A. INTRODUCTION
CONSTRUCTION PLANNING
A.1. PROJECT INFORMATION
1. PROJECT NAME : PT. LYONDELLBASELL
2. PROJECT LOCATION : GEMPOL PASURUAN - JAWA TIMUR
3. OWNER : APS GEMPOL EXPANSION PROJECT
4. SCOPE OF WORK : Civil, Structure & Architecture
6. CONSTRUCTION PERIOD : (5 Calendar Months)
CONSTRUCTION PLANNING
B. CONSTRUCTION PLANNING
CONSTRUCTION PLANNING
12/18/2022
CONSTRUCTION PLANNING
SITE FACILITY
12/18/2022
CONSTRUCTION PLANNING
SEQUENCE & PLANNING SCHEDULE
A F IL L IN G L IN E (W E E K 0 1 - W E E K 2 1 )
B D E B A G G IN G & P R E M IX IN G (W E E K 0 3 -W E E K 2 0 )
C C O M P R E S S O R (W E E K 0 4 - W E E K 1 2 )
D M V & L V (W E E K 0 5 - W E E K 1 5 )
E T R A N S F O R M E R (W E E K 0 6 - W E E K 2 1 )
F C O O L IN G T O W E R (W E E K 0 8 W E E K 1 7 )
G P A N T R Y R O O M (W E E K 0 9 - W E E K 1 8 )
H F U M E (W E E K 1 0 - W E E K 1 7 )
I F U R N A C E (W E E K 1 0 - W E E K 2 2 )
12/18/2022
CONSTRUCTION PLANNING
DEMOLISH EXISTING AREA (EQUIPMENT USED)
EXCAVATOR CRAWLER
WITH RUBBER TIRE
DUMP TRUCK
AREA DEMOLISH
CONSTRUCTION PLANNING
SEQUENCE OF WORK FOR STEEL STRUCTURE
YES
NO
YES
NO
DAILY INSPECTION NOTICE
VERIFY,JOINT
INSPECTION
WITH OWNER
FINISH
PRODUCT
A B C
VERIFY
INTERNAL
INSPECTION
GENERAL QUALITY CONTROL FLOWCHART FOR CONSTRUCTION WORKS (2)
CONSTRUCTION PLANNING
YES
NO
YES
NO
QUALITY CONTROL RECEIVING MATERIAL PLAN
QUALITY CONTROL DEPARTMENT
1. INSPECTION & TEST PLAN
2. QC SHEET FORM
WAREHOUSE
APPROVED MATERIAL
START
FINISH
ENGINEERING DEPARTMENT
1. APPROVAL MATERIAL
2. SAMPLE
PROCUREMENT/PURCHASING DEPARTMENT
PURCHASING ORDER (PO)
SUPPLIER
MATERIAL
PRODUCTION DEPARTMENT
SURAT PERMINTAAN PENGADAAN
BARANG (SPP)
PROJECT MANAGER
1. FOR CONSTRUCTION DWG
2. TECHNICAL SPECIFICATION
3. GENERAL NOTES
VERIFY MATERIAL
RECEIVING
INSPECTION
VERIFY
INDEPENDENT
LABORATORIU
M
CONSTRUCTION PLANNING
b. Execution
YES
NO
YES
NO
OK
QUALITY CONTROL INSPECTION FOR CONCRETING GROUND SLAB PLAN (1)
QUALITY CONTROL DEPARTMENT
VERIFY
INTERNAL
INSPECTION
INSTALL SCAFFOLDING & FORM WORK
PRODUCTION DEPARTMENT
START
ENGINEERING DEPARTMENT
1. DETAIL DWG/SHOP DWG
2. WORK PROCEDURES
3. WORK INSTRUCTIONS
PROCUREMENT DEPARTMENT / E N T DEPARTMENT
1. INSPECTION AND TEST PLAN
2. QC SHEET FORM
SUPPLY EQUIPMENT, TOOLS AND MATERIAL
PREPARATION FOR MAN POWER, EQUIPMENT,
MATERIAL AND TIME SCHEDULE
PROJECT MANAGER
1. FOR CONSTRUCTION DWG
2. TECHNICAL SPECIFICATION
3. GENERAL NOTES
VERIFY, MATERIAL
RECEIVING &
CALIBRATION
INSPECTION
A B
INSTALL REBAR BEAM, SLAB & STARTER BAR
C
VERIFY
INTERNAL
INSPECTION
a. Preparing
CONSTRUCTION PLANNING
YES
NO
YES
NO
YES
QUALITY CONTROL INSPECTION FOR CONCRETING GROUND SLAB PLAN (2)
DAILY INSPECTION NOTICE
FINISH
ORDER CONCRETE TO BATCHING PLANT
C
VERIFY,JOINT
INSPECTION WITH
OWNER
A B
REQUEST FOR HANDLING CONCRETE
CONCRETE
CONCRETE
INSPECTION
FOR SLUMP
VERIFY INTERNAL
INSPECTION
INSTALL LEVELING TOP CONCRETE & CLEANING
CONSTRUCTION PLANNING
b. Execution
YES
NO
OK
QUALITY CONTROL INSPECTION FOR CONCRETING COLUMN PLAN (1)
QUALITY CONTROL DEPARTMENT
SETTING OUT AND MARKING POSITION FOR
COLUMN
PRODUCTION DEPARTMENT
START
ENGINEERING DEPARTMENT
1. DETAIL DWG/SHOP DWG
2. WORK PROCEDURES
3. WORK INSTRUCTIONS
PROCUREMENT DEPARTMENT / E N T DEPARTMENT
1. INSPECTION AND TEST PLAN
2. QC SHEET FORM
SUPPLY EQUIPMENT, TOOLS AND MATERIAL
PREPARATION FOR MAN POWER, EQUIPMENT,
MATERIAL AND TIME SCHEDULE
PROJECT MANAGER
1. FOR CONSTRUCTION DWG
2. TECHNICAL SPECIFICATION
3. GENERAL NOTES
VERIFY, MATERIAL
RECEIVING &
CALIBRATION
INSPECTION
A
B
REQUEST FOR HANDLING CONCRETE
C
VERIFY
INTERNAL
INSPECTION
a. Preparing
INSTALL REBAR
CLEANING
CONSTRUCTION PLANNING
YES
NO
YES
NO
YES
NO
YES
NO
QUALITY CONTROL INSPECTION FOR CONCRETING COLUMN PLAN (2)
VERIFY,JOINT
INSPECTION
WITH OWNER
FINISH
ORDER CONCRETE TO BATCHING PLANT
INSTALL FORMWORK
VERIFY,JOINT
INSPECTION
WITH OWNER
A B C
CONCRETE
CONCRETE
INSPECTION
FOR SLUMP
DAILY INSPECTION NOTICE
VERIFY
INTERNAL
INSPECTION
DAILY INSPECTION NOTICE
CONSTRUCTION PLANNING
I. Making Safety Plan
• Forming a HSE project organization,
• List of equipment that need special handling,
• Hazard identification and prevention,
• HSE site plan,
• Hygiene program and brief, clean, neatly, diligent, & treatment.
II. Prepare HSE supporting equipment and personal protective equipment
• Fire extinguishers,
• HSE signs,
• Safety instruction,
• Supporting tools: temporary toilet, urinoir, & water pump equipment,
• Helmet, safety belt, mask , safety shoes, safety belt, & medicine box.
III. Cooperation with Hospital, Clinic and insure Labour to Jamsostek
(Labour insurance)
CONSTRUCTION PLANNING
B.6. HSE PROGRAM
Safety, Security & Housekeeping Program
Project Start
Planning
Organizing
Controlling
Clean,
Organize,
Healthy & Safe
-Project Safety Objective
-Risk Assessment and Risk Management
-Site Safety Plan
-Safety, Security, and Environment budget
-Forming safety organization and
safety committee
-Standard and procedure of
safe work practice
-Inspection Plan
-Audit
CONSTRUCTION PLANNING
Corporate Organization
CONSTRUCTION PLANNING
Project Organization
PROJECT OPERATION
GENERAL MANAGER
PROJECT MANAGER
ENGINEERING
MANAGER
CONSTRUCTION
MANAGER
ADMINISTRATION
G / A
HSE MANAGER
HSE COMMITTEE
Chairman : Safety Officer
Member : PM, Eng.Mng, Const. Mgr
Sub Member : Sub Contractor PM
SAFETY ENGINEER
SAFETY INSPECTOR
SUPERVISOR
CIVIL / FINISHING
SUPERVISOR
M / E / P
SURVEYOR MECHANIC
& OPERATOR
CONSTRUCTION PLANNING
EHS MEETING PROGRAM
Description Of Meeting Schedule Chairman & Attendants
1. Morning Gathering Daily
Chaired by HSE Officer to be attended by safety Supervisors,
and field workers.
2. Tool Box Meeting Daily
Chaired by construction Supervisors assisted HSE supervisor
to be attended by crafts foremen personnel.
3. Security Meeting Daily Chaired by HSE officer, to be attended by security personnel.
4. Supervisors Progress and Safety Meeting Weekly
Chaired by HSE Manager/ Officer or construction manager, to
be attended by HSE supervisors, construction engineers and
supervisors.
5. Progress and Safety Meeting Monthly
Chaired by Project Manager and or HSE Manager to be
attended by HSE officers, construction Engineers
6. Meeting for specific accident/ incident
Decided by HSE
Manager or Officer
Chaired by HSE Manager or Office to ber attended by
concerned individuals.
GENERAL INSPECTION PROGRAM
HSE Particulars General Inspection Checklist
House Keeping And fire Protection
Waste disposal, cleaning methods, access ways, material/ tools/ equipment
storage, extinguisher, alarm, non smoking areas, response instructions,
emergency exits, sign boards.
Excavation/ Trenches Shoring, Civil Works
Barricades, warning sign in place, access ways, work procedures, work
practices, work permits.
Personal Protective Gadget
Safety helmet, hand gloves, safety footwear, eye protection, hearing
protection, respirator, safety belt.
Confined Space Entry, Restricted Area,
Hazardous Work, Lock out/ Tag out
Work permits, Barricades, warning, sign in place, access ways, ventilation,
work procedures, work practices, lock out and tag out sign
Electrical Works
Breakers switches, fuses, grounding, lock out/ tag out, plugs, warning sign,
distribution boards, equipment & tools, work procedures, work permit.
Mechanical Works, Equipment Installation
Machine guards, lighting levels, emergency shutdown, work space,
barricades, work permit, work procedures, lock out/ tag out/ work practices.
Welding And Other Hot Works
Hot work permit, work procedure, work practices, equipment & tools,
warning sign, ventilation, hot work protective gadgets.
Scaffolding, Cappers, And Fall Protection
Warning sign, walkways, ladders, stairs, bracing's, handrails, supports,
safety net, work procedures, work permit.
Rigging, Cranes, Material Handling
Work procedures, work permit, work practices, slings, chains block,
barricades, work space, warning sign, storage methods, handling methods,
operators.
Others (including Environmental and Health)
Noise pollution, dust pollution, traffic sign, sanitary facilities, hygiene
practices, waste management, hazardous material labeling, first aid facilities,
other applicable items not included in above list.
JOB SAFETY ANALYSIS
Pre-Task analysis shall be undertaken for jobs with high risk nature. Risks and hazard shall
be identified and work procedure shall be developed to minimize if not to totally eliminate
such risks and hazards.
A. Work Execution Procedure
The work procedure is a documented step by step or sequencing of various tasks to
guide the employees to perform and complete a particular activity.
B. The work permit
C. The work Permit provide rules and practices to guide employees safe behavior or action
for critical tasks that have high risk potential.
D. The following work activities shall or might require work procedure and work permits:
• Hot works
• Excavation, trenching and shoring work
• Works on confined spaces or restricted areas
• Utility Tie-ins or disconnection's
• Works that involve hazardous materials/Compound
• Scaffolding erection works
• Heavy lighting and rigging works
• Start-up and commissioning works
For projects which requires Job Safety Analysis, HIRARC (Hazard Identification, Risk
Assessment and Risk Control) will be changed into JSA format
P
S
NO SMOKING
FIRE PROHIBITED
PASS PROHIBITED
PASS PROHIBITED
FIRIE EXTINGUISHIER
EQUIPMENT
NO PARKING
NO STOP
DO NOT OPEN THE PANEL
OBLIGED TO WEAR SAFETY GLASS
OBLIGED TO WEAR HELMET
OBLIGED TO WEAR GAUNTLET
OBLIGET TO WEAR SAFETY BELT
OBLIGED TO WEAR SAFETY
SHOES
OBLIGED TO WEAR
MASKER
OBLIGED TO WEAR EARMUFF
OBLIGED TO WEAR
WLDING HELMET
DANGER PATH
DANGER PATH OF TOWER
CRANE
FLAMMABLE
HIGH VOLTAGE
MEDICATION CLINIC
[FIRE/BURNING]
DIRECTION
MUST
ER
AREA
SAFE AREA FOR EMERGENCY
CONDITION
BE CAREFULLY
HSE SIGNED
CONSTRUCTION PLANNING
HSE APPLICATION ON SITE
CONSTRUCTION PLANNING
SITE INSPECTION
SAFETY & HEALTH WEEKLY
MEETING SAFETY MORNING
MEETING
HSE APPLICATION ON SITE
CONSTRUCTION PLANNING
FIRE FIGHTING TRAINING
HSE APPLICATION ON SITE
CONSTRUCTION PLANNING
HSE APPLICATION ON SITE
CONSTRUCTION PLANNING
HSE SIGNS
CONSTRUCTION PLANNING
RAILING FOR PERIMETER AREA
SAFETY NET
SAFETY NET
RAILING FOR STAIR
HSE APPLICATION ON SITE
CONSTRUCTION PLANNING

Más contenido relacionado

Similar a PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx

Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
Ali Khidr
 
ajay jain FINAL REPORT
ajay jain FINAL REPORTajay jain FINAL REPORT
ajay jain FINAL REPORT
AJAY JAIN
 
CV of Prabu-HSE Engineer.DOCX
CV of Prabu-HSE Engineer.DOCXCV of Prabu-HSE Engineer.DOCX
CV of Prabu-HSE Engineer.DOCX
Prabu Thangavel
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
Ali Khidr
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015
Arun Jothilingam
 

Similar a PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx (20)

Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
Nino Balmes resume (1) (2)
Nino Balmes resume (1) (2)Nino Balmes resume (1) (2)
Nino Balmes resume (1) (2)
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
 
ajay jain FINAL REPORT
ajay jain FINAL REPORTajay jain FINAL REPORT
ajay jain FINAL REPORT
 
CV of Prabu-HSE Engineer.DOCX
CV of Prabu-HSE Engineer.DOCXCV of Prabu-HSE Engineer.DOCX
CV of Prabu-HSE Engineer.DOCX
 
2017 Safety Professional
2017 Safety Professional2017 Safety Professional
2017 Safety Professional
 
2017 Safety Professional
2017 Safety Professional2017 Safety Professional
2017 Safety Professional
 
Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)Ms pipe internal cleaning (2)
Ms pipe internal cleaning (2)
 
Khaled CV
Khaled CVKhaled CV
Khaled CV
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
 
Safety health and environment
Safety health and environmentSafety health and environment
Safety health and environment
 
VJ Presentation 3 Oct 2022.pptx
VJ Presentation 3 Oct 2022.pptxVJ Presentation 3 Oct 2022.pptx
VJ Presentation 3 Oct 2022.pptx
 
vijay cv
vijay cvvijay cv
vijay cv
 
CV@JOMY NEW
CV@JOMY NEWCV@JOMY NEW
CV@JOMY NEW
 
Resume Tahir
Resume TahirResume Tahir
Resume Tahir
 
PROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLAN
PROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLANPROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLAN
PROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLAN
 
Giridhar
GiridharGiridhar
Giridhar
 
General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015General_ENTRION_Presentation_December2015
General_ENTRION_Presentation_December2015
 
SANTHOSH KUMAR UP RCV
SANTHOSH KUMAR UP RCVSANTHOSH KUMAR UP RCV
SANTHOSH KUMAR UP RCV
 
Mira Abdelaziz resume
Mira Abdelaziz resumeMira Abdelaziz resume
Mira Abdelaziz resume
 

Último

Simple Conference Style Presentation by Slidesgo.pptx
Simple Conference Style Presentation by Slidesgo.pptxSimple Conference Style Presentation by Slidesgo.pptx
Simple Conference Style Presentation by Slidesgo.pptx
balqisyamutia
 
Top profile Call Girls In Meerut [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Meerut [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Meerut [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Meerut [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
yhavx
 
poliovirus-190801072449. pptx
poliovirus-190801072449.            pptxpoliovirus-190801072449.            pptx
poliovirus-190801072449. pptx
ssuser0ad194
 
Top profile Call Girls In eluru [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In eluru [ 7014168258 ] Call Me For Genuine Models We ...Top profile Call Girls In eluru [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In eluru [ 7014168258 ] Call Me For Genuine Models We ...
gajnagarg
 
Q4-Trends-Networks-Module-3.pdfqquater days sheets123456789
Q4-Trends-Networks-Module-3.pdfqquater days sheets123456789Q4-Trends-Networks-Module-3.pdfqquater days sheets123456789
Q4-Trends-Networks-Module-3.pdfqquater days sheets123456789
CristineGraceAcuyan
 
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
instagramfab782445
 
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
wpkuukw
 
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
awasv46j
 
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
eqaqen
 

Último (20)

Simple Conference Style Presentation by Slidesgo.pptx
Simple Conference Style Presentation by Slidesgo.pptxSimple Conference Style Presentation by Slidesgo.pptx
Simple Conference Style Presentation by Slidesgo.pptx
 
The hottest UI and UX Design Trends 2024
The hottest UI and UX Design Trends 2024The hottest UI and UX Design Trends 2024
The hottest UI and UX Design Trends 2024
 
Independent Escorts Goregaon WhatsApp +91-9930687706, Best Service
Independent Escorts Goregaon WhatsApp +91-9930687706, Best ServiceIndependent Escorts Goregaon WhatsApp +91-9930687706, Best Service
Independent Escorts Goregaon WhatsApp +91-9930687706, Best Service
 
Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...
Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...
Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...
 
Top profile Call Girls In Meerut [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Meerut [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Meerut [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Meerut [ 7014168258 ] Call Me For Genuine Models We...
 
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
 
Raebareli Girl Whatsapp Number 📞 8617370543 | Girls Number for Friendship
Raebareli Girl Whatsapp Number 📞 8617370543 | Girls Number for FriendshipRaebareli Girl Whatsapp Number 📞 8617370543 | Girls Number for Friendship
Raebareli Girl Whatsapp Number 📞 8617370543 | Girls Number for Friendship
 
poliovirus-190801072449. pptx
poliovirus-190801072449.            pptxpoliovirus-190801072449.            pptx
poliovirus-190801072449. pptx
 
Just Call Vip call girls Kasganj Escorts ☎️8617370543 Two shot with one girl ...
Just Call Vip call girls Kasganj Escorts ☎️8617370543 Two shot with one girl ...Just Call Vip call girls Kasganj Escorts ☎️8617370543 Two shot with one girl ...
Just Call Vip call girls Kasganj Escorts ☎️8617370543 Two shot with one girl ...
 
Top profile Call Girls In eluru [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In eluru [ 7014168258 ] Call Me For Genuine Models We ...Top profile Call Girls In eluru [ 7014168258 ] Call Me For Genuine Models We ...
Top profile Call Girls In eluru [ 7014168258 ] Call Me For Genuine Models We ...
 
Q4-Trends-Networks-Module-3.pdfqquater days sheets123456789
Q4-Trends-Networks-Module-3.pdfqquater days sheets123456789Q4-Trends-Networks-Module-3.pdfqquater days sheets123456789
Q4-Trends-Networks-Module-3.pdfqquater days sheets123456789
 
How to Create a Productive Workspace Trends and Tips.pdf
How to Create a Productive Workspace Trends and Tips.pdfHow to Create a Productive Workspace Trends and Tips.pdf
How to Create a Productive Workspace Trends and Tips.pdf
 
Pondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime Pondicherry
Pondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime PondicherryPondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime Pondicherry
Pondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime Pondicherry
 
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
 
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
Abortion pill for sale in Muscat (+918761049707)) Get Cytotec Cash on deliver...
 
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
一比一定(购)滑铁卢大学毕业证(UW毕业证)成绩单学位证
 
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
一比一原版(WLU毕业证)罗瑞尔大学毕业证成绩单留信学历认证原版一模一样
 
Q4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentationQ4-W4-SCIENCE-5 power point presentation
Q4-W4-SCIENCE-5 power point presentation
 
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
一比一定(购)西悉尼大学毕业证(WSU毕业证)成绩单学位证
 
Sweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptxSweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptx
 

PRESENTATION- APS GEMPOL EXPANSION PROJECT.pptx

  • 2. A.1. PROJECT INFORMATION 1. PROJECT NAME : PT. LYONDELLBASELL 2. PROJECT LOCATION : GEMPOL PASURUAN - JAWA TIMUR 3. OWNER : APS GEMPOL EXPANSION PROJECT 4. SCOPE OF WORK : Civil, Structure & Architecture 6. CONSTRUCTION PERIOD : (5 Calendar Months) CONSTRUCTION PLANNING
  • 5. 12/18/2022 CONSTRUCTION PLANNING SEQUENCE & PLANNING SCHEDULE A F IL L IN G L IN E (W E E K 0 1 - W E E K 2 1 ) B D E B A G G IN G & P R E M IX IN G (W E E K 0 3 -W E E K 2 0 ) C C O M P R E S S O R (W E E K 0 4 - W E E K 1 2 ) D M V & L V (W E E K 0 5 - W E E K 1 5 ) E T R A N S F O R M E R (W E E K 0 6 - W E E K 2 1 ) F C O O L IN G T O W E R (W E E K 0 8 W E E K 1 7 ) G P A N T R Y R O O M (W E E K 0 9 - W E E K 1 8 ) H F U M E (W E E K 1 0 - W E E K 1 7 ) I F U R N A C E (W E E K 1 0 - W E E K 2 2 )
  • 6. 12/18/2022 CONSTRUCTION PLANNING DEMOLISH EXISTING AREA (EQUIPMENT USED) EXCAVATOR CRAWLER WITH RUBBER TIRE DUMP TRUCK AREA DEMOLISH
  • 7. CONSTRUCTION PLANNING SEQUENCE OF WORK FOR STEEL STRUCTURE
  • 8. YES NO YES NO DAILY INSPECTION NOTICE VERIFY,JOINT INSPECTION WITH OWNER FINISH PRODUCT A B C VERIFY INTERNAL INSPECTION GENERAL QUALITY CONTROL FLOWCHART FOR CONSTRUCTION WORKS (2) CONSTRUCTION PLANNING
  • 9. YES NO YES NO QUALITY CONTROL RECEIVING MATERIAL PLAN QUALITY CONTROL DEPARTMENT 1. INSPECTION & TEST PLAN 2. QC SHEET FORM WAREHOUSE APPROVED MATERIAL START FINISH ENGINEERING DEPARTMENT 1. APPROVAL MATERIAL 2. SAMPLE PROCUREMENT/PURCHASING DEPARTMENT PURCHASING ORDER (PO) SUPPLIER MATERIAL PRODUCTION DEPARTMENT SURAT PERMINTAAN PENGADAAN BARANG (SPP) PROJECT MANAGER 1. FOR CONSTRUCTION DWG 2. TECHNICAL SPECIFICATION 3. GENERAL NOTES VERIFY MATERIAL RECEIVING INSPECTION VERIFY INDEPENDENT LABORATORIU M CONSTRUCTION PLANNING
  • 10. b. Execution YES NO YES NO OK QUALITY CONTROL INSPECTION FOR CONCRETING GROUND SLAB PLAN (1) QUALITY CONTROL DEPARTMENT VERIFY INTERNAL INSPECTION INSTALL SCAFFOLDING & FORM WORK PRODUCTION DEPARTMENT START ENGINEERING DEPARTMENT 1. DETAIL DWG/SHOP DWG 2. WORK PROCEDURES 3. WORK INSTRUCTIONS PROCUREMENT DEPARTMENT / E N T DEPARTMENT 1. INSPECTION AND TEST PLAN 2. QC SHEET FORM SUPPLY EQUIPMENT, TOOLS AND MATERIAL PREPARATION FOR MAN POWER, EQUIPMENT, MATERIAL AND TIME SCHEDULE PROJECT MANAGER 1. FOR CONSTRUCTION DWG 2. TECHNICAL SPECIFICATION 3. GENERAL NOTES VERIFY, MATERIAL RECEIVING & CALIBRATION INSPECTION A B INSTALL REBAR BEAM, SLAB & STARTER BAR C VERIFY INTERNAL INSPECTION a. Preparing CONSTRUCTION PLANNING
  • 11. YES NO YES NO YES QUALITY CONTROL INSPECTION FOR CONCRETING GROUND SLAB PLAN (2) DAILY INSPECTION NOTICE FINISH ORDER CONCRETE TO BATCHING PLANT C VERIFY,JOINT INSPECTION WITH OWNER A B REQUEST FOR HANDLING CONCRETE CONCRETE CONCRETE INSPECTION FOR SLUMP VERIFY INTERNAL INSPECTION INSTALL LEVELING TOP CONCRETE & CLEANING CONSTRUCTION PLANNING
  • 12. b. Execution YES NO OK QUALITY CONTROL INSPECTION FOR CONCRETING COLUMN PLAN (1) QUALITY CONTROL DEPARTMENT SETTING OUT AND MARKING POSITION FOR COLUMN PRODUCTION DEPARTMENT START ENGINEERING DEPARTMENT 1. DETAIL DWG/SHOP DWG 2. WORK PROCEDURES 3. WORK INSTRUCTIONS PROCUREMENT DEPARTMENT / E N T DEPARTMENT 1. INSPECTION AND TEST PLAN 2. QC SHEET FORM SUPPLY EQUIPMENT, TOOLS AND MATERIAL PREPARATION FOR MAN POWER, EQUIPMENT, MATERIAL AND TIME SCHEDULE PROJECT MANAGER 1. FOR CONSTRUCTION DWG 2. TECHNICAL SPECIFICATION 3. GENERAL NOTES VERIFY, MATERIAL RECEIVING & CALIBRATION INSPECTION A B REQUEST FOR HANDLING CONCRETE C VERIFY INTERNAL INSPECTION a. Preparing INSTALL REBAR CLEANING CONSTRUCTION PLANNING
  • 13. YES NO YES NO YES NO YES NO QUALITY CONTROL INSPECTION FOR CONCRETING COLUMN PLAN (2) VERIFY,JOINT INSPECTION WITH OWNER FINISH ORDER CONCRETE TO BATCHING PLANT INSTALL FORMWORK VERIFY,JOINT INSPECTION WITH OWNER A B C CONCRETE CONCRETE INSPECTION FOR SLUMP DAILY INSPECTION NOTICE VERIFY INTERNAL INSPECTION DAILY INSPECTION NOTICE CONSTRUCTION PLANNING
  • 14. I. Making Safety Plan • Forming a HSE project organization, • List of equipment that need special handling, • Hazard identification and prevention, • HSE site plan, • Hygiene program and brief, clean, neatly, diligent, & treatment. II. Prepare HSE supporting equipment and personal protective equipment • Fire extinguishers, • HSE signs, • Safety instruction, • Supporting tools: temporary toilet, urinoir, & water pump equipment, • Helmet, safety belt, mask , safety shoes, safety belt, & medicine box. III. Cooperation with Hospital, Clinic and insure Labour to Jamsostek (Labour insurance) CONSTRUCTION PLANNING B.6. HSE PROGRAM
  • 15.
  • 16.
  • 17. Safety, Security & Housekeeping Program Project Start Planning Organizing Controlling Clean, Organize, Healthy & Safe -Project Safety Objective -Risk Assessment and Risk Management -Site Safety Plan -Safety, Security, and Environment budget -Forming safety organization and safety committee -Standard and procedure of safe work practice -Inspection Plan -Audit CONSTRUCTION PLANNING
  • 19. Project Organization PROJECT OPERATION GENERAL MANAGER PROJECT MANAGER ENGINEERING MANAGER CONSTRUCTION MANAGER ADMINISTRATION G / A HSE MANAGER HSE COMMITTEE Chairman : Safety Officer Member : PM, Eng.Mng, Const. Mgr Sub Member : Sub Contractor PM SAFETY ENGINEER SAFETY INSPECTOR SUPERVISOR CIVIL / FINISHING SUPERVISOR M / E / P SURVEYOR MECHANIC & OPERATOR CONSTRUCTION PLANNING
  • 20. EHS MEETING PROGRAM Description Of Meeting Schedule Chairman & Attendants 1. Morning Gathering Daily Chaired by HSE Officer to be attended by safety Supervisors, and field workers. 2. Tool Box Meeting Daily Chaired by construction Supervisors assisted HSE supervisor to be attended by crafts foremen personnel. 3. Security Meeting Daily Chaired by HSE officer, to be attended by security personnel. 4. Supervisors Progress and Safety Meeting Weekly Chaired by HSE Manager/ Officer or construction manager, to be attended by HSE supervisors, construction engineers and supervisors. 5. Progress and Safety Meeting Monthly Chaired by Project Manager and or HSE Manager to be attended by HSE officers, construction Engineers 6. Meeting for specific accident/ incident Decided by HSE Manager or Officer Chaired by HSE Manager or Office to ber attended by concerned individuals.
  • 21. GENERAL INSPECTION PROGRAM HSE Particulars General Inspection Checklist House Keeping And fire Protection Waste disposal, cleaning methods, access ways, material/ tools/ equipment storage, extinguisher, alarm, non smoking areas, response instructions, emergency exits, sign boards. Excavation/ Trenches Shoring, Civil Works Barricades, warning sign in place, access ways, work procedures, work practices, work permits. Personal Protective Gadget Safety helmet, hand gloves, safety footwear, eye protection, hearing protection, respirator, safety belt. Confined Space Entry, Restricted Area, Hazardous Work, Lock out/ Tag out Work permits, Barricades, warning, sign in place, access ways, ventilation, work procedures, work practices, lock out and tag out sign Electrical Works Breakers switches, fuses, grounding, lock out/ tag out, plugs, warning sign, distribution boards, equipment & tools, work procedures, work permit. Mechanical Works, Equipment Installation Machine guards, lighting levels, emergency shutdown, work space, barricades, work permit, work procedures, lock out/ tag out/ work practices. Welding And Other Hot Works Hot work permit, work procedure, work practices, equipment & tools, warning sign, ventilation, hot work protective gadgets. Scaffolding, Cappers, And Fall Protection Warning sign, walkways, ladders, stairs, bracing's, handrails, supports, safety net, work procedures, work permit. Rigging, Cranes, Material Handling Work procedures, work permit, work practices, slings, chains block, barricades, work space, warning sign, storage methods, handling methods, operators. Others (including Environmental and Health) Noise pollution, dust pollution, traffic sign, sanitary facilities, hygiene practices, waste management, hazardous material labeling, first aid facilities, other applicable items not included in above list.
  • 22. JOB SAFETY ANALYSIS Pre-Task analysis shall be undertaken for jobs with high risk nature. Risks and hazard shall be identified and work procedure shall be developed to minimize if not to totally eliminate such risks and hazards. A. Work Execution Procedure The work procedure is a documented step by step or sequencing of various tasks to guide the employees to perform and complete a particular activity. B. The work permit C. The work Permit provide rules and practices to guide employees safe behavior or action for critical tasks that have high risk potential. D. The following work activities shall or might require work procedure and work permits: • Hot works • Excavation, trenching and shoring work • Works on confined spaces or restricted areas • Utility Tie-ins or disconnection's • Works that involve hazardous materials/Compound • Scaffolding erection works • Heavy lighting and rigging works • Start-up and commissioning works For projects which requires Job Safety Analysis, HIRARC (Hazard Identification, Risk Assessment and Risk Control) will be changed into JSA format
  • 23. P S NO SMOKING FIRE PROHIBITED PASS PROHIBITED PASS PROHIBITED FIRIE EXTINGUISHIER EQUIPMENT NO PARKING NO STOP DO NOT OPEN THE PANEL OBLIGED TO WEAR SAFETY GLASS OBLIGED TO WEAR HELMET OBLIGED TO WEAR GAUNTLET OBLIGET TO WEAR SAFETY BELT OBLIGED TO WEAR SAFETY SHOES OBLIGED TO WEAR MASKER OBLIGED TO WEAR EARMUFF OBLIGED TO WEAR WLDING HELMET DANGER PATH DANGER PATH OF TOWER CRANE FLAMMABLE HIGH VOLTAGE MEDICATION CLINIC [FIRE/BURNING] DIRECTION MUST ER AREA SAFE AREA FOR EMERGENCY CONDITION BE CAREFULLY HSE SIGNED CONSTRUCTION PLANNING
  • 24. HSE APPLICATION ON SITE CONSTRUCTION PLANNING
  • 25. SITE INSPECTION SAFETY & HEALTH WEEKLY MEETING SAFETY MORNING MEETING HSE APPLICATION ON SITE CONSTRUCTION PLANNING
  • 26. FIRE FIGHTING TRAINING HSE APPLICATION ON SITE CONSTRUCTION PLANNING