SlideShare una empresa de Scribd logo
1 de 18
Presented by: Sameer D Amale
Definition:
 Material requirements planning (MRP) is a production planning
and inventory control system used to manage
manufacturing processes.
MRP is the common tool used for tracking dependent demand
items
Determines quantity & timing of dependent demand items.
Determines how much and when to buy, how much to make and
when to make
Objective:
Ensure materials are available for production and products are
available for delivery to customers.
Maintain the lowest possible material and product levels in store
Plan manufacturing activities, delivery schedules and purchasing
activities.
Goal is to accomplish the MPS – Master Production Schedule
Dependent Demand
 The demand for one item is related to the demand for
another item
 Component part to be used in the production of finished
goods.
Independent Demand
 When demand for one item is not related to the demand for
another item
 Independent demand is fairly stable once allowances are
made for seasonal variations.
LLA
B C
D E GF
Independent vs. Dependent Demand
Dependent Demand
Independent Demand
L (0)
L (1)
L (2)
MRP INPUTS
1)The master production schedule:
States which end items to be produced, when they are needed,
and in what quantities
The quantities are determined through customers order ,forecast
& orders from warehouse.
For Eg: Master Production Schedule for end item X
Week Number
ITEM X 1 2 3 4 5 6 7 8
Quantity 400 150
2) Bill of material
 Contains list of all the assemblies , subassemblies ,parts raw
materials needed to produce one unit of a finished Product.
Listing in the bill of materials is hierarchical.
It is represented through a product tree structure.
X (1)
A(1) C(1)
D(2)
B(1)
E(2) F(1)
J(2) K(1)
G(1) H(3) F(1)
J(2)
For Eg : Suppose we want to manufacture 100 units of X then
What quantities of A B C D E F G H J K are required?
Product Structure for item X
100 100 100
100
400
100200200
200
100
200
300
100
3) Inventory Records:
Gives complete and up to date information of on hand
inventory, Gross requirement , Scheduled receipts and planned
order release for the item
It also includes details such as lot sizes ,lead times, safety
stocks.
Basically its job is to keep data about the projected use and
receipts of each item and to determine amount of inventory
available
10
©The McGraw-Hill Companies, Inc., 2004
Firm orders
from known
customers
Forecasts
of demand
from random
customers
Aggregate
product
plan
Bill of
material
file
Engineering
design
changes
Inventory
record file
Inventory
transactions
Master production
Schedule (MPS)
Primary reports
Secondary reports
Planned order schedule for
inventory and production
control
Exception reports
Planning reports
Reports for performance
control
Material
planning
(MRP
computer
program)
Useful Formulae :
Net Requirement
= (Gross Requirement) – (Inventory on hand)
+ ( Inventory on order )
On Hand Inventory over period ( t )
= on hand inventory over period (t-1) + (Scheduled receipt –
Projected requirement )
MRP Lot-Sizing: Using Lot-for-Lot
MRP Lot-Sizing Problem:
Using the EOQ
A(1)
B(2) C(1)
D(1)
E(2)
F(3)E(2)
80 120
50
130
130
200 200
D(1) G(2)
390 195
Eg :Use MRP format to determine the order size for all
item and when each order should be released.
Net Requirements Plan
Net Requirements Plan (cont.)
• Increased customer satisfaction due to
meeting delivery schedules
• Faster response to market changes
• Improved Labour & equipment utilization
• Better inventory planning & scheduling
• Reduced inventory levels without reduced
customer service
MRP Benefits
samer amale   mrp presentation

Más contenido relacionado

La actualidad más candente

Material requirement planning (mrp)
Material requirement planning (mrp)Material requirement planning (mrp)
Material requirement planning (mrp)Viany Adriana
 
MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)Dipesh Pandey
 
Recent Trends in Inventory Control
Recent Trends in Inventory ControlRecent Trends in Inventory Control
Recent Trends in Inventory Controlshaikhsaif
 
Sap mm bom
Sap mm bomSap mm bom
Sap mm bomVannak9
 
material requirement planning Presentation
material requirement planning Presentationmaterial requirement planning Presentation
material requirement planning Presentationhaitham elshennawy
 
Material Requirement planning (factors,inputs,outputs,benifits)
Material Requirement planning  (factors,inputs,outputs,benifits)Material Requirement planning  (factors,inputs,outputs,benifits)
Material Requirement planning (factors,inputs,outputs,benifits)razinbabaria786
 
Production order - Murali krishna nookella
Production order - Murali krishna nookellaProduction order - Murali krishna nookella
Production order - Murali krishna nookellamurali nookella
 
ERP - Production Planning, Manufacturing
ERP - Production Planning, ManufacturingERP - Production Planning, Manufacturing
ERP - Production Planning, ManufacturingAsher Jawad
 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final examMARKSHEET
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planningDinesh Nikam
 
sap b one production module
sap b one production modulesap b one production module
sap b one production moduleFaisal Mk
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)Mostafa Ewees
 
MATERIAL PLANNING PROCESS
MATERIAL PLANNING PROCESSMATERIAL PLANNING PROCESS
MATERIAL PLANNING PROCESSNEHA GAUTAM
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)saleh asgari
 
MRP system series 1 - What is MRP?
MRP system series 1 - What is MRP?MRP system series 1 - What is MRP?
MRP system series 1 - What is MRP?MRPeasy
 
SAP MM PP Material requirement planning
SAP MM PP Material requirement planning SAP MM PP Material requirement planning
SAP MM PP Material requirement planning Lokesh Modem
 

La actualidad más candente (20)

Material requirement planning (mrp)
Material requirement planning (mrp)Material requirement planning (mrp)
Material requirement planning (mrp)
 
Bom in sap
Bom in sapBom in sap
Bom in sap
 
MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)MATERIAL REQUIREMENTS PLANNING (MRP)
MATERIAL REQUIREMENTS PLANNING (MRP)
 
Recent Trends in Inventory Control
Recent Trends in Inventory ControlRecent Trends in Inventory Control
Recent Trends in Inventory Control
 
Sap mm bom
Sap mm bomSap mm bom
Sap mm bom
 
Session 4
Session 4Session 4
Session 4
 
material requirement planning Presentation
material requirement planning Presentationmaterial requirement planning Presentation
material requirement planning Presentation
 
Material Requirement planning (factors,inputs,outputs,benifits)
Material Requirement planning  (factors,inputs,outputs,benifits)Material Requirement planning  (factors,inputs,outputs,benifits)
Material Requirement planning (factors,inputs,outputs,benifits)
 
Production order - Murali krishna nookella
Production order - Murali krishna nookellaProduction order - Murali krishna nookella
Production order - Murali krishna nookella
 
ERP - Production Planning, Manufacturing
ERP - Production Planning, ManufacturingERP - Production Planning, Manufacturing
ERP - Production Planning, Manufacturing
 
Ops 571 final exam
Ops 571 final examOps 571 final exam
Ops 571 final exam
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planning
 
sap b one production module
sap b one production modulesap b one production module
sap b one production module
 
Operations Management Material Requirements Planning (MRP)
Operations ManagementMaterial Requirements Planning (MRP)Operations ManagementMaterial Requirements Planning (MRP)
Operations Management Material Requirements Planning (MRP)
 
MATERIAL PLANNING PROCESS
MATERIAL PLANNING PROCESSMATERIAL PLANNING PROCESS
MATERIAL PLANNING PROCESS
 
Material requirement planning (mrp1)
Material requirement planning (mrp1)Material requirement planning (mrp1)
Material requirement planning (mrp1)
 
MRP system series 1 - What is MRP?
MRP system series 1 - What is MRP?MRP system series 1 - What is MRP?
MRP system series 1 - What is MRP?
 
Mrp
MrpMrp
Mrp
 
SAP MM PP Material requirement planning
SAP MM PP Material requirement planning SAP MM PP Material requirement planning
SAP MM PP Material requirement planning
 
Input to MRP
Input to MRPInput to MRP
Input to MRP
 

Similar a samer amale mrp presentation

Similar a samer amale mrp presentation (20)

Planned order release
Planned order releasePlanned order release
Planned order release
 
Mrp1 prsntation-slides-1226827392037035-8
Mrp1 prsntation-slides-1226827392037035-8Mrp1 prsntation-slides-1226827392037035-8
Mrp1 prsntation-slides-1226827392037035-8
 
Module11. Material requirement plan..pdf
Module11. Material requirement plan..pdfModule11. Material requirement plan..pdf
Module11. Material requirement plan..pdf
 
Mrpmep
MrpmepMrpmep
Mrpmep
 
(Mrp 1) Prsntation Slides
(Mrp 1) Prsntation Slides(Mrp 1) Prsntation Slides
(Mrp 1) Prsntation Slides
 
UNIT VI-3.pptx
UNIT VI-3.pptxUNIT VI-3.pptx
UNIT VI-3.pptx
 
Mrp 2 Manufact Resou Plannin
Mrp 2 Manufact Resou PlanninMrp 2 Manufact Resou Plannin
Mrp 2 Manufact Resou Plannin
 
Material requirement planning
Material requirement planningMaterial requirement planning
Material requirement planning
 
IT for Production & Manufacturing
IT for Production & ManufacturingIT for Production & Manufacturing
IT for Production & Manufacturing
 
MRP
MRPMRP
MRP
 
Scps -materials_requirements_planning
Scps  -materials_requirements_planningScps  -materials_requirements_planning
Scps -materials_requirements_planning
 
5089529.ppt
5089529.ppt5089529.ppt
5089529.ppt
 
Master Scheduling
Master SchedulingMaster Scheduling
Master Scheduling
 
SAP Flexible Planning
SAP Flexible PlanningSAP Flexible Planning
SAP Flexible Planning
 
Horizontal plan description
Horizontal plan descriptionHorizontal plan description
Horizontal plan description
 
Inventory planning & control
Inventory planning & controlInventory planning & control
Inventory planning & control
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource Planning
 
Capacity Planning Product and operation management
Capacity Planning Product and operation managementCapacity Planning Product and operation management
Capacity Planning Product and operation management
 
MASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxMASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptx
 
0201B Aggregate Resource Planning
0201B Aggregate Resource Planning0201B Aggregate Resource Planning
0201B Aggregate Resource Planning
 

Más de Akash Maurya

Marketing information system akash deep maurya
Marketing information system akash deep mauryaMarketing information system akash deep maurya
Marketing information system akash deep mauryaAkash Maurya
 
vinay kumar actuators report
vinay kumar   actuators reportvinay kumar   actuators report
vinay kumar actuators reportAkash Maurya
 
vinay kumar actuators presentation
vinay kumar   actuators presentationvinay kumar   actuators presentation
vinay kumar actuators presentationAkash Maurya
 
ashok mule rapid prototyping questions
ashok mule   rapid prototyping questionsashok mule   rapid prototyping questions
ashok mule rapid prototyping questionsAkash Maurya
 
ashok mule rapid prototyping presentation
ashok mule   rapid prototyping presentationashok mule   rapid prototyping presentation
ashok mule rapid prototyping presentationAkash Maurya
 
prakash agrawal rapid tooling questions
prakash agrawal   rapid tooling questionsprakash agrawal   rapid tooling questions
prakash agrawal rapid tooling questionsAkash Maurya
 
prakash agrawal rapid tooling presentation
prakash agrawal   rapid tooling presentationprakash agrawal   rapid tooling presentation
prakash agrawal rapid tooling presentationAkash Maurya
 
shashank soni sensors presentation
shashank soni   sensors presentationshashank soni   sensors presentation
shashank soni sensors presentationAkash Maurya
 
santosh kumar fuzzy logic presentation
santosh kumar   fuzzy logic presentationsantosh kumar   fuzzy logic presentation
santosh kumar fuzzy logic presentationAkash Maurya
 
mohsin dalvi artificial neural networks questions
mohsin dalvi   artificial neural networks questionsmohsin dalvi   artificial neural networks questions
mohsin dalvi artificial neural networks questionsAkash Maurya
 
mohsin dalvi artificial neural networks presentation
mohsin dalvi   artificial neural networks presentationmohsin dalvi   artificial neural networks presentation
mohsin dalvi artificial neural networks presentationAkash Maurya
 
sameer amale edm presentation
sameer amale   edm presentationsameer amale   edm presentation
sameer amale edm presentationAkash Maurya
 
vivek sharma agv and asrs
vivek sharma   agv and asrsvivek sharma   agv and asrs
vivek sharma agv and asrsAkash Maurya
 
nakul agarwal micromachining presentation
nakul agarwal   micromachining presentationnakul agarwal   micromachining presentation
nakul agarwal micromachining presentationAkash Maurya
 
ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02Akash Maurya
 
shivkumar pathak web based manufacturing presentation
shivkumar pathak   web based manufacturing presentationshivkumar pathak   web based manufacturing presentation
shivkumar pathak web based manufacturing presentationAkash Maurya
 
nishit ambule special purpose machines questions
nishit ambule   special purpose machines questionsnishit ambule   special purpose machines questions
nishit ambule special purpose machines questionsAkash Maurya
 
nishit ambule special purpose machines presentation
nishit ambule   special purpose machines presentationnishit ambule   special purpose machines presentation
nishit ambule special purpose machines presentationAkash Maurya
 
visheshwar oraon robotics presentation
visheshwar oraon   robotics presentationvisheshwar oraon   robotics presentation
visheshwar oraon robotics presentationAkash Maurya
 
nikhil bhagat cmm presentation
nikhil bhagat   cmm presentationnikhil bhagat   cmm presentation
nikhil bhagat cmm presentationAkash Maurya
 

Más de Akash Maurya (20)

Marketing information system akash deep maurya
Marketing information system akash deep mauryaMarketing information system akash deep maurya
Marketing information system akash deep maurya
 
vinay kumar actuators report
vinay kumar   actuators reportvinay kumar   actuators report
vinay kumar actuators report
 
vinay kumar actuators presentation
vinay kumar   actuators presentationvinay kumar   actuators presentation
vinay kumar actuators presentation
 
ashok mule rapid prototyping questions
ashok mule   rapid prototyping questionsashok mule   rapid prototyping questions
ashok mule rapid prototyping questions
 
ashok mule rapid prototyping presentation
ashok mule   rapid prototyping presentationashok mule   rapid prototyping presentation
ashok mule rapid prototyping presentation
 
prakash agrawal rapid tooling questions
prakash agrawal   rapid tooling questionsprakash agrawal   rapid tooling questions
prakash agrawal rapid tooling questions
 
prakash agrawal rapid tooling presentation
prakash agrawal   rapid tooling presentationprakash agrawal   rapid tooling presentation
prakash agrawal rapid tooling presentation
 
shashank soni sensors presentation
shashank soni   sensors presentationshashank soni   sensors presentation
shashank soni sensors presentation
 
santosh kumar fuzzy logic presentation
santosh kumar   fuzzy logic presentationsantosh kumar   fuzzy logic presentation
santosh kumar fuzzy logic presentation
 
mohsin dalvi artificial neural networks questions
mohsin dalvi   artificial neural networks questionsmohsin dalvi   artificial neural networks questions
mohsin dalvi artificial neural networks questions
 
mohsin dalvi artificial neural networks presentation
mohsin dalvi   artificial neural networks presentationmohsin dalvi   artificial neural networks presentation
mohsin dalvi artificial neural networks presentation
 
sameer amale edm presentation
sameer amale   edm presentationsameer amale   edm presentation
sameer amale edm presentation
 
vivek sharma agv and asrs
vivek sharma   agv and asrsvivek sharma   agv and asrs
vivek sharma agv and asrs
 
nakul agarwal micromachining presentation
nakul agarwal   micromachining presentationnakul agarwal   micromachining presentation
nakul agarwal micromachining presentation
 
ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02ravi reverseengineeringitsapplication01 121101044845-phpapp02
ravi reverseengineeringitsapplication01 121101044845-phpapp02
 
shivkumar pathak web based manufacturing presentation
shivkumar pathak   web based manufacturing presentationshivkumar pathak   web based manufacturing presentation
shivkumar pathak web based manufacturing presentation
 
nishit ambule special purpose machines questions
nishit ambule   special purpose machines questionsnishit ambule   special purpose machines questions
nishit ambule special purpose machines questions
 
nishit ambule special purpose machines presentation
nishit ambule   special purpose machines presentationnishit ambule   special purpose machines presentation
nishit ambule special purpose machines presentation
 
visheshwar oraon robotics presentation
visheshwar oraon   robotics presentationvisheshwar oraon   robotics presentation
visheshwar oraon robotics presentation
 
nikhil bhagat cmm presentation
nikhil bhagat   cmm presentationnikhil bhagat   cmm presentation
nikhil bhagat cmm presentation
 

Último

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 

Último (20)

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 

samer amale mrp presentation

  • 2. Definition:  Material requirements planning (MRP) is a production planning and inventory control system used to manage manufacturing processes. MRP is the common tool used for tracking dependent demand items Determines quantity & timing of dependent demand items. Determines how much and when to buy, how much to make and when to make
  • 3. Objective: Ensure materials are available for production and products are available for delivery to customers. Maintain the lowest possible material and product levels in store Plan manufacturing activities, delivery schedules and purchasing activities. Goal is to accomplish the MPS – Master Production Schedule
  • 4. Dependent Demand  The demand for one item is related to the demand for another item  Component part to be used in the production of finished goods. Independent Demand  When demand for one item is not related to the demand for another item  Independent demand is fairly stable once allowances are made for seasonal variations.
  • 5. LLA B C D E GF Independent vs. Dependent Demand Dependent Demand Independent Demand L (0) L (1) L (2)
  • 6. MRP INPUTS 1)The master production schedule: States which end items to be produced, when they are needed, and in what quantities The quantities are determined through customers order ,forecast & orders from warehouse. For Eg: Master Production Schedule for end item X Week Number ITEM X 1 2 3 4 5 6 7 8 Quantity 400 150
  • 7. 2) Bill of material  Contains list of all the assemblies , subassemblies ,parts raw materials needed to produce one unit of a finished Product. Listing in the bill of materials is hierarchical. It is represented through a product tree structure.
  • 8. X (1) A(1) C(1) D(2) B(1) E(2) F(1) J(2) K(1) G(1) H(3) F(1) J(2) For Eg : Suppose we want to manufacture 100 units of X then What quantities of A B C D E F G H J K are required? Product Structure for item X 100 100 100 100 400 100200200 200 100 200 300 100
  • 9. 3) Inventory Records: Gives complete and up to date information of on hand inventory, Gross requirement , Scheduled receipts and planned order release for the item It also includes details such as lot sizes ,lead times, safety stocks. Basically its job is to keep data about the projected use and receipts of each item and to determine amount of inventory available
  • 10. 10 ©The McGraw-Hill Companies, Inc., 2004 Firm orders from known customers Forecasts of demand from random customers Aggregate product plan Bill of material file Engineering design changes Inventory record file Inventory transactions Master production Schedule (MPS) Primary reports Secondary reports Planned order schedule for inventory and production control Exception reports Planning reports Reports for performance control Material planning (MRP computer program)
  • 11. Useful Formulae : Net Requirement = (Gross Requirement) – (Inventory on hand) + ( Inventory on order ) On Hand Inventory over period ( t ) = on hand inventory over period (t-1) + (Scheduled receipt – Projected requirement )
  • 12. MRP Lot-Sizing: Using Lot-for-Lot
  • 14. A(1) B(2) C(1) D(1) E(2) F(3)E(2) 80 120 50 130 130 200 200 D(1) G(2) 390 195 Eg :Use MRP format to determine the order size for all item and when each order should be released.
  • 17. • Increased customer satisfaction due to meeting delivery schedules • Faster response to market changes • Improved Labour & equipment utilization • Better inventory planning & scheduling • Reduced inventory levels without reduced customer service MRP Benefits