SlideShare una empresa de Scribd logo
1 de 79
POWER QUALITY
VOLTAGE SAG
• A voltage magnitude event with a
magnitude between 10% and 90% of the
nominal RMS voltage and duration
between 0.5 cycles and one minute. [ieee
std. 1159].
100 200 400300 500
20
40
20
60
80
100
Voltagemagnitude(%)
Time (ms)
Voltage Sag
Voltaje sag
duration
Voltage sag
magnitude
CLASSIFICATION OF VOLTAGE SAG
MULTI PHASE SAGS AND SINGLE PHASE
SAGS
• SINGLE PHASE SAGS
• The most common voltage sags, over 70%, are single phase events which are typically
due to a phase to ground fault occurring somewhere on the system. This phase to
ground fault appears as a single phase voltage sag on other feeders from the same
substation. Typical causes are lightning strikes, tree branches, animal contact etc. It is
not uncommon to see single phase voltage sags to 30% of nominal voltage or even
lower in industrial plants.
• PHASE TO PHASE SAGS
• 2 phase, phase to phase sags may be caused by tree branches, adverse weather,
animals or vehicle collision with utility poles. The two phase voltage sag will typically
appear on other feeders from the same substation.
• 3 PHASE SAGS
• Symmetrical 3 phase sags account for less than 20% of all sag events and are caused
either by switching or tripping of a 3 phase circuit breaker, switch or recloser which will
create a 3 phase voltage sag on other lines fed from the same substation.
• 3 phase sags will also be caused by starting large motors but this type of event typically
causes voltage sags to approximately 80% of nominal voltage and are usually confined
to an industrial plant or its immediate neighbours
WHERE DO VOLTAGE SAGS OCCUR?
1.UTILITY SYSTEMS
• Voltage sags can occur on utility systems
both at distribution voltages and
transmission voltages. voltage sags
which occur at higher voltages will
normally spread through a utility system
and will be transmitted to lower voltage
systems via transformers
WHERE DO VOLTAGE SAGS OCCUR?
2. INSIDE INDUSTRIAL PLANTS
• Voltage sags can be created within an industrial complex without any influence from the
utility system. These sags are typically caused by starting large motors or by electrical
faults inside the facility.
CAUSES OF VOLTAGE SAGS
UTILITY SYSTEMS
• OPERATION OF RECLOSERS AND CIRCUIT BREAKERS
• If for any reason a sub-station circuit breaker or a recloser is tripped, then the line which
it is feeding will be temporarily disconnected. All other feeder lines from the same
substation system will see this disconnection event as a voltage sag which will spread to
consumers on these other lines (see fig). The depth of the voltage sag at the consumer’s
site will vary depending on the supply line voltage and the distance from the fault.
• EQUIPMENT FAILURE
• If electrical equipment fails due to overloading, cable faults etc, protective equipment will
operate at the sub-station and voltage sags will be seen on other feeder lines across the
utility system
• BAD WEATHER
• Thunderstorms and lightning strikes cause a significant number of voltage sags. If lightning
strikes a power line and continues to ground, this creates a line to ground fault. The line to
ground fault in turn creates a voltage sag and this reduced voltage can be seen over a wide
area. Note that the lightning strike to ground causes voltage sags on all other lines. Circuit
breakers and Reclosers operate more frequently in poor weather conditions.
• High winds can blow tree branches into power lines. As the tree branch strikes the line, a
line to ground fault occurs which creates a voltage sag. If the line protection system
does not operate immediately, a series of sags will occur if the branch repeatedly
touches the power line. Broken branches landing on power lines cause phase to phase
and phase to ground faults
• Snow and ice build up on power line insulators can cause flash-over, either phase to
ground or phase to phase. Similarly snow or ice falling from one line can cause it to
rebound and strike another line. These events cause voltage sags to spread through
other feeders on the system
• POLLUTION
• Salt spray build up on power line insulators over time in coastal areas can cause flash
over especially in stormy weather. Dust in arid inland areas can cause similar problems.
As circuit protector devices operate, voltage sags appear on other feeders
• VEHICLE PROBLEMS
• Utility power lines frequently run alongside public roads. Vehicles occasionally collide
with utility poles causing lines to touch, protective devices trip and voltage sags occur.
• ANIMALS & BIRDS
• Animals particularly squirrels, snakes occasionally find there way onto power lines or
transformers and can cause a short circuit either phase to phase or phase to ground.
large birds, geese and swans, fly into power lines and cause similar faults. while the
creature rarely survives, the protective circuit breaker operates and a voltage sag is
created on other feeders
• CONSTRUCTION ACTIVITY
• Even when all power lines are underground, digging foundations for new building
construction can result in damage to underground power lines and create voltage sags
• TRANSFER OF LOADS FROM ONE POWER SOURCE TO ANOTHER
• Most facilities contain emergency generators to maintain power to critical loads in case
of an emergency. Sudden application and rejection of loads to a generator could create
significant voltage sags or swells
• During power transfer from the utility to the generator, frequency deviations occur along
with voltage changes. The generator frequency can fluctuate as much as ±5 Hz for a
brief duration during this time. It is once again important to ensure that sensitive loads
can perform satisfactorily within this frequency tolerance for the duration of the
disturbance
• INDUSTRIAL PLANTS
• Voltage sags can be caused within an industrial facility or a group of facilities by the
starting of large electric motors either individually or in groups. The large current inrush
on starting can cause voltage sags in the local or adjacent areas even if the utility line
voltage remains at a constant nominal value
• INDUCTION MOTORS
• Draw starting currents ranging between 600 and 800% of their nominal full load currents.
The current starts at the high value and tapers off to the normal running current in about
2 to 8 sec, based on the motor design and load inertia. Depending on the instant at
which the voltage is applied to the motor, the current can be highly asymmetrical
• ARC FURNACES
• Arc furnaces operate by imposing a short circuit in a batch of metal and then drawing an
arc, which produces temperatures in excess of 10,000°c, which melt the metal batch.
Arc furnaces employ large inductors to stabilize the current due to the arc. Thousands of
amperes are drawn during the initial few seconds of the process.
• Once the arc becomes stable, the current draw becomes more uniform. Due to the
nature of the current drawn by the arc furnace, which is extremely nonlinear, large
harmonic currents are also produced. Severe voltage sags are common in power lines
that supply large arc furnaces.
• furnaces are operated in conjunction with large capacitor banks and harmonic filters to
improve the power factor and also to filter the harmonic frequency currents so they do
not unduly affect other power users sharing the same power lines
• It is not uncommon to see arc furnaces supplied from dedicated utility power lines try to
minimize their impact on other power users. The presence of large capacitance in an
electrical system can result in voltage rise due to the leading reactive power demands of
the capacitors, unless they are adequately canceled by the lagging reactive power
required by the loads. This is why capacitor banks, whether for power factor correction
or harmonic current filtration, are switched on when the furnace is brought on line and
switched off when the arc furnace is off line.
CHARACTERISTICS OF VOLTAGE SAG
• Magnitude of the sag
• Duration of the sag
• Balanced or unbalanced
• Phase-angle jump
• Missing voltage
• Point at which sag initiated ..
Estimate the voltage sag magnitude
• The magnitude of voltage sag determined from RMS voltage.
• The magnitude of the sag is considered as the residual voltage or remaining voltage during
the event
• RMS value during the sag is not completely constant and that the voltage does not
immediately recover after the fault.
• There are various ways of obtaining the sag magnitude from the RMS voltages.
• Most power quality monitors take the lowest value obtained during the event. As sags
normally have a constant RMS value during the deep part of the sag, using the lowest value
is an acceptable approximation
• In the case of a three phase system,
• Voltage sag can also be characterized by the minimum RMS -voltage during the sag if
the sag is symmetrical i.e. equally deep in all three phases
• If the sag is unsymmetrical, i.e. the sag is not equally deep in all three phases, the
phase with the lowest remaining voltage is used to characterize the sag
• The magnitude of voltage sags at a certain point in the system depends
1. The type and the resistance of the fault
2. The distance to the fault
3. The system configuration
The calculation of the sag magnitude for a fault
somewhere within a radial distribution system
• ZS is the source impedance at the PCC
and ZF is the impedance between the
PCC and the fault
• The voltage sag at the PCC equals the
voltage at the equipment terminals
• Assume that the pre-event voltage is
exactly 1 pu, thus E= 1.
• N is the number of samples per cycle
• Vi is the sampled voltage
• K is the instant at which RMS voltage is
estimated
• RMS value is calculated from previous
samples of voltage- post estimation
• One cycle window algorithm: RMS values
are estimated with one cycle of
instantaneous values
• Half cycle window algorithm: choose
instantaneous values over a half cycle
• More sensitive and faster response than
other
SAG DURATION
• The duration of voltage sag is mainly determined by the fault–clearing time.
• The actual duration of a sag is normally longer than the fault-clearing time.
• The duration of a voltage sag is the amount of time during which the voltage magnitude
is below threshold is typically chosen as 90% of the nominal voltage magnitude
• For three phase system, consider the three RMS values to find the duration
• The voltage sag starts when at least one of the RMS voltages drops below the sag-
starting threshold. The sag ends when all three voltages have recovered above the sag-
ending threshold
• The commonly used definition of sag duration is the number of cycles during which the
RMS voltage is below a given threshold.
• This threshold will be somewhat different for each monitor. But typical values are around
90% of the nominal voltage.
• A power quality monitor will typically calculate the RMS value once every cycle
• Post-fault sag will affect the sag duration.
• When the fault is cleared, the voltage does not recover immediately. This is mainly due
to the reenergizing and reacceleration of induction motor load
• This post-fault sag can last several seconds, much longer than the actual sag
• Magnitude-duration plot is a common tool used to show the quality of supply at a certain
location or the average quality of supply of a number of locations as the fault clearing
time depends on the type of transmission distribution system
• Faults in transmission systems are cleared faster than faults in distribution systems. In
transmission systems, the critical fault-clearing time is rather small
• Fast protection and fast circuit breakers are essential
• Distance protection or differential protection, both of which allow for fast clearing of the
fault
• The protection schemes used should have the ability to clear a fault within one half-cycle
MONITORING AND
MITIGATION TECHNIQUES
INTRODUCTION
• Voltage sags are most costly of all power quality disturbances.
• Lead to disruption of manufacturing processes due to equipment being
unable to operate correctly at the reduced voltage levels.
• Industrial equipment such as variable speed drives and some control
systems are particularly sensitive to voltage sags.
• In many manufacturing processes, loss of only a few vital pieces of
equipment may lead to a full shut down of production leading to
significant financial losses.
• For some processes which are thermally sensitive a significant loss of
material as well as the time taken to clean up and restart the process
must also be considered.
1.Ferroresonant transformers
• FERRORESONANT transformers are designed to achieve
regulation with non-linear operation. They provide line
regulation, reduce harmonics, and are current limiting.
• Also known as Constant Voltage Transformers(CVT)
• Operates in the saturation region of the transformer B-H curve
REGION OF OPERATION
• A ferroresonant transformer
consists of a core, a primary
winding, two secondary windings
(one for the load and one for the
capacitor) and a magnetic shunt
that separates the primary and
secondary windings
• The magnetic shunt provides a path for the imbalanced flux of the primary
and secondary by allowing a portion of the primary flux to return to the
primary winding without coupling the secondary. At the same time, it
allows the secondary flux to return to the secondary winding without
coupling the primary.
• OPERATION:
• When a voltage is applied to the primary winding the secondary voltage
increases as the primary voltage increases. As the primary voltage
increases the secondary voltage continues to increase up to a point of
discontinuity, or secondary resonance, where an abrupt increase, about
20 %, in secondary voltage occurs. The resonance effect immediately
increases the secondary flux density and causes saturation of that portion
of the core. This partial core saturation is the key to the magnetic design
of the ferroresonant transformer.
• The voltage induced in the capacitor winding by the primary flux causes a
capacitive current to flow. The flux due this current is in phase with the
primary flux. This flux addition occurs in the secondary portion of the
core. The increased flux saturates the portion of the core on the
secondary winding only. The primary portion of the core is operating
below saturation or below the “knee” of the magnetization curve.
• FERRORESONANT TRANSFORMERS are inherently self-protected
against short circuits, and are able to supply large surge currents if
required because of the large amount of energy stored in the secondary
circuit.
• Ferroresonant transformers are simple and relatively maintenance free
devices which can be very effective for small loads.
• Ferroresonant transformers are available in sizes up to around 25 KVA
• Voltage sags down to 30 % retained voltage can be mitigated through the
use of ferroresonant transformers.
• Typically ferroresonant transformer regulators can maintain secondary
voltage to within ±0.5% for changes in the primary voltages of ±20%
• The disadvantages of a ferroresonant transformer are:
• Frequency sensitive.
• Temperature sensitive.
• External magnetic field may require shielding for sensitive component.
• Ferroresonant transformers are generally not suitable for loads with high
inrush currents such as direct-on-line motors
STATIC TRANSFER SWITCH
• For facilities with a dual supply, one possible method of voltage sag
mitigation is through the use of a automatic static transfer switch.
• Upon detection of a voltage sag, these devices can transfer the load from
the normal supply feeder to the alternative supply feeder within half a
cycle.
• Conventional transfer switches will switch from the primary supply to a
backup supply in seconds.
• Fast transfer switches that use vacuum breaker technology are available
that can transfer in about 2 electrical cycles. This can be fast enough to
protect many sensitive loads.
• Static switches use power electronic switches to accomplish the transfer
within about a quarter of an electrical cycle
VOLTAGE REGULATOR
VOLTAGE REGULATOR
• Voltage regulators are devices that can maintain a constant voltage
(within tolerance) for voltage changes of predetermined limits above and
below the nominal value.
• A switching voltage regulator maintains constant output voltage by
switching the taps of an autotransformer in response to changes in the
system voltage
• The electronic switch responds to a signal from the voltage-sensing
circuitry and switches to the tap connection necessary to maintain the
output voltage constant.
• The switching is typically accomplished within half of a cycle, which is
within the ride-through capability of most sensitive devices.
UNINTERRUPTIBLE POWER SUPPLIES (UPS)
• UPS mitigate voltage sags by supplying the load using stored energy.
• Upon detection of a voltage sag, the load is transferred from the mains
supply to the ups. Obviously, the capacity of load that can be supplied is
directly proportional to the amount of energy storage available.
• Ups systems have the advantage that they can mitigate all voltage sags
including outages for significant periods of time (depending on the size of
the ups).
• 3 CONFIGURATIONS
• ONLINE UPS
• OFFLINE/STANDBY UPS
• HYBRID UPS
ONLINE UPS
• The load is always fed through the UPS. The incoming ac power is
rectified into dc power, which charges a bank of batteries. This dc power
is then inverted back into ac power, to feed the load.
• If the incoming ac power fails, the inverter is fed from the batteries and
continues to supply the load.
• However, the on-line operation increases the losses and may be
unnecessary for protection of many loads.
OFFLINE/STANDBY UPS
• A standby power supply is sometimes termed off-line UPS since the
normal line power is used to power the equipment until a disturbance is
detected and a switch transfers the load to the battery backed inverter.
The transfer time from the normal source to the battery-backed inverter is
important.
• 8 ms is the lower limit on interruption through for power-conscious
manufacturers. Therefore a transfer time of 4 ms would ensure continuity
of operation for the critical load.
• A standby power supply does not typically provide any transient
protection or voltage regulation as does an on-line ups. This is the most
common configuration for commodity UPS units available at retail stores
for protection of small computer loads.
• UPS specifications include kilo-voltampere capacity, dynamic and static
voltage regulation, harmonic distortion of the input current and output
voltage, surge protection, and noise attenuation. The specifications
should indicate, or the supplier should furnish, the test conditions under
which the specifications are valid.
HYBRID UPS
• Similar in design to the standby UPS, the hybrid UPS utilizes a voltage
regulator on the UPS output to provide regulation to the load and
momentary ride-through when the transfer from normal to UPS supply is
made
FLY WHEEL AND MOTOR- GENERATOR SETS
• Flywheel systems use the energy stored in the inertia of a rotating
flywheel to mitigate voltage sags.
• A flywheel is coupled in series with a motor and a generator which in turn
is connected in series with the load.
• The flywheel is accelerated to a very high speed and when a voltage sag
occurs, the rotational energy of the decelerating flywheel is utilised to
supply the load.
• Flywheel storage systems are effective for mitigation of all voltage sags
including interruptions and can supply the load for a significant period of
time (up to several seconds depending on the size of the flywheel).
• Flywheels have maintenance and reliability advantages over other energy
storage systems such as batteries. However, if large energy storage
capacities are required, flywheels must be large and are heavy. The
configuration has high losses during normal operation.
• In this configuration, the motor which drives the flywheel is connected
through a variable speed drive. This connection arrangement results in
better starting characteristics for the flywheel and efficiency gains for the
motor.
• Connection of the ac generator to a voltage source converter increases
the amount of energy that can be extracted from the flywheel due to the
fact that the converter is able to produce a constant dc voltage, which
may then be used directly or converted back to ac voltage, over a wide
speed range.
SAG PROOFING TRANSFORMERS
• Known as voltage sag compensators
• A multi-winding transformer connected in series with the load
• These devices use static switches to change the transformer
turns ratio to compensate for the voltage sag
• Sag proofing transformers are effective for voltage sags to
approximately 40 % retained voltage
• ADVANTAGE:
• Maintenance free and do not have the problems associated
with energy storage components
• DISADVANTAGE:
• Sag proofing transformers are only available for relatively small
loads of up to approximately 5 kVA.
• With the transformer connected in series, the system also adds
to losses and any failure of the transformer will lead to an
immediate loss of supply.
UTILITY EFFORTS IN MITIGATION OF VOLTAGE
SAGS
• REDUCE THE NUMBER OF FAULTS
• Limiting the number of faults is an effective way not only to reduce the
number of faults but also to reduce the frequencies of short and long term
interruptions
FAULT PREVENTIVE ACTION includes
• Tree trimming policies
• Addition of lightning arresters
• Proper insulators
• Addition of animal guards
• Considerable reduction of faults can be achieved by replacing
overhead lines by underground cables which are less affected
by bad weather
• REDUCE THE FAULT CLEARING TIME
• The modern static circuit breakers available are able to clear
the fault within a half cycle at power frequencies ensuring that
no voltage sag can last longer
• Redesign existing systems to achieve faster fault clearing time
• SYSTEM DESIGN AND CONFIGURATION
• By proper changes in the design and configuration we can
achieve reduction in voltage sag and other problems
INTERRUPTIONS
• SHORT INTERRUPTIONS
• LONG INTERRUPTIONS
SHORT INTERRUPTIONS
• Total interruption of electrical supply for duration from few
milliseconds to one or two seconds
• Causes:
• Opening and reclosing of protective device to decommission
the faulty part
• Insulation failure, insulator flashover, lightning
LONG INTERRUPTIONS
• Total interruption of electrical power supply for a duration greater
than one or two seconds
• Causes:
• Equipment failure in power system network
• Storms and objects(trees, vehicles etc)
• Striking lines, poles
• Fire
• Bad coordination of protective device
MOMENTARY POWER INTERRUPTIONS
• Lasts no longer than few seconds
• Causes:
• Lightning strikes
• Fallen branches
• Animals coming into contact with power lines
• Transfer of load from one source to another
• Advanced electronic devices are more sensitive to
disturbances
• How to minimize momentary interruptions
• Taller trees should be planted at a minimum distance of
30feets away from power lines
• Medium sized trees should be planted atleast 15 feet away
from power lines
• Care should be taken if small sized trees are planted near the
power lines
• Vulnerable equipments are
• Digital clocks
• VCR
• Microwave ovens
• Stereos, TV
• Computers
POWER OUTAGES
Total interruption of electrical supply
Utilities have installed protection devices that briefly interrupts power to
allow time for a disturbance to dissipate
If lightning strikes the power line, large voltage is induced into the power
lines. The protection equipment momentarily interrupts power, allowing
time for the surge to dissipate
• Types of power outages:
• A transient fault is a momentary loss of power typically caused
by a temporary fault on a power line. Power is automatically
restored once the fault is cleared
• A blackout refers to the total loss of power to an area and is
the most severs form of power outage that can occur. It is
difficult to recover from it quickly
CAUSES:
• Ice storms, lightning, wind, utility equipment failure
VULNERABLE EQUIPMENT:
• All electrical equipments
EFFECTS:
Complete disruption of operation
Solutions: Transient voltage surge suppression, UPS

Más contenido relacionado

La actualidad más candente

Basic types of facts controllers
Basic types of facts controllersBasic types of facts controllers
Basic types of facts controllersAyyarao T S L V
 
Introduction to reactive power control in electrical power
Introduction to reactive power control in electrical powerIntroduction to reactive power control in electrical power
Introduction to reactive power control in electrical powerDr.Raja R
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformerssiddharam kantoli
 
Voltage sag and it’s mitigation
Voltage sag and it’s mitigationVoltage sag and it’s mitigation
Voltage sag and it’s mitigationMayur Dhande
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION moiz89
 
Voltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSVoltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSKarthik Bharadwaj
 
Power Quality and Monitoring
Power Quality and MonitoringPower Quality and Monitoring
Power Quality and Monitoringash08031996
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Deviceskhemraj298
 
Firing angle control
Firing angle controlFiring angle control
Firing angle controljawaharramaya
 
Power Quality Measurement Devices & Monotoring
Power Quality Measurement Devices & MonotoringPower Quality Measurement Devices & Monotoring
Power Quality Measurement Devices & MonotoringParth Patel
 
Representation of short & medium transmission lines
Representation of short & medium transmission linesRepresentation of short & medium transmission lines
Representation of short & medium transmission linesvishalgohel12195
 
Grid integration issues and solutions
Grid integration issues and solutionsGrid integration issues and solutions
Grid integration issues and solutionsSwathi Venugopal
 

La actualidad más candente (20)

Dynamic voltage restorer (dvr)2
Dynamic voltage restorer (dvr)2Dynamic voltage restorer (dvr)2
Dynamic voltage restorer (dvr)2
 
Tcsc ppt
Tcsc pptTcsc ppt
Tcsc ppt
 
Basic types of facts controllers
Basic types of facts controllersBasic types of facts controllers
Basic types of facts controllers
 
EXCITATION SYSTEMS
EXCITATION SYSTEMSEXCITATION SYSTEMS
EXCITATION SYSTEMS
 
Introduction to reactive power control in electrical power
Introduction to reactive power control in electrical powerIntroduction to reactive power control in electrical power
Introduction to reactive power control in electrical power
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
MTDC SYSTEMS
MTDC SYSTEMSMTDC SYSTEMS
MTDC SYSTEMS
 
Voltage sag and it’s mitigation
Voltage sag and it’s mitigationVoltage sag and it’s mitigation
Voltage sag and it’s mitigation
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Power quality
Power qualityPower quality
Power quality
 
Reactive power
Reactive powerReactive power
Reactive power
 
Voltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSVoltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTS
 
Unified power quality conditioner 2
Unified power quality conditioner 2Unified power quality conditioner 2
Unified power quality conditioner 2
 
Power Quality and Monitoring
Power Quality and MonitoringPower Quality and Monitoring
Power Quality and Monitoring
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
 
Firing angle control
Firing angle controlFiring angle control
Firing angle control
 
Power Quality Measurement Devices & Monotoring
Power Quality Measurement Devices & MonotoringPower Quality Measurement Devices & Monotoring
Power Quality Measurement Devices & Monotoring
 
Representation of short & medium transmission lines
Representation of short & medium transmission linesRepresentation of short & medium transmission lines
Representation of short & medium transmission lines
 
Grid integration issues and solutions
Grid integration issues and solutionsGrid integration issues and solutions
Grid integration issues and solutions
 
Power quality
Power qualityPower quality
Power quality
 

Destacado

Power Quality Issues _Literature Survey
Power Quality Issues _Literature SurveyPower Quality Issues _Literature Survey
Power Quality Issues _Literature SurveyKetan Bhavsar
 
Take Advantage Of Future Of Solar Energy
Take Advantage Of Future Of Solar EnergyTake Advantage Of Future Of Solar Energy
Take Advantage Of Future Of Solar EnergyHarpreet Singh Tibb
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesYashwant Chaudhari
 
Power Electronic Converter
Power Electronic ConverterPower Electronic Converter
Power Electronic ConverterAli
 
Semiconductors
SemiconductorsSemiconductors
SemiconductorsMian Usman
 
Wind power plant
Wind power plantWind power plant
Wind power plantshrey1993
 
controlled rectifiers
controlled rectifierscontrolled rectifiers
controlled rectifiersAnkur Mahajan
 
POWER ELECTRONIC DEVICES
POWER ELECTRONIC DEVICESPOWER ELECTRONIC DEVICES
POWER ELECTRONIC DEVICESshazaliza
 

Destacado (10)

Power Quality
Power QualityPower Quality
Power Quality
 
Power Quality Issues _Literature Survey
Power Quality Issues _Literature SurveyPower Quality Issues _Literature Survey
Power Quality Issues _Literature Survey
 
Presentation new
Presentation newPresentation new
Presentation new
 
Take Advantage Of Future Of Solar Energy
Take Advantage Of Future Of Solar EnergyTake Advantage Of Future Of Solar Energy
Take Advantage Of Future Of Solar Energy
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniques
 
Power Electronic Converter
Power Electronic ConverterPower Electronic Converter
Power Electronic Converter
 
Semiconductors
SemiconductorsSemiconductors
Semiconductors
 
Wind power plant
Wind power plantWind power plant
Wind power plant
 
controlled rectifiers
controlled rectifierscontrolled rectifiers
controlled rectifiers
 
POWER ELECTRONIC DEVICES
POWER ELECTRONIC DEVICESPOWER ELECTRONIC DEVICES
POWER ELECTRONIC DEVICES
 

Similar a Voltage sag

Chep 02 Power Frequency Disturbance
Chep 02 Power Frequency DisturbanceChep 02 Power Frequency Disturbance
Chep 02 Power Frequency DisturbancePiyush Tandel
 
4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptx4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptxNoname812799
 
Transcat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 WebinarTranscat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 WebinarTranscat
 
Generator Protection
Generator ProtectionGenerator Protection
Generator ProtectionPriten Vasa
 
Inspection of voltage sags and voltage swells incident in power quality probl...
Inspection of voltage sags and voltage swells incident in power quality probl...Inspection of voltage sags and voltage swells incident in power quality probl...
Inspection of voltage sags and voltage swells incident in power quality probl...IRJET Journal
 
Surge arrester ppt
Surge arrester pptSurge arrester ppt
Surge arrester pptIrinElsa
 
Distribu pQ.pptx
Distribu pQ.pptxDistribu pQ.pptx
Distribu pQ.pptxbhuvana71
 
PROTECTION AGAINST OVER VOLTAGE AND GROUNDING
PROTECTION AGAINST OVER VOLTAGE AND GROUNDINGPROTECTION AGAINST OVER VOLTAGE AND GROUNDING
PROTECTION AGAINST OVER VOLTAGE AND GROUNDINGDr. Rohit Babu
 
PROTECTION AGAINST OVER VOLTAGE AND GROUNDING Part 2
PROTECTION AGAINST OVER VOLTAGE AND GROUNDING Part 2PROTECTION AGAINST OVER VOLTAGE AND GROUNDING Part 2
PROTECTION AGAINST OVER VOLTAGE AND GROUNDING Part 2Dr. Rohit Babu
 
power system 1 unit 5 contains for various faults & circuit breakers
power system 1 unit 5 contains for various faults & circuit breakerspower system 1 unit 5 contains for various faults & circuit breakers
power system 1 unit 5 contains for various faults & circuit breakersmonikavardia
 
Power Quality Variations in Distribution Circuits
Power Quality Variations in Distribution CircuitsPower Quality Variations in Distribution Circuits
Power Quality Variations in Distribution CircuitsRaja Adapa
 
Electrical Basics-VBR
Electrical Basics-VBRElectrical Basics-VBR
Electrical Basics-VBRVijay Raskar
 
Switchgear and protection engineering Lecture 02.pptx
Switchgear and protection engineering Lecture 02.pptxSwitchgear and protection engineering Lecture 02.pptx
Switchgear and protection engineering Lecture 02.pptxLoitaFredy
 
High voltage grounding methods
High voltage grounding methods High voltage grounding methods
High voltage grounding methods Adnan Khan
 
WHY POWER QUALITY AUDIT IS IMPORTANT ???
WHY POWER QUALITY AUDIT IS IMPORTANT ???WHY POWER QUALITY AUDIT IS IMPORTANT ???
WHY POWER QUALITY AUDIT IS IMPORTANT ???chandan sudip
 
SGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptxSGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptxSHIVANICHAUUHAN1
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in briefMuthar Hussain
 

Similar a Voltage sag (20)

Chep 02 Power Frequency Disturbance
Chep 02 Power Frequency DisturbanceChep 02 Power Frequency Disturbance
Chep 02 Power Frequency Disturbance
 
4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptx4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptx
 
Transcat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 WebinarTranscat and Megger: Power Quality 101 Webinar
Transcat and Megger: Power Quality 101 Webinar
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Inspection of voltage sags and voltage swells incident in power quality probl...
Inspection of voltage sags and voltage swells incident in power quality probl...Inspection of voltage sags and voltage swells incident in power quality probl...
Inspection of voltage sags and voltage swells incident in power quality probl...
 
s.pdf
s.pdfs.pdf
s.pdf
 
Surge arrester ppt
Surge arrester pptSurge arrester ppt
Surge arrester ppt
 
Distribu pQ.pptx
Distribu pQ.pptxDistribu pQ.pptx
Distribu pQ.pptx
 
PROTECTION AGAINST OVER VOLTAGE AND GROUNDING
PROTECTION AGAINST OVER VOLTAGE AND GROUNDINGPROTECTION AGAINST OVER VOLTAGE AND GROUNDING
PROTECTION AGAINST OVER VOLTAGE AND GROUNDING
 
PROTECTION AGAINST OVER VOLTAGE AND GROUNDING Part 2
PROTECTION AGAINST OVER VOLTAGE AND GROUNDING Part 2PROTECTION AGAINST OVER VOLTAGE AND GROUNDING Part 2
PROTECTION AGAINST OVER VOLTAGE AND GROUNDING Part 2
 
power system 1 unit 5 contains for various faults & circuit breakers
power system 1 unit 5 contains for various faults & circuit breakerspower system 1 unit 5 contains for various faults & circuit breakers
power system 1 unit 5 contains for various faults & circuit breakers
 
Power Quality Variations in Distribution Circuits
Power Quality Variations in Distribution CircuitsPower Quality Variations in Distribution Circuits
Power Quality Variations in Distribution Circuits
 
Power quality 2
Power quality 2Power quality 2
Power quality 2
 
Electrical Basics-VBR
Electrical Basics-VBRElectrical Basics-VBR
Electrical Basics-VBR
 
Switchgear and protection engineering Lecture 02.pptx
Switchgear and protection engineering Lecture 02.pptxSwitchgear and protection engineering Lecture 02.pptx
Switchgear and protection engineering Lecture 02.pptx
 
High voltage grounding methods
High voltage grounding methods High voltage grounding methods
High voltage grounding methods
 
Ac.generators
Ac.generatorsAc.generators
Ac.generators
 
WHY POWER QUALITY AUDIT IS IMPORTANT ???
WHY POWER QUALITY AUDIT IS IMPORTANT ???WHY POWER QUALITY AUDIT IS IMPORTANT ???
WHY POWER QUALITY AUDIT IS IMPORTANT ???
 
SGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptxSGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptx
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
 

Más de AJAL A J

KEAM KERALA ENTRANCE EXAM
KEAM KERALA ENTRANCE EXAMKEAM KERALA ENTRANCE EXAM
KEAM KERALA ENTRANCE EXAMAJAL A J
 
Paleontology Career
Paleontology  CareerPaleontology  Career
Paleontology CareerAJAL A J
 
CHEMISTRY basic concepts of chemistry
CHEMISTRY  basic concepts of chemistryCHEMISTRY  basic concepts of chemistry
CHEMISTRY basic concepts of chemistryAJAL A J
 
Biogeochemical cycles
Biogeochemical cyclesBiogeochemical cycles
Biogeochemical cyclesAJAL A J
 
ac dc bridges
ac dc bridgesac dc bridges
ac dc bridgesAJAL A J
 
Hays bridge schering bridge wien bridge
Hays bridge  schering bridge  wien bridgeHays bridge  schering bridge  wien bridge
Hays bridge schering bridge wien bridgeAJAL A J
 
App Naming Tip
App Naming TipApp Naming Tip
App Naming Tip AJAL A J
 
flora and fauna of himachal pradesh and kerala
flora and fauna of himachal pradesh and keralaflora and fauna of himachal pradesh and kerala
flora and fauna of himachal pradesh and keralaAJAL A J
 
B.Sc Cardiovascular Technology(CVT)
 B.Sc Cardiovascular Technology(CVT)  B.Sc Cardiovascular Technology(CVT)
B.Sc Cardiovascular Technology(CVT) AJAL A J
 
11 business strategies to make profit
11 business strategies to make profit 11 business strategies to make profit
11 business strategies to make profit AJAL A J
 
PCOS Polycystic Ovary Syndrome
PCOS  Polycystic Ovary SyndromePCOS  Polycystic Ovary Syndrome
PCOS Polycystic Ovary SyndromeAJAL A J
 
Courses and Career Options after Class 12 in Humanities
Courses and Career Options after Class 12 in HumanitiesCourses and Career Options after Class 12 in Humanities
Courses and Career Options after Class 12 in HumanitiesAJAL A J
 
MANAGEMENT Stories
 MANAGEMENT Stories MANAGEMENT Stories
MANAGEMENT StoriesAJAL A J
 
NEET PREPRATION TIPS AND STRATEGY
NEET PREPRATION TIPS AND STRATEGYNEET PREPRATION TIPS AND STRATEGY
NEET PREPRATION TIPS AND STRATEGYAJAL A J
 
REVOLUTIONS IN AGRICULTURE
REVOLUTIONS IN AGRICULTUREREVOLUTIONS IN AGRICULTURE
REVOLUTIONS IN AGRICULTUREAJAL A J
 
NRI QUOTA IN NIT'S
NRI QUOTA IN NIT'S NRI QUOTA IN NIT'S
NRI QUOTA IN NIT'S AJAL A J
 
Subjects to study if you want to work for a charity
Subjects to study if you want to work for a charitySubjects to study if you want to work for a charity
Subjects to study if you want to work for a charityAJAL A J
 
IIT JEE A KERALA PERSPECTIVE
IIT JEE A KERALA PERSPECTIVE IIT JEE A KERALA PERSPECTIVE
IIT JEE A KERALA PERSPECTIVE AJAL A J
 
Clat 2020 exam COMPLETE DETAILS
Clat 2020 exam COMPLETE DETAILSClat 2020 exam COMPLETE DETAILS
Clat 2020 exam COMPLETE DETAILSAJAL A J
 

Más de AJAL A J (20)

KEAM KERALA ENTRANCE EXAM
KEAM KERALA ENTRANCE EXAMKEAM KERALA ENTRANCE EXAM
KEAM KERALA ENTRANCE EXAM
 
Paleontology Career
Paleontology  CareerPaleontology  Career
Paleontology Career
 
CHEMISTRY basic concepts of chemistry
CHEMISTRY  basic concepts of chemistryCHEMISTRY  basic concepts of chemistry
CHEMISTRY basic concepts of chemistry
 
Ecology
EcologyEcology
Ecology
 
Biogeochemical cycles
Biogeochemical cyclesBiogeochemical cycles
Biogeochemical cycles
 
ac dc bridges
ac dc bridgesac dc bridges
ac dc bridges
 
Hays bridge schering bridge wien bridge
Hays bridge  schering bridge  wien bridgeHays bridge  schering bridge  wien bridge
Hays bridge schering bridge wien bridge
 
App Naming Tip
App Naming TipApp Naming Tip
App Naming Tip
 
flora and fauna of himachal pradesh and kerala
flora and fauna of himachal pradesh and keralaflora and fauna of himachal pradesh and kerala
flora and fauna of himachal pradesh and kerala
 
B.Sc Cardiovascular Technology(CVT)
 B.Sc Cardiovascular Technology(CVT)  B.Sc Cardiovascular Technology(CVT)
B.Sc Cardiovascular Technology(CVT)
 
11 business strategies to make profit
11 business strategies to make profit 11 business strategies to make profit
11 business strategies to make profit
 
PCOS Polycystic Ovary Syndrome
PCOS  Polycystic Ovary SyndromePCOS  Polycystic Ovary Syndrome
PCOS Polycystic Ovary Syndrome
 
Courses and Career Options after Class 12 in Humanities
Courses and Career Options after Class 12 in HumanitiesCourses and Career Options after Class 12 in Humanities
Courses and Career Options after Class 12 in Humanities
 
MANAGEMENT Stories
 MANAGEMENT Stories MANAGEMENT Stories
MANAGEMENT Stories
 
NEET PREPRATION TIPS AND STRATEGY
NEET PREPRATION TIPS AND STRATEGYNEET PREPRATION TIPS AND STRATEGY
NEET PREPRATION TIPS AND STRATEGY
 
REVOLUTIONS IN AGRICULTURE
REVOLUTIONS IN AGRICULTUREREVOLUTIONS IN AGRICULTURE
REVOLUTIONS IN AGRICULTURE
 
NRI QUOTA IN NIT'S
NRI QUOTA IN NIT'S NRI QUOTA IN NIT'S
NRI QUOTA IN NIT'S
 
Subjects to study if you want to work for a charity
Subjects to study if you want to work for a charitySubjects to study if you want to work for a charity
Subjects to study if you want to work for a charity
 
IIT JEE A KERALA PERSPECTIVE
IIT JEE A KERALA PERSPECTIVE IIT JEE A KERALA PERSPECTIVE
IIT JEE A KERALA PERSPECTIVE
 
Clat 2020 exam COMPLETE DETAILS
Clat 2020 exam COMPLETE DETAILSClat 2020 exam COMPLETE DETAILS
Clat 2020 exam COMPLETE DETAILS
 

Último

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 

Último (20)

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 

Voltage sag

  • 2. VOLTAGE SAG • A voltage magnitude event with a magnitude between 10% and 90% of the nominal RMS voltage and duration between 0.5 cycles and one minute. [ieee std. 1159]. 100 200 400300 500 20 40 20 60 80 100 Voltagemagnitude(%) Time (ms) Voltage Sag Voltaje sag duration Voltage sag magnitude
  • 4. MULTI PHASE SAGS AND SINGLE PHASE SAGS • SINGLE PHASE SAGS • The most common voltage sags, over 70%, are single phase events which are typically due to a phase to ground fault occurring somewhere on the system. This phase to ground fault appears as a single phase voltage sag on other feeders from the same substation. Typical causes are lightning strikes, tree branches, animal contact etc. It is not uncommon to see single phase voltage sags to 30% of nominal voltage or even lower in industrial plants.
  • 5. • PHASE TO PHASE SAGS • 2 phase, phase to phase sags may be caused by tree branches, adverse weather, animals or vehicle collision with utility poles. The two phase voltage sag will typically appear on other feeders from the same substation.
  • 6. • 3 PHASE SAGS • Symmetrical 3 phase sags account for less than 20% of all sag events and are caused either by switching or tripping of a 3 phase circuit breaker, switch or recloser which will create a 3 phase voltage sag on other lines fed from the same substation. • 3 phase sags will also be caused by starting large motors but this type of event typically causes voltage sags to approximately 80% of nominal voltage and are usually confined to an industrial plant or its immediate neighbours
  • 7. WHERE DO VOLTAGE SAGS OCCUR? 1.UTILITY SYSTEMS • Voltage sags can occur on utility systems both at distribution voltages and transmission voltages. voltage sags which occur at higher voltages will normally spread through a utility system and will be transmitted to lower voltage systems via transformers
  • 8. WHERE DO VOLTAGE SAGS OCCUR? 2. INSIDE INDUSTRIAL PLANTS • Voltage sags can be created within an industrial complex without any influence from the utility system. These sags are typically caused by starting large motors or by electrical faults inside the facility.
  • 9. CAUSES OF VOLTAGE SAGS UTILITY SYSTEMS • OPERATION OF RECLOSERS AND CIRCUIT BREAKERS • If for any reason a sub-station circuit breaker or a recloser is tripped, then the line which it is feeding will be temporarily disconnected. All other feeder lines from the same substation system will see this disconnection event as a voltage sag which will spread to consumers on these other lines (see fig). The depth of the voltage sag at the consumer’s site will vary depending on the supply line voltage and the distance from the fault.
  • 10. • EQUIPMENT FAILURE • If electrical equipment fails due to overloading, cable faults etc, protective equipment will operate at the sub-station and voltage sags will be seen on other feeder lines across the utility system • BAD WEATHER • Thunderstorms and lightning strikes cause a significant number of voltage sags. If lightning strikes a power line and continues to ground, this creates a line to ground fault. The line to ground fault in turn creates a voltage sag and this reduced voltage can be seen over a wide area. Note that the lightning strike to ground causes voltage sags on all other lines. Circuit breakers and Reclosers operate more frequently in poor weather conditions.
  • 11. • High winds can blow tree branches into power lines. As the tree branch strikes the line, a line to ground fault occurs which creates a voltage sag. If the line protection system does not operate immediately, a series of sags will occur if the branch repeatedly touches the power line. Broken branches landing on power lines cause phase to phase and phase to ground faults • Snow and ice build up on power line insulators can cause flash-over, either phase to ground or phase to phase. Similarly snow or ice falling from one line can cause it to rebound and strike another line. These events cause voltage sags to spread through other feeders on the system
  • 12. • POLLUTION • Salt spray build up on power line insulators over time in coastal areas can cause flash over especially in stormy weather. Dust in arid inland areas can cause similar problems. As circuit protector devices operate, voltage sags appear on other feeders • VEHICLE PROBLEMS • Utility power lines frequently run alongside public roads. Vehicles occasionally collide with utility poles causing lines to touch, protective devices trip and voltage sags occur.
  • 13. • ANIMALS & BIRDS • Animals particularly squirrels, snakes occasionally find there way onto power lines or transformers and can cause a short circuit either phase to phase or phase to ground. large birds, geese and swans, fly into power lines and cause similar faults. while the creature rarely survives, the protective circuit breaker operates and a voltage sag is created on other feeders • CONSTRUCTION ACTIVITY • Even when all power lines are underground, digging foundations for new building construction can result in damage to underground power lines and create voltage sags
  • 14. • TRANSFER OF LOADS FROM ONE POWER SOURCE TO ANOTHER • Most facilities contain emergency generators to maintain power to critical loads in case of an emergency. Sudden application and rejection of loads to a generator could create significant voltage sags or swells • During power transfer from the utility to the generator, frequency deviations occur along with voltage changes. The generator frequency can fluctuate as much as ±5 Hz for a brief duration during this time. It is once again important to ensure that sensitive loads can perform satisfactorily within this frequency tolerance for the duration of the disturbance
  • 15. • INDUSTRIAL PLANTS • Voltage sags can be caused within an industrial facility or a group of facilities by the starting of large electric motors either individually or in groups. The large current inrush on starting can cause voltage sags in the local or adjacent areas even if the utility line voltage remains at a constant nominal value
  • 16. • INDUCTION MOTORS • Draw starting currents ranging between 600 and 800% of their nominal full load currents. The current starts at the high value and tapers off to the normal running current in about 2 to 8 sec, based on the motor design and load inertia. Depending on the instant at which the voltage is applied to the motor, the current can be highly asymmetrical
  • 17. • ARC FURNACES • Arc furnaces operate by imposing a short circuit in a batch of metal and then drawing an arc, which produces temperatures in excess of 10,000°c, which melt the metal batch. Arc furnaces employ large inductors to stabilize the current due to the arc. Thousands of amperes are drawn during the initial few seconds of the process.
  • 18.
  • 19. • Once the arc becomes stable, the current draw becomes more uniform. Due to the nature of the current drawn by the arc furnace, which is extremely nonlinear, large harmonic currents are also produced. Severe voltage sags are common in power lines that supply large arc furnaces. • furnaces are operated in conjunction with large capacitor banks and harmonic filters to improve the power factor and also to filter the harmonic frequency currents so they do not unduly affect other power users sharing the same power lines
  • 20. • It is not uncommon to see arc furnaces supplied from dedicated utility power lines try to minimize their impact on other power users. The presence of large capacitance in an electrical system can result in voltage rise due to the leading reactive power demands of the capacitors, unless they are adequately canceled by the lagging reactive power required by the loads. This is why capacitor banks, whether for power factor correction or harmonic current filtration, are switched on when the furnace is brought on line and switched off when the arc furnace is off line.
  • 21. CHARACTERISTICS OF VOLTAGE SAG • Magnitude of the sag • Duration of the sag • Balanced or unbalanced • Phase-angle jump • Missing voltage • Point at which sag initiated ..
  • 22. Estimate the voltage sag magnitude
  • 23. • The magnitude of voltage sag determined from RMS voltage. • The magnitude of the sag is considered as the residual voltage or remaining voltage during the event • RMS value during the sag is not completely constant and that the voltage does not immediately recover after the fault. • There are various ways of obtaining the sag magnitude from the RMS voltages. • Most power quality monitors take the lowest value obtained during the event. As sags normally have a constant RMS value during the deep part of the sag, using the lowest value is an acceptable approximation
  • 24. • In the case of a three phase system, • Voltage sag can also be characterized by the minimum RMS -voltage during the sag if the sag is symmetrical i.e. equally deep in all three phases • If the sag is unsymmetrical, i.e. the sag is not equally deep in all three phases, the phase with the lowest remaining voltage is used to characterize the sag
  • 25. • The magnitude of voltage sags at a certain point in the system depends 1. The type and the resistance of the fault 2. The distance to the fault 3. The system configuration
  • 26. The calculation of the sag magnitude for a fault somewhere within a radial distribution system • ZS is the source impedance at the PCC and ZF is the impedance between the PCC and the fault • The voltage sag at the PCC equals the voltage at the equipment terminals
  • 27. • Assume that the pre-event voltage is exactly 1 pu, thus E= 1.
  • 28. • N is the number of samples per cycle • Vi is the sampled voltage • K is the instant at which RMS voltage is estimated • RMS value is calculated from previous samples of voltage- post estimation • One cycle window algorithm: RMS values are estimated with one cycle of instantaneous values
  • 29. • Half cycle window algorithm: choose instantaneous values over a half cycle • More sensitive and faster response than other
  • 30. SAG DURATION • The duration of voltage sag is mainly determined by the fault–clearing time. • The actual duration of a sag is normally longer than the fault-clearing time. • The duration of a voltage sag is the amount of time during which the voltage magnitude is below threshold is typically chosen as 90% of the nominal voltage magnitude • For three phase system, consider the three RMS values to find the duration • The voltage sag starts when at least one of the RMS voltages drops below the sag- starting threshold. The sag ends when all three voltages have recovered above the sag- ending threshold
  • 31. • The commonly used definition of sag duration is the number of cycles during which the RMS voltage is below a given threshold. • This threshold will be somewhat different for each monitor. But typical values are around 90% of the nominal voltage. • A power quality monitor will typically calculate the RMS value once every cycle
  • 32. • Post-fault sag will affect the sag duration. • When the fault is cleared, the voltage does not recover immediately. This is mainly due to the reenergizing and reacceleration of induction motor load • This post-fault sag can last several seconds, much longer than the actual sag
  • 33. • Magnitude-duration plot is a common tool used to show the quality of supply at a certain location or the average quality of supply of a number of locations as the fault clearing time depends on the type of transmission distribution system • Faults in transmission systems are cleared faster than faults in distribution systems. In transmission systems, the critical fault-clearing time is rather small • Fast protection and fast circuit breakers are essential • Distance protection or differential protection, both of which allow for fast clearing of the fault • The protection schemes used should have the ability to clear a fault within one half-cycle
  • 35. INTRODUCTION • Voltage sags are most costly of all power quality disturbances. • Lead to disruption of manufacturing processes due to equipment being unable to operate correctly at the reduced voltage levels. • Industrial equipment such as variable speed drives and some control systems are particularly sensitive to voltage sags. • In many manufacturing processes, loss of only a few vital pieces of equipment may lead to a full shut down of production leading to significant financial losses. • For some processes which are thermally sensitive a significant loss of material as well as the time taken to clean up and restart the process must also be considered.
  • 36.
  • 37. 1.Ferroresonant transformers • FERRORESONANT transformers are designed to achieve regulation with non-linear operation. They provide line regulation, reduce harmonics, and are current limiting. • Also known as Constant Voltage Transformers(CVT) • Operates in the saturation region of the transformer B-H curve
  • 39. • A ferroresonant transformer consists of a core, a primary winding, two secondary windings (one for the load and one for the capacitor) and a magnetic shunt that separates the primary and secondary windings
  • 40. • The magnetic shunt provides a path for the imbalanced flux of the primary and secondary by allowing a portion of the primary flux to return to the primary winding without coupling the secondary. At the same time, it allows the secondary flux to return to the secondary winding without coupling the primary.
  • 41. • OPERATION: • When a voltage is applied to the primary winding the secondary voltage increases as the primary voltage increases. As the primary voltage increases the secondary voltage continues to increase up to a point of discontinuity, or secondary resonance, where an abrupt increase, about 20 %, in secondary voltage occurs. The resonance effect immediately increases the secondary flux density and causes saturation of that portion of the core. This partial core saturation is the key to the magnetic design of the ferroresonant transformer.
  • 42. • The voltage induced in the capacitor winding by the primary flux causes a capacitive current to flow. The flux due this current is in phase with the primary flux. This flux addition occurs in the secondary portion of the core. The increased flux saturates the portion of the core on the secondary winding only. The primary portion of the core is operating below saturation or below the “knee” of the magnetization curve.
  • 43. • FERRORESONANT TRANSFORMERS are inherently self-protected against short circuits, and are able to supply large surge currents if required because of the large amount of energy stored in the secondary circuit. • Ferroresonant transformers are simple and relatively maintenance free devices which can be very effective for small loads.
  • 44. • Ferroresonant transformers are available in sizes up to around 25 KVA • Voltage sags down to 30 % retained voltage can be mitigated through the use of ferroresonant transformers. • Typically ferroresonant transformer regulators can maintain secondary voltage to within ±0.5% for changes in the primary voltages of ±20%
  • 45. • The disadvantages of a ferroresonant transformer are: • Frequency sensitive. • Temperature sensitive. • External magnetic field may require shielding for sensitive component. • Ferroresonant transformers are generally not suitable for loads with high inrush currents such as direct-on-line motors
  • 46. STATIC TRANSFER SWITCH • For facilities with a dual supply, one possible method of voltage sag mitigation is through the use of a automatic static transfer switch. • Upon detection of a voltage sag, these devices can transfer the load from the normal supply feeder to the alternative supply feeder within half a cycle.
  • 47.
  • 48. • Conventional transfer switches will switch from the primary supply to a backup supply in seconds. • Fast transfer switches that use vacuum breaker technology are available that can transfer in about 2 electrical cycles. This can be fast enough to protect many sensitive loads. • Static switches use power electronic switches to accomplish the transfer within about a quarter of an electrical cycle
  • 50. VOLTAGE REGULATOR • Voltage regulators are devices that can maintain a constant voltage (within tolerance) for voltage changes of predetermined limits above and below the nominal value. • A switching voltage regulator maintains constant output voltage by switching the taps of an autotransformer in response to changes in the system voltage • The electronic switch responds to a signal from the voltage-sensing circuitry and switches to the tap connection necessary to maintain the output voltage constant. • The switching is typically accomplished within half of a cycle, which is within the ride-through capability of most sensitive devices.
  • 51. UNINTERRUPTIBLE POWER SUPPLIES (UPS) • UPS mitigate voltage sags by supplying the load using stored energy. • Upon detection of a voltage sag, the load is transferred from the mains supply to the ups. Obviously, the capacity of load that can be supplied is directly proportional to the amount of energy storage available. • Ups systems have the advantage that they can mitigate all voltage sags including outages for significant periods of time (depending on the size of the ups).
  • 52. • 3 CONFIGURATIONS • ONLINE UPS • OFFLINE/STANDBY UPS • HYBRID UPS
  • 54. • The load is always fed through the UPS. The incoming ac power is rectified into dc power, which charges a bank of batteries. This dc power is then inverted back into ac power, to feed the load. • If the incoming ac power fails, the inverter is fed from the batteries and continues to supply the load. • However, the on-line operation increases the losses and may be unnecessary for protection of many loads.
  • 56. • A standby power supply is sometimes termed off-line UPS since the normal line power is used to power the equipment until a disturbance is detected and a switch transfers the load to the battery backed inverter. The transfer time from the normal source to the battery-backed inverter is important. • 8 ms is the lower limit on interruption through for power-conscious manufacturers. Therefore a transfer time of 4 ms would ensure continuity of operation for the critical load. • A standby power supply does not typically provide any transient protection or voltage regulation as does an on-line ups. This is the most common configuration for commodity UPS units available at retail stores for protection of small computer loads.
  • 57. • UPS specifications include kilo-voltampere capacity, dynamic and static voltage regulation, harmonic distortion of the input current and output voltage, surge protection, and noise attenuation. The specifications should indicate, or the supplier should furnish, the test conditions under which the specifications are valid.
  • 59. • Similar in design to the standby UPS, the hybrid UPS utilizes a voltage regulator on the UPS output to provide regulation to the load and momentary ride-through when the transfer from normal to UPS supply is made
  • 60. FLY WHEEL AND MOTOR- GENERATOR SETS • Flywheel systems use the energy stored in the inertia of a rotating flywheel to mitigate voltage sags. • A flywheel is coupled in series with a motor and a generator which in turn is connected in series with the load. • The flywheel is accelerated to a very high speed and when a voltage sag occurs, the rotational energy of the decelerating flywheel is utilised to supply the load. • Flywheel storage systems are effective for mitigation of all voltage sags including interruptions and can supply the load for a significant period of time (up to several seconds depending on the size of the flywheel).
  • 61.
  • 62. • Flywheels have maintenance and reliability advantages over other energy storage systems such as batteries. However, if large energy storage capacities are required, flywheels must be large and are heavy. The configuration has high losses during normal operation.
  • 63.
  • 64. • In this configuration, the motor which drives the flywheel is connected through a variable speed drive. This connection arrangement results in better starting characteristics for the flywheel and efficiency gains for the motor. • Connection of the ac generator to a voltage source converter increases the amount of energy that can be extracted from the flywheel due to the fact that the converter is able to produce a constant dc voltage, which may then be used directly or converted back to ac voltage, over a wide speed range.
  • 65. SAG PROOFING TRANSFORMERS • Known as voltage sag compensators • A multi-winding transformer connected in series with the load • These devices use static switches to change the transformer turns ratio to compensate for the voltage sag • Sag proofing transformers are effective for voltage sags to approximately 40 % retained voltage
  • 66.
  • 67. • ADVANTAGE: • Maintenance free and do not have the problems associated with energy storage components • DISADVANTAGE: • Sag proofing transformers are only available for relatively small loads of up to approximately 5 kVA. • With the transformer connected in series, the system also adds to losses and any failure of the transformer will lead to an immediate loss of supply.
  • 68. UTILITY EFFORTS IN MITIGATION OF VOLTAGE SAGS • REDUCE THE NUMBER OF FAULTS • Limiting the number of faults is an effective way not only to reduce the number of faults but also to reduce the frequencies of short and long term interruptions
  • 69. FAULT PREVENTIVE ACTION includes • Tree trimming policies • Addition of lightning arresters • Proper insulators • Addition of animal guards • Considerable reduction of faults can be achieved by replacing overhead lines by underground cables which are less affected by bad weather
  • 70. • REDUCE THE FAULT CLEARING TIME • The modern static circuit breakers available are able to clear the fault within a half cycle at power frequencies ensuring that no voltage sag can last longer • Redesign existing systems to achieve faster fault clearing time • SYSTEM DESIGN AND CONFIGURATION • By proper changes in the design and configuration we can achieve reduction in voltage sag and other problems
  • 72. SHORT INTERRUPTIONS • Total interruption of electrical supply for duration from few milliseconds to one or two seconds • Causes: • Opening and reclosing of protective device to decommission the faulty part • Insulation failure, insulator flashover, lightning
  • 73. LONG INTERRUPTIONS • Total interruption of electrical power supply for a duration greater than one or two seconds • Causes: • Equipment failure in power system network • Storms and objects(trees, vehicles etc) • Striking lines, poles • Fire • Bad coordination of protective device
  • 74. MOMENTARY POWER INTERRUPTIONS • Lasts no longer than few seconds • Causes: • Lightning strikes • Fallen branches • Animals coming into contact with power lines • Transfer of load from one source to another • Advanced electronic devices are more sensitive to disturbances
  • 75. • How to minimize momentary interruptions • Taller trees should be planted at a minimum distance of 30feets away from power lines • Medium sized trees should be planted atleast 15 feet away from power lines • Care should be taken if small sized trees are planted near the power lines
  • 76. • Vulnerable equipments are • Digital clocks • VCR • Microwave ovens • Stereos, TV • Computers
  • 77. POWER OUTAGES Total interruption of electrical supply Utilities have installed protection devices that briefly interrupts power to allow time for a disturbance to dissipate If lightning strikes the power line, large voltage is induced into the power lines. The protection equipment momentarily interrupts power, allowing time for the surge to dissipate
  • 78. • Types of power outages: • A transient fault is a momentary loss of power typically caused by a temporary fault on a power line. Power is automatically restored once the fault is cleared • A blackout refers to the total loss of power to an area and is the most severs form of power outage that can occur. It is difficult to recover from it quickly
  • 79. CAUSES: • Ice storms, lightning, wind, utility equipment failure VULNERABLE EQUIPMENT: • All electrical equipments EFFECTS: Complete disruption of operation Solutions: Transient voltage surge suppression, UPS