CONTENTS
DADO
Brief Specification
 Detailed Specification
 Rate Analysis

FLY OVER
 Approximate Estimate
Brief Specification for Dado

Provide dado on 12 mm thick rough cement plaster (1:3)
base and jointed with alkali resisted cement as per IS: 4457
completed as per the direction of Engineer-In-Charge.
Detailed Specification for Dado
1. Materials
2. Preparation of surface & laying
3. Mortar and bedding
4. Fixing tiles for dado
5. Cleaning
6. Pointing and finishing
7. Mode of measurement
MATERIALS
 White Glazed Tiles : The tiles shall be of approved and shall







generally conform to IS : 777.
They shall be flat and true to shape and free from cracks,
blisters, welts, crawling, crazing spots, chipped edges,
corners or other imperfections detracting from their
appearance.
The tiles shall be of square or rectangular of nominal sizes
such as 300x200mm, 150x150mm, 100x100mm.
Samples of tiles shall be got approved by the Engineer-incharge before use on the work.
Top surface of tile shall be glossy or matt as specified.
PREPARATION OF SURFACE & LAYING
 Sub grade concrete or RCC slab or side brick wall/ or







plastered surfaces on which tiles are to be laid shall be
cleaned, wetted and mopped.
The bedding/backing for the tile shall be of C.M. 1.3 or as
specified and shall be applied and allowed to harden.
The mortar shall be roughened with wire brushes or by
scratching diagonal lines 1.5mm. deep at 7.5mm.
dado shall be truly horizontal and joints truly vertical.
After the tiles have been laid, surplus cement grout shall be
cleaned off.
MORTAR AND BEDDING
 Cement mortar shall conform to the specification for

materials, preparations etc. as specified under cement
mortar.
 The amount of water added while preparing mortar shall be
the minimum necessary to give sufficient plasticity for
laying.
 Care shall be taken in preparation of the mortar to ensure
that there are no hard lumps that would interfere with even
bedding of the tiles.
 The mortar of specified proportion and thickness shall then
be even and smoothly spread over the base by use of screed
battens to proper level or slope.
FIXING TILES FOR DADO
 The dado work, shall be done only after fixing the tiles/slabs







on the floor.
The approved white glazed tiles before laying shall be soaked
in water for at least 2 hours.
Tiles shall be fixed when the cushioning mortar is still plastic
and before it gets very stiff.
The back of the tile shall be covered with this layer of cement
mortar 1:2 using fine sand (table III, zone IV, I.S. 383-1963)
and the edge of the tile smeared with neat white cement
slurry.
The tile shall then be pressed in the mortar and gently tapped
against the wall with a wooden mallet.
 The fixing shall be done from bottom of wall upwards without any








hollows in the bed of joints.
Each tile shall be as close as possible to one adjoining.
The tiles shall be jointed with white cement slurry.
Any thickness difference in the thickness of the tiles shall be
arranged out in cushioning mortar so that all tiles faces are in one
vertical plane.
The top of the dado shall be touched up neatly with the rest of the
plaster above.
After fixing the dado/skirting etc. they shall be kept continuously
wet for 7 days.
If doors, windows or other openings are located within the dado
area, the corners, sills, jambs etc. shall be provided with true right
angles without any specials.
CLEANING
 After the tiles have been laid in a room or the days fixing






work is completed, the surplus cement grout that may have
come out of the joints shall be cleaned off before it sets.
After the complete curing, the dado or skirting over shall be
washed thoroughly clean.
In the case of flooring, once the floor has set, the floor shall
be carefully washed clean and dried.
When dry, the floor shall be covered with oil free dry saw
dust.
It shall be removed only after completion of the construction
work and just before the floor is used.
MODE OF MEASUREMENT
 Dado/flooring/skirting shall be measured in sqm.

correct to two places of decimal.
 Length and breadth shall be measured correct to 1 cm.
 Between the exposed surfaces of skirting or dado. No
deductions shall be made nor extra paid for any opening
of area up to 0.1 sqm.
 The rate shall include all the cost of labour and materials
involved.
Rate Analysis for Dado
Rate Analysis for 10 sq-m
The quantity of white-glazed tile is worked out by assuming 1 mm on
either side for thickness in joint & tolerance in size of tiles. Thus, no of
white-gazed tiles
= 10/(0.152X0.152)
= ~ 432 tiles
Particulars

Quantity
Or
Numbers

Rate

Per

Amounts

White Gazed Tiles

432 Nos

Rs. 8.00

no

Rs. 3456.00

Wastage o white
gazed tiles @ 5%

Rs. 172.00

C.M. (1:3) for
rough plaster,
bedding & wastage

0.18 cu m

Rs. 2510.00

Cu m

Rs. 451.80

White Cement
Sundries

0.25 bags

Rs. 950.00

bag

Rs. 237.50
Rs. 6.90

Material Cost =

Rs. 4325.00

Sq m

Rs. 1000.00

Labour:
Labour for fixing,
making rough coat
of plaster, filling
joints etc

10.00 sq m

Rs. 100.00
Labour Cost
Add Material Cost

=
=

Rs. 1000.00
Rs. 4325.00
------------------Total
=
Rs 5325.00
10% Contractors’ Profit =
Rs. 532.50
1.5% Water and electric
consumption charges
=
Rate per 10 sq m
Rate per sq m
Say

Rs. 79.88
-------------------=
Rs. 5937.38
=
Rs. 593.74
=
Rs. 595.00
Approximate Estimate of FLY OVER
Examples:
National ProjectAt Mohan Nagar Junction in Ghaziabad, India.

At Kampthee, Nagpur on NH-7, India
At Sirmaur Chauraha Rewa, M.P., India
International ProjectAt Junction of Che Kung Road and Hung Mui Road, Honkong.
At Mohan Nagar Junction in Ghaziabad, India
 Name of Project
 Detail of Client
 Details of Contractor

:
:
:

 Scope of Work

:






Cost of Work
:
Duration of Work
:
Details, Project Progress:
Resources Used
:

 New Technology

control
 Per meter cost

Construction of Fly Over
National Capital Region Planning Board
Asian Development Bank and
Wilbur Smith Associates
Fly Over with 2 lanes on existing road for
700 meters
Rs. 539,160,413.00
2 Years (work started on July 2008)
Completed on July 2010
Manpower, Equipments, Machineries

:

Paver Finisher Hydrostatic with sensor

:

Rs. 7,70,229
At Kampthee, Nagpur on NH-7, India
 Name of Project
 Detail of Client
 Details of Contractor

 Scope of Work








:
:
:

:
Cost of Work
:
Duration of Work
:
Details, Project Progress:
Resources Used
:
New Technology
:
Per meter cost
:

Construction of Fly Over
NHAI
Oriental Construction Company Pvt. Ltd
Backbone Enterprises
Fly Over on 850 Meter 2 lane road
Rs. 721,122,350.00
2 Years (work started on July 2010)
Completed on July 2012
Manpower, Equipments, Machineries
Fly Ash was used, Pile foundation was done
Rs. 8,48,379.00
At Sirmaur Chauraha Rewa, M.P., India
 Name of Project

 Detail of Client









:

:
Details of Contractor :
Scope of Work
:
lane
Cost of Work
:
Duration of Work
:
Project Progress
:
Resources Used
:
Per meter cost

Construction of Flyover Bridge at
Sirmour Chouraha Rewa on VaranasiNagpur Road, Rewa, MP
Public Works Department M.P.
Abhay Mishra Comstruction company
Fly Over with 750 meters long two
Rs. 25 Crors
2 Years (Started on 2012)
Under Process
Manpower, Equipments, Machineries
:
Rs. 3,33,333
At Junction of Che Kung Road & Hung Mui Road, Honkong.
 Name of Project

 Detail of Client

:
:

 Details of Contractor :
 Scope of Work
 Cost of Work






:

:
Duration of Work
:
Details, Project Progress:
Resources Used
:
Per meter cost
:

Construction of Fly Over
Government of the Hong Kong
Special Administrative Region
HKSAR
Construction of approximate 600
metres long dual 2-lane
Rs. 537,140,479.00
December 2007
Completion January 2013
Manpower, Equipments, Machineries
RS. 8,98,600
Average cost per meter
=

Rs. 5,37,635
THANK YOU

Más contenido relacionado

La actualidad más candente

estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingsooricivil
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSShourya Puri
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and EstimationGide India
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality controlSOURAV4798
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering MeasurmentSultan M Muzahir
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential buildingShariful Haque Robin
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and CostingSakshi Kirar
 
Cement Plastering procedure
Cement Plastering procedureCement Plastering procedure
Cement Plastering procedureSyed Javed
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017bee_by
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORTFresher Thinking
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of buildingARUN KUMAR
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkAshwiniChaudhari13
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructureguasiya
 

La actualidad más candente (20)

estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODS
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Estimation
EstimationEstimation
Estimation
 
Insepction and quality control
Insepction and quality controlInsepction and quality control
Insepction and quality control
 
Civil Engineering Measurment
Civil Engineering MeasurmentCivil Engineering Measurment
Civil Engineering Measurment
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Cement Plastering procedure
Cement Plastering procedureCement Plastering procedure
Cement Plastering procedure
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickwork
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 

Destacado

Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
Top 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answersTop 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answersmitchellparker911
 
Table of specification
Table of specificationTable of specification
Table of specificationAbigail Sapico
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Felix Vong
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil constructiondiasawada12345
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methodsSimarpreet Singh
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costingGanesh Murugan
 

Destacado (9)

Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
Top 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answersTop 10 project quantity surveyor interview questions and answers
Top 10 project quantity surveyor interview questions and answers
 
Table of specification
Table of specificationTable of specification
Table of specification
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
SPECIFICATIONS
SPECIFICATIONSSPECIFICATIONS
SPECIFICATIONS
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil construction
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methods
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 

Similar a Estimation and quantity surveying

Kajaria tiles installtion
Kajaria tiles installtionKajaria tiles installtion
Kajaria tiles installtionChuchu Beera
 
02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptx02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptxPAVITRA GOYAL
 
Building specfication ppt- avneet.pptx
Building specfication ppt- avneet.pptxBuilding specfication ppt- avneet.pptx
Building specfication ppt- avneet.pptxSanskritiJindal4
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxswethasekhar5
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specificationsSimran Vats
 
B.3. Arch 561 LEC-10 detail spec example.pdf
B.3. Arch 561  LEC-10 detail spec example.pdfB.3. Arch 561  LEC-10 detail spec example.pdf
B.3. Arch 561 LEC-10 detail spec example.pdfRahul Chandra Deb Nath
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation Prabhat chhirolya
 
Ppt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SitePpt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SiteAlok Mishra
 
Finishing works Part 1.pptx
Finishing works Part 1.pptxFinishing works Part 1.pptx
Finishing works Part 1.pptxSandipPaul46
 
Presentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkPresentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkCivil 4M
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIPMkh Nantu
 

Similar a Estimation and quantity surveying (20)

Finishing of cement
Finishing of cementFinishing of cement
Finishing of cement
 
Kajaria tiles installtion
Kajaria tiles installtionKajaria tiles installtion
Kajaria tiles installtion
 
02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptx02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptx
 
QSCM.pptx
QSCM.pptxQSCM.pptx
QSCM.pptx
 
cereamic
cereamiccereamic
cereamic
 
Building specfication ppt- avneet.pptx
Building specfication ppt- avneet.pptxBuilding specfication ppt- avneet.pptx
Building specfication ppt- avneet.pptx
 
Specifications for rcc
Specifications for rcc Specifications for rcc
Specifications for rcc
 
plaster.pptx
plaster.pptxplaster.pptx
plaster.pptx
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Types of floor finishes
Types of floor finishesTypes of floor finishes
Types of floor finishes
 
Types of floor finishes
Types of floor finishesTypes of floor finishes
Types of floor finishes
 
B.3. Arch 561 LEC-10 detail spec example.pdf
B.3. Arch 561  LEC-10 detail spec example.pdfB.3. Arch 561  LEC-10 detail spec example.pdf
B.3. Arch 561 LEC-10 detail spec example.pdf
 
Specifications of rcc foundation
Specifications of rcc foundation Specifications of rcc foundation
Specifications of rcc foundation
 
Ppt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SitePpt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction Site
 
Kota stone
Kota stoneKota stone
Kota stone
 
Finishing works Part 1.pptx
Finishing works Part 1.pptxFinishing works Part 1.pptx
Finishing works Part 1.pptx
 
Flooring.ppt
Flooring.pptFlooring.ppt
Flooring.ppt
 
Presentation on how to do AAC Blockwork
Presentation on how to do AAC BlockworkPresentation on how to do AAC Blockwork
Presentation on how to do AAC Blockwork
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 

Más de Awanish Shukla

Case study on small firm
Case study on small firmCase study on small firm
Case study on small firmAwanish Shukla
 
Green building challenges
Green building challengesGreen building challenges
Green building challengesAwanish Shukla
 
Swot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourneSwot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourneAwanish Shukla
 
Concrete bag selling consept....
Concrete bag selling consept....Concrete bag selling consept....
Concrete bag selling consept....Awanish Shukla
 
Project ppt guide shri a.n.dabhade sir 1
Project ppt guide  shri a.n.dabhade sir 1Project ppt guide  shri a.n.dabhade sir 1
Project ppt guide shri a.n.dabhade sir 1Awanish Shukla
 

Más de Awanish Shukla (10)

Case study on small firm
Case study on small firmCase study on small firm
Case study on small firm
 
Mass housing
Mass housingMass housing
Mass housing
 
Green building challenges
Green building challengesGreen building challenges
Green building challenges
 
Metro project
Metro projectMetro project
Metro project
 
Water auditing
Water auditingWater auditing
Water auditing
 
Kuwait oil field
Kuwait oil fieldKuwait oil field
Kuwait oil field
 
Global warming
Global warmingGlobal warming
Global warming
 
Swot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourneSwot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourne
 
Concrete bag selling consept....
Concrete bag selling consept....Concrete bag selling consept....
Concrete bag selling consept....
 
Project ppt guide shri a.n.dabhade sir 1
Project ppt guide  shri a.n.dabhade sir 1Project ppt guide  shri a.n.dabhade sir 1
Project ppt guide shri a.n.dabhade sir 1
 

Último

BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 

Último (20)

BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 

Estimation and quantity surveying

  • 1. Estimation And Quantity Surveying Presented ByAWANISH SHUKLA Roll No 271303 Branch- ACM Section- IV NATIONAL INSTITUTE OF CONSTRUCTION MANAGEMENT AND RESEARCH
  • 2. CONTENTS DADO Brief Specification  Detailed Specification  Rate Analysis FLY OVER  Approximate Estimate
  • 3. Brief Specification for Dado Provide dado on 12 mm thick rough cement plaster (1:3) base and jointed with alkali resisted cement as per IS: 4457 completed as per the direction of Engineer-In-Charge.
  • 4. Detailed Specification for Dado 1. Materials 2. Preparation of surface & laying 3. Mortar and bedding 4. Fixing tiles for dado 5. Cleaning 6. Pointing and finishing 7. Mode of measurement
  • 5. MATERIALS  White Glazed Tiles : The tiles shall be of approved and shall     generally conform to IS : 777. They shall be flat and true to shape and free from cracks, blisters, welts, crawling, crazing spots, chipped edges, corners or other imperfections detracting from their appearance. The tiles shall be of square or rectangular of nominal sizes such as 300x200mm, 150x150mm, 100x100mm. Samples of tiles shall be got approved by the Engineer-incharge before use on the work. Top surface of tile shall be glossy or matt as specified.
  • 6. PREPARATION OF SURFACE & LAYING  Sub grade concrete or RCC slab or side brick wall/ or     plastered surfaces on which tiles are to be laid shall be cleaned, wetted and mopped. The bedding/backing for the tile shall be of C.M. 1.3 or as specified and shall be applied and allowed to harden. The mortar shall be roughened with wire brushes or by scratching diagonal lines 1.5mm. deep at 7.5mm. dado shall be truly horizontal and joints truly vertical. After the tiles have been laid, surplus cement grout shall be cleaned off.
  • 7. MORTAR AND BEDDING  Cement mortar shall conform to the specification for materials, preparations etc. as specified under cement mortar.  The amount of water added while preparing mortar shall be the minimum necessary to give sufficient plasticity for laying.  Care shall be taken in preparation of the mortar to ensure that there are no hard lumps that would interfere with even bedding of the tiles.  The mortar of specified proportion and thickness shall then be even and smoothly spread over the base by use of screed battens to proper level or slope.
  • 8. FIXING TILES FOR DADO  The dado work, shall be done only after fixing the tiles/slabs     on the floor. The approved white glazed tiles before laying shall be soaked in water for at least 2 hours. Tiles shall be fixed when the cushioning mortar is still plastic and before it gets very stiff. The back of the tile shall be covered with this layer of cement mortar 1:2 using fine sand (table III, zone IV, I.S. 383-1963) and the edge of the tile smeared with neat white cement slurry. The tile shall then be pressed in the mortar and gently tapped against the wall with a wooden mallet.
  • 9.  The fixing shall be done from bottom of wall upwards without any       hollows in the bed of joints. Each tile shall be as close as possible to one adjoining. The tiles shall be jointed with white cement slurry. Any thickness difference in the thickness of the tiles shall be arranged out in cushioning mortar so that all tiles faces are in one vertical plane. The top of the dado shall be touched up neatly with the rest of the plaster above. After fixing the dado/skirting etc. they shall be kept continuously wet for 7 days. If doors, windows or other openings are located within the dado area, the corners, sills, jambs etc. shall be provided with true right angles without any specials.
  • 10. CLEANING  After the tiles have been laid in a room or the days fixing     work is completed, the surplus cement grout that may have come out of the joints shall be cleaned off before it sets. After the complete curing, the dado or skirting over shall be washed thoroughly clean. In the case of flooring, once the floor has set, the floor shall be carefully washed clean and dried. When dry, the floor shall be covered with oil free dry saw dust. It shall be removed only after completion of the construction work and just before the floor is used.
  • 11. MODE OF MEASUREMENT  Dado/flooring/skirting shall be measured in sqm. correct to two places of decimal.  Length and breadth shall be measured correct to 1 cm.  Between the exposed surfaces of skirting or dado. No deductions shall be made nor extra paid for any opening of area up to 0.1 sqm.  The rate shall include all the cost of labour and materials involved.
  • 12. Rate Analysis for Dado Rate Analysis for 10 sq-m The quantity of white-glazed tile is worked out by assuming 1 mm on either side for thickness in joint & tolerance in size of tiles. Thus, no of white-gazed tiles = 10/(0.152X0.152) = ~ 432 tiles
  • 13. Particulars Quantity Or Numbers Rate Per Amounts White Gazed Tiles 432 Nos Rs. 8.00 no Rs. 3456.00 Wastage o white gazed tiles @ 5% Rs. 172.00 C.M. (1:3) for rough plaster, bedding & wastage 0.18 cu m Rs. 2510.00 Cu m Rs. 451.80 White Cement Sundries 0.25 bags Rs. 950.00 bag Rs. 237.50 Rs. 6.90 Material Cost = Rs. 4325.00 Sq m Rs. 1000.00 Labour: Labour for fixing, making rough coat of plaster, filling joints etc 10.00 sq m Rs. 100.00
  • 14. Labour Cost Add Material Cost = = Rs. 1000.00 Rs. 4325.00 ------------------Total = Rs 5325.00 10% Contractors’ Profit = Rs. 532.50 1.5% Water and electric consumption charges = Rate per 10 sq m Rate per sq m Say Rs. 79.88 -------------------= Rs. 5937.38 = Rs. 593.74 = Rs. 595.00
  • 15. Approximate Estimate of FLY OVER Examples: National ProjectAt Mohan Nagar Junction in Ghaziabad, India. At Kampthee, Nagpur on NH-7, India At Sirmaur Chauraha Rewa, M.P., India International ProjectAt Junction of Che Kung Road and Hung Mui Road, Honkong.
  • 16. At Mohan Nagar Junction in Ghaziabad, India  Name of Project  Detail of Client  Details of Contractor : : :  Scope of Work :     Cost of Work : Duration of Work : Details, Project Progress: Resources Used :  New Technology control  Per meter cost Construction of Fly Over National Capital Region Planning Board Asian Development Bank and Wilbur Smith Associates Fly Over with 2 lanes on existing road for 700 meters Rs. 539,160,413.00 2 Years (work started on July 2008) Completed on July 2010 Manpower, Equipments, Machineries : Paver Finisher Hydrostatic with sensor : Rs. 7,70,229
  • 17. At Kampthee, Nagpur on NH-7, India  Name of Project  Detail of Client  Details of Contractor  Scope of Work       : : : : Cost of Work : Duration of Work : Details, Project Progress: Resources Used : New Technology : Per meter cost : Construction of Fly Over NHAI Oriental Construction Company Pvt. Ltd Backbone Enterprises Fly Over on 850 Meter 2 lane road Rs. 721,122,350.00 2 Years (work started on July 2010) Completed on July 2012 Manpower, Equipments, Machineries Fly Ash was used, Pile foundation was done Rs. 8,48,379.00
  • 18. At Sirmaur Chauraha Rewa, M.P., India  Name of Project  Detail of Client        : : Details of Contractor : Scope of Work : lane Cost of Work : Duration of Work : Project Progress : Resources Used : Per meter cost Construction of Flyover Bridge at Sirmour Chouraha Rewa on VaranasiNagpur Road, Rewa, MP Public Works Department M.P. Abhay Mishra Comstruction company Fly Over with 750 meters long two Rs. 25 Crors 2 Years (Started on 2012) Under Process Manpower, Equipments, Machineries : Rs. 3,33,333
  • 19. At Junction of Che Kung Road & Hung Mui Road, Honkong.  Name of Project  Detail of Client : :  Details of Contractor :  Scope of Work  Cost of Work     : : Duration of Work : Details, Project Progress: Resources Used : Per meter cost : Construction of Fly Over Government of the Hong Kong Special Administrative Region HKSAR Construction of approximate 600 metres long dual 2-lane Rs. 537,140,479.00 December 2007 Completion January 2013 Manpower, Equipments, Machineries RS. 8,98,600
  • 20. Average cost per meter = Rs. 5,37,635