The Nationwide Health Information Network (NHIN) Architecture Prototype Project   Health Care Markets – Participants Tasks April 2006 DRAFT
The NHIN Project will run through the end of the year and consists of 4 phases 11/24/06 5/15/06 140 days Fostering NHIN Adoption 12/29/06 12/19/06 9 days Prototype Demonstration Phase 12/18/06 6/20/06 130 days Implementation Phase 6/19/06 4/17/06 40 days Requirements & Design Phase 12/29/06 4/17/06 185 days NHIN Architecture Prototype Project
NHIN Prototype Project Deliverables The ONC Milestones dates are currently as planned but are subject to change 12/29/06 MILESTONE: Prototype Demonstration Complete 12/29/06 MILESTONE: Final deployment and operational plan deliverables to ONC 11/30/06 MILESTONE: Detailed design and architecture deliverable to ONC 10/27/06 MILESTONE: Cost and revenue model deliverable to ONC 9/8/06 MILESTONE: Security model deliverable to ONC 8/25/06 MILESTONE: Draft deployment and operational plan deliverables to ONC 6/19/06 MILESTONE: Communications and interface requirements deliverable to ONC 4/28/06 MILESTONE: Functional and performance requirements to ONC
Requirements  & Design Phase 4/17/06- 6/19/06   The task dates are currently as planned but are subject to change 6/7/06 6/6/06 2 days Provide input into  communications and interface requirements deliverable 6/2/06 5/15/06 15 days Assist in determining assets, communication and interface requirements for organization participation 5/17/06 5/16/06 2 days Supply information regarding security, privacy, data sharing policies and procedures 5/17/06 5/16/06 2 days Supply information to IBM regarding technical environment 5/16/06 5/16/06 1 day Attend Kick off meeting 5/12/06 5/12/06 0 days MILESTONE: Sign agreements/contracts with IBM 5/1/06 5/1/06 1 day Determine communicate to IBM extent to which organization will participate in each use case 5/1/06 5/1/06 1 day Communicate to IBM any gaps between use case requirements and organization's current capabilities 4/28/06 4/21/06 6 days Review use case documents and document gaps between use case requirements and organization's current capabilities 4/25/06 4/21/06 3 days Provide input into functional requirements deliverable  4/20/06 4/19/06 2 days Review use case documents 4/18/06 4/18/06 1 day Provide contact information to IBM for software vendors if applicable for systems involved in implementing the use cases 6/19/06 4/18/06 38 days Champion project throughout organization 4/18/06 4/18/06 1 day Identify and Recruit Resources for Project 4/17/06 4/17/06 1 day Appoint and provide contact information to IBM for organization's liaison/leader for project 4/17/06 4/17/06 0 days MILESTONE: Communicate to IBM commitment to participate in project
Implementation Phase 6/20/06- 12/18/06   The task dates are currently as planned but are subject to change 12/18/06 6/20/06 26 wks Champion project throughout organization 11/23/06 11/17/06 5 days Provide input into detailed design and architecture deliverable 9/5/06 8/30/06 5 days Provide input into security model deliverable 12/18/06 6/20/06 26 wks Assist with testing of prototype 12/18/06 6/20/06 26 wks Attend user training 12/18/06 6/20/06 26 wks Facilitate IBM access to system vendors and organizational resources 12/18/06 6/20/06 26 wks Assist with installation and configuration of hardware, software & interfaces 12/18/06 6/20/06 26 wks Supply information regarding technical environment
Prototype Demonstration Phase 6/20/06- 12/18/06   The dates and details of the demonstration are still to be determined 12/29/06 12/19/06 9 days Champion project throughout organization 12/29/06 12/19/06 9 days Contribute to evaluation of prototype 12/29/06 12/19/06 9 days Participate in demonstration:    - maintain performance and availability of systems,    - assure accuracy of any real data shared,    - assure appropriate consent is secured for any real data shared,    - perform end user functions
Hospital Participant Resources and Tasks for NHIN Project x Assure contracts and data use agreements are signed X X X X X X x Contribute to evaluation of prototype   x x x x x   Assist with testing and demonstration of prototype         x     Assist with installation and configuration of hardware, software & interfaces x x   x x     Supply information to IBM regarding technical and business environment x x x x x x x Provide input into deliverables documents           x x Determine extent to which organization will participate in each use case     x     x x Champion project throughout organization           x x Facilitate IBM access to organizational resources and system vendors x x x x x x x Participate in planning meetings and workshops 12 hrs 32 hrs 70 hrs 100 hrs 130 hrs 108 hrs 40- 80 hrs TASKS Medical Records Security Officer Clinician Application Data Technical Project Liaison CIO or Designee             RESOURCES  
Ambulatory Practice Participant with EHR Resources and Tasks for NHIN Project     x Assure contracts and data use agreements are signed x x   Contribute to evaluation of prototype x x   Assist with testing and demonstration of prototype x x   Assist with or facilitate installation and configuration of hardware, software & interfaces x x   Supply information to IBM regarding technical and business environment x x   Provide input into deliverables documents     x Determine extent to which organization will participate in each use case   x x Champion project throughout organization   x x Facilitate IBM access to organizational resources and system vendors x x x Participate in planning meetings and workshops  80 hrs 40 hrs 20 hrs TASKS Technical (Practice or Vendor) Clinical or Practice Administrator Project Sponsor   RESOURCES  
Ambulatory Practice Participant without EHR Resources and Tasks for NHIN Project   x Assure contracts and data use agreements are signed x   Contribute to evaluation of prototype x   Assist with testing and demonstration of prototype x   Assist with or facilitate installation and configuration of hardware, software & interfaces x   Supply information to IBM regarding technical and business environment x   Provide input into deliverables documents   x Determine extent to which organization will participate in each use case x x Champion project throughout organization x x Facilitate IBM access to organizational resources and system vendors x x Participate in planning meetings and workshops 40 hrs 20 hrs TASKS Clinical or  Practice Administrator Project Sponsor   RESOURCES  

Más contenido relacionado

La actualidad más candente

La actualidad más candente (9)

An explanation on how the CDE competition works.
An explanation on how the CDE competition works.An explanation on how the CDE competition works.
An explanation on how the CDE competition works.
 
Benchmarking Linked Data Introductory Remarks
Benchmarking Linked Data Introductory RemarksBenchmarking Linked Data Introductory Remarks
Benchmarking Linked Data Introductory Remarks
 
A4I Round 5 Overview
A4I Round 5 OverviewA4I Round 5 Overview
A4I Round 5 Overview
 
Knowledge Manager - Fit for the Future
Knowledge Manager - Fit for the Future Knowledge Manager - Fit for the Future
Knowledge Manager - Fit for the Future
 
How to establish an Archtiecture capability
How to establish an Archtiecture capabilityHow to establish an Archtiecture capability
How to establish an Archtiecture capability
 
Justice lab UK
Justice lab UKJustice lab UK
Justice lab UK
 
Supersede overview presentation
Supersede overview presentationSupersede overview presentation
Supersede overview presentation
 
Caltrans Office of Asphalt Pavement Update
Caltrans Office of Asphalt Pavement UpdateCaltrans Office of Asphalt Pavement Update
Caltrans Office of Asphalt Pavement Update
 
Agile and its frameworks
Agile and its frameworks Agile and its frameworks
Agile and its frameworks
 

Similar a Nhin Participant Tasks Slides 042106 V04

Developing of a web-based application to facilitate patient treatment adheren...
Developing of a web-based application to facilitate patient treatment adheren...Developing of a web-based application to facilitate patient treatment adheren...
Developing of a web-based application to facilitate patient treatment adheren...Gunther Eysenbach
 
Developing of a web-based application to facilitate patient treatment adheren...
Developing of a web-based application to facilitate patient treatment adheren...Developing of a web-based application to facilitate patient treatment adheren...
Developing of a web-based application to facilitate patient treatment adheren...Gunther Eysenbach
 
Rick Hathaway V SCTCday cloud 24 feb16 Barcelona
Rick Hathaway V SCTCday cloud 24 feb16 BarcelonaRick Hathaway V SCTCday cloud 24 feb16 Barcelona
Rick Hathaway V SCTCday cloud 24 feb16 BarcelonaAgustin Argelich Casals
 
Public Sector Agility Accelerator
Public Sector Agility AcceleratorPublic Sector Agility Accelerator
Public Sector Agility AcceleratorCraig Smith
 
xAPI State of the State: xAPI for Reals
xAPI State of the State: xAPI for RealsxAPI State of the State: xAPI for Reals
xAPI State of the State: xAPI for RealsMegan Bowe
 
Practical Test Strategy Using Heuristics
Practical Test Strategy Using HeuristicsPractical Test Strategy Using Heuristics
Practical Test Strategy Using HeuristicsTEST Huddle
 
PS2_FinalReport_2011B1A7689G
PS2_FinalReport_2011B1A7689GPS2_FinalReport_2011B1A7689G
PS2_FinalReport_2011B1A7689GTrishu Dey
 
13 0820 Session 1 Management Team
13 0820 Session 1 Management Team13 0820 Session 1 Management Team
13 0820 Session 1 Management TeamCleantechOpen
 
UKRDDS 1st Workshop 20150423 - plan walkthrough
UKRDDS 1st Workshop 20150423 - plan walkthroughUKRDDS 1st Workshop 20150423 - plan walkthrough
UKRDDS 1st Workshop 20150423 - plan walkthroughChristopher Brown
 
CSC - Presentation at Hortonworks Booth - Strata 2014
CSC - Presentation at Hortonworks Booth - Strata 2014CSC - Presentation at Hortonworks Booth - Strata 2014
CSC - Presentation at Hortonworks Booth - Strata 2014Hortonworks
 
Running Head TOWN GUIDE ANDROID APPLICATION5TOWN GUIDE ANDROI.docx
Running Head TOWN GUIDE ANDROID APPLICATION5TOWN GUIDE ANDROI.docxRunning Head TOWN GUIDE ANDROID APPLICATION5TOWN GUIDE ANDROI.docx
Running Head TOWN GUIDE ANDROID APPLICATION5TOWN GUIDE ANDROI.docxtoltonkendal
 
nologies Semester 2 Lecture 1
nologies Semester 2 Lecture 1nologies Semester 2 Lecture 1
nologies Semester 2 Lecture 1Frances Bell
 
Vd&P Citec 071911
Vd&P Citec 071911Vd&P Citec 071911
Vd&P Citec 071911hutchhtr
 
Public Sector Agility Accelerator
Public Sector Agility AcceleratorPublic Sector Agility Accelerator
Public Sector Agility AcceleratorCraig Smith
 
Public Sector Agility Accelerator
Public Sector Agility AcceleratorPublic Sector Agility Accelerator
Public Sector Agility AcceleratorCraig Smith
 
Using CMMI Process Management Practices to Build and Maintain a QMS
Using CMMI Process Management Practices to Build and Maintain a QMSUsing CMMI Process Management Practices to Build and Maintain a QMS
Using CMMI Process Management Practices to Build and Maintain a QMSPECB
 
2014 Asdenca - Capability-driven development of a soa platform, a case study
2014 Asdenca - Capability-driven development of a soa platform, a case study2014 Asdenca - Capability-driven development of a soa platform, a case study
2014 Asdenca - Capability-driven development of a soa platform, a case studyCaaS EU FP7 Project
 
Spira Team Overview Presentation
Spira Team Overview PresentationSpira Team Overview Presentation
Spira Team Overview PresentationAdam Sandman
 
You're Live, Now What?
You're Live, Now What?You're Live, Now What?
You're Live, Now What?Evergreen ILS
 

Similar a Nhin Participant Tasks Slides 042106 V04 (20)

Developing of a web-based application to facilitate patient treatment adheren...
Developing of a web-based application to facilitate patient treatment adheren...Developing of a web-based application to facilitate patient treatment adheren...
Developing of a web-based application to facilitate patient treatment adheren...
 
Developing of a web-based application to facilitate patient treatment adheren...
Developing of a web-based application to facilitate patient treatment adheren...Developing of a web-based application to facilitate patient treatment adheren...
Developing of a web-based application to facilitate patient treatment adheren...
 
Rick Hathaway V SCTCday cloud 24 feb16 Barcelona
Rick Hathaway V SCTCday cloud 24 feb16 BarcelonaRick Hathaway V SCTCday cloud 24 feb16 Barcelona
Rick Hathaway V SCTCday cloud 24 feb16 Barcelona
 
Public Sector Agility Accelerator
Public Sector Agility AcceleratorPublic Sector Agility Accelerator
Public Sector Agility Accelerator
 
xAPI State of the State: xAPI for Reals
xAPI State of the State: xAPI for RealsxAPI State of the State: xAPI for Reals
xAPI State of the State: xAPI for Reals
 
Practical Test Strategy Using Heuristics
Practical Test Strategy Using HeuristicsPractical Test Strategy Using Heuristics
Practical Test Strategy Using Heuristics
 
PS2_FinalReport_2011B1A7689G
PS2_FinalReport_2011B1A7689GPS2_FinalReport_2011B1A7689G
PS2_FinalReport_2011B1A7689G
 
13 0820 Session 1 Management Team
13 0820 Session 1 Management Team13 0820 Session 1 Management Team
13 0820 Session 1 Management Team
 
UKRDDS 1st Workshop 20150423 - plan walkthrough
UKRDDS 1st Workshop 20150423 - plan walkthroughUKRDDS 1st Workshop 20150423 - plan walkthrough
UKRDDS 1st Workshop 20150423 - plan walkthrough
 
CSC - Presentation at Hortonworks Booth - Strata 2014
CSC - Presentation at Hortonworks Booth - Strata 2014CSC - Presentation at Hortonworks Booth - Strata 2014
CSC - Presentation at Hortonworks Booth - Strata 2014
 
Running Head TOWN GUIDE ANDROID APPLICATION5TOWN GUIDE ANDROI.docx
Running Head TOWN GUIDE ANDROID APPLICATION5TOWN GUIDE ANDROI.docxRunning Head TOWN GUIDE ANDROID APPLICATION5TOWN GUIDE ANDROI.docx
Running Head TOWN GUIDE ANDROID APPLICATION5TOWN GUIDE ANDROI.docx
 
nologies Semester 2 Lecture 1
nologies Semester 2 Lecture 1nologies Semester 2 Lecture 1
nologies Semester 2 Lecture 1
 
Vd&P Citec 071911
Vd&P Citec 071911Vd&P Citec 071911
Vd&P Citec 071911
 
Public Sector Agility Accelerator
Public Sector Agility AcceleratorPublic Sector Agility Accelerator
Public Sector Agility Accelerator
 
Public Sector Agility Accelerator
Public Sector Agility AcceleratorPublic Sector Agility Accelerator
Public Sector Agility Accelerator
 
Using CMMI Process Management Practices to Build and Maintain a QMS
Using CMMI Process Management Practices to Build and Maintain a QMSUsing CMMI Process Management Practices to Build and Maintain a QMS
Using CMMI Process Management Practices to Build and Maintain a QMS
 
2014 Asdenca - Capability-driven development of a soa platform, a case study
2014 Asdenca - Capability-driven development of a soa platform, a case study2014 Asdenca - Capability-driven development of a soa platform, a case study
2014 Asdenca - Capability-driven development of a soa platform, a case study
 
SAP sample
SAP sampleSAP sample
SAP sample
 
Spira Team Overview Presentation
Spira Team Overview PresentationSpira Team Overview Presentation
Spira Team Overview Presentation
 
You're Live, Now What?
You're Live, Now What?You're Live, Now What?
You're Live, Now What?
 

Último

Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...ShrutiBose4
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 

Último (20)

Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 

Nhin Participant Tasks Slides 042106 V04

  • 1. The Nationwide Health Information Network (NHIN) Architecture Prototype Project Health Care Markets – Participants Tasks April 2006 DRAFT
  • 2. The NHIN Project will run through the end of the year and consists of 4 phases 11/24/06 5/15/06 140 days Fostering NHIN Adoption 12/29/06 12/19/06 9 days Prototype Demonstration Phase 12/18/06 6/20/06 130 days Implementation Phase 6/19/06 4/17/06 40 days Requirements & Design Phase 12/29/06 4/17/06 185 days NHIN Architecture Prototype Project
  • 3. NHIN Prototype Project Deliverables The ONC Milestones dates are currently as planned but are subject to change 12/29/06 MILESTONE: Prototype Demonstration Complete 12/29/06 MILESTONE: Final deployment and operational plan deliverables to ONC 11/30/06 MILESTONE: Detailed design and architecture deliverable to ONC 10/27/06 MILESTONE: Cost and revenue model deliverable to ONC 9/8/06 MILESTONE: Security model deliverable to ONC 8/25/06 MILESTONE: Draft deployment and operational plan deliverables to ONC 6/19/06 MILESTONE: Communications and interface requirements deliverable to ONC 4/28/06 MILESTONE: Functional and performance requirements to ONC
  • 4. Requirements & Design Phase 4/17/06- 6/19/06   The task dates are currently as planned but are subject to change 6/7/06 6/6/06 2 days Provide input into communications and interface requirements deliverable 6/2/06 5/15/06 15 days Assist in determining assets, communication and interface requirements for organization participation 5/17/06 5/16/06 2 days Supply information regarding security, privacy, data sharing policies and procedures 5/17/06 5/16/06 2 days Supply information to IBM regarding technical environment 5/16/06 5/16/06 1 day Attend Kick off meeting 5/12/06 5/12/06 0 days MILESTONE: Sign agreements/contracts with IBM 5/1/06 5/1/06 1 day Determine communicate to IBM extent to which organization will participate in each use case 5/1/06 5/1/06 1 day Communicate to IBM any gaps between use case requirements and organization's current capabilities 4/28/06 4/21/06 6 days Review use case documents and document gaps between use case requirements and organization's current capabilities 4/25/06 4/21/06 3 days Provide input into functional requirements deliverable 4/20/06 4/19/06 2 days Review use case documents 4/18/06 4/18/06 1 day Provide contact information to IBM for software vendors if applicable for systems involved in implementing the use cases 6/19/06 4/18/06 38 days Champion project throughout organization 4/18/06 4/18/06 1 day Identify and Recruit Resources for Project 4/17/06 4/17/06 1 day Appoint and provide contact information to IBM for organization's liaison/leader for project 4/17/06 4/17/06 0 days MILESTONE: Communicate to IBM commitment to participate in project
  • 5. Implementation Phase 6/20/06- 12/18/06   The task dates are currently as planned but are subject to change 12/18/06 6/20/06 26 wks Champion project throughout organization 11/23/06 11/17/06 5 days Provide input into detailed design and architecture deliverable 9/5/06 8/30/06 5 days Provide input into security model deliverable 12/18/06 6/20/06 26 wks Assist with testing of prototype 12/18/06 6/20/06 26 wks Attend user training 12/18/06 6/20/06 26 wks Facilitate IBM access to system vendors and organizational resources 12/18/06 6/20/06 26 wks Assist with installation and configuration of hardware, software & interfaces 12/18/06 6/20/06 26 wks Supply information regarding technical environment
  • 6. Prototype Demonstration Phase 6/20/06- 12/18/06   The dates and details of the demonstration are still to be determined 12/29/06 12/19/06 9 days Champion project throughout organization 12/29/06 12/19/06 9 days Contribute to evaluation of prototype 12/29/06 12/19/06 9 days Participate in demonstration: - maintain performance and availability of systems, - assure accuracy of any real data shared, - assure appropriate consent is secured for any real data shared, - perform end user functions
  • 7. Hospital Participant Resources and Tasks for NHIN Project x Assure contracts and data use agreements are signed X X X X X X x Contribute to evaluation of prototype   x x x x x   Assist with testing and demonstration of prototype         x     Assist with installation and configuration of hardware, software & interfaces x x   x x     Supply information to IBM regarding technical and business environment x x x x x x x Provide input into deliverables documents           x x Determine extent to which organization will participate in each use case     x     x x Champion project throughout organization           x x Facilitate IBM access to organizational resources and system vendors x x x x x x x Participate in planning meetings and workshops 12 hrs 32 hrs 70 hrs 100 hrs 130 hrs 108 hrs 40- 80 hrs TASKS Medical Records Security Officer Clinician Application Data Technical Project Liaison CIO or Designee             RESOURCES  
  • 8. Ambulatory Practice Participant with EHR Resources and Tasks for NHIN Project     x Assure contracts and data use agreements are signed x x   Contribute to evaluation of prototype x x   Assist with testing and demonstration of prototype x x   Assist with or facilitate installation and configuration of hardware, software & interfaces x x   Supply information to IBM regarding technical and business environment x x   Provide input into deliverables documents     x Determine extent to which organization will participate in each use case   x x Champion project throughout organization   x x Facilitate IBM access to organizational resources and system vendors x x x Participate in planning meetings and workshops 80 hrs 40 hrs 20 hrs TASKS Technical (Practice or Vendor) Clinical or Practice Administrator Project Sponsor   RESOURCES  
  • 9. Ambulatory Practice Participant without EHR Resources and Tasks for NHIN Project   x Assure contracts and data use agreements are signed x   Contribute to evaluation of prototype x   Assist with testing and demonstration of prototype x   Assist with or facilitate installation and configuration of hardware, software & interfaces x   Supply information to IBM regarding technical and business environment x   Provide input into deliverables documents   x Determine extent to which organization will participate in each use case x x Champion project throughout organization x x Facilitate IBM access to organizational resources and system vendors x x Participate in planning meetings and workshops 40 hrs 20 hrs TASKS Clinical or Practice Administrator Project Sponsor   RESOURCES