a
TOT
aaaaa
RCERCOpexFoNICapexVRG ++++=
a
FoNI
a
FoNI
a
FoNI
a
CUITAMMFNIFoNI ∆++=
a
al
a
end
a
OpexOpexOpex +=
aaa
sCReEnvCERC +=
( ) ( )∏−=
+++++=
a
at
ta
ALTRO
aa
ws
a
EE
a
VOL
a
TOT IRcRimbRcRcRcRc
1
335 1*
6
NEW WATER TARIFF METHOD MTI - 2
• AEEGSI intends to confirm the
general structure of VRG for the
period 2016-2019
Cap to the variation of the tariff
multiplier
Schemes I e II )1(1
Krpia
a
++≤−
ϑ
ϑ
Schemes III e IV ]*)1(1[1
Krpia
a
γ
ϑ
ϑ
+++≤−
7
Maximum limit to the variation of the tariff multiplier, except for any specific inquiry in case the
limit needs to be passed in order to ensure that specific objectives are met
6,5%
9,0%
( )
∑ −−
−−
+•
−+
=
u
a
b
Ta
uu
a
b
a
b
a
a
Rvscaltarif
CRVRG
222012
22
)(
*5,0
ϑ
Tariffs applied in 2012 (calculated on the base of the old Method MTN) have to be updated
multiplying them by a factor ϑ
TARIFF MULTIPLIER FOR THE YEARS 2014-2015
Half margin from
competitive water activities
is used to reduce the tariffs
of monopoly water activities
NEW WATER TARIFF METHOD MTI - 2
• AEEGSI intends to confirm the general update mechanism of tariffs, based on the tariff multiplier
Arrearage costs
Arrearage costs ( ) defined as Unpaid Ratio (UR) in 24
months, are recognised as a parameter in order to encourage an
efficient credit-recovery activity, and they are differentiated
across geographical macro-areas, as a function of the different
average incidence on the revenues.
a
morCO
Past credit billing
Any possible balancing with periods preceding the attribution of sector regulation and monitoring powers
to AEEGSI, and not yet considered in the calculation of past tariffs, is quantified and approved by 30
June 2014 by the entitled entity or any other competent entity, and they are communicated to AEEGSI
Terminal value
Residual value for the operator of the Integrated Water Services (SII) in case of replacement is calculated:
a) from a minimum value, equal to the residual value of assets of the SII operator, according to
the following formula:
b) up to a maximum value that includes a), the value of past accounts that have already been
quantified and approved by the competent entities, and any guarantees possibly required by the lender
MEASURES FOR AN EFFICIENT FINANCIAL SUSTAINABILITY
( ) ( )[ ]∑ ∑ +






−−−=
=c
a
a
t
a
ttcCFPtctcIPtc
a
LICdflFACFPFAIPVR
1961
,,,,,, *
NORTH:
1,6%
CENTRE:
3,0%
SOUTH:
6,5%
RESULTS
OUTCOME OF THE DECISION-MAKING PROCESS
OF THE LOCAL AUTHORITIES [YEARS 2014-2015]
10
Identifying
critical issues
Defining specific
objectives
Planning investments
for the period 2014-
2017
Choosing the Regulatory
Scheme
Regulatory Schemes selected by local Authorities
FOCUS ON TARIFFS APPROVED BY AEEGSI [YEARS 2014-2015]
11
68%
3%
12%
17%
Schemi regolatori Teta 1 Teta 0,9 Non approvati
Tariffs approved (% inhabitants)
AEEGSI approved tariffs for 1.961 operators regarding 49.820.708 inhabitants.
The new tariffs had an average yearly increase of 4.04% in 2014 and 4.46% in 2015
TREND OF INVESTMENTS AFTER THE ACTION OF A
CENTRAL REGULATOR
12
NET INVESTMENTS
2012 (€)
NET INVESTMENTS
2013 (€)
NET INVESTMENTS
2014 (€)
NET INVESTMENTS
2015 (€)
North-West 195.741.644 184.324.445 350.241.242 440.956.598
Nord-East 266.595.624 332.483.991 323.830.781 429.109.401
Centre 333.369.137 344.173.029 387.298.944 427.190.417
South 153.725.206 60.434.581 108.306.589 149.297.118
Islands 11.522.585 6.057.384 31.914.845 44.120.667
Italy 960.954.196 927.473.430 1.201.592.401 1.490.674.201
-
50.000.000
100.000.000
150.000.000
200.000.000
250.000.000
300.000.000
350.000.000
400.000.000
450.000.000
Nord
Ovest
Nord Est Centro Sud Isole
Netinvestments(€)
2012 2015
Data referred to:
127 operators
40 mln inhabitants (2/3 of Italian
population)
+55%
PLANNED
INVESTMENTS FOR THE
PERIOD
2014-2017:
€ 5.506.412.296*
PLANNED ACTIONS:
Maintenance of water
supplying systems and
plants;
Development of new
sewerage nets and wwt
plants (higher
compliance rates);
Placing of metering
systems
CRITICAL ISSUES:
Old networks and plants;
Partial coverage of the
sewerage and waste
water treatment (wwt);
Water losses;
Lacking of metering
systems
CRITICALITY &
PLANNED INVESTMENTS FOR THE PERIOD 2014-2017
13
[*data refered to 127 operators; 40 mln inhabitants] Planned investments (%) for regulatory Scheme
14
Tariff variation - year 2014 Planned investments for the period 2014-2017
TARIFF SUSTAINABILITY &
RESILIENCE OF INVESTMENTS
TARIFF
VARIATION AT
NATIONAL
LEVEL:
+4,04%
15
VALUE OF RAB &
NEED TO INVEST IN WATER INFRASTRUCTURES
Low value of Regulatory Asset = 13 Billion euros
RAB per capita for geographic area
[Cross Section Analysis for the year 2014]
46%
28%
21%
3%
2%
Opex-end
Opex-al
Capex
FoNI
RCtot
VRG configuration (%)
SECOND REGULATORY PERIOD
17
DEVELOPMENT OF THE NEW TARIFF METHOD ON THE
BASE OF THE COLLECTED INFORMATION
OPEX/PROVIDED UNITS OF WATER (€/mc)
Min: 0,52 Mean: 1,49 Max: 2,72
OPEX/SERVED INHABITANTS (€/per capita)
Min: 50,32 Mean: 108,60 Max: 200,09
ENERGY COSTS/OPEX
Min: 3% Mean: 17% Max: 36%
LABOUR COSTS/OPEX
Min: 4% Mean: 25% Max: 47%
Cross Section Analysis for the year 2014 [data referred to 105 operators, 32 mln inhabitants]
OPM
pop
Opex
≤
2014
OPM
pop
Opex
>
2014 AGGREGAZIONI, VARIAZIONI
NEGLI OBIETTIVI O NELLE
ATTIVITÀ DEL GESTORE
INVESTIMENTI
ω≤
∑
MTI
t
RAB
PI exp2019
2016
SCHEMA I
Limite di prezzo:
( )XKrpia
a
−++≤−
11
ϑ
ϑ
SCHEMA II
Limite di prezzo:
( )XKrpia
a
211
−++≤−
ϑ
ϑ
SCHEMA III
Limite di prezzo:
( )Krpia
a
++≤−
11
ϑ
ϑ
ω>
∑
MTI
t
RAB
PI exp2019
2016
SCHEMA IV
Limite di prezzo:
( )XKrpia
a
−++≤−
*5,111
ϑ
ϑ
SCHEMA V
Limite di prezzo:
( )XKrpia
a
2*5,111
−++≤−
ϑ
ϑ
SCHEMA VI
Limite di prezzo
( )Krpia
a
*5,111
++≤−
ϑ
ϑ
Regulatory Schemes for the second regulatory period
18
Mean of Opex
per capita
Mean of Opex
per capita
Factor Sharing, named as X, applied to the maximum limit allowable increase for every single year consideredFactor Sharing, named as X, applied to the maximum limit allowable increase for every single year considered
19
Limite di prezzo per tipo di Schema regolatorio
:
:
OPM
pop
Opex
≤
2014
OPM
pop
Opex
>
2014 AGGREGAZIONI, VARIAZIONI
NEGLI OBIETTIVI O NELLE
ATTIVITÀ DEL GESTORE
INVESTIMENTI
ω≤
∑
MTI
t
RAB
PI exp2019
2016
SCHEMA I
Limite di prezzo:
( )XKrpia
a
−++≤−
11
ϑ
ϑ
SCHEMA II
Limite di prezzo:
( )XKrpia
a
211
−++≤−
ϑ
ϑ
SCHEMA III
Limite di prezzo:
( )Krpia
a
++≤−
11
ϑ
ϑ
ω>
∑
MTI
t
RAB
PI exp2019
2016
SCHEMA IV
Limite di prezzo:
( )XKrpia
a
−++≤−
*5,111
ϑ
ϑ
SCHEMA V
Limite di prezzo:
( )XKrpia
a
2*5,111
−++≤−
ϑ
ϑ
SCHEMA VI
Limite di prezzo
( )Krpia
a
*5,111
++≤−
ϑ
ϑ
20
NEW OBLIGATIONS FOR
SUPPLIERS
Regulation of quality of water service [DCO 665/2014/R/idr
and DCO 273/2015/R/idr];
Rules about collection expenditure [Del. 7/2015/R/idr]
SHARING THE RISK IN
THE NEW REGULATORY
FRAMEWORK
Schemes of standard agreement between ATO and
service providers [DCO 171/2014/R/idr and DCO 274/2013/R/idr]
INCREASING PRICE
REFLECTIVITY AND
PROMOTING BETTER
STANDARD FOR
ENVIRONMENTAL
PROTECTION
Definition of tariffs for sewerage and treatment of
industrial wastewater [DCO 299/2014/R/idr and 620/2014/R/idr]
Explicit identification of environment and resource
costs [DCO 539/2014/R/idr and Del. 662/2014/R/idr]
Unbundling (with definition of the “integrated water
service” perimeter) [DCO 379/20145R/idr]
Strategic guidelines for the next regulatory period (Water Tariff Method MTI - 2), starting
in 2016 [DCO 406/2014/R/idr]
i. Promoting efficiency;
ii. Increasing investments (also following an “output-based” approach);
iii. Reorganizing water industry (from 2500 to less than 100…)
OTHER FIELDS OF ACTION
for the definition of a clear and coherent framework of rules
ROADMAP FOR A NEW REGULATION OF
QUALITY & STANDARD AGREEMENTS
21
Consultation
Paper
665/2014/R/idr:
AEEGSI general
orientations on
contracting conditions
regarding:
- Billing
- Payment
modalities
- Customer heldesk
- Call centers
- Requests of
information
- Dispute settllement
23 Dec 2014 4 June 2015
Consultation
Paper
273/2015/R/idr :
Additional
principles on
contracting
conditions
regarding :
- Termination
- Management
- Information
required
- Data collection
and protection
27 Mar 2014
Resolution
142/2014/R/idr:
Start of regulatory
decision-making
procedure on
quality of
(intergated) water
services, setting out
objectives and
powers of:
- Data collection
- Consultation
- Meetings with
operators
10 Apr 2014
Consultation
Paper
171/2014/R/idr:
AEEGSI general
orientations on
schemes of
concession
contracts between
ATO and service
providers
Consultation
Paper
274/2015/R/idr:
AEEGSI general
orientations on
schemes of
concession
contracts between
ATO and service
providers
Oct/
Nov 2015
AEGGSI
final
decisions
about
contractual
quality &
schemes of
concession
contracts
Jan
2016
NEW
RULES
ARE
APPLIED
Quality Quality Quality
Concession
contracts
Concession
contracts
• Commercial (in water we use the term contractual) and technical
• Further dimensions of water service (other than quantity)
• Mechanism proposed in Consultation Paper 273/2015/R/idr
(contractual quality):
Minimum level of quality granted homogeneously for all Italian
consumers, paid in tariff (in the so called VRG)
Penalties for operators if quality under the minimum threshold with
prohibition to recover in tariff any penalty
Possibility to ask for premium if quality above threshold and after
cost – benefit analysis of the underlying investments
Premium paid by all served consumers through a specific tariff
component
QUALITY OF WATER SERVICES
22
The current consultation process on commercial quality aims at
regulating the following contracting conditions:
• Billing
• Connection to the networks
• Management of helpdesk and website
• Management of call center
• Request of information
• Reimbursement for consumers
• Management of complaints
• Dispute settlement
QUALITY OF WATER SERVICES (2)
23
24
STANDARD AGREEMENTS
AEEGSI draws up also standard agreements (SA) to regulate contractual
relations between local authorities and undertakings
SA is an important tool to define the contractual framework at local level and
ensure certanty and affordability of the general regulatory framework
In particular, the SA sets:
• maximum duration of public concessions and conditions for their
possible extension;
• terms and procedures for asset payment at the end of public concession
(terminal value) to ensure the maintenance of economic-financial
viability;
• risk sharing between undertakings and public system, which is
diversified in accordance with the organisational model chosen
AEEGSI is defining SA by the end of the year (cfr. consultation paper
274/2015/R/idr)

Más contenido relacionado

La actualidad más candente

3Q13 Presentation
 3Q13 Presentation 3Q13 Presentation
3Q13 PresentationCteep_ri
 
Service Tax: Departmental Perspective
Service Tax: Departmental PerspectiveService Tax: Departmental Perspective
Service Tax: Departmental PerspectiveManish Mohan
 
Dkt 2013 0141 decoupling order 31mar2015
Dkt 2013 0141 decoupling order 31mar2015Dkt 2013 0141 decoupling order 31mar2015
Dkt 2013 0141 decoupling order 31mar2015Honolulu Civil Beat
 
Snam FY 2019 results
Snam FY 2019 resultsSnam FY 2019 results
Snam FY 2019 resultsSnam
 
CPFL Energia - Itaú inglês
CPFL Energia - Itaú inglêsCPFL Energia - Itaú inglês
CPFL Energia - Itaú inglêsCPFL RI
 
tew (10.10.18) - Transmission tariff calculation for ukraine, using the capac...
tew (10.10.18) - Transmission tariff calculation for ukraine, using the capac...tew (10.10.18) - Transmission tariff calculation for ukraine, using the capac...
tew (10.10.18) - Transmission tariff calculation for ukraine, using the capac...Денис Киркач
 
GPR0003-Stage-1-Final-Report-final-version-for-publication.PDF
GPR0003-Stage-1-Final-Report-final-version-for-publication.PDFGPR0003-Stage-1-Final-Report-final-version-for-publication.PDF
GPR0003-Stage-1-Final-Report-final-version-for-publication.PDFMatt Unicomb
 
#ACCIONA9M19 results report
#ACCIONA9M19 results report#ACCIONA9M19 results report
#ACCIONA9M19 results reportacciona
 
CBEC - GST - Registration Amendment
CBEC - GST - Registration AmendmentCBEC - GST - Registration Amendment
CBEC - GST - Registration Amendmentgst-trichy
 
Corporate Presentation - CPFL Energia
Corporate Presentation - CPFL EnergiaCorporate Presentation - CPFL Energia
Corporate Presentation - CPFL EnergiaCPFL RI
 
Corporate Presentation CPFL Energia - Janeiro 2016
Corporate Presentation CPFL Energia - Janeiro 2016Corporate Presentation CPFL Energia - Janeiro 2016
Corporate Presentation CPFL Energia - Janeiro 2016CPFL RI
 
CEN ISSS Public Workshop R Diemer[1]
CEN ISSS Public Workshop R Diemer[1]CEN ISSS Public Workshop R Diemer[1]
CEN ISSS Public Workshop R Diemer[1]guest642d13
 
ACCIONA first quarter 2019 results
ACCIONA first quarter 2019 resultsACCIONA first quarter 2019 results
ACCIONA first quarter 2019 resultsacciona
 

La actualidad más candente (20)

tew (09.10.18) - Oshchepkova
tew (09.10.18) - Oshchepkovatew (09.10.18) - Oshchepkova
tew (09.10.18) - Oshchepkova
 
Power Market regulation
Power Market regulationPower Market regulation
Power Market regulation
 
3Q13 Presentation
 3Q13 Presentation 3Q13 Presentation
3Q13 Presentation
 
Service Tax: Departmental Perspective
Service Tax: Departmental PerspectiveService Tax: Departmental Perspective
Service Tax: Departmental Perspective
 
tew (09.10.18) - Garcia
tew (09.10.18) - Garciatew (09.10.18) - Garcia
tew (09.10.18) - Garcia
 
Dkt 2013 0141 decoupling order 31mar2015
Dkt 2013 0141 decoupling order 31mar2015Dkt 2013 0141 decoupling order 31mar2015
Dkt 2013 0141 decoupling order 31mar2015
 
Snam FY 2019 results
Snam FY 2019 resultsSnam FY 2019 results
Snam FY 2019 results
 
CPFL Energia - Itaú inglês
CPFL Energia - Itaú inglêsCPFL Energia - Itaú inglês
CPFL Energia - Itaú inglês
 
Brazilian Electricity Market - Business France
Brazilian Electricity Market - Business FranceBrazilian Electricity Market - Business France
Brazilian Electricity Market - Business France
 
tew (10.10.18) - Transmission tariff calculation for ukraine, using the capac...
tew (10.10.18) - Transmission tariff calculation for ukraine, using the capac...tew (10.10.18) - Transmission tariff calculation for ukraine, using the capac...
tew (10.10.18) - Transmission tariff calculation for ukraine, using the capac...
 
GPR0003-Stage-1-Final-Report-final-version-for-publication.PDF
GPR0003-Stage-1-Final-Report-final-version-for-publication.PDFGPR0003-Stage-1-Final-Report-final-version-for-publication.PDF
GPR0003-Stage-1-Final-Report-final-version-for-publication.PDF
 
#ACCIONA9M19 results report
#ACCIONA9M19 results report#ACCIONA9M19 results report
#ACCIONA9M19 results report
 
CBEC - GST - Registration Amendment
CBEC - GST - Registration AmendmentCBEC - GST - Registration Amendment
CBEC - GST - Registration Amendment
 
Corporate Presentation - CPFL Energia
Corporate Presentation - CPFL EnergiaCorporate Presentation - CPFL Energia
Corporate Presentation - CPFL Energia
 
Corporate Presentation CPFL Energia - Janeiro 2016
Corporate Presentation CPFL Energia - Janeiro 2016Corporate Presentation CPFL Energia - Janeiro 2016
Corporate Presentation CPFL Energia - Janeiro 2016
 
BMC BUDGET
BMC  BUDGET  BMC  BUDGET
BMC BUDGET
 
CEN ISSS Public Workshop R Diemer[1]
CEN ISSS Public Workshop R Diemer[1]CEN ISSS Public Workshop R Diemer[1]
CEN ISSS Public Workshop R Diemer[1]
 
Crc Presentation
Crc PresentationCrc Presentation
Crc Presentation
 
Social-Cost Pricing in Freight Transportation
Social-Cost Pricing in Freight TransportationSocial-Cost Pricing in Freight Transportation
Social-Cost Pricing in Freight Transportation
 
ACCIONA first quarter 2019 results
ACCIONA first quarter 2019 resultsACCIONA first quarter 2019 results
ACCIONA first quarter 2019 results
 

Destacado

WACC calculation methodology review
WACC calculation methodology reviewWACC calculation methodology review
WACC calculation methodology reviewARERA
 
Indici di performance per la quantificazione delle criticità del Servizio Idr...
Indici di performance per la quantificazione delle criticità del Servizio Idr...Indici di performance per la quantificazione delle criticità del Servizio Idr...
Indici di performance per la quantificazione delle criticità del Servizio Idr...ARERA
 
La Governance del settore idrico
La Governance del settore idricoLa Governance del settore idrico
La Governance del settore idricoARERA
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoARERA
 
Riforma dispacciamento elettrico (RDE)- Principali linee d'azione
Riforma dispacciamento elettrico (RDE)- Principali linee d'azioneRiforma dispacciamento elettrico (RDE)- Principali linee d'azione
Riforma dispacciamento elettrico (RDE)- Principali linee d'azioneARERA
 
Mercati energetici concorrenziali e funzione giustiziale
Mercati energetici concorrenziali e funzione giustizialeMercati energetici concorrenziali e funzione giustiziale
Mercati energetici concorrenziali e funzione giustizialeARERA
 
La generazione distribuita: novità regolatorie
La generazione distribuita: novità regolatorieLa generazione distribuita: novità regolatorie
La generazione distribuita: novità regolatorieARERA
 
Sviluppo e nuove tecnologie: quale regolazione
Sviluppo e nuove tecnologie: quale regolazioneSviluppo e nuove tecnologie: quale regolazione
Sviluppo e nuove tecnologie: quale regolazioneARERA
 
Servizio di bilanciamento del gas naturale
Servizio di bilanciamento del gas naturaleServizio di bilanciamento del gas naturale
Servizio di bilanciamento del gas naturaleARERA
 
Le linee strategiche della regolazione e dell’enforcement dell’energia: un co...
Le linee strategiche della regolazione e dell’enforcement dell’energia:un co...Le linee strategiche della regolazione e dell’enforcement dell’energia:un co...
Le linee strategiche della regolazione e dell’enforcement dell’energia: un co...ARERA
 
La misura del gas naturale
La misura del gas naturaleLa misura del gas naturale
La misura del gas naturaleARERA
 
Gare gas : raccolta RAB – Cespiti di proprietà del gestore
Gare gas : raccolta RAB – Cespiti di proprietà del gestoreGare gas : raccolta RAB – Cespiti di proprietà del gestore
Gare gas : raccolta RAB – Cespiti di proprietà del gestoreARERA
 
Riforma del dispacciamento elettrico - RDE. Il modello organizzativo del prog...
Riforma del dispacciamento elettrico - RDE. Il modello organizzativo del prog...Riforma del dispacciamento elettrico - RDE. Il modello organizzativo del prog...
Riforma del dispacciamento elettrico - RDE. Il modello organizzativo del prog...ARERA
 
Dare più "energia" ai Regolatori? L'Istituzione tra le Istituzioni
Dare più "energia" ai Regolatori? L'Istituzione tra le IstituzioniDare più "energia" ai Regolatori? L'Istituzione tra le Istituzioni
Dare più "energia" ai Regolatori? L'Istituzione tra le IstituzioniARERA
 
La consultazione dell'Autorità sullo sviluppo della metodologia di analisi co...
La consultazione dell'Autorità sullo sviluppo della metodologia di analisi co...La consultazione dell'Autorità sullo sviluppo della metodologia di analisi co...
La consultazione dell'Autorità sullo sviluppo della metodologia di analisi co...ARERA
 
Regolazione dei servizi di connessione, trasmissione, distribuzione, misura e...
Regolazione dei servizi di connessione, trasmissione, distribuzione, misura e...Regolazione dei servizi di connessione, trasmissione, distribuzione, misura e...
Regolazione dei servizi di connessione, trasmissione, distribuzione, misura e...ARERA
 
Riforma del dispacciamento elettrico - RDE - Consultazione prezzi negativi
Riforma del dispacciamento elettrico - RDE - Consultazione prezzi negativiRiforma del dispacciamento elettrico - RDE - Consultazione prezzi negativi
Riforma del dispacciamento elettrico - RDE - Consultazione prezzi negativiARERA
 
Non solo sanzioni: gli strumenti a tutela dei consumatori
Non solo sanzioni: gli strumenti a tutela dei consumatoriNon solo sanzioni: gli strumenti a tutela dei consumatori
Non solo sanzioni: gli strumenti a tutela dei consumatoriARERA
 
Bonus elettrico e gas: evidenze dopo otto anni di attuazione
Bonus elettrico e gas: evidenze dopo otto anni di attuazioneBonus elettrico e gas: evidenze dopo otto anni di attuazione
Bonus elettrico e gas: evidenze dopo otto anni di attuazioneARERA
 
Tariffe dei servizi di distribuzione e misura del gas per il quarto periodo d...
Tariffe dei servizi di distribuzione e misura del gas per il quarto periodo d...Tariffe dei servizi di distribuzione e misura del gas per il quarto periodo d...
Tariffe dei servizi di distribuzione e misura del gas per il quarto periodo d...ARERA
 

Destacado (20)

WACC calculation methodology review
WACC calculation methodology reviewWACC calculation methodology review
WACC calculation methodology review
 
Indici di performance per la quantificazione delle criticità del Servizio Idr...
Indici di performance per la quantificazione delle criticità del Servizio Idr...Indici di performance per la quantificazione delle criticità del Servizio Idr...
Indici di performance per la quantificazione delle criticità del Servizio Idr...
 
La Governance del settore idrico
La Governance del settore idricoLa Governance del settore idrico
La Governance del settore idrico
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integrato
 
Riforma dispacciamento elettrico (RDE)- Principali linee d'azione
Riforma dispacciamento elettrico (RDE)- Principali linee d'azioneRiforma dispacciamento elettrico (RDE)- Principali linee d'azione
Riforma dispacciamento elettrico (RDE)- Principali linee d'azione
 
Mercati energetici concorrenziali e funzione giustiziale
Mercati energetici concorrenziali e funzione giustizialeMercati energetici concorrenziali e funzione giustiziale
Mercati energetici concorrenziali e funzione giustiziale
 
La generazione distribuita: novità regolatorie
La generazione distribuita: novità regolatorieLa generazione distribuita: novità regolatorie
La generazione distribuita: novità regolatorie
 
Sviluppo e nuove tecnologie: quale regolazione
Sviluppo e nuove tecnologie: quale regolazioneSviluppo e nuove tecnologie: quale regolazione
Sviluppo e nuove tecnologie: quale regolazione
 
Servizio di bilanciamento del gas naturale
Servizio di bilanciamento del gas naturaleServizio di bilanciamento del gas naturale
Servizio di bilanciamento del gas naturale
 
Le linee strategiche della regolazione e dell’enforcement dell’energia: un co...
Le linee strategiche della regolazione e dell’enforcement dell’energia:un co...Le linee strategiche della regolazione e dell’enforcement dell’energia:un co...
Le linee strategiche della regolazione e dell’enforcement dell’energia: un co...
 
La misura del gas naturale
La misura del gas naturaleLa misura del gas naturale
La misura del gas naturale
 
Gare gas : raccolta RAB – Cespiti di proprietà del gestore
Gare gas : raccolta RAB – Cespiti di proprietà del gestoreGare gas : raccolta RAB – Cespiti di proprietà del gestore
Gare gas : raccolta RAB – Cespiti di proprietà del gestore
 
Riforma del dispacciamento elettrico - RDE. Il modello organizzativo del prog...
Riforma del dispacciamento elettrico - RDE. Il modello organizzativo del prog...Riforma del dispacciamento elettrico - RDE. Il modello organizzativo del prog...
Riforma del dispacciamento elettrico - RDE. Il modello organizzativo del prog...
 
Dare più "energia" ai Regolatori? L'Istituzione tra le Istituzioni
Dare più "energia" ai Regolatori? L'Istituzione tra le IstituzioniDare più "energia" ai Regolatori? L'Istituzione tra le Istituzioni
Dare più "energia" ai Regolatori? L'Istituzione tra le Istituzioni
 
La consultazione dell'Autorità sullo sviluppo della metodologia di analisi co...
La consultazione dell'Autorità sullo sviluppo della metodologia di analisi co...La consultazione dell'Autorità sullo sviluppo della metodologia di analisi co...
La consultazione dell'Autorità sullo sviluppo della metodologia di analisi co...
 
Regolazione dei servizi di connessione, trasmissione, distribuzione, misura e...
Regolazione dei servizi di connessione, trasmissione, distribuzione, misura e...Regolazione dei servizi di connessione, trasmissione, distribuzione, misura e...
Regolazione dei servizi di connessione, trasmissione, distribuzione, misura e...
 
Riforma del dispacciamento elettrico - RDE - Consultazione prezzi negativi
Riforma del dispacciamento elettrico - RDE - Consultazione prezzi negativiRiforma del dispacciamento elettrico - RDE - Consultazione prezzi negativi
Riforma del dispacciamento elettrico - RDE - Consultazione prezzi negativi
 
Non solo sanzioni: gli strumenti a tutela dei consumatori
Non solo sanzioni: gli strumenti a tutela dei consumatoriNon solo sanzioni: gli strumenti a tutela dei consumatori
Non solo sanzioni: gli strumenti a tutela dei consumatori
 
Bonus elettrico e gas: evidenze dopo otto anni di attuazione
Bonus elettrico e gas: evidenze dopo otto anni di attuazioneBonus elettrico e gas: evidenze dopo otto anni di attuazione
Bonus elettrico e gas: evidenze dopo otto anni di attuazione
 
Tariffe dei servizi di distribuzione e misura del gas per il quarto periodo d...
Tariffe dei servizi di distribuzione e misura del gas per il quarto periodo d...Tariffe dei servizi di distribuzione e misura del gas per il quarto periodo d...
Tariffe dei servizi di distribuzione e misura del gas per il quarto periodo d...
 

Similar a Financing the water sector

Presentation - OECD workshop on the performance of utilities for wastewater, ...
Presentation - OECD workshop on the performance of utilities for wastewater, ...Presentation - OECD workshop on the performance of utilities for wastewater, ...
Presentation - OECD workshop on the performance of utilities for wastewater, ...OECD Environment
 
Report on water services & waste management
Report on water services & waste managementReport on water services & waste management
Report on water services & waste managementARERA
 
Evaluation of Energy Efficiency policies in Italy - Daniel Giannetti, GSE
Evaluation of Energy Efficiency policies in Italy - Daniel Giannetti, GSEEvaluation of Energy Efficiency policies in Italy - Daniel Giannetti, GSE
Evaluation of Energy Efficiency policies in Italy - Daniel Giannetti, GSEGestore dei Servizi Energetici
 
1Q 2015 Consolidated Results (6 Maggio 2015)
1Q 2015 Consolidated Results (6 Maggio 2015)1Q 2015 Consolidated Results (6 Maggio 2015)
1Q 2015 Consolidated Results (6 Maggio 2015)Terna SpA
 
FY2014 and 2015-2019 Strategic Plan (26 marzo 2015)
FY2014 and 2015-2019 Strategic Plan (26 marzo 2015)FY2014 and 2015-2019 Strategic Plan (26 marzo 2015)
FY2014 and 2015-2019 Strategic Plan (26 marzo 2015)Terna SpA
 
2014 Full Year Results & Strategy Update
2014 Full Year Results & Strategy Update2014 Full Year Results & Strategy Update
2014 Full Year Results & Strategy UpdateSnam
 
International Taxation - BEPS Pillar 1 _ Pillar 2 Overview.pdf
International Taxation - BEPS Pillar 1 _ Pillar 2 Overview.pdfInternational Taxation - BEPS Pillar 1 _ Pillar 2 Overview.pdf
International Taxation - BEPS Pillar 1 _ Pillar 2 Overview.pdfSteadfast Business Consulting
 
Transfer Pricing - Indian Budget 2022 and Global TP Updates.pdf
Transfer Pricing - Indian Budget 2022 and Global TP Updates.pdfTransfer Pricing - Indian Budget 2022 and Global TP Updates.pdf
Transfer Pricing - Indian Budget 2022 and Global TP Updates.pdfSteadfast Business Consulting
 
Wind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptxWind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptxlengoclong8513
 
The EU Renewables Directive
The EU Renewables DirectiveThe EU Renewables Directive
The EU Renewables DirectiveLeonardo ENERGY
 
Addressing international corporate tax evasion an analysis of the oecd acti...
Addressing international corporate tax evasion   an analysis of the oecd acti...Addressing international corporate tax evasion   an analysis of the oecd acti...
Addressing international corporate tax evasion an analysis of the oecd acti...Florian Marchal
 
The Renewables EU Directive
The Renewables EU DirectiveThe Renewables EU Directive
The Renewables EU Directivefernando nuño
 
#ACCIONA9M17 results report
#ACCIONA9M17 results report#ACCIONA9M17 results report
#ACCIONA9M17 results reportacciona
 
Implementation of BAT approach
Implementation of BAT approachImplementation of BAT approach
Implementation of BAT approachOECD Environment
 
Introduction to network regulation - Investment Incentives
Introduction to network regulation - Investment IncentivesIntroduction to network regulation - Investment Incentives
Introduction to network regulation - Investment IncentivesLeonardo ENERGY
 
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to Save
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to SaveOntario Cap & Trade - Time is Running Out for Small & Medium Business to Save
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to SaveDuncan Rotherham
 
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to Save
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to SaveOntario Cap & Trade - Time is Running Out for Small & Medium Business to Save
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to SaveSheldon Fernandes, P.Eng., MBA
 

Similar a Financing the water sector (20)

Presentation - OECD workshop on the performance of utilities for wastewater, ...
Presentation - OECD workshop on the performance of utilities for wastewater, ...Presentation - OECD workshop on the performance of utilities for wastewater, ...
Presentation - OECD workshop on the performance of utilities for wastewater, ...
 
Report on water services & waste management
Report on water services & waste managementReport on water services & waste management
Report on water services & waste management
 
Evaluations of SEAPs: strengths and weaknesses - Melica
Evaluations of SEAPs: strengths and weaknesses - MelicaEvaluations of SEAPs: strengths and weaknesses - Melica
Evaluations of SEAPs: strengths and weaknesses - Melica
 
Evaluation of Energy Efficiency policies in Italy - Daniel Giannetti, GSE
Evaluation of Energy Efficiency policies in Italy - Daniel Giannetti, GSEEvaluation of Energy Efficiency policies in Italy - Daniel Giannetti, GSE
Evaluation of Energy Efficiency policies in Italy - Daniel Giannetti, GSE
 
1Q 2015 Consolidated Results (6 Maggio 2015)
1Q 2015 Consolidated Results (6 Maggio 2015)1Q 2015 Consolidated Results (6 Maggio 2015)
1Q 2015 Consolidated Results (6 Maggio 2015)
 
FY2014 and 2015-2019 Strategic Plan (26 marzo 2015)
FY2014 and 2015-2019 Strategic Plan (26 marzo 2015)FY2014 and 2015-2019 Strategic Plan (26 marzo 2015)
FY2014 and 2015-2019 Strategic Plan (26 marzo 2015)
 
2014 Full Year Results & Strategy Update
2014 Full Year Results & Strategy Update2014 Full Year Results & Strategy Update
2014 Full Year Results & Strategy Update
 
International Taxation - BEPS Pillar 1 _ Pillar 2 Overview.pdf
International Taxation - BEPS Pillar 1 _ Pillar 2 Overview.pdfInternational Taxation - BEPS Pillar 1 _ Pillar 2 Overview.pdf
International Taxation - BEPS Pillar 1 _ Pillar 2 Overview.pdf
 
Transfer Pricing - Indian Budget 2022 and Global TP Updates.pdf
Transfer Pricing - Indian Budget 2022 and Global TP Updates.pdfTransfer Pricing - Indian Budget 2022 and Global TP Updates.pdf
Transfer Pricing - Indian Budget 2022 and Global TP Updates.pdf
 
Poster - How to promove with water and waste price regulation
Poster - How to promove with water and waste price regulationPoster - How to promove with water and waste price regulation
Poster - How to promove with water and waste price regulation
 
Investment Incentives
Investment IncentivesInvestment Incentives
Investment Incentives
 
Wind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptxWind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptx
 
The EU Renewables Directive
The EU Renewables DirectiveThe EU Renewables Directive
The EU Renewables Directive
 
Addressing international corporate tax evasion an analysis of the oecd acti...
Addressing international corporate tax evasion   an analysis of the oecd acti...Addressing international corporate tax evasion   an analysis of the oecd acti...
Addressing international corporate tax evasion an analysis of the oecd acti...
 
The Renewables EU Directive
The Renewables EU DirectiveThe Renewables EU Directive
The Renewables EU Directive
 
#ACCIONA9M17 results report
#ACCIONA9M17 results report#ACCIONA9M17 results report
#ACCIONA9M17 results report
 
Implementation of BAT approach
Implementation of BAT approachImplementation of BAT approach
Implementation of BAT approach
 
Introduction to network regulation - Investment Incentives
Introduction to network regulation - Investment IncentivesIntroduction to network regulation - Investment Incentives
Introduction to network regulation - Investment Incentives
 
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to Save
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to SaveOntario Cap & Trade - Time is Running Out for Small & Medium Business to Save
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to Save
 
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to Save
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to SaveOntario Cap & Trade - Time is Running Out for Small & Medium Business to Save
Ontario Cap & Trade - Time is Running Out for Small & Medium Business to Save
 

Más de ARERA

Report on Electricity and Gas
Report on Electricity and GasReport on Electricity and Gas
Report on Electricity and GasARERA
 
230222Autoconsumo.pdf
230222Autoconsumo.pdf230222Autoconsumo.pdf
230222Autoconsumo.pdfARERA
 
TIDE_Seminario_23.pdf
TIDE_Seminario_23.pdfTIDE_Seminario_23.pdf
TIDE_Seminario_23.pdfARERA
 
Bonus sociale idrico. Modalità attuative e attività in capo ai gestori idrici
Bonus sociale idrico. Modalità attuative e attività in capo ai gestori idriciBonus sociale idrico. Modalità attuative e attività in capo ai gestori idrici
Bonus sociale idrico. Modalità attuative e attività in capo ai gestori idriciARERA
 
Ricarica dei veicoli elettrici in luoghi non accessibili al pubblico
Ricarica dei veicoli elettrici in luoghi non accessibili al pubblicoRicarica dei veicoli elettrici in luoghi non accessibili al pubblico
Ricarica dei veicoli elettrici in luoghi non accessibili al pubblicoARERA
 
Riassetto dell’attività di misura sulla rete di trasporto gas
Riassetto dell’attività di misura sulla rete di trasporto gasRiassetto dell’attività di misura sulla rete di trasporto gas
Riassetto dell’attività di misura sulla rete di trasporto gasARERA
 
L'evoluzione della regolazione del settore idrico
L'evoluzione della regolazione del settore idrico L'evoluzione della regolazione del settore idrico
L'evoluzione della regolazione del settore idrico ARERA
 
Servizio Conciliazione - Relazione annuale sulle attività
Servizio Conciliazione - Relazione annuale sulle attività Servizio Conciliazione - Relazione annuale sulle attività
Servizio Conciliazione - Relazione annuale sulle attività ARERA
 
Ammodernamento delle colonne montanti vetuste
Ammodernamento delle colonne montanti vetusteAmmodernamento delle colonne montanti vetuste
Ammodernamento delle colonne montanti vetusteARERA
 
Regolazione della qualità tecnica del servizio di telecalore
Regolazione della qualità tecnica del servizio di telecaloreRegolazione della qualità tecnica del servizio di telecalore
Regolazione della qualità tecnica del servizio di telecaloreARERA
 
Teleriscaldamento - Modalità di esercizio del diritto di recesso
Teleriscaldamento - Modalità di esercizio del diritto di recessoTeleriscaldamento - Modalità di esercizio del diritto di recesso
Teleriscaldamento - Modalità di esercizio del diritto di recessoARERA
 
Primi orientamenti in materia di regolazione della misura nel servizio di tel...
Primi orientamenti in materia di regolazione della misura nel servizio di tel...Primi orientamenti in materia di regolazione della misura nel servizio di tel...
Primi orientamenti in materia di regolazione della misura nel servizio di tel...ARERA
 
Regolazione della trasparenza del servizio di telecalore (TITT)
Regolazione della trasparenza del servizio di telecalore (TITT)Regolazione della trasparenza del servizio di telecalore (TITT)
Regolazione della trasparenza del servizio di telecalore (TITT)ARERA
 
Stato della regolazione del settore del teleriscaldamento e teleraffrescamento
Stato della regolazione del settore del teleriscaldamento e teleraffrescamentoStato della regolazione del settore del teleriscaldamento e teleraffrescamento
Stato della regolazione del settore del teleriscaldamento e teleraffrescamentoARERA
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoARERA
 
Il MTI-3 alla luce delle prospettive regolatorie europee
Il MTI-3 alla luce delle prospettive regolatorie europeeIl MTI-3 alla luce delle prospettive regolatorie europee
Il MTI-3 alla luce delle prospettive regolatorie europeeARERA
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoARERA
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoARERA
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoARERA
 
TIDE - Testo Integrato del Dispacciamento Elettrico
TIDE - Testo Integrato del Dispacciamento ElettricoTIDE - Testo Integrato del Dispacciamento Elettrico
TIDE - Testo Integrato del Dispacciamento ElettricoARERA
 

Más de ARERA (20)

Report on Electricity and Gas
Report on Electricity and GasReport on Electricity and Gas
Report on Electricity and Gas
 
230222Autoconsumo.pdf
230222Autoconsumo.pdf230222Autoconsumo.pdf
230222Autoconsumo.pdf
 
TIDE_Seminario_23.pdf
TIDE_Seminario_23.pdfTIDE_Seminario_23.pdf
TIDE_Seminario_23.pdf
 
Bonus sociale idrico. Modalità attuative e attività in capo ai gestori idrici
Bonus sociale idrico. Modalità attuative e attività in capo ai gestori idriciBonus sociale idrico. Modalità attuative e attività in capo ai gestori idrici
Bonus sociale idrico. Modalità attuative e attività in capo ai gestori idrici
 
Ricarica dei veicoli elettrici in luoghi non accessibili al pubblico
Ricarica dei veicoli elettrici in luoghi non accessibili al pubblicoRicarica dei veicoli elettrici in luoghi non accessibili al pubblico
Ricarica dei veicoli elettrici in luoghi non accessibili al pubblico
 
Riassetto dell’attività di misura sulla rete di trasporto gas
Riassetto dell’attività di misura sulla rete di trasporto gasRiassetto dell’attività di misura sulla rete di trasporto gas
Riassetto dell’attività di misura sulla rete di trasporto gas
 
L'evoluzione della regolazione del settore idrico
L'evoluzione della regolazione del settore idrico L'evoluzione della regolazione del settore idrico
L'evoluzione della regolazione del settore idrico
 
Servizio Conciliazione - Relazione annuale sulle attività
Servizio Conciliazione - Relazione annuale sulle attività Servizio Conciliazione - Relazione annuale sulle attività
Servizio Conciliazione - Relazione annuale sulle attività
 
Ammodernamento delle colonne montanti vetuste
Ammodernamento delle colonne montanti vetusteAmmodernamento delle colonne montanti vetuste
Ammodernamento delle colonne montanti vetuste
 
Regolazione della qualità tecnica del servizio di telecalore
Regolazione della qualità tecnica del servizio di telecaloreRegolazione della qualità tecnica del servizio di telecalore
Regolazione della qualità tecnica del servizio di telecalore
 
Teleriscaldamento - Modalità di esercizio del diritto di recesso
Teleriscaldamento - Modalità di esercizio del diritto di recessoTeleriscaldamento - Modalità di esercizio del diritto di recesso
Teleriscaldamento - Modalità di esercizio del diritto di recesso
 
Primi orientamenti in materia di regolazione della misura nel servizio di tel...
Primi orientamenti in materia di regolazione della misura nel servizio di tel...Primi orientamenti in materia di regolazione della misura nel servizio di tel...
Primi orientamenti in materia di regolazione della misura nel servizio di tel...
 
Regolazione della trasparenza del servizio di telecalore (TITT)
Regolazione della trasparenza del servizio di telecalore (TITT)Regolazione della trasparenza del servizio di telecalore (TITT)
Regolazione della trasparenza del servizio di telecalore (TITT)
 
Stato della regolazione del settore del teleriscaldamento e teleraffrescamento
Stato della regolazione del settore del teleriscaldamento e teleraffrescamentoStato della regolazione del settore del teleriscaldamento e teleraffrescamento
Stato della regolazione del settore del teleriscaldamento e teleraffrescamento
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integrato
 
Il MTI-3 alla luce delle prospettive regolatorie europee
Il MTI-3 alla luce delle prospettive regolatorie europeeIl MTI-3 alla luce delle prospettive regolatorie europee
Il MTI-3 alla luce delle prospettive regolatorie europee
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integrato
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integrato
 
La recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integratoLa recente evoluzione della regolazione del servizio idrico integrato
La recente evoluzione della regolazione del servizio idrico integrato
 
TIDE - Testo Integrato del Dispacciamento Elettrico
TIDE - Testo Integrato del Dispacciamento ElettricoTIDE - Testo Integrato del Dispacciamento Elettrico
TIDE - Testo Integrato del Dispacciamento Elettrico
 

Último

2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetkumargunjan9515
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...Namrata Singh
 
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgergMadhuKothuru
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberSareena Khatun
 
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...kajalverma014
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Partito democratico
 
Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!SERUDS INDIA
 
NGO working for orphan children’s education
NGO working for orphan children’s educationNGO working for orphan children’s education
NGO working for orphan children’s educationSERUDS INDIA
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfSERUDS INDIA
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...gajnagarg
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
 
2024 UNESCO/Guillermo Cano World Press Freedom Prize
2024 UNESCO/Guillermo Cano World Press Freedom Prize2024 UNESCO/Guillermo Cano World Press Freedom Prize
2024 UNESCO/Guillermo Cano World Press Freedom PrizeChristina Parmionova
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfScottMeyers35
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.Christina Parmionova
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterChristina Parmionova
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCNAP Global Network
 

Último (20)

2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
 
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
2024 asthma jkdjkfjsdklfjsdlkfjskldfgdsgerg
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
 
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
 
Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!
 
NGO working for orphan children’s education
NGO working for orphan children’s educationNGO working for orphan children’s education
NGO working for orphan children’s education
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
2024 UNESCO/Guillermo Cano World Press Freedom Prize
2024 UNESCO/Guillermo Cano World Press Freedom Prize2024 UNESCO/Guillermo Cano World Press Freedom Prize
2024 UNESCO/Guillermo Cano World Press Freedom Prize
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 

Financing the water sector

  • 1. SEMINAR FOR FINANCIAL ANALYSTS Financing the water sector Lorenzo Bardelli Director Water System Directorate 12th October 2015
  • 3. Authority approach to Water regulation Piecemeal activity within a comprehensive strategy Local decision making process Empowerment: self determination at decentralized level Coherency Cost reimbursement rules Constraints on Operating Costs (endogenous vs. exogenous) Priority to Investments Price Cap and Full Cost Recovery Pricing to end-users Tariff multiplier Reorganise tariff structure applied to consumers Rebalancing past disequilibria Past credit billing Investigation on above-the-cap proposals Measures to avoid default Urgent equalisation
  • 4. MTI REGULATORY PROCESS 4 PHASE 1 AEEGSI defines the tariff rules (2 or 3 consultations before the final decision) PHASE 2 Local Authorities (Ato) approve the tariff proposal (specific regulatory scheme), composed of investment plan and related financial plan, in agreement with the operators PHASE 3 AEEGSI collects all the proposal and all the other relevant data PHASE 4 AEEGSI investigates and verifies one-by-one the collected proposals, asking for further information, if necessary PHASE 5 AEEGSI approves – with or without modification or prescription, the proposal IDLE ATO Local Operator can communicate the proposal to AEEGSI (approves/modifies); otherwise AEEGSI takes the final decision (with penalization of 10% on the tariff)
  • 5. COST REIMBURSEMENT RULES DEPEND ON REGULATORY SCHEMES FOR THE YEARS 2014-2015 OPERATING COSTS NO VARIATIONS IN THE OPERATOR’S OBJECTIVES OR ACTIVITIES PRESENCE OF VARIATIONS IN THE OPERATOR’S OBJECTIVES OR ACTIVITIES INVESTMENTS SCHEME I – ordinary case Opex: more push on operating efficiency through a rolling cap, assuming the invariance over the period Capex recognised ex post using technical lives SCHEME II Opex: possibility to cover more opex motivating the request (and taking in consideration scale economies) Capex: same as ordinary case SCHEME III Opex: same as ordinary case Capex: more accelerated depreciation admitted, together with (limited) anticipation on investments SCHEME IV Opex: possibility to cover more opex motivating the request (and taking in consideration scale economies) Capex: more accelerated depreciation admitted, together with (limited) anticipation on investments Ordinary case is sufficient to finance investments Ordinary case not sufficient to finance investments 5,0 exp3 ≤ ∑ + MTT t t t RAB PI 5,0 exp3 > ∑ + MTT t t t RAB PI not a constraint, but a way to evaluate the most appropriate regulatory option More investments More activities 5
  • 6. DEFINITION OF THE COST COMPONENTS IN MTI (2014-2015) [1] [2] [3] [4] [5] [1] IMMOBILIZATION COSTS [2] COMPONENT IN SUPPORT OF SPECIFIC OBJECTIVES [3] OPERATING COSTS [4] COMPONENT TO COVER ENVIRONMENTAL AND RESOURCE COSTS [5] COMPONENT TO BALANCE THE REVENUES LIMIT FOR THE OPERATOR IN THE PREVIOUS YEARS aaaaa CUITOFiscOFAMMCapex ∆+++= a TOT aaaaa RCERCOpexFoNICapexVRG ++++= a FoNI a FoNI a FoNI a CUITAMMFNIFoNI ∆++= a al a end a OpexOpexOpex += aaa sCReEnvCERC += ( ) ( )∏−= +++++= a at ta ALTRO aa ws a EE a VOL a TOT IRcRimbRcRcRcRc 1 335 1* 6 NEW WATER TARIFF METHOD MTI - 2 • AEEGSI intends to confirm the general structure of VRG for the period 2016-2019
  • 7. Cap to the variation of the tariff multiplier Schemes I e II )1(1 Krpia a ++≤− ϑ ϑ Schemes III e IV ]*)1(1[1 Krpia a γ ϑ ϑ +++≤− 7 Maximum limit to the variation of the tariff multiplier, except for any specific inquiry in case the limit needs to be passed in order to ensure that specific objectives are met 6,5% 9,0% ( ) ∑ −− −− +• −+ = u a b Ta uu a b a b a a Rvscaltarif CRVRG 222012 22 )( *5,0 ϑ Tariffs applied in 2012 (calculated on the base of the old Method MTN) have to be updated multiplying them by a factor ϑ TARIFF MULTIPLIER FOR THE YEARS 2014-2015 Half margin from competitive water activities is used to reduce the tariffs of monopoly water activities NEW WATER TARIFF METHOD MTI - 2 • AEEGSI intends to confirm the general update mechanism of tariffs, based on the tariff multiplier
  • 8. Arrearage costs Arrearage costs ( ) defined as Unpaid Ratio (UR) in 24 months, are recognised as a parameter in order to encourage an efficient credit-recovery activity, and they are differentiated across geographical macro-areas, as a function of the different average incidence on the revenues. a morCO Past credit billing Any possible balancing with periods preceding the attribution of sector regulation and monitoring powers to AEEGSI, and not yet considered in the calculation of past tariffs, is quantified and approved by 30 June 2014 by the entitled entity or any other competent entity, and they are communicated to AEEGSI Terminal value Residual value for the operator of the Integrated Water Services (SII) in case of replacement is calculated: a) from a minimum value, equal to the residual value of assets of the SII operator, according to the following formula: b) up to a maximum value that includes a), the value of past accounts that have already been quantified and approved by the competent entities, and any guarantees possibly required by the lender MEASURES FOR AN EFFICIENT FINANCIAL SUSTAINABILITY ( ) ( )[ ]∑ ∑ +       −−−= =c a a t a ttcCFPtctcIPtc a LICdflFACFPFAIPVR 1961 ,,,,,, * NORTH: 1,6% CENTRE: 3,0% SOUTH: 6,5%
  • 10. OUTCOME OF THE DECISION-MAKING PROCESS OF THE LOCAL AUTHORITIES [YEARS 2014-2015] 10 Identifying critical issues Defining specific objectives Planning investments for the period 2014- 2017 Choosing the Regulatory Scheme Regulatory Schemes selected by local Authorities
  • 11. FOCUS ON TARIFFS APPROVED BY AEEGSI [YEARS 2014-2015] 11 68% 3% 12% 17% Schemi regolatori Teta 1 Teta 0,9 Non approvati Tariffs approved (% inhabitants) AEEGSI approved tariffs for 1.961 operators regarding 49.820.708 inhabitants. The new tariffs had an average yearly increase of 4.04% in 2014 and 4.46% in 2015
  • 12. TREND OF INVESTMENTS AFTER THE ACTION OF A CENTRAL REGULATOR 12 NET INVESTMENTS 2012 (€) NET INVESTMENTS 2013 (€) NET INVESTMENTS 2014 (€) NET INVESTMENTS 2015 (€) North-West 195.741.644 184.324.445 350.241.242 440.956.598 Nord-East 266.595.624 332.483.991 323.830.781 429.109.401 Centre 333.369.137 344.173.029 387.298.944 427.190.417 South 153.725.206 60.434.581 108.306.589 149.297.118 Islands 11.522.585 6.057.384 31.914.845 44.120.667 Italy 960.954.196 927.473.430 1.201.592.401 1.490.674.201 - 50.000.000 100.000.000 150.000.000 200.000.000 250.000.000 300.000.000 350.000.000 400.000.000 450.000.000 Nord Ovest Nord Est Centro Sud Isole Netinvestments(€) 2012 2015 Data referred to: 127 operators 40 mln inhabitants (2/3 of Italian population) +55%
  • 13. PLANNED INVESTMENTS FOR THE PERIOD 2014-2017: € 5.506.412.296* PLANNED ACTIONS: Maintenance of water supplying systems and plants; Development of new sewerage nets and wwt plants (higher compliance rates); Placing of metering systems CRITICAL ISSUES: Old networks and plants; Partial coverage of the sewerage and waste water treatment (wwt); Water losses; Lacking of metering systems CRITICALITY & PLANNED INVESTMENTS FOR THE PERIOD 2014-2017 13 [*data refered to 127 operators; 40 mln inhabitants] Planned investments (%) for regulatory Scheme
  • 14. 14 Tariff variation - year 2014 Planned investments for the period 2014-2017 TARIFF SUSTAINABILITY & RESILIENCE OF INVESTMENTS TARIFF VARIATION AT NATIONAL LEVEL: +4,04%
  • 15. 15 VALUE OF RAB & NEED TO INVEST IN WATER INFRASTRUCTURES Low value of Regulatory Asset = 13 Billion euros RAB per capita for geographic area [Cross Section Analysis for the year 2014] 46% 28% 21% 3% 2% Opex-end Opex-al Capex FoNI RCtot VRG configuration (%)
  • 17. 17 DEVELOPMENT OF THE NEW TARIFF METHOD ON THE BASE OF THE COLLECTED INFORMATION OPEX/PROVIDED UNITS OF WATER (€/mc) Min: 0,52 Mean: 1,49 Max: 2,72 OPEX/SERVED INHABITANTS (€/per capita) Min: 50,32 Mean: 108,60 Max: 200,09 ENERGY COSTS/OPEX Min: 3% Mean: 17% Max: 36% LABOUR COSTS/OPEX Min: 4% Mean: 25% Max: 47% Cross Section Analysis for the year 2014 [data referred to 105 operators, 32 mln inhabitants]
  • 18. OPM pop Opex ≤ 2014 OPM pop Opex > 2014 AGGREGAZIONI, VARIAZIONI NEGLI OBIETTIVI O NELLE ATTIVITÀ DEL GESTORE INVESTIMENTI ω≤ ∑ MTI t RAB PI exp2019 2016 SCHEMA I Limite di prezzo: ( )XKrpia a −++≤− 11 ϑ ϑ SCHEMA II Limite di prezzo: ( )XKrpia a 211 −++≤− ϑ ϑ SCHEMA III Limite di prezzo: ( )Krpia a ++≤− 11 ϑ ϑ ω> ∑ MTI t RAB PI exp2019 2016 SCHEMA IV Limite di prezzo: ( )XKrpia a −++≤− *5,111 ϑ ϑ SCHEMA V Limite di prezzo: ( )XKrpia a 2*5,111 −++≤− ϑ ϑ SCHEMA VI Limite di prezzo ( )Krpia a *5,111 ++≤− ϑ ϑ Regulatory Schemes for the second regulatory period 18 Mean of Opex per capita Mean of Opex per capita Factor Sharing, named as X, applied to the maximum limit allowable increase for every single year consideredFactor Sharing, named as X, applied to the maximum limit allowable increase for every single year considered
  • 19. 19 Limite di prezzo per tipo di Schema regolatorio : : OPM pop Opex ≤ 2014 OPM pop Opex > 2014 AGGREGAZIONI, VARIAZIONI NEGLI OBIETTIVI O NELLE ATTIVITÀ DEL GESTORE INVESTIMENTI ω≤ ∑ MTI t RAB PI exp2019 2016 SCHEMA I Limite di prezzo: ( )XKrpia a −++≤− 11 ϑ ϑ SCHEMA II Limite di prezzo: ( )XKrpia a 211 −++≤− ϑ ϑ SCHEMA III Limite di prezzo: ( )Krpia a ++≤− 11 ϑ ϑ ω> ∑ MTI t RAB PI exp2019 2016 SCHEMA IV Limite di prezzo: ( )XKrpia a −++≤− *5,111 ϑ ϑ SCHEMA V Limite di prezzo: ( )XKrpia a 2*5,111 −++≤− ϑ ϑ SCHEMA VI Limite di prezzo ( )Krpia a *5,111 ++≤− ϑ ϑ
  • 20. 20 NEW OBLIGATIONS FOR SUPPLIERS Regulation of quality of water service [DCO 665/2014/R/idr and DCO 273/2015/R/idr]; Rules about collection expenditure [Del. 7/2015/R/idr] SHARING THE RISK IN THE NEW REGULATORY FRAMEWORK Schemes of standard agreement between ATO and service providers [DCO 171/2014/R/idr and DCO 274/2013/R/idr] INCREASING PRICE REFLECTIVITY AND PROMOTING BETTER STANDARD FOR ENVIRONMENTAL PROTECTION Definition of tariffs for sewerage and treatment of industrial wastewater [DCO 299/2014/R/idr and 620/2014/R/idr] Explicit identification of environment and resource costs [DCO 539/2014/R/idr and Del. 662/2014/R/idr] Unbundling (with definition of the “integrated water service” perimeter) [DCO 379/20145R/idr] Strategic guidelines for the next regulatory period (Water Tariff Method MTI - 2), starting in 2016 [DCO 406/2014/R/idr] i. Promoting efficiency; ii. Increasing investments (also following an “output-based” approach); iii. Reorganizing water industry (from 2500 to less than 100…) OTHER FIELDS OF ACTION for the definition of a clear and coherent framework of rules
  • 21. ROADMAP FOR A NEW REGULATION OF QUALITY & STANDARD AGREEMENTS 21 Consultation Paper 665/2014/R/idr: AEEGSI general orientations on contracting conditions regarding: - Billing - Payment modalities - Customer heldesk - Call centers - Requests of information - Dispute settllement 23 Dec 2014 4 June 2015 Consultation Paper 273/2015/R/idr : Additional principles on contracting conditions regarding : - Termination - Management - Information required - Data collection and protection 27 Mar 2014 Resolution 142/2014/R/idr: Start of regulatory decision-making procedure on quality of (intergated) water services, setting out objectives and powers of: - Data collection - Consultation - Meetings with operators 10 Apr 2014 Consultation Paper 171/2014/R/idr: AEEGSI general orientations on schemes of concession contracts between ATO and service providers Consultation Paper 274/2015/R/idr: AEEGSI general orientations on schemes of concession contracts between ATO and service providers Oct/ Nov 2015 AEGGSI final decisions about contractual quality & schemes of concession contracts Jan 2016 NEW RULES ARE APPLIED Quality Quality Quality Concession contracts Concession contracts
  • 22. • Commercial (in water we use the term contractual) and technical • Further dimensions of water service (other than quantity) • Mechanism proposed in Consultation Paper 273/2015/R/idr (contractual quality): Minimum level of quality granted homogeneously for all Italian consumers, paid in tariff (in the so called VRG) Penalties for operators if quality under the minimum threshold with prohibition to recover in tariff any penalty Possibility to ask for premium if quality above threshold and after cost – benefit analysis of the underlying investments Premium paid by all served consumers through a specific tariff component QUALITY OF WATER SERVICES 22
  • 23. The current consultation process on commercial quality aims at regulating the following contracting conditions: • Billing • Connection to the networks • Management of helpdesk and website • Management of call center • Request of information • Reimbursement for consumers • Management of complaints • Dispute settlement QUALITY OF WATER SERVICES (2) 23
  • 24. 24 STANDARD AGREEMENTS AEEGSI draws up also standard agreements (SA) to regulate contractual relations between local authorities and undertakings SA is an important tool to define the contractual framework at local level and ensure certanty and affordability of the general regulatory framework In particular, the SA sets: • maximum duration of public concessions and conditions for their possible extension; • terms and procedures for asset payment at the end of public concession (terminal value) to ensure the maintenance of economic-financial viability; • risk sharing between undertakings and public system, which is diversified in accordance with the organisational model chosen AEEGSI is defining SA by the end of the year (cfr. consultation paper 274/2015/R/idr)