Toronto Pearson Airport
Terminal Expansion Project
Presented by:
Ahmed Mahmoud
Toronto Pearson Airport - Terminal Expansion Project
Topics
 Introduction
 Procurement Strategy
 Change and Conflict Management
 Recommendations & Conclusion
Introduction
Toronto Pearson Airport - Terminal Expansion Project
Introduction
GTAA needs to address the following challenges:
1. Rapid increase in passenger volumes and cargo movement;
2. Overcrowding; and
3. Overall efficiency of the airport
Toronto Pearson Airport - Terminal Expansion Project
Introduction
Best approach to solving these challenges:
A TERMINAL EXPANSION PROJECT!
Toronto Pearson Airport - Terminal Expansion Project
Introduction
Aviation Activity & Forecast
Actual Forecast
Year 1990 1995 2000 2005 2010 2015 2020 2025 2030
Passengers 22 22.4 28.9 29.9 36 42.9 50.3 58.1 66
In 2010, approximately 36 million passengers passed through Toronto Pearson
Forecast of 58 million passengers by 2025
Toronto Pearson Airport - Terminal Expansion Project
Introduction
Terminal Expansion Project Components
 Terminal 1 Expansion of 400,000m²;
 Three piers G, H & I to be built: Pier G will provide 18 gates; Pier H will provide 31
gates and Pier I will provide 14 gates;
 New pedestrian tunnel connection to GO train platform;
 New parking facility will provide 4,000 parking spaces;
 New pedestrian tunnel connection between new parking facility and Terminal; and
 New baggage claim areas.
Toronto Pearson Airport - Terminal Expansion Project
Introduction
Procurement Strategy
Toronto Pearson Airport - Terminal Expansion Project
Procurement Strategy
Project delivery method
The recommended project delivery method is Construction
Management at Fee
Why Construction Management
 The effective use of available funds
 Enhanced control of the scope of the work
 Optimum project scheduling options
 flexibility in procurement options
 Strategies to avoid delays, changes and claims
 Assist in Design Consultant selection
 Enhanced design and construction quality
Toronto Pearson Airport - Terminal Expansion Project
Procurement Strategy
Project delivery method
As a best practice major airport owners selected construction management
project delivery over other methods, for example the following International
Airports:
 Toronto Pearson
 London Heathrow
 Seattle-Tacoma
 Philadelphia
 San Francisco
 Los Angeles
 Cairo
 Jeddah
 Dubai
 Abu Dhabi
 Muscat
 Doha
Toronto Pearson Airport - Terminal Expansion Project
Procurement Strategy
Procurement Model
The recommended procurement model is the
Traditional Model (Design-Bid-Build)
Why traditional procurement model
 This model is widely applicable, well understood, and
clearly defined roles for the parties involved.
 This model is the most common approach for public
owners having to comply with regional, provincial or
federal procurement statutes.
 The owner has a significant amount of control over the
end product.
Toronto Pearson Airport - Terminal Expansion Project
Procurement Strategy
Scheduling Approach
The recommended scheduling approach is the
Sequential Approach
Sequential versus Fast-Track
 In sequential construction, construction does not begin until design is complete.
 In Fast-Track construction, design and construction activities overlap, with the goal
of reducing the overall time required to complete a project.
 Phased construction also introduces more complexity into the design process and
increases the potential for costly design errors.
 project estimated duration is not required to be fast-tracked.
 it’s required to be simple with minimum risk allocation.
Toronto Pearson Airport - Terminal Expansion Project
Procurement Strategy
Forms of Agreement
Legal relations
Owner + Construction Manager = Management Services Contract;
Owner + Design Consultant = Design Services Contract;
Owner + General Contractor = Construction Services Contract.
Owner Issuing Organization
Construction Manager CCDC 5A Canadian Construction Documents Committee
Design Consultant RAIC Document 6 Royal Architectural Institute of Canada
General Contactor CCDC 2 Canadian Construction Documents Committee
CCDC 5A 2010 Construction Management Contract – For Services
RAIC Document 6 2006 Canadian Standard Form of Contract for Architectural Services
CCDC 2 2008 Stipulated Price Contract
Toronto Pearson Airport - Terminal Expansion Project
Procurement Strategy
Project Organization
Toronto Pearson Airport - Terminal Expansion Project
Procurement Strategy
Procurement Strategy Benefits
Using hybrid procurement strategy of construction management as a project
delivery method with traditional procurement model and sequential construction
approach will maximize the advantage of each method and minimize the concerns
of each one if used separately; which will lead to minimum risk allocation and best
value for construction dollar as briefly listed as follows:
 Development teams selection based upon qualifications.
 Owner can select sub-contractors/sub-consultants.
 Can be fast-tracked; if requested by the owner.
 CM responsible to deliver the project on budget and on schedule.
 Defined roles/responsibilities for the development teams.
 Initially presents the lowest potential cost for the project.
 Design change claims during construction are the minimum compared to other
strategies.
Toronto Pearson Airport - Terminal Expansion Project
Procurement Strategy
Procurement Strategy Benefits
Why P3 is not recommended
There has been increasing discussion recently of P3 financing for airport projects as
a response to the tightening of availability of financial resources for airports.
 P3 is not recommend for the terminal expansion project because it has conflict of
interest between the private investor and the public entity serving the taxpayers
interest;
 plus the partial risk and control to an outside entity for such a strategic facility;
 It is suitable for services & maintenance facilities where owner control is
non‐critical, through a limited and controlled scope.
Recommendations &
Conclusion
No procurement strategy is faultless
Toronto Pearson Airport - Terminal Expansion Project
Recommendations
 Effectively communicate to the various development project team members, It is
important that all parties understand and commit to the owner’s expectations.
 Ensure that the terms and conditions of the various contracts reflect the goals,
objectives, issues, and expectations for the project owner;
 Consider legal assistance experienced in construction matters for crafting the
contract language;
 Commit to the appropriate level of owner involvement;
 Assess potential risks and plan how to manage the overall project via a
professional construction management consultant.
 Consider using alternate dispute resolution (ADR) approaches such as, dispute
review boards, or similar alternatives.
 Finally, Define how such disputes will be handled so that disruption and
cost/schedule impact are minimized.
Toronto Pearson Airport - Terminal Expansion Project
Conclusion
No procurement strategy is faultless. But, choosing the system that
best works for this specific project and actively ensuring that it is
properly implemented, can mean the difference between the success
and failure of your project.
If the terminal expansion project is undertaken it will address the
demand and be designed to provide a better flow of passengers,
baggage and new commercial retail offerings all designed to enhance
the customer travel and service experience and solidify Toronto
Pearson as a truly global hub, attracting passengers from around the
globe.
Thank You!

Más contenido relacionado

La actualidad más candente

Scheduling and Revenue Management
Scheduling and Revenue ManagementScheduling and Revenue Management
Scheduling and Revenue Managementnsihammou
 
Airline Industry
Airline IndustryAirline Industry
Airline Industryautomotive
 
Incheon international airport
Incheon international airportIncheon international airport
Incheon international airportShubham Bathwal
 
Strategic management ryanair
Strategic management ryanairStrategic management ryanair
Strategic management ryanairSharif Sabbir
 
Comprehensive Marketing Presentation on Emirates Airlines
Comprehensive Marketing Presentation on Emirates AirlinesComprehensive Marketing Presentation on Emirates Airlines
Comprehensive Marketing Presentation on Emirates AirlinesSheikh_Rehmat
 
Air Canada Presentation
Air Canada PresentationAir Canada Presentation
Air Canada Presentationjessicamcafee
 
Air Cargo Handling Teaching Material
Air Cargo Handling Teaching MaterialAir Cargo Handling Teaching Material
Air Cargo Handling Teaching MaterialTanade Sirinumas
 
airside operation 3
airside operation 3airside operation 3
airside operation 3AiDY
 
Airline Marketing 2 principle of marketing
Airline Marketing 2 principle of marketingAirline Marketing 2 principle of marketing
Airline Marketing 2 principle of marketingNarudh Cheramakara
 
Airline business- Air Industry II
Airline business- Air Industry IIAirline business- Air Industry II
Airline business- Air Industry IIToy Ang
 
Emirates - airline - flight
Emirates - airline - flight Emirates - airline - flight
Emirates - airline - flight Paareetosh Kumaar
 
Emirates Strategy Analysis
Emirates Strategy AnalysisEmirates Strategy Analysis
Emirates Strategy AnalysisTina Sepehrifar
 
Southwest Airlines Portfolio
Southwest Airlines PortfolioSouthwest Airlines Portfolio
Southwest Airlines PortfolioAmber Berlin
 
Air canada- Digital Marketing Strategy
Air canada- Digital Marketing StrategyAir canada- Digital Marketing Strategy
Air canada- Digital Marketing StrategyKeshav Arora
 

La actualidad más candente (20)

Scheduling and Revenue Management
Scheduling and Revenue ManagementScheduling and Revenue Management
Scheduling and Revenue Management
 
Airport
AirportAirport
Airport
 
Airports presentation
Airports presentationAirports presentation
Airports presentation
 
Airline Industry
Airline IndustryAirline Industry
Airline Industry
 
Porter's Analysis
Porter's AnalysisPorter's Analysis
Porter's Analysis
 
Airline Industry
Airline IndustryAirline Industry
Airline Industry
 
Incheon international airport
Incheon international airportIncheon international airport
Incheon international airport
 
Strategic management ryanair
Strategic management ryanairStrategic management ryanair
Strategic management ryanair
 
Emirates
EmiratesEmirates
Emirates
 
Comprehensive Marketing Presentation on Emirates Airlines
Comprehensive Marketing Presentation on Emirates AirlinesComprehensive Marketing Presentation on Emirates Airlines
Comprehensive Marketing Presentation on Emirates Airlines
 
Air Canada Presentation
Air Canada PresentationAir Canada Presentation
Air Canada Presentation
 
Air Cargo Handling Teaching Material
Air Cargo Handling Teaching MaterialAir Cargo Handling Teaching Material
Air Cargo Handling Teaching Material
 
airside operation 3
airside operation 3airside operation 3
airside operation 3
 
Airline Marketing 2 principle of marketing
Airline Marketing 2 principle of marketingAirline Marketing 2 principle of marketing
Airline Marketing 2 principle of marketing
 
Airline business- Air Industry II
Airline business- Air Industry IIAirline business- Air Industry II
Airline business- Air Industry II
 
Lufthansa Consulting overview
Lufthansa Consulting overviewLufthansa Consulting overview
Lufthansa Consulting overview
 
Emirates - airline - flight
Emirates - airline - flight Emirates - airline - flight
Emirates - airline - flight
 
Emirates Strategy Analysis
Emirates Strategy AnalysisEmirates Strategy Analysis
Emirates Strategy Analysis
 
Southwest Airlines Portfolio
Southwest Airlines PortfolioSouthwest Airlines Portfolio
Southwest Airlines Portfolio
 
Air canada- Digital Marketing Strategy
Air canada- Digital Marketing StrategyAir canada- Digital Marketing Strategy
Air canada- Digital Marketing Strategy
 

Destacado

Panoramique sur les paysages franciliens depuis la tour montparnasse pierre m...
Panoramique sur les paysages franciliens depuis la tour montparnasse pierre m...Panoramique sur les paysages franciliens depuis la tour montparnasse pierre m...
Panoramique sur les paysages franciliens depuis la tour montparnasse pierre m...L'Institut Paris Region
 
The Connected Traveler - Eindhoven Airport Digital Strategy
The Connected Traveler - Eindhoven Airport Digital StrategyThe Connected Traveler - Eindhoven Airport Digital Strategy
The Connected Traveler - Eindhoven Airport Digital Strategyelilejeune
 
Hongkong international airport
Hongkong international airportHongkong international airport
Hongkong international airportVedo Yudistira
 
Schiphol marketting strategies
Schiphol marketting strategiesSchiphol marketting strategies
Schiphol marketting strategiesKivanc Ozuolmez
 
The Case For Change: Rethinking Library Services, Staffing, and Spaces
The Case For Change: Rethinking Library Services, Staffing, and SpacesThe Case For Change: Rethinking Library Services, Staffing, and Spaces
The Case For Change: Rethinking Library Services, Staffing, and Spacesbrightspot
 
Key factors of attractiveness for Airport Areas and the special role of human...
Key factors of attractiveness for Airport Areas and the special role of human...Key factors of attractiveness for Airport Areas and the special role of human...
Key factors of attractiveness for Airport Areas and the special role of human...L'Institut Paris Region
 
Case Study of Changi Airport,Singapore
Case Study of Changi Airport,SingaporeCase Study of Changi Airport,Singapore
Case Study of Changi Airport,Singaporeeileen_0692
 
Singapore changi airport (wh)
Singapore changi airport (wh)Singapore changi airport (wh)
Singapore changi airport (wh)Mee Rul
 
IT Reference Architectures at Amsterdam Airport Schiphol
IT Reference Architectures at Amsterdam Airport SchipholIT Reference Architectures at Amsterdam Airport Schiphol
IT Reference Architectures at Amsterdam Airport SchipholMarc Chang Sing Pang
 
Dubai Airport 2012 Data Center Strategies
Dubai Airport  2012 Data Center Strategies Dubai Airport  2012 Data Center Strategies
Dubai Airport 2012 Data Center Strategies Sarmad Ibrahim
 
Business intelligence competency centre strategy and road map
Business intelligence competency centre strategy and road mapBusiness intelligence competency centre strategy and road map
Business intelligence competency centre strategy and road mapOmar Khan
 

Destacado (15)

Panoramique sur les paysages franciliens depuis la tour montparnasse pierre m...
Panoramique sur les paysages franciliens depuis la tour montparnasse pierre m...Panoramique sur les paysages franciliens depuis la tour montparnasse pierre m...
Panoramique sur les paysages franciliens depuis la tour montparnasse pierre m...
 
The Connected Traveler - Eindhoven Airport Digital Strategy
The Connected Traveler - Eindhoven Airport Digital StrategyThe Connected Traveler - Eindhoven Airport Digital Strategy
The Connected Traveler - Eindhoven Airport Digital Strategy
 
Hongkong international airport
Hongkong international airportHongkong international airport
Hongkong international airport
 
Schiphol marketting strategies
Schiphol marketting strategiesSchiphol marketting strategies
Schiphol marketting strategies
 
Airport IT Strategy
Airport IT Strategy Airport IT Strategy
Airport IT Strategy
 
The Case For Change: Rethinking Library Services, Staffing, and Spaces
The Case For Change: Rethinking Library Services, Staffing, and SpacesThe Case For Change: Rethinking Library Services, Staffing, and Spaces
The Case For Change: Rethinking Library Services, Staffing, and Spaces
 
Key factors of attractiveness for Airport Areas and the special role of human...
Key factors of attractiveness for Airport Areas and the special role of human...Key factors of attractiveness for Airport Areas and the special role of human...
Key factors of attractiveness for Airport Areas and the special role of human...
 
Case Study of Changi Airport,Singapore
Case Study of Changi Airport,SingaporeCase Study of Changi Airport,Singapore
Case Study of Changi Airport,Singapore
 
Singapore changi airport (wh)
Singapore changi airport (wh)Singapore changi airport (wh)
Singapore changi airport (wh)
 
Changi Airport Process Technology
Changi Airport Process TechnologyChangi Airport Process Technology
Changi Airport Process Technology
 
IT Reference Architectures at Amsterdam Airport Schiphol
IT Reference Architectures at Amsterdam Airport SchipholIT Reference Architectures at Amsterdam Airport Schiphol
IT Reference Architectures at Amsterdam Airport Schiphol
 
Dubai Airport 2012 Data Center Strategies
Dubai Airport  2012 Data Center Strategies Dubai Airport  2012 Data Center Strategies
Dubai Airport 2012 Data Center Strategies
 
CHANGI AIRPORT
CHANGI AIRPORTCHANGI AIRPORT
CHANGI AIRPORT
 
Kansai airport ppt
Kansai airport pptKansai airport ppt
Kansai airport ppt
 
Business intelligence competency centre strategy and road map
Business intelligence competency centre strategy and road mapBusiness intelligence competency centre strategy and road map
Business intelligence competency centre strategy and road map
 

Similar a Toronto Pearson Airport - Terminal Expansion Project Presentation

ProTech an introduction (client) v1.3 8jun2017ml (lowres)
ProTech an introduction (client) v1.3 8jun2017ml (lowres)ProTech an introduction (client) v1.3 8jun2017ml (lowres)
ProTech an introduction (client) v1.3 8jun2017ml (lowres)Giselle Duran
 
Project success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementProject success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementCatherine Bendell
 
2016 McKinsey Tim McManus Managing big projects
2016 McKinsey Tim McManus Managing big projects2016 McKinsey Tim McManus Managing big projects
2016 McKinsey Tim McManus Managing big projectsTim McManus
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
Suggested Best Practices for Design-Build in Transportation Construction
Suggested Best Practices for Design-Build in Transportation ConstructionSuggested Best Practices for Design-Build in Transportation Construction
Suggested Best Practices for Design-Build in Transportation Constructionartba
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaNarendra Vasudeva
 
ProTech training presentation
ProTech training presentationProTech training presentation
ProTech training presentationGiselle Duran
 
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon
 
Project success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementProject success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementAssociation for Project Management
 

Similar a Toronto Pearson Airport - Terminal Expansion Project Presentation (20)

Capital Programs - O'Hare 21
Capital Programs - O'Hare 21 Capital Programs - O'Hare 21
Capital Programs - O'Hare 21
 
ASCE T&DI Abstract 40 - Final Paper
ASCE T&DI Abstract 40 - Final PaperASCE T&DI Abstract 40 - Final Paper
ASCE T&DI Abstract 40 - Final Paper
 
Oman EPC 2015 summary and recommendations
Oman EPC 2015 summary and recommendationsOman EPC 2015 summary and recommendations
Oman EPC 2015 summary and recommendations
 
ProTech an introduction (client) v1.3 8jun2017ml (lowres)
ProTech an introduction (client) v1.3 8jun2017ml (lowres)ProTech an introduction (client) v1.3 8jun2017ml (lowres)
ProTech an introduction (client) v1.3 8jun2017ml (lowres)
 
Project success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementProject success through excellence in procurement and contract management
Project success through excellence in procurement and contract management
 
Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17 Contract and procuremet guide evening launch slides 05 10-17
Contract and procuremet guide evening launch slides 05 10-17
 
2016 McKinsey Tim McManus Managing big projects
2016 McKinsey Tim McManus Managing big projects2016 McKinsey Tim McManus Managing big projects
2016 McKinsey Tim McManus Managing big projects
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
50456_DBTR34_P_Info
50456_DBTR34_P_Info50456_DBTR34_P_Info
50456_DBTR34_P_Info
 
FPSO
FPSOFPSO
FPSO
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
 
Standard forms lgtf
Standard forms lgtfStandard forms lgtf
Standard forms lgtf
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
Suggested Best Practices for Design-Build in Transportation Construction
Suggested Best Practices for Design-Build in Transportation ConstructionSuggested Best Practices for Design-Build in Transportation Construction
Suggested Best Practices for Design-Build in Transportation Construction
 
4
44
4
 
PPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudevaPPM BIM summer school presentation vasudeva
PPM BIM summer school presentation vasudeva
 
SDCV1116
SDCV1116SDCV1116
SDCV1116
 
ProTech training presentation
ProTech training presentationProTech training presentation
ProTech training presentation
 
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016
 
Project success through excellence in procurement and contract management
Project success through excellence in procurement and contract managementProject success through excellence in procurement and contract management
Project success through excellence in procurement and contract management
 

Último

data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 

Último (20)

(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 

Toronto Pearson Airport - Terminal Expansion Project Presentation

  • 1. Toronto Pearson Airport Terminal Expansion Project Presented by: Ahmed Mahmoud
  • 2. Toronto Pearson Airport - Terminal Expansion Project Topics  Introduction  Procurement Strategy  Change and Conflict Management  Recommendations & Conclusion
  • 4. Toronto Pearson Airport - Terminal Expansion Project Introduction GTAA needs to address the following challenges: 1. Rapid increase in passenger volumes and cargo movement; 2. Overcrowding; and 3. Overall efficiency of the airport
  • 5. Toronto Pearson Airport - Terminal Expansion Project Introduction Best approach to solving these challenges: A TERMINAL EXPANSION PROJECT!
  • 6. Toronto Pearson Airport - Terminal Expansion Project Introduction Aviation Activity & Forecast Actual Forecast Year 1990 1995 2000 2005 2010 2015 2020 2025 2030 Passengers 22 22.4 28.9 29.9 36 42.9 50.3 58.1 66 In 2010, approximately 36 million passengers passed through Toronto Pearson Forecast of 58 million passengers by 2025
  • 7. Toronto Pearson Airport - Terminal Expansion Project Introduction Terminal Expansion Project Components  Terminal 1 Expansion of 400,000m²;  Three piers G, H & I to be built: Pier G will provide 18 gates; Pier H will provide 31 gates and Pier I will provide 14 gates;  New pedestrian tunnel connection to GO train platform;  New parking facility will provide 4,000 parking spaces;  New pedestrian tunnel connection between new parking facility and Terminal; and  New baggage claim areas.
  • 8. Toronto Pearson Airport - Terminal Expansion Project Introduction
  • 10. Toronto Pearson Airport - Terminal Expansion Project Procurement Strategy Project delivery method The recommended project delivery method is Construction Management at Fee Why Construction Management  The effective use of available funds  Enhanced control of the scope of the work  Optimum project scheduling options  flexibility in procurement options  Strategies to avoid delays, changes and claims  Assist in Design Consultant selection  Enhanced design and construction quality
  • 11. Toronto Pearson Airport - Terminal Expansion Project Procurement Strategy Project delivery method As a best practice major airport owners selected construction management project delivery over other methods, for example the following International Airports:  Toronto Pearson  London Heathrow  Seattle-Tacoma  Philadelphia  San Francisco  Los Angeles  Cairo  Jeddah  Dubai  Abu Dhabi  Muscat  Doha
  • 12. Toronto Pearson Airport - Terminal Expansion Project Procurement Strategy Procurement Model The recommended procurement model is the Traditional Model (Design-Bid-Build) Why traditional procurement model  This model is widely applicable, well understood, and clearly defined roles for the parties involved.  This model is the most common approach for public owners having to comply with regional, provincial or federal procurement statutes.  The owner has a significant amount of control over the end product.
  • 13. Toronto Pearson Airport - Terminal Expansion Project Procurement Strategy Scheduling Approach The recommended scheduling approach is the Sequential Approach Sequential versus Fast-Track  In sequential construction, construction does not begin until design is complete.  In Fast-Track construction, design and construction activities overlap, with the goal of reducing the overall time required to complete a project.  Phased construction also introduces more complexity into the design process and increases the potential for costly design errors.  project estimated duration is not required to be fast-tracked.  it’s required to be simple with minimum risk allocation.
  • 14. Toronto Pearson Airport - Terminal Expansion Project Procurement Strategy Forms of Agreement Legal relations Owner + Construction Manager = Management Services Contract; Owner + Design Consultant = Design Services Contract; Owner + General Contractor = Construction Services Contract. Owner Issuing Organization Construction Manager CCDC 5A Canadian Construction Documents Committee Design Consultant RAIC Document 6 Royal Architectural Institute of Canada General Contactor CCDC 2 Canadian Construction Documents Committee CCDC 5A 2010 Construction Management Contract – For Services RAIC Document 6 2006 Canadian Standard Form of Contract for Architectural Services CCDC 2 2008 Stipulated Price Contract
  • 15. Toronto Pearson Airport - Terminal Expansion Project Procurement Strategy Project Organization
  • 16. Toronto Pearson Airport - Terminal Expansion Project Procurement Strategy Procurement Strategy Benefits Using hybrid procurement strategy of construction management as a project delivery method with traditional procurement model and sequential construction approach will maximize the advantage of each method and minimize the concerns of each one if used separately; which will lead to minimum risk allocation and best value for construction dollar as briefly listed as follows:  Development teams selection based upon qualifications.  Owner can select sub-contractors/sub-consultants.  Can be fast-tracked; if requested by the owner.  CM responsible to deliver the project on budget and on schedule.  Defined roles/responsibilities for the development teams.  Initially presents the lowest potential cost for the project.  Design change claims during construction are the minimum compared to other strategies.
  • 17. Toronto Pearson Airport - Terminal Expansion Project Procurement Strategy Procurement Strategy Benefits Why P3 is not recommended There has been increasing discussion recently of P3 financing for airport projects as a response to the tightening of availability of financial resources for airports.  P3 is not recommend for the terminal expansion project because it has conflict of interest between the private investor and the public entity serving the taxpayers interest;  plus the partial risk and control to an outside entity for such a strategic facility;  It is suitable for services & maintenance facilities where owner control is non‐critical, through a limited and controlled scope.
  • 19. Toronto Pearson Airport - Terminal Expansion Project Recommendations  Effectively communicate to the various development project team members, It is important that all parties understand and commit to the owner’s expectations.  Ensure that the terms and conditions of the various contracts reflect the goals, objectives, issues, and expectations for the project owner;  Consider legal assistance experienced in construction matters for crafting the contract language;  Commit to the appropriate level of owner involvement;  Assess potential risks and plan how to manage the overall project via a professional construction management consultant.  Consider using alternate dispute resolution (ADR) approaches such as, dispute review boards, or similar alternatives.  Finally, Define how such disputes will be handled so that disruption and cost/schedule impact are minimized.
  • 20. Toronto Pearson Airport - Terminal Expansion Project Conclusion No procurement strategy is faultless. But, choosing the system that best works for this specific project and actively ensuring that it is properly implemented, can mean the difference between the success and failure of your project. If the terminal expansion project is undertaken it will address the demand and be designed to provide a better flow of passengers, baggage and new commercial retail offerings all designed to enhance the customer travel and service experience and solidify Toronto Pearson as a truly global hub, attracting passengers from around the globe.

Notas del editor

  1. 1