SlideShare una empresa de Scribd logo
1 de 74
RESULT-BASED 
MONITORING AND EVALUATION 
(24 – 26 January 2012) 
By: Bilal Naqeeb
2 
OVERALL OBJECTIVES 
To create a conceptual clarity in participants 
on result-based Monitoring and Evaluation 
To improve the skills of the participants to 
carry out planning, monitoring and reporting 
of programmes
3 
SPECIFIC OUTPUTS 
• Increased knowledge on concepts of Result-based 
Management 
• Improved understanding on logframe and Result-based LFA 
approaches 
• Enhanced skills to determine programme results and 
develop appropriate indicators for monitoring, evaluation 
and reporting proposes 
• Increased understanding of result-based reporting and skills 
to report on results as per predefined formats
4 
AGENDA – DAY I 
S.No. Session Time 
DAY-I: 
1. Introduction and Objectives 1145 – 1200 
2. Session 1.1: Basic Concepts 
- Result-based Management 
- Project Cycle Management 
1200 – 1315 
3. Lunch 1315 – 1400 
4. Session 1.2: Monitoring and Evaluation, 
Use of Logframe and its types 
1400 – 1530 
5. Tea 1530 – 1545 
6. Session 1.3: Results, Result Chain Logic 1545 – 1700
5 
AGENDA – DAY II 
S.No. Session Time 
DAY-II: 
7. Review of Day-I 0900 – 0915 
8. Session 2.1: Orientation on Performance 
Indicators Indicators (Process, Output, 
Outcome, Impact) 
- Indicators Development 
0915 – 1130 
9. Tea 1130 – 1145 
10. Session 2.2 Performance Management 
Framework (Data Collection, Methods, 
Frequency) 
1145 – 1315 
11. Lunch 1315 – 1400 
12. Session 2.3 Risk and Assumptions & 
Stakeholders Analysis 
1400 – 1530 
13. Tea 1530 – 1545 
14. Session 2.4 Result-based Work Plans 1545 – 1700
6 
AGENDA – DAY III 
S.No. Session Time 
DAY-III: 
15. Review of Day-II 0900 – 0915 
16. Session 3.1 Result-based Reporting 0915 – 1130 
17. Tea 1130 – 1145 
18. Session 3.1 Result-base Reporting 
(Continued) 
1130 – 1315 
19. Lunch 1315 – 1400 
20. Session 3.2 Institutional Arrangement for 
M&E 
1400 – 1500 
21. Wrap up 1500 – 1530
Session I.I: 
Basic Concepts of Project Cycle and 
Result-based Management
Project Cycle 
• The project cycle visually reminds us that there 
is a logical sequence to be followed in project 
planning. 
• 
• There are numerous diagrammatic 
representations of the project planning cycle. A 
summary would present a sequence of 
identification, implementation and information 
management (or project control).
Project Design 
and Planning 
Continuous 
Performance 
Monitoring and 
Reporting 
Annual 
Performance 
Appraisal 
Project 
Adjustment 
Situational 
Analysis 
Project Cycle
Key M&E Activities in Project Cycle
11 
Exercise: 
Reorganize the planning stages of the community 
development project shown below into a more logical 
sequence
Result-based Management 
• RBM is an approach to project/programme 
management based on clearly defined results, and 
the methodologies and tools to measure and achieve 
them. 
• RBM supports better performance and greater 
accountability by applying a clear, logical framework 
to plan, manage and measure an intervention with a 
focus on the results you want to achieve.
Characteristics of Result-based Project 
Cycle Management 
Participatory 
Approach 
Logicality 
Consistency 
Transparency 
Problem- 
Solving
Session 1.2: 
Use of LFA for Monitoring and 
Evaluation
15 
Monitoring 
1. It is the continuous and periodic 
assessment of the physical 
implementation of a project/programme 
2. To assess if inputs have been delivered 
and activities carried out according to 
plans, and if the project has achieved its 
outputs
16 
Evaluation 
• Evaluation provides a “thumbs up” or thumbs 
down” judgment of the project/programme. 
• Evaluation is a systematic and objective assessment 
of the design, implementation and results of an on-going 
or completed project or programme. 
• The aim of the evaluation is to determine the 
efficiency, effectiveness, impact, sustainability and 
relevance of the project.
17 
Participatory M&E 
Participatory Monitoring and Evaluation is a 
democratic process for examining the values, 
progress, constraints and achievements of 
projects and programmes by all relevant 
stakeholders.
18 
Difference 
Participatory Monitoring 
&Evaluation 
-Participant focus and 
ownership 
-Broad range of stakeholder 
participation 
-Focus on learning 
-Flexible design 
-Rapid appraisal method 
-Outsiders are facilitators 
Traditional Monitoring 
&Evaluation 
-Funder focus and 
ownership 
-Stakeholders often don’t 
participate 
-Focus on accountability 
-Formal methods 
-Outsiders are evaluators
19 
Participatory M&E 
• The Logical Framework Approach (LFA) is a 
management tool mainly used in the design, 
monitoring and evaluation of international 
development projects. It is also widely known as 
Goal Oriented Project Planning (GOPP) or 
Objectives Oriented Project Planning (OOPP). 
• It is useful to distinguish between the two terms: 
the Logical Framework Approach (LFA) and 
Logical Framework (LF or Logframe). They are 
sometimes confused. The Logical Framework 
Approach is a project design methodology, the 
LogFrame is a document.
20 
Result-based LFA 
The Results Based LFA is a document used for 
planning and review. 
It contains information about what an organization 
hopes to achieve in the short, medium, and long 
term, how that achievement will be measured, and 
some key assumptions that the organization is 
making about the conditions necessary for its 
success.
21 
European Logframe 
Hierarchy of 
Objectives 
Objectively Verifiable 
Indicators 
Means of 
Verifications 
Risks/Assumptions 
Goal: Indicators 
Project Purpose: Indicators: 
Outputs: Indicators 
Activities Resource/Inputs: Budget
22 
Results-Based LFA Format 
NARRATIVE 
SUMMARY 
EXPECTED RESULTS PERFORMANCE 
MEASUREMENT 
ASSUMPTIONS/RISKS 
AND INDICATORS 
Goal (link to 
Country Program 
Goal): 
Impact: Performance 
Indicators: 
Assumptions: 
Risk Indicators: 
(High, Medium, Low) 
Purpose: Outcomes: Performance 
Indicators: 
Assumptions: 
Risk Indicators: (High, 
Medium, Low) 
Inputs/Resources: Outputs: Performance 
Indicators: 
Assumptions: 
Risk Indicators: (High, 
Medium, Low)
23 
What is a Result? 
• A result is a describable or measurable 
development change resulting from a cause and 
effect relationship. 
Development results involve changes in: 
• power relations, 
• how resources are distributed, 
• improvements in the well-being of a local 
population, or organization, 
• changes in attitudes and behaviours of people, 
among other things.
24 
What is a Good Result? 
• Results should be G-SMART 
– Gender-inclusive 
– Specific 
– Measurable 
– Achievable 
– Relevant 
– Time-bound 
• A result is NOT a completed activity, but … 
completed activities should lead to results
25 
Key Results Words 
• Improved 
• Increased 
• Strengthened 
• Reduced 
• Enhanced 
• HINT: any change that can be stated in terms 
of either quality or quantity
26 
Results Chain 
• These results are linked together into what is 
commonly referred to as a results chain. 
• It is very difficult to contribute to the impact 
without first achieving some intermediate 
steps: the outputs or short-term results and 
outcomes or medium term results.
Results Chain 
27 
ACTIVITY (IES) OUTPUT(S) OUTCOME(S) IMPACT 
Activities: 
Judges and 
More 
Designing and 
lawyers more 
considered 
delivery of 
knowledgeable 
interpretation 
curriculum on human 
about human 
of gender 
rights and potential 
rights and 
equality issues. 
gender biases in 
gender 
Increased new 
hearing cases and 
equality 
legal decisions 
interpreting evidence. 
standards and 
that reflect 
Arrange discussion of 
how to apply 
greater gender 
judges and lawyers 
them. 
equality. 
on issues of human 
rights and gender 
equality in hearing 
cases. 
More 
considered 
interpretation 
of gender 
equality issues. 
Increase in new 
legal decisions 
that reflect 
greater gender 
equality.
Short-term Medium-term Long-term 
28 
Operational vs Developmental Results 
Program / Project Management 
Inputs Activities Outputs Outcomes Impact 
Operational Results: 
The administrative and 
management product 
of an agency, its 
programs or projects 
Developmental Results: 
An actual change in the state of 
human development is the logical 
consequence of a CIDA investment in 
a developing country
29 
Operational vs Developmental Results 
Resources and Activities 
Outputs 
Outputs 
Outputs 
Outputs 
Outputs 
Outcomes 
Outcomes 
Impact
30 
Beneficiary Reach 
Beneficiary Reach is the overarching term that includes all 
individuals and groups or organizations benefiting either directly 
or indirectly from a funded project or programme. 
Direct Beneficiaries are those populations, groups or 
organizations which are within the immediate reach of a 
funded programme or project which are expected to benefit 
at the output and outcome levels. 
Indirect beneficiaries are those populations, groups or 
organizations who will indirectly benefit from the project and 
are outside the immediate reach of a given funded project or 
programme, yet are expected to benefit at the impact level.
31 
RESULT-CHAIN EXERCISES
Session 1.3: 
PERFORMANCE INDCATORS
An indicator is a pointer. It is a number, a 
fact or a perception that measures changes 
in a specific condition over time. Indicators 
are the key in monitoring and evaluation. 
Indicators define the data required to 
compare actual results with planned results 
over time. 
33 
Indicator
34 
What is a Result Indicator? 
• An indicator provides evidence that a result 
has been achieved. 
• An indicator measures progress, by noting 
changes at different points in time. 
• Indicators can be qualitative or quantitative.
Process and Result Indicators 
• Results indicators are used to measure project 
performance 
35 
– Input Indicators 
– Process Indicators 
– Output Indicators 
– Outcome Indicators
36 
Indicators Types 
• Quantitative 
–numbers, statistics, frequency, ratios, 
variances, etc. 
• Qualitative 
– changes in attitudes, behaviours, skills, 
perceptions, quality, level of understanding, 
etc. 
– Both Quantitative and Qualitative (QQTTP)
37 
Program / Project Management 
Resources Reach 
Developmental Results 
Inputs / 
Activities Short-term 
Outputs 
Medium-term 
Outcomes 
Long-term 
Impact 
Partner 
Clients / 
Beneficiaries 
Performance 
Indicators 
Performance 
Indicators 
Performance 
Indicators 
Indicators in Result Chain
38 
Criteria to Select Indicators 
• Validity 
• Reliability 
• Sensitivity 
• Simplicity 
• Utility 
• Affordability 
• Gender-sensitivity
• For each output, outcome and impact statement, 
brainstorm a list of several key indicators 
(qualitative, quantitative, and gender-sensitive). 
• Apply the criteria to narrow the list to 
MAXIMUM two to three indicators per result 
statement. 
• Make sure that baseline information is available 
for each indicator. 
39 
Steps for Indicator Design
40 
Developing Indicators using QQTTP 
• Quantity 
• Quality 
• Target 
• Time 
• Place
41 
Exercise-1: Designing Indicators
Exercise-2: Indicators Development 
42
Session 2.2: 
Performance Management 
Framework
The Performance Management Framework 
44 
Performance 
Framework 
Performance 
Indicators 
Data 
Sources 
Collection 
Methods 
Frequency Responsibilities 
Impact 
Outcomes 1 
2 
Outputs 1.1 
1.2 
2.1 
2.2
• Sources of performance information include 
individual beneficiaries, groups of beneficiaries, 
organizations, partners, documents, etc. 
• Identify data sources for each indicator 
• To ensure reliability, try not to change data 
sources over time 
45 
Performance Data Sources
• Sources of performance information include 
individual beneficiaries, groups of beneficiaries, 
organizations, partners, documents, etc. 
• Identify data sources for each indicator 
• To ensure reliability, try not to change data 
sources over time 
46 
Source of Verification
47 
Performance Data Analysis 
• Compare changes to baseline data. 
• ‘Triangulate’ data by trying to collect similar 
information from different sources. 
• Ensure that data is gender disaggregated so 
that different information about men and 
women is clearly shown.
Roles and Responsibilities for Collecting Performance Data 
48 
• Who will collect the data? 
• Who will analyze the data? 
• Who will prepare the reports? 
• How will the information on performance be 
shared with stakeholders? 
• How will the performance information be 
used to make decisions?
49 
Frequency of Data Collection 
Performance 
Indicators 
Performance 
Indicators 
Performance 
Indicators 
Program/Project 
Management 
Performance review 
in light of 
assumptions made 
about causal links 
between activities, 
outputs, outcomes 
and impact 
Output Outcome Impact 
Continuous 
Self-Assessment 
Annual Project 
Performance Appraisal 
Program Impact 
Evaluation
• Community-designed indicators can be 
measured by communities themselves through 
simple data collection instruments (records, 
meetings, interviews, PRA tools, testimonials, 
self-assessments, etc.). 
• Technical indicators sometimes require that 
questionnaires or surveys be administered by 
specialized researchers. 
50 
Data Collection Methods
51 
Data Collection Techniques 
1. QUESTIONNAIRE 
2. INTERVIEW 
3. OBSERVATION 
4. FOCUSED GROUP DISCUSSION/OTHER PRA 
TECHNIQUES 
5. TALLY METHOD
52 
Sources of Information 
• PRIMARY 
– KEY INFORMANTS 
– ORGANIZATIONS 
– COMMUNITY/RELEVANT STAKEHOLDERS 
– PROJECT BENEFICIARIES 
• SECONDARY 
– JOURNALS/NEWSPAPERS 
– DOCUMENTS AND RECORDS 
– CENSUS REPORTS 
– ANNUAL REPORTS
Exercise: Performance Management 
53 
Framework
Session 2.2: 
RISKS AND ASSUMPTIONS
• Factors that will negatively affect the 
assumptions and that negate the positive 
conditions required to produce results. Risks 
may or may not be within the control of project 
managers. 
• External risks include the development context. 
• Internal risks include such things as changes in 
key project personnel, availability of resources, 
etc. 
55 
What are Risks?
56 
What is Risk Analysis? 
• Risk analysis involved ‘rating’ of assumptions 
based on their likelihood of holding true. 
– Low risk assumptions will probably hold true (little 
threat to project) 
– Medium risk assumptions may or may not hold 
true (some threat to project) 
– High risk assumptions will probably NOT hold true 
(high threat to project)
Identifying Assumptions and Analyzing Risks 
57 
Assumptions Assumptions Assumptions 
Moderate Risk High Risk 
Outputs Outcomes Impact 
Inputs / 
Activities 
Low Risk 
Decreasing Management Control
EXERCISE: Risk Analysis and Mitigation 
58 
Risk Likelihood 
(H/M/L) 
Impact 
(H/M/L) 
Management 
Impact: 
Outcome: 
Output:
59 
EXERCISE: 
STAKEHOLDERS ANALYSIS 
Stakeholders 
Type of 
Effect 
Risk Potential 
Impact 
Likelihood Value PLAN 
Punchayat 
Negative Gender-biased 
approach in 
decision making 
6 6 36 PLAN 
Institutions 
Influential 
(Men/ Women) 
Marginalized or 
Vulnerable 
groups 
(Men / 
Women)
60 
Exercise: Risk Analysis
Session 2.4: 
Result-based Work Plans
Gender Analysis 
– Level of women’s participation (Control, 
Planning, implementation, monitoring) 
– Women’s empowerment 
• Decision making 
• Economic Independence 
• Mobility 
– Ratio of women’s beneficiaries 
11/29/2014 62
Environmental Analysis 
– Determine Environmental objectives (e.g. health 
clinic and environment Awareness) 
– Components leading to environmental effect? 
– What are these effects and their significance? 
– What strategies and specific measures will be 
implemented to alleviate or eliminate the 
negative effects and increase its benefits? 
– How will the project be monitored to ensure the 
effective implementation of these measure? 
11/29/2014 63
64 
Exercise: Work Plan and Budgeting 
Average Targets Target Target Target Total Budget Budget Budget Budget Grand 
Code Results/Activities 
Buduget 
Notes 
Unit Type Unit Cost Q-I Q-II Q-III Q-IV Targets Q-I Q-II Q-III Q-IV Total 
Outcom 
e 1: 
Output 
1: 
1 
2 
3 
Personnel Costs 
Other Direct Costs 
Total of Output 1: 
Output 
2: 
1 
2 
3 
Personnel Costs 
Other Direct Costs 
Total of Output 2: 
Total of Outcome 1: 
5 Capital Costs 
6 Personnel Costs (Admin) 
7 Other Direct Costs (Admin) 
8 5% Contingency Budget 
Grand Total
65 
Salaries and Benefits 
Gross Gross Annual Annual (Entitled) Total 
Monthly Yearly Tax Employer Medical Package 
S. No,. Name DESIGNATION Salary Salary Deduction Cont. PF Allowance (in PKR) 
Staff Salaries 
Output 1 
1 
2 
3 
4 
Total Staff Salaries 
Staff Salaries 
Output 2 
1 
2 
3 
4 
Total Salaries 
Output 2 
Admin Staff 
Salaries 
1 
2 
3 
4 
Total Admin Costs 
Grand Total
66 
Other Direct Costs 
Distribution of costs by initiatives 
S.No. Other Direct Costs Output 1 Output 2 Admin Total 
1 Utility Bills (Electricity / Gas / Water) 
2 Telephone / Mobile 
3 Vehicle Running & Maintenance 
4 Internet Charges 
5 Entertainment 
6 Printing And Stationary 
7 Books And News Paper 
8 Postage And Courier 
9 Repair And Maintenance 
10 Audit Fee (Internal and External) 
11 Misc. / Others 
Grand Total (in USD)
67 
Budget Notes 
S.No. Description of Line Items Cost Days Pax Cost (in PKR) 
1 Consultant/Trainers' Fee 
2 Food and Accommodation 
3 Material 
4 Travel Costs 
5 Communication 
6 Misc. Costs 
Grand Total
Session 3.1: 
Result-based Reporting
69 
Reporting 
• All stakeholders need to be kept informed about 
the project/programme through periodic and 
extra-ordinary reports 
• MER systems have to be designed in such a way 
that they are able to generate appropriate reports 
for the various audiences (e.g. Governing body, 
donors and communities etc.) 
• Users of Reports 
• Communities / CBOs / Local Institutions / Donors
70 
Exercises: Activity and Monitoring 
Reports
Session 3.1: 
INSTITUTIONAL 
ARRANGEMENTS FOR M&E
72 
Functions of M&E Section 
• Guide and oversee the implementation of the 
project’s MER systems and requirements; 
• Ensure consistency in the objectives and indicators 
in the program(s); 
• Prepare and monitor the program’s Performance 
Monitoring Plan (PMP); 
• Spearhead and coordinate the development of 
quarterly reports for the donor, as well as other 
required reports; 
• Coordinate and ensure timely and quality sub-grantee 
reporting;
Functions of M&E Section (Continue) 
• Design and implement MER training programs for 
program sub-grantees; 
• Work with the field staff to develop program 
success stories; 
• Design and implement a system to identify, analyze, 
document and disseminate lessons learned; 
• Work with the Budget program coordinators to 
monitor program implementation; 
• Acquaint programme staff and partners with MER 
tools, strategies and plans; 
• Constantly work to improve MER strategies and 
reporting formats. 
73
THANK YOU!!!

Más contenido relacionado

La actualidad más candente

Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)Vilimaka Foliaki
 
7 M&E: Indicators
7 M&E: Indicators7 M&E: Indicators
7 M&E: IndicatorsTony
 
Monitoring and Evaluation: Lesson 2
Monitoring and Evaluation: Lesson 2Monitoring and Evaluation: Lesson 2
Monitoring and Evaluation: Lesson 2Meshack Lomoywara
 
Monitoring and evaluation frameworks logical framework
Monitoring and evaluation frameworks logical frameworkMonitoring and evaluation frameworks logical framework
Monitoring and evaluation frameworks logical frameworkPreston Healthcare Consulting
 
monitoring and evaluation
monitoring and evaluationmonitoring and evaluation
monitoring and evaluationTarek Sallam
 
Monitoring and evaluation
Monitoring and evaluationMonitoring and evaluation
Monitoring and evaluationMd Rifat Anam
 
Introduction to monitoring and evaluation
Introduction to monitoring and evaluationIntroduction to monitoring and evaluation
Introduction to monitoring and evaluationMeshack Lomoywara
 
Monitoring and Evaluating
Monitoring and EvaluatingMonitoring and Evaluating
Monitoring and EvaluatingGlobalGiving
 
Monotoring and evaluation principles and theories
Monotoring and evaluation  principles and theoriesMonotoring and evaluation  principles and theories
Monotoring and evaluation principles and theoriescommochally
 
Monitoring and Evaluation for Project management.
Monitoring and Evaluation for Project management.Monitoring and Evaluation for Project management.
Monitoring and Evaluation for Project management.Muthuraj K
 
Monitoring And Evaluation Presentation
Monitoring And Evaluation PresentationMonitoring And Evaluation Presentation
Monitoring And Evaluation PresentationEquiGov Institute
 
TTIPEC: Monitoring and Evaluation (Session 2)
TTIPEC: Monitoring and Evaluation (Session 2)TTIPEC: Monitoring and Evaluation (Session 2)
TTIPEC: Monitoring and Evaluation (Session 2)Research to Action
 

La actualidad más candente (20)

Monitoring and Evaluation
Monitoring and EvaluationMonitoring and Evaluation
Monitoring and Evaluation
 
Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)Monitoring and evaluation (Part 1)
Monitoring and evaluation (Part 1)
 
7 M&E: Indicators
7 M&E: Indicators7 M&E: Indicators
7 M&E: Indicators
 
Components of a monitoring and evaluation system
Components of a monitoring and evaluation system  Components of a monitoring and evaluation system
Components of a monitoring and evaluation system
 
Result based management
Result based management Result based management
Result based management
 
Monitoring and Evaluation: Lesson 2
Monitoring and Evaluation: Lesson 2Monitoring and Evaluation: Lesson 2
Monitoring and Evaluation: Lesson 2
 
Monitoring and evaluation frameworks logical framework
Monitoring and evaluation frameworks logical frameworkMonitoring and evaluation frameworks logical framework
Monitoring and evaluation frameworks logical framework
 
Project Monitoring & Evaluation
Project Monitoring & EvaluationProject Monitoring & Evaluation
Project Monitoring & Evaluation
 
monitoring and evaluation
monitoring and evaluationmonitoring and evaluation
monitoring and evaluation
 
Monitoring and evaluation
Monitoring and evaluationMonitoring and evaluation
Monitoring and evaluation
 
Introduction to monitoring and evaluation
Introduction to monitoring and evaluationIntroduction to monitoring and evaluation
Introduction to monitoring and evaluation
 
Monitoring and Evaluating
Monitoring and EvaluatingMonitoring and Evaluating
Monitoring and Evaluating
 
M&E Plan
M&E PlanM&E Plan
M&E Plan
 
RBM and LFA
RBM and LFARBM and LFA
RBM and LFA
 
Monitoring process
Monitoring processMonitoring process
Monitoring process
 
Monotoring and evaluation principles and theories
Monotoring and evaluation  principles and theoriesMonotoring and evaluation  principles and theories
Monotoring and evaluation principles and theories
 
Monitoring and Evaluation for Project management.
Monitoring and Evaluation for Project management.Monitoring and Evaluation for Project management.
Monitoring and Evaluation for Project management.
 
Results based monitoring
Results based monitoringResults based monitoring
Results based monitoring
 
Monitoring And Evaluation Presentation
Monitoring And Evaluation PresentationMonitoring And Evaluation Presentation
Monitoring And Evaluation Presentation
 
TTIPEC: Monitoring and Evaluation (Session 2)
TTIPEC: Monitoring and Evaluation (Session 2)TTIPEC: Monitoring and Evaluation (Session 2)
TTIPEC: Monitoring and Evaluation (Session 2)
 

Similar a Results based planning and management

Monitoring and evaluation1
Monitoring and evaluation1Monitoring and evaluation1
Monitoring and evaluation1PCPD Palestine
 
MEAL ETH11171-draft.pptx
MEAL ETH11171-draft.pptxMEAL ETH11171-draft.pptx
MEAL ETH11171-draft.pptxAbraham Lebeza
 
Almm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acmAlmm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acmAlberto Mico
 
MEAL WORKSHOP ON ETH1224-draft.pptx
MEAL WORKSHOP ON ETH1224-draft.pptxMEAL WORKSHOP ON ETH1224-draft.pptx
MEAL WORKSHOP ON ETH1224-draft.pptxAbraham Lebeza
 
M&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburM&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburDr. Md. Taibur Rahman
 
M3_S5_logframe_KSD_180916.pptx
M3_S5_logframe_KSD_180916.pptxM3_S5_logframe_KSD_180916.pptx
M3_S5_logframe_KSD_180916.pptxbipuait
 
C8 logical framework approach (lfa)
C8 logical framework approach (lfa)C8 logical framework approach (lfa)
C8 logical framework approach (lfa)ocasiconference
 
evaluation of deped proj,prog and activi
evaluation of deped proj,prog and activievaluation of deped proj,prog and activi
evaluation of deped proj,prog and activiMei Miraflor
 
Ten_Steps_Results_Based_MESystem.ppt
Ten_Steps_Results_Based_MESystem.pptTen_Steps_Results_Based_MESystem.ppt
Ten_Steps_Results_Based_MESystem.pptNegussie5
 
Report on overview monitoring and evaluation in Strategic Management_Report p...
Report on overview monitoring and evaluation in Strategic Management_Report p...Report on overview monitoring and evaluation in Strategic Management_Report p...
Report on overview monitoring and evaluation in Strategic Management_Report p...Filo Tubo
 
lecture about project management: Logical Framework.ppt
lecture about project management: Logical Framework.pptlecture about project management: Logical Framework.ppt
lecture about project management: Logical Framework.pptNguyenDanhTai
 
Monitoring and evaluation presentatios
Monitoring and evaluation presentatios Monitoring and evaluation presentatios
Monitoring and evaluation presentatios athanzeer
 

Similar a Results based planning and management (20)

UNIT - I - ppe.pptx
UNIT - I - ppe.pptxUNIT - I - ppe.pptx
UNIT - I - ppe.pptx
 
Project Monitoring and Evaluation (M and E Plan) Notes
Project Monitoring and Evaluation (M and E Plan) NotesProject Monitoring and Evaluation (M and E Plan) Notes
Project Monitoring and Evaluation (M and E Plan) Notes
 
M&E.ppt
M&E.pptM&E.ppt
M&E.ppt
 
Monitoring and evaluation1
Monitoring and evaluation1Monitoring and evaluation1
Monitoring and evaluation1
 
Project management
Project managementProject management
Project management
 
MEAL ETH11171-draft.pptx
MEAL ETH11171-draft.pptxMEAL ETH11171-draft.pptx
MEAL ETH11171-draft.pptx
 
Almm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acmAlmm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acm
 
MEAL WORKSHOP ON ETH1224-draft.pptx
MEAL WORKSHOP ON ETH1224-draft.pptxMEAL WORKSHOP ON ETH1224-draft.pptx
MEAL WORKSHOP ON ETH1224-draft.pptx
 
M&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburM&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taibur
 
Day 1
Day 1Day 1
Day 1
 
M3_S5_logframe_KSD_180916.pptx
M3_S5_logframe_KSD_180916.pptxM3_S5_logframe_KSD_180916.pptx
M3_S5_logframe_KSD_180916.pptx
 
C8 logical framework approach (lfa)
C8 logical framework approach (lfa)C8 logical framework approach (lfa)
C8 logical framework approach (lfa)
 
evaluation of deped proj,prog and activi
evaluation of deped proj,prog and activievaluation of deped proj,prog and activi
evaluation of deped proj,prog and activi
 
Ten_Steps_Results_Based_MESystem.ppt
Ten_Steps_Results_Based_MESystem.pptTen_Steps_Results_Based_MESystem.ppt
Ten_Steps_Results_Based_MESystem.ppt
 
Report on overview monitoring and evaluation in Strategic Management_Report p...
Report on overview monitoring and evaluation in Strategic Management_Report p...Report on overview monitoring and evaluation in Strategic Management_Report p...
Report on overview monitoring and evaluation in Strategic Management_Report p...
 
lecture about project management: Logical Framework.ppt
lecture about project management: Logical Framework.pptlecture about project management: Logical Framework.ppt
lecture about project management: Logical Framework.ppt
 
project m&e
 project m&e project m&e
project m&e
 
Monitoring & Evaluation Framework - Fiinovation
Monitoring & Evaluation Framework - FiinovationMonitoring & Evaluation Framework - Fiinovation
Monitoring & Evaluation Framework - Fiinovation
 
Lfa
LfaLfa
Lfa
 
Monitoring and evaluation presentatios
Monitoring and evaluation presentatios Monitoring and evaluation presentatios
Monitoring and evaluation presentatios
 

Más de Bilal Naqeeb

Glimpses of Pakistan's movement (1849 - 1947)
Glimpses of Pakistan's movement (1849 - 1947)Glimpses of Pakistan's movement (1849 - 1947)
Glimpses of Pakistan's movement (1849 - 1947)Bilal Naqeeb
 
World Happiness Report 2018
World Happiness Report 2018World Happiness Report 2018
World Happiness Report 2018Bilal Naqeeb
 
Universal Declaration of Human Rights (Child-Friendly Version)
Universal Declaration of Human Rights (Child-Friendly Version)Universal Declaration of Human Rights (Child-Friendly Version)
Universal Declaration of Human Rights (Child-Friendly Version)Bilal Naqeeb
 
Sustainable Development Goals (with Urdu Translation)
Sustainable Development Goals (with Urdu Translation)Sustainable Development Goals (with Urdu Translation)
Sustainable Development Goals (with Urdu Translation)Bilal Naqeeb
 
Gold Price History in Pakistan (1947 2017)
Gold Price History in Pakistan (1947   2017)Gold Price History in Pakistan (1947   2017)
Gold Price History in Pakistan (1947 2017)Bilal Naqeeb
 
Pakistan General Elections (1997 - 2013)
Pakistan General Elections (1997 - 2013)Pakistan General Elections (1997 - 2013)
Pakistan General Elections (1997 - 2013)Bilal Naqeeb
 
Chiefs of Army Staff (Pakistan)
Chiefs of Army Staff (Pakistan)Chiefs of Army Staff (Pakistan)
Chiefs of Army Staff (Pakistan)Bilal Naqeeb
 
Prime Ministers of pakistan
Prime Ministers of pakistanPrime Ministers of pakistan
Prime Ministers of pakistanBilal Naqeeb
 
Pakistan Census 2017
Pakistan Census 2017Pakistan Census 2017
Pakistan Census 2017Bilal Naqeeb
 
Illustrations of selected Urdu poetry
Illustrations of selected Urdu poetryIllustrations of selected Urdu poetry
Illustrations of selected Urdu poetryBilal Naqeeb
 
Pakitsan's Governance Timeline (Presidents, Prime Ministers, COAS and CJs)
Pakitsan's Governance Timeline (Presidents, Prime Ministers, COAS and CJs)Pakitsan's Governance Timeline (Presidents, Prime Ministers, COAS and CJs)
Pakitsan's Governance Timeline (Presidents, Prime Ministers, COAS and CJs)Bilal Naqeeb
 
PROMOTING PEACE AND TOLERANCE THROUGH SOCIAL MEDIA
PROMOTING PEACE AND TOLERANCE THROUGH SOCIAL MEDIAPROMOTING PEACE AND TOLERANCE THROUGH SOCIAL MEDIA
PROMOTING PEACE AND TOLERANCE THROUGH SOCIAL MEDIABilal Naqeeb
 
Guide to Gender-Sensitive Indicators
Guide to Gender-Sensitive IndicatorsGuide to Gender-Sensitive Indicators
Guide to Gender-Sensitive IndicatorsBilal Naqeeb
 
Personality types and styles of conflict management
Personality types and styles of conflict managementPersonality types and styles of conflict management
Personality types and styles of conflict managementBilal Naqeeb
 
SPO A Brief History, Compiled by: Bilal Naqeeb
SPO A Brief History, Compiled by: Bilal NaqeebSPO A Brief History, Compiled by: Bilal Naqeeb
SPO A Brief History, Compiled by: Bilal NaqeebBilal Naqeeb
 
Home-based Workers in Lahore, Pakistan
Home-based Workers in Lahore, Pakistan Home-based Workers in Lahore, Pakistan
Home-based Workers in Lahore, Pakistan Bilal Naqeeb
 
100 ways to energise groups: Games to use in workshops, meetings and the comm...
100 ways to energise groups: Games to use in workshops, meetings and the comm...100 ways to energise groups: Games to use in workshops, meetings and the comm...
100 ways to energise groups: Games to use in workshops, meetings and the comm...Bilal Naqeeb
 
Basic listening skills
Basic listening skillsBasic listening skills
Basic listening skillsBilal Naqeeb
 
Social Demand of Development
Social Demand of DevelopmentSocial Demand of Development
Social Demand of DevelopmentBilal Naqeeb
 

Más de Bilal Naqeeb (20)

Glimpses of Pakistan's movement (1849 - 1947)
Glimpses of Pakistan's movement (1849 - 1947)Glimpses of Pakistan's movement (1849 - 1947)
Glimpses of Pakistan's movement (1849 - 1947)
 
World Happiness Report 2018
World Happiness Report 2018World Happiness Report 2018
World Happiness Report 2018
 
Universal Declaration of Human Rights (Child-Friendly Version)
Universal Declaration of Human Rights (Child-Friendly Version)Universal Declaration of Human Rights (Child-Friendly Version)
Universal Declaration of Human Rights (Child-Friendly Version)
 
Sustainable Development Goals (with Urdu Translation)
Sustainable Development Goals (with Urdu Translation)Sustainable Development Goals (with Urdu Translation)
Sustainable Development Goals (with Urdu Translation)
 
Gold Price History in Pakistan (1947 2017)
Gold Price History in Pakistan (1947   2017)Gold Price History in Pakistan (1947   2017)
Gold Price History in Pakistan (1947 2017)
 
Pakistan General Elections (1997 - 2013)
Pakistan General Elections (1997 - 2013)Pakistan General Elections (1997 - 2013)
Pakistan General Elections (1997 - 2013)
 
Chiefs of Army Staff (Pakistan)
Chiefs of Army Staff (Pakistan)Chiefs of Army Staff (Pakistan)
Chiefs of Army Staff (Pakistan)
 
Prime Ministers of pakistan
Prime Ministers of pakistanPrime Ministers of pakistan
Prime Ministers of pakistan
 
Pakistan Census 2017
Pakistan Census 2017Pakistan Census 2017
Pakistan Census 2017
 
Illustrations of selected Urdu poetry
Illustrations of selected Urdu poetryIllustrations of selected Urdu poetry
Illustrations of selected Urdu poetry
 
Pakitsan's Governance Timeline (Presidents, Prime Ministers, COAS and CJs)
Pakitsan's Governance Timeline (Presidents, Prime Ministers, COAS and CJs)Pakitsan's Governance Timeline (Presidents, Prime Ministers, COAS and CJs)
Pakitsan's Governance Timeline (Presidents, Prime Ministers, COAS and CJs)
 
PROMOTING PEACE AND TOLERANCE THROUGH SOCIAL MEDIA
PROMOTING PEACE AND TOLERANCE THROUGH SOCIAL MEDIAPROMOTING PEACE AND TOLERANCE THROUGH SOCIAL MEDIA
PROMOTING PEACE AND TOLERANCE THROUGH SOCIAL MEDIA
 
Guide to Gender-Sensitive Indicators
Guide to Gender-Sensitive IndicatorsGuide to Gender-Sensitive Indicators
Guide to Gender-Sensitive Indicators
 
Mediation skills
Mediation skillsMediation skills
Mediation skills
 
Personality types and styles of conflict management
Personality types and styles of conflict managementPersonality types and styles of conflict management
Personality types and styles of conflict management
 
SPO A Brief History, Compiled by: Bilal Naqeeb
SPO A Brief History, Compiled by: Bilal NaqeebSPO A Brief History, Compiled by: Bilal Naqeeb
SPO A Brief History, Compiled by: Bilal Naqeeb
 
Home-based Workers in Lahore, Pakistan
Home-based Workers in Lahore, Pakistan Home-based Workers in Lahore, Pakistan
Home-based Workers in Lahore, Pakistan
 
100 ways to energise groups: Games to use in workshops, meetings and the comm...
100 ways to energise groups: Games to use in workshops, meetings and the comm...100 ways to energise groups: Games to use in workshops, meetings and the comm...
100 ways to energise groups: Games to use in workshops, meetings and the comm...
 
Basic listening skills
Basic listening skillsBasic listening skills
Basic listening skills
 
Social Demand of Development
Social Demand of DevelopmentSocial Demand of Development
Social Demand of Development
 

Último

The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...tanu pandey
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.Christina Parmionova
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...Hemant Purohit
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28JSchaus & Associates
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...tanu pandey
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...CedZabala
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.Christina Parmionova
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escortsaditipandeya
 

Último (20)

The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
(PRIYA) Call Girls Rajgurunagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
2024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 282024: The FAR, Federal Acquisition Regulations - Part 28
2024: The FAR, Federal Acquisition Regulations - Part 28
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In  Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Rohini ꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
 
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.WIPO magazine issue -1 - 2024 World Intellectual Property organization.
WIPO magazine issue -1 - 2024 World Intellectual Property organization.
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
 

Results based planning and management

  • 1. RESULT-BASED MONITORING AND EVALUATION (24 – 26 January 2012) By: Bilal Naqeeb
  • 2. 2 OVERALL OBJECTIVES To create a conceptual clarity in participants on result-based Monitoring and Evaluation To improve the skills of the participants to carry out planning, monitoring and reporting of programmes
  • 3. 3 SPECIFIC OUTPUTS • Increased knowledge on concepts of Result-based Management • Improved understanding on logframe and Result-based LFA approaches • Enhanced skills to determine programme results and develop appropriate indicators for monitoring, evaluation and reporting proposes • Increased understanding of result-based reporting and skills to report on results as per predefined formats
  • 4. 4 AGENDA – DAY I S.No. Session Time DAY-I: 1. Introduction and Objectives 1145 – 1200 2. Session 1.1: Basic Concepts - Result-based Management - Project Cycle Management 1200 – 1315 3. Lunch 1315 – 1400 4. Session 1.2: Monitoring and Evaluation, Use of Logframe and its types 1400 – 1530 5. Tea 1530 – 1545 6. Session 1.3: Results, Result Chain Logic 1545 – 1700
  • 5. 5 AGENDA – DAY II S.No. Session Time DAY-II: 7. Review of Day-I 0900 – 0915 8. Session 2.1: Orientation on Performance Indicators Indicators (Process, Output, Outcome, Impact) - Indicators Development 0915 – 1130 9. Tea 1130 – 1145 10. Session 2.2 Performance Management Framework (Data Collection, Methods, Frequency) 1145 – 1315 11. Lunch 1315 – 1400 12. Session 2.3 Risk and Assumptions & Stakeholders Analysis 1400 – 1530 13. Tea 1530 – 1545 14. Session 2.4 Result-based Work Plans 1545 – 1700
  • 6. 6 AGENDA – DAY III S.No. Session Time DAY-III: 15. Review of Day-II 0900 – 0915 16. Session 3.1 Result-based Reporting 0915 – 1130 17. Tea 1130 – 1145 18. Session 3.1 Result-base Reporting (Continued) 1130 – 1315 19. Lunch 1315 – 1400 20. Session 3.2 Institutional Arrangement for M&E 1400 – 1500 21. Wrap up 1500 – 1530
  • 7. Session I.I: Basic Concepts of Project Cycle and Result-based Management
  • 8. Project Cycle • The project cycle visually reminds us that there is a logical sequence to be followed in project planning. • • There are numerous diagrammatic representations of the project planning cycle. A summary would present a sequence of identification, implementation and information management (or project control).
  • 9. Project Design and Planning Continuous Performance Monitoring and Reporting Annual Performance Appraisal Project Adjustment Situational Analysis Project Cycle
  • 10. Key M&E Activities in Project Cycle
  • 11. 11 Exercise: Reorganize the planning stages of the community development project shown below into a more logical sequence
  • 12. Result-based Management • RBM is an approach to project/programme management based on clearly defined results, and the methodologies and tools to measure and achieve them. • RBM supports better performance and greater accountability by applying a clear, logical framework to plan, manage and measure an intervention with a focus on the results you want to achieve.
  • 13. Characteristics of Result-based Project Cycle Management Participatory Approach Logicality Consistency Transparency Problem- Solving
  • 14. Session 1.2: Use of LFA for Monitoring and Evaluation
  • 15. 15 Monitoring 1. It is the continuous and periodic assessment of the physical implementation of a project/programme 2. To assess if inputs have been delivered and activities carried out according to plans, and if the project has achieved its outputs
  • 16. 16 Evaluation • Evaluation provides a “thumbs up” or thumbs down” judgment of the project/programme. • Evaluation is a systematic and objective assessment of the design, implementation and results of an on-going or completed project or programme. • The aim of the evaluation is to determine the efficiency, effectiveness, impact, sustainability and relevance of the project.
  • 17. 17 Participatory M&E Participatory Monitoring and Evaluation is a democratic process for examining the values, progress, constraints and achievements of projects and programmes by all relevant stakeholders.
  • 18. 18 Difference Participatory Monitoring &Evaluation -Participant focus and ownership -Broad range of stakeholder participation -Focus on learning -Flexible design -Rapid appraisal method -Outsiders are facilitators Traditional Monitoring &Evaluation -Funder focus and ownership -Stakeholders often don’t participate -Focus on accountability -Formal methods -Outsiders are evaluators
  • 19. 19 Participatory M&E • The Logical Framework Approach (LFA) is a management tool mainly used in the design, monitoring and evaluation of international development projects. It is also widely known as Goal Oriented Project Planning (GOPP) or Objectives Oriented Project Planning (OOPP). • It is useful to distinguish between the two terms: the Logical Framework Approach (LFA) and Logical Framework (LF or Logframe). They are sometimes confused. The Logical Framework Approach is a project design methodology, the LogFrame is a document.
  • 20. 20 Result-based LFA The Results Based LFA is a document used for planning and review. It contains information about what an organization hopes to achieve in the short, medium, and long term, how that achievement will be measured, and some key assumptions that the organization is making about the conditions necessary for its success.
  • 21. 21 European Logframe Hierarchy of Objectives Objectively Verifiable Indicators Means of Verifications Risks/Assumptions Goal: Indicators Project Purpose: Indicators: Outputs: Indicators Activities Resource/Inputs: Budget
  • 22. 22 Results-Based LFA Format NARRATIVE SUMMARY EXPECTED RESULTS PERFORMANCE MEASUREMENT ASSUMPTIONS/RISKS AND INDICATORS Goal (link to Country Program Goal): Impact: Performance Indicators: Assumptions: Risk Indicators: (High, Medium, Low) Purpose: Outcomes: Performance Indicators: Assumptions: Risk Indicators: (High, Medium, Low) Inputs/Resources: Outputs: Performance Indicators: Assumptions: Risk Indicators: (High, Medium, Low)
  • 23. 23 What is a Result? • A result is a describable or measurable development change resulting from a cause and effect relationship. Development results involve changes in: • power relations, • how resources are distributed, • improvements in the well-being of a local population, or organization, • changes in attitudes and behaviours of people, among other things.
  • 24. 24 What is a Good Result? • Results should be G-SMART – Gender-inclusive – Specific – Measurable – Achievable – Relevant – Time-bound • A result is NOT a completed activity, but … completed activities should lead to results
  • 25. 25 Key Results Words • Improved • Increased • Strengthened • Reduced • Enhanced • HINT: any change that can be stated in terms of either quality or quantity
  • 26. 26 Results Chain • These results are linked together into what is commonly referred to as a results chain. • It is very difficult to contribute to the impact without first achieving some intermediate steps: the outputs or short-term results and outcomes or medium term results.
  • 27. Results Chain 27 ACTIVITY (IES) OUTPUT(S) OUTCOME(S) IMPACT Activities: Judges and More Designing and lawyers more considered delivery of knowledgeable interpretation curriculum on human about human of gender rights and potential rights and equality issues. gender biases in gender Increased new hearing cases and equality legal decisions interpreting evidence. standards and that reflect Arrange discussion of how to apply greater gender judges and lawyers them. equality. on issues of human rights and gender equality in hearing cases. More considered interpretation of gender equality issues. Increase in new legal decisions that reflect greater gender equality.
  • 28. Short-term Medium-term Long-term 28 Operational vs Developmental Results Program / Project Management Inputs Activities Outputs Outcomes Impact Operational Results: The administrative and management product of an agency, its programs or projects Developmental Results: An actual change in the state of human development is the logical consequence of a CIDA investment in a developing country
  • 29. 29 Operational vs Developmental Results Resources and Activities Outputs Outputs Outputs Outputs Outputs Outcomes Outcomes Impact
  • 30. 30 Beneficiary Reach Beneficiary Reach is the overarching term that includes all individuals and groups or organizations benefiting either directly or indirectly from a funded project or programme. Direct Beneficiaries are those populations, groups or organizations which are within the immediate reach of a funded programme or project which are expected to benefit at the output and outcome levels. Indirect beneficiaries are those populations, groups or organizations who will indirectly benefit from the project and are outside the immediate reach of a given funded project or programme, yet are expected to benefit at the impact level.
  • 33. An indicator is a pointer. It is a number, a fact or a perception that measures changes in a specific condition over time. Indicators are the key in monitoring and evaluation. Indicators define the data required to compare actual results with planned results over time. 33 Indicator
  • 34. 34 What is a Result Indicator? • An indicator provides evidence that a result has been achieved. • An indicator measures progress, by noting changes at different points in time. • Indicators can be qualitative or quantitative.
  • 35. Process and Result Indicators • Results indicators are used to measure project performance 35 – Input Indicators – Process Indicators – Output Indicators – Outcome Indicators
  • 36. 36 Indicators Types • Quantitative –numbers, statistics, frequency, ratios, variances, etc. • Qualitative – changes in attitudes, behaviours, skills, perceptions, quality, level of understanding, etc. – Both Quantitative and Qualitative (QQTTP)
  • 37. 37 Program / Project Management Resources Reach Developmental Results Inputs / Activities Short-term Outputs Medium-term Outcomes Long-term Impact Partner Clients / Beneficiaries Performance Indicators Performance Indicators Performance Indicators Indicators in Result Chain
  • 38. 38 Criteria to Select Indicators • Validity • Reliability • Sensitivity • Simplicity • Utility • Affordability • Gender-sensitivity
  • 39. • For each output, outcome and impact statement, brainstorm a list of several key indicators (qualitative, quantitative, and gender-sensitive). • Apply the criteria to narrow the list to MAXIMUM two to three indicators per result statement. • Make sure that baseline information is available for each indicator. 39 Steps for Indicator Design
  • 40. 40 Developing Indicators using QQTTP • Quantity • Quality • Target • Time • Place
  • 43. Session 2.2: Performance Management Framework
  • 44. The Performance Management Framework 44 Performance Framework Performance Indicators Data Sources Collection Methods Frequency Responsibilities Impact Outcomes 1 2 Outputs 1.1 1.2 2.1 2.2
  • 45. • Sources of performance information include individual beneficiaries, groups of beneficiaries, organizations, partners, documents, etc. • Identify data sources for each indicator • To ensure reliability, try not to change data sources over time 45 Performance Data Sources
  • 46. • Sources of performance information include individual beneficiaries, groups of beneficiaries, organizations, partners, documents, etc. • Identify data sources for each indicator • To ensure reliability, try not to change data sources over time 46 Source of Verification
  • 47. 47 Performance Data Analysis • Compare changes to baseline data. • ‘Triangulate’ data by trying to collect similar information from different sources. • Ensure that data is gender disaggregated so that different information about men and women is clearly shown.
  • 48. Roles and Responsibilities for Collecting Performance Data 48 • Who will collect the data? • Who will analyze the data? • Who will prepare the reports? • How will the information on performance be shared with stakeholders? • How will the performance information be used to make decisions?
  • 49. 49 Frequency of Data Collection Performance Indicators Performance Indicators Performance Indicators Program/Project Management Performance review in light of assumptions made about causal links between activities, outputs, outcomes and impact Output Outcome Impact Continuous Self-Assessment Annual Project Performance Appraisal Program Impact Evaluation
  • 50. • Community-designed indicators can be measured by communities themselves through simple data collection instruments (records, meetings, interviews, PRA tools, testimonials, self-assessments, etc.). • Technical indicators sometimes require that questionnaires or surveys be administered by specialized researchers. 50 Data Collection Methods
  • 51. 51 Data Collection Techniques 1. QUESTIONNAIRE 2. INTERVIEW 3. OBSERVATION 4. FOCUSED GROUP DISCUSSION/OTHER PRA TECHNIQUES 5. TALLY METHOD
  • 52. 52 Sources of Information • PRIMARY – KEY INFORMANTS – ORGANIZATIONS – COMMUNITY/RELEVANT STAKEHOLDERS – PROJECT BENEFICIARIES • SECONDARY – JOURNALS/NEWSPAPERS – DOCUMENTS AND RECORDS – CENSUS REPORTS – ANNUAL REPORTS
  • 54. Session 2.2: RISKS AND ASSUMPTIONS
  • 55. • Factors that will negatively affect the assumptions and that negate the positive conditions required to produce results. Risks may or may not be within the control of project managers. • External risks include the development context. • Internal risks include such things as changes in key project personnel, availability of resources, etc. 55 What are Risks?
  • 56. 56 What is Risk Analysis? • Risk analysis involved ‘rating’ of assumptions based on their likelihood of holding true. – Low risk assumptions will probably hold true (little threat to project) – Medium risk assumptions may or may not hold true (some threat to project) – High risk assumptions will probably NOT hold true (high threat to project)
  • 57. Identifying Assumptions and Analyzing Risks 57 Assumptions Assumptions Assumptions Moderate Risk High Risk Outputs Outcomes Impact Inputs / Activities Low Risk Decreasing Management Control
  • 58. EXERCISE: Risk Analysis and Mitigation 58 Risk Likelihood (H/M/L) Impact (H/M/L) Management Impact: Outcome: Output:
  • 59. 59 EXERCISE: STAKEHOLDERS ANALYSIS Stakeholders Type of Effect Risk Potential Impact Likelihood Value PLAN Punchayat Negative Gender-biased approach in decision making 6 6 36 PLAN Institutions Influential (Men/ Women) Marginalized or Vulnerable groups (Men / Women)
  • 60. 60 Exercise: Risk Analysis
  • 62. Gender Analysis – Level of women’s participation (Control, Planning, implementation, monitoring) – Women’s empowerment • Decision making • Economic Independence • Mobility – Ratio of women’s beneficiaries 11/29/2014 62
  • 63. Environmental Analysis – Determine Environmental objectives (e.g. health clinic and environment Awareness) – Components leading to environmental effect? – What are these effects and their significance? – What strategies and specific measures will be implemented to alleviate or eliminate the negative effects and increase its benefits? – How will the project be monitored to ensure the effective implementation of these measure? 11/29/2014 63
  • 64. 64 Exercise: Work Plan and Budgeting Average Targets Target Target Target Total Budget Budget Budget Budget Grand Code Results/Activities Buduget Notes Unit Type Unit Cost Q-I Q-II Q-III Q-IV Targets Q-I Q-II Q-III Q-IV Total Outcom e 1: Output 1: 1 2 3 Personnel Costs Other Direct Costs Total of Output 1: Output 2: 1 2 3 Personnel Costs Other Direct Costs Total of Output 2: Total of Outcome 1: 5 Capital Costs 6 Personnel Costs (Admin) 7 Other Direct Costs (Admin) 8 5% Contingency Budget Grand Total
  • 65. 65 Salaries and Benefits Gross Gross Annual Annual (Entitled) Total Monthly Yearly Tax Employer Medical Package S. No,. Name DESIGNATION Salary Salary Deduction Cont. PF Allowance (in PKR) Staff Salaries Output 1 1 2 3 4 Total Staff Salaries Staff Salaries Output 2 1 2 3 4 Total Salaries Output 2 Admin Staff Salaries 1 2 3 4 Total Admin Costs Grand Total
  • 66. 66 Other Direct Costs Distribution of costs by initiatives S.No. Other Direct Costs Output 1 Output 2 Admin Total 1 Utility Bills (Electricity / Gas / Water) 2 Telephone / Mobile 3 Vehicle Running & Maintenance 4 Internet Charges 5 Entertainment 6 Printing And Stationary 7 Books And News Paper 8 Postage And Courier 9 Repair And Maintenance 10 Audit Fee (Internal and External) 11 Misc. / Others Grand Total (in USD)
  • 67. 67 Budget Notes S.No. Description of Line Items Cost Days Pax Cost (in PKR) 1 Consultant/Trainers' Fee 2 Food and Accommodation 3 Material 4 Travel Costs 5 Communication 6 Misc. Costs Grand Total
  • 69. 69 Reporting • All stakeholders need to be kept informed about the project/programme through periodic and extra-ordinary reports • MER systems have to be designed in such a way that they are able to generate appropriate reports for the various audiences (e.g. Governing body, donors and communities etc.) • Users of Reports • Communities / CBOs / Local Institutions / Donors
  • 70. 70 Exercises: Activity and Monitoring Reports
  • 71. Session 3.1: INSTITUTIONAL ARRANGEMENTS FOR M&E
  • 72. 72 Functions of M&E Section • Guide and oversee the implementation of the project’s MER systems and requirements; • Ensure consistency in the objectives and indicators in the program(s); • Prepare and monitor the program’s Performance Monitoring Plan (PMP); • Spearhead and coordinate the development of quarterly reports for the donor, as well as other required reports; • Coordinate and ensure timely and quality sub-grantee reporting;
  • 73. Functions of M&E Section (Continue) • Design and implement MER training programs for program sub-grantees; • Work with the field staff to develop program success stories; • Design and implement a system to identify, analyze, document and disseminate lessons learned; • Work with the Budget program coordinators to monitor program implementation; • Acquaint programme staff and partners with MER tools, strategies and plans; • Constantly work to improve MER strategies and reporting formats. 73