The document describes the calculation methodology for the Project Status and Performance index. It defines key terms like Earned Value (EV), Actual Value (AV), and Planned Value (PV) that are used to calculate the Schedule Performance Index (SPI) and Schedule Variance (SV). An example calculation is provided where the SPI is 0.8125, indicating the project is slightly behind schedule. SPI values between 0.8-0.99 are considered yellow status.