SlideShare una empresa de Scribd logo
1 de 14
CASE 1: LEARNING 
CURVE ANALYSIS 
Group 7
Problem #1 
The ABC Company has just been given the 
following production schedule for ski-lift 
gondola cars. This product is considerably 
different from any others the company has 
produced. Historically, the company‘s learning 
rate has been 80% on large projects. The first 
unit took 1,000 hours to produce.
Month Units Cumulative 
1 3 3 
2 7 10 
3 10 20 
4 12 32 
5 4 36 
6 2 38 
a. Estimate how many hours would be 
required to complete the 38th unit.
Solution 
a) a. We use the learning curve formulas to 
calculate the time required for the 38th unit: 
a. Given: L=0.80 T1= 1000 hrs. 
T38 = T1 (N (log L/log 2)) 
= 1000 (38 log 0.80/log 2) 
= 310.04 hrs
• b. If the budget only provides for a maximum 
of 30 direct labor employees in any month and 
a total of 15,000 direct labor hours for the 
entire schedule, will the budget be adequate? 
Assume that each direct labor employee is 
productive for 150 work hours each month.
Cumulative Hours 
Mont 
hs Units 
Cummulative 
Units 
Cumulative 
Average 
Cumulative 
Average Time per 
Unit 
Cumulative Total 
Hours for all Units 
1 3 3 0.834034568 834.034568 2502.103704 
2 7 10 0.631537303 631.5373025 6315.373025 
3 10 20 0.524247142 524.2471422 10484.94284 
4 12 32 0.45870687 458.7068697 14678.61983 
5 4 36 0.443285172 443.2851721 15958.26619 
6 2 38 0.436342826 436.3428259 16581.02738
Number of hours per month. 
Month 
1 2502.103704 - 0 = 2502.103704 hrs 
2 6315.373025-2502.103704= 3813.269321 hrs 
3 10484.94284-6315.373025 = 4169.569815 hrs. 
4 14678.61983-10484.94284= 4193.67699 hrs. 
5 15958.26619-14678.61983= 1279.64636 hrs. 
6 16581.02738-15958.26619= 622.76119 hrs.
Direct Labor Hours 
Month Direct Labor Workers by Month 
1 (2,502.1 hr)/(150 hr) = 16.7, or 17 
2 (3,813.3 hr)/(150 hr) = 25.4, or 26 
3 (4,169.6 hr)/(150 hr) = 27.8, or 28 
4 (4,193.7 hr)/(150 hr) = 27.9, or 28 
5 (1,279.7 hr)/(150 hr) = 8.5, or 9 
6 (622.5 hr)/(150 hr) = 4.2, or 5
Conclusion: 
*The schedule is sufficient in terms of the 
maximum direct labor required in any month because 
it never exceeds 30 employees. However, the total 
cumulative hours are 16,581, which exceeds the 
budgeted amount by 1,581 hours. Therefore, the 
budget will not be adequate.
Problem 2 
XYZ Company has $200,000 in cash, no inventory, and a 90 
percent learning curve. To reduce the complexity of this problem, ignore 
the hiring and training costs associated with dramatically increased 
production. Employees are paid $20 per hour every Friday for that 
week‘s work. XYZ has received an order to build 1,000 oak desks over 
the next 15 weeks. Materials cost $400 per desk. Suppliers make 
deliveries each Monday and insist on cash upon delivery. The first desk 
takes 100 hours of direct labor to build. XYZ will be paid $1,500 per 
desk two weeks after the desks are delivered. Should XYZ take this 
order? 
Additional Assumptions: 
• Products are delivered at the end of each week. 
Cash inflow from sales occurs at the end of the week.
Given: $ 20 per hour 
100 hours per desk 
$ 400 material cost per desk 
$ 20 per hour x 100 hours per desk 
= $ 2000 per desk 
Cost: 
$ 400 material cost per desk + $ 2000 per desk 
= $ 2400 per desk
Week Units Total cost Inflows every after 2 weeks 
1 2 4800 
2 4 9600 
3 8 19200 3000 
4 12 28800 6000 
5 14 33600 12000 
6 24 57600 18000 
7 64 153600 21000 
8 128 307200 36000 
9 128 307200 96000 
10 128 307200 192000 
11 88 211200 192000 
12 100 240000 192000 
13 100 240000 132000 
14 100 240000 150000 
15 100 240000 150000 
150000 
150000 
Cash Outflows & Inflows
350000 
300000 
250000 
200000 
150000 
100000 
50000 
0 
Cash Flow Chart 
0 2 4 6 8 10 12 14 16 
Values 
Weeks 
Total cost Inflows every after 2 weeks
Conclusion: 
The company should not take the 
order, because the total cost exceed the 
cash inflow every after two weeks.

Más contenido relacionado

La actualidad más candente

Variable costing & absorption costing
Variable costing & absorption costingVariable costing & absorption costing
Variable costing & absorption costingnaimhossain8
 
Simulation in Operation Research
Simulation in Operation ResearchSimulation in Operation Research
Simulation in Operation ResearchYamini Kahaliya
 
Process losses
Process lossesProcess losses
Process lossesOnline
 
Linear programming 1
Linear programming 1Linear programming 1
Linear programming 1Rezaul Karim
 
Product Life Cycle Costing
Product Life Cycle CostingProduct Life Cycle Costing
Product Life Cycle CostingTanvirul Islam
 
Job Order Costing
Job Order CostingJob Order Costing
Job Order Costingnarman1402
 
OPERATION RESEARCH Simulation
OPERATION RESEARCH SimulationOPERATION RESEARCH Simulation
OPERATION RESEARCH SimulationKomal Hambir
 
Production planning techniques- aggregate planning
Production planning techniques- aggregate planningProduction planning techniques- aggregate planning
Production planning techniques- aggregate planningArushi Verma
 
fm working capital management for mba
fm working capital management for mbafm working capital management for mba
fm working capital management for mbasravankumar dasari
 
Breakeven Analysis (Introduction)
Breakeven Analysis (Introduction)Breakeven Analysis (Introduction)
Breakeven Analysis (Introduction)tutor2u
 
Budgeting & budgetary control f
Budgeting & budgetary  control fBudgeting & budgetary  control f
Budgeting & budgetary control fsachin kumar sharma
 
Absorption costing vs variable costing
Absorption costing  vs variable costingAbsorption costing  vs variable costing
Absorption costing vs variable costingShankar Jyoti Doley
 
Process dsign and facility layout
Process dsign and facility layoutProcess dsign and facility layout
Process dsign and facility layoutNsbmUcd
 
Aggregate Production Planning
Aggregate Production PlanningAggregate Production Planning
Aggregate Production Planning3abooodi
 
99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problemsvarsha nihanth lade
 

La actualidad más candente (20)

Variable costing & absorption costing
Variable costing & absorption costingVariable costing & absorption costing
Variable costing & absorption costing
 
Simulation in Operation Research
Simulation in Operation ResearchSimulation in Operation Research
Simulation in Operation Research
 
Planned order release
Planned order releasePlanned order release
Planned order release
 
Process losses
Process lossesProcess losses
Process losses
 
Linear programming 1
Linear programming 1Linear programming 1
Linear programming 1
 
Product Life Cycle Costing
Product Life Cycle CostingProduct Life Cycle Costing
Product Life Cycle Costing
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Job Order Costing
Job Order CostingJob Order Costing
Job Order Costing
 
OPERATION RESEARCH Simulation
OPERATION RESEARCH SimulationOPERATION RESEARCH Simulation
OPERATION RESEARCH Simulation
 
Production planning techniques- aggregate planning
Production planning techniques- aggregate planningProduction planning techniques- aggregate planning
Production planning techniques- aggregate planning
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
 
fm working capital management for mba
fm working capital management for mbafm working capital management for mba
fm working capital management for mba
 
Breakeven Analysis (Introduction)
Breakeven Analysis (Introduction)Breakeven Analysis (Introduction)
Breakeven Analysis (Introduction)
 
Budgeting & budgetary control f
Budgeting & budgetary  control fBudgeting & budgetary  control f
Budgeting & budgetary control f
 
Minimization model by simplex method
Minimization model by simplex methodMinimization model by simplex method
Minimization model by simplex method
 
Absorption costing vs variable costing
Absorption costing  vs variable costingAbsorption costing  vs variable costing
Absorption costing vs variable costing
 
Process dsign and facility layout
Process dsign and facility layoutProcess dsign and facility layout
Process dsign and facility layout
 
Aggregate Production Planning
Aggregate Production PlanningAggregate Production Planning
Aggregate Production Planning
 
99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems99700905 cost-of-capital-solved-problems
99700905 cost-of-capital-solved-problems
 

Destacado

operations strategy and competitiveness
operations strategy and competitivenessoperations strategy and competitiveness
operations strategy and competitivenessMeenakshi Singh
 
Product design and development ch2
Product design and development ch2Product design and development ch2
Product design and development ch2Kavindra Singh
 
Product design and development ch3
Product design and development ch3Product design and development ch3
Product design and development ch3Kavindra Singh
 
MARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORTMARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORTViʞaƨh ʞumar
 
C5 process & layout
C5 process & layoutC5 process & layout
C5 process & layouthakimizaki
 
Aggregate planning and mps om
Aggregate planning and mps omAggregate planning and mps om
Aggregate planning and mps omfatuma ahmed
 
Operation strategy at galanze
Operation strategy at galanzeOperation strategy at galanze
Operation strategy at galanzeNiilm-Cms
 
Product designing strategy
Product designing strategyProduct designing strategy
Product designing strategyMegha Jain
 
Operations strategy and competitiveness
Operations strategy and competitivenessOperations strategy and competitiveness
Operations strategy and competitivenessVaibhav Gupta
 
Learning Curves in Production Management
Learning Curves in Production ManagementLearning Curves in Production Management
Learning Curves in Production ManagementJoshua Miranda
 
Product design and development ch4
Product design and development ch4Product design and development ch4
Product design and development ch4Kavindra Singh
 
Operations strategy and competitiveness
Operations strategy and competitivenessOperations strategy and competitiveness
Operations strategy and competitivenessArun Kandukuri
 
Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivityahmad bassiouny
 
Product design and development
Product design and developmentProduct design and development
Product design and developmentVishal Kachhdiya
 
2.6 & 2.7 & 2.8 Operations Strategy and Competitiveness
2.6 & 2.7 & 2.8 Operations Strategy and Competitiveness2.6 & 2.7 & 2.8 Operations Strategy and Competitiveness
2.6 & 2.7 & 2.8 Operations Strategy and CompetitivenessLauraRLR
 

Destacado (20)

Learn curve
Learn curveLearn curve
Learn curve
 
operations strategy and competitiveness
operations strategy and competitivenessoperations strategy and competitiveness
operations strategy and competitiveness
 
Learning curve
Learning curveLearning curve
Learning curve
 
Product design and development ch2
Product design and development ch2Product design and development ch2
Product design and development ch2
 
Product design and development ch3
Product design and development ch3Product design and development ch3
Product design and development ch3
 
MARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORTMARUTI SUZUKI PRODUCT ANALYSIS REPORT
MARUTI SUZUKI PRODUCT ANALYSIS REPORT
 
C5 process & layout
C5 process & layoutC5 process & layout
C5 process & layout
 
Aggregate planning and mps om
Aggregate planning and mps omAggregate planning and mps om
Aggregate planning and mps om
 
Learning curve
Learning curveLearning curve
Learning curve
 
Operation strategy at galanze
Operation strategy at galanzeOperation strategy at galanze
Operation strategy at galanze
 
Product designing strategy
Product designing strategyProduct designing strategy
Product designing strategy
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
 
Operations strategy and competitiveness
Operations strategy and competitivenessOperations strategy and competitiveness
Operations strategy and competitiveness
 
Learning Curves in Production Management
Learning Curves in Production ManagementLearning Curves in Production Management
Learning Curves in Production Management
 
Product design and development ch4
Product design and development ch4Product design and development ch4
Product design and development ch4
 
Product design
Product designProduct design
Product design
 
Operations strategy and competitiveness
Operations strategy and competitivenessOperations strategy and competitiveness
Operations strategy and competitiveness
 
Work Study & Productivity
Work Study & ProductivityWork Study & Productivity
Work Study & Productivity
 
Product design and development
Product design and developmentProduct design and development
Product design and development
 
2.6 & 2.7 & 2.8 Operations Strategy and Competitiveness
2.6 & 2.7 & 2.8 Operations Strategy and Competitiveness2.6 & 2.7 & 2.8 Operations Strategy and Competitiveness
2.6 & 2.7 & 2.8 Operations Strategy and Competitiveness
 

Similar a Learning Curve Sample Problem

Cost accounting (Hypothetical problems of labor costing and solution of these...
Cost accounting (Hypothetical problems of labor costing and solution of these...Cost accounting (Hypothetical problems of labor costing and solution of these...
Cost accounting (Hypothetical problems of labor costing and solution of these...Md. Shamim Ahmed
 
BRUSNSWICK MOTORS, INC
BRUSNSWICK MOTORS, INCBRUSNSWICK MOTORS, INC
BRUSNSWICK MOTORS, INCPravin Narwade
 
Managerial Accounting Presentation, v.3
Managerial Accounting Presentation, v.3Managerial Accounting Presentation, v.3
Managerial Accounting Presentation, v.3Thana Kittisathanon
 
Practice topic 9 - answers (1)
Practice   topic 9 - answers (1)Practice   topic 9 - answers (1)
Practice topic 9 - answers (1)IrfanKhan679364
 
Contoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas ManufakturContoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas ManufakturMahros Darsin
 
Presentation aggregate planning
Presentation aggregate planningPresentation aggregate planning
Presentation aggregate planningLauraRLR
 
MBA: Accounting for Business Decision Making
MBA:  Accounting for Business Decision MakingMBA:  Accounting for Business Decision Making
MBA: Accounting for Business Decision MakingRofidah Azman
 
Lean Back Offices Project
Lean Back Offices ProjectLean Back Offices Project
Lean Back Offices ProjectParag Kapile
 
Costing assignment.docx
Costing assignment.docxCosting assignment.docx
Costing assignment.docxssuserdcbf4e
 
Course project ie6560 group 10_presentation
Course project ie6560 group 10_presentationCourse project ie6560 group 10_presentation
Course project ie6560 group 10_presentationNishant Pathak
 
Directions for Multiple Trendlines on a Single Graph· After yo.docx
Directions for Multiple Trendlines on a Single Graph· After yo.docxDirections for Multiple Trendlines on a Single Graph· After yo.docx
Directions for Multiple Trendlines on a Single Graph· After yo.docxlynettearnold46882
 
Process Costing- Chapter Four
Process Costing- Chapter FourProcess Costing- Chapter Four
Process Costing- Chapter FourEmily Bauer
 

Similar a Learning Curve Sample Problem (20)

Cost accounting (Hypothetical problems of labor costing and solution of these...
Cost accounting (Hypothetical problems of labor costing and solution of these...Cost accounting (Hypothetical problems of labor costing and solution of these...
Cost accounting (Hypothetical problems of labor costing and solution of these...
 
BRUSNSWICK MOTORS, INC
BRUSNSWICK MOTORS, INCBRUSNSWICK MOTORS, INC
BRUSNSWICK MOTORS, INC
 
Brunswick motors, inc
Brunswick motors, incBrunswick motors, inc
Brunswick motors, inc
 
Brunswick motors, inc
Brunswick motors, incBrunswick motors, inc
Brunswick motors, inc
 
Chapter no.9
Chapter no.9Chapter no.9
Chapter no.9
 
Mojakoe ab-uts-20111
Mojakoe ab-uts-20111Mojakoe ab-uts-20111
Mojakoe ab-uts-20111
 
Uts ab 2011 2012 gasal
Uts ab 2011 2012 gasalUts ab 2011 2012 gasal
Uts ab 2011 2012 gasal
 
Managerial Accounting Presentation, v.3
Managerial Accounting Presentation, v.3Managerial Accounting Presentation, v.3
Managerial Accounting Presentation, v.3
 
Practice topic 9 - answers (1)
Practice   topic 9 - answers (1)Practice   topic 9 - answers (1)
Practice topic 9 - answers (1)
 
Log11 uitwerking opdrachten
Log11 uitwerking opdrachtenLog11 uitwerking opdrachten
Log11 uitwerking opdrachten
 
Contoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas ManufakturContoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas Manufaktur
 
Kompilasi bahan-sebelum-uts
Kompilasi bahan-sebelum-utsKompilasi bahan-sebelum-uts
Kompilasi bahan-sebelum-uts
 
Presentation aggregate planning
Presentation aggregate planningPresentation aggregate planning
Presentation aggregate planning
 
MBA: Accounting for Business Decision Making
MBA:  Accounting for Business Decision MakingMBA:  Accounting for Business Decision Making
MBA: Accounting for Business Decision Making
 
Operational Research: LPP.pptx
Operational Research: LPP.pptxOperational Research: LPP.pptx
Operational Research: LPP.pptx
 
Lean Back Offices Project
Lean Back Offices ProjectLean Back Offices Project
Lean Back Offices Project
 
Costing assignment.docx
Costing assignment.docxCosting assignment.docx
Costing assignment.docx
 
Course project ie6560 group 10_presentation
Course project ie6560 group 10_presentationCourse project ie6560 group 10_presentation
Course project ie6560 group 10_presentation
 
Directions for Multiple Trendlines on a Single Graph· After yo.docx
Directions for Multiple Trendlines on a Single Graph· After yo.docxDirections for Multiple Trendlines on a Single Graph· After yo.docx
Directions for Multiple Trendlines on a Single Graph· After yo.docx
 
Process Costing- Chapter Four
Process Costing- Chapter FourProcess Costing- Chapter Four
Process Costing- Chapter Four
 

Último

Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 

Último (20)

Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 

Learning Curve Sample Problem

  • 1. CASE 1: LEARNING CURVE ANALYSIS Group 7
  • 2. Problem #1 The ABC Company has just been given the following production schedule for ski-lift gondola cars. This product is considerably different from any others the company has produced. Historically, the company‘s learning rate has been 80% on large projects. The first unit took 1,000 hours to produce.
  • 3. Month Units Cumulative 1 3 3 2 7 10 3 10 20 4 12 32 5 4 36 6 2 38 a. Estimate how many hours would be required to complete the 38th unit.
  • 4. Solution a) a. We use the learning curve formulas to calculate the time required for the 38th unit: a. Given: L=0.80 T1= 1000 hrs. T38 = T1 (N (log L/log 2)) = 1000 (38 log 0.80/log 2) = 310.04 hrs
  • 5. • b. If the budget only provides for a maximum of 30 direct labor employees in any month and a total of 15,000 direct labor hours for the entire schedule, will the budget be adequate? Assume that each direct labor employee is productive for 150 work hours each month.
  • 6. Cumulative Hours Mont hs Units Cummulative Units Cumulative Average Cumulative Average Time per Unit Cumulative Total Hours for all Units 1 3 3 0.834034568 834.034568 2502.103704 2 7 10 0.631537303 631.5373025 6315.373025 3 10 20 0.524247142 524.2471422 10484.94284 4 12 32 0.45870687 458.7068697 14678.61983 5 4 36 0.443285172 443.2851721 15958.26619 6 2 38 0.436342826 436.3428259 16581.02738
  • 7. Number of hours per month. Month 1 2502.103704 - 0 = 2502.103704 hrs 2 6315.373025-2502.103704= 3813.269321 hrs 3 10484.94284-6315.373025 = 4169.569815 hrs. 4 14678.61983-10484.94284= 4193.67699 hrs. 5 15958.26619-14678.61983= 1279.64636 hrs. 6 16581.02738-15958.26619= 622.76119 hrs.
  • 8. Direct Labor Hours Month Direct Labor Workers by Month 1 (2,502.1 hr)/(150 hr) = 16.7, or 17 2 (3,813.3 hr)/(150 hr) = 25.4, or 26 3 (4,169.6 hr)/(150 hr) = 27.8, or 28 4 (4,193.7 hr)/(150 hr) = 27.9, or 28 5 (1,279.7 hr)/(150 hr) = 8.5, or 9 6 (622.5 hr)/(150 hr) = 4.2, or 5
  • 9. Conclusion: *The schedule is sufficient in terms of the maximum direct labor required in any month because it never exceeds 30 employees. However, the total cumulative hours are 16,581, which exceeds the budgeted amount by 1,581 hours. Therefore, the budget will not be adequate.
  • 10. Problem 2 XYZ Company has $200,000 in cash, no inventory, and a 90 percent learning curve. To reduce the complexity of this problem, ignore the hiring and training costs associated with dramatically increased production. Employees are paid $20 per hour every Friday for that week‘s work. XYZ has received an order to build 1,000 oak desks over the next 15 weeks. Materials cost $400 per desk. Suppliers make deliveries each Monday and insist on cash upon delivery. The first desk takes 100 hours of direct labor to build. XYZ will be paid $1,500 per desk two weeks after the desks are delivered. Should XYZ take this order? Additional Assumptions: • Products are delivered at the end of each week. Cash inflow from sales occurs at the end of the week.
  • 11. Given: $ 20 per hour 100 hours per desk $ 400 material cost per desk $ 20 per hour x 100 hours per desk = $ 2000 per desk Cost: $ 400 material cost per desk + $ 2000 per desk = $ 2400 per desk
  • 12. Week Units Total cost Inflows every after 2 weeks 1 2 4800 2 4 9600 3 8 19200 3000 4 12 28800 6000 5 14 33600 12000 6 24 57600 18000 7 64 153600 21000 8 128 307200 36000 9 128 307200 96000 10 128 307200 192000 11 88 211200 192000 12 100 240000 192000 13 100 240000 132000 14 100 240000 150000 15 100 240000 150000 150000 150000 Cash Outflows & Inflows
  • 13. 350000 300000 250000 200000 150000 100000 50000 0 Cash Flow Chart 0 2 4 6 8 10 12 14 16 Values Weeks Total cost Inflows every after 2 weeks
  • 14. Conclusion: The company should not take the order, because the total cost exceed the cash inflow every after two weeks.