2. DISTANCES
Performance JAR 25
DISTANCES
 Screen height
 Definitions
 Declared distances
 Required distances
 Balanced field length
 Unbalanced field length
SCREEN HEIGHT
Screen height is different depending on the type of aeroplane:
JAR 23: 50 ft
JAR 25: 35 ft
JAR 25 (WET RUNWAY): 15 ft
35 ft
JAR 25 Screen height
DEFINITIONS
RUNWAY: Defined rectangular area on a land airport that is prepared
for the landing and takeoff run of aircraft along its length.
STOPWAY: An area beyond the takeoff runway that is at least as wide
as the runway, is centred upon the extended runway centreline, and is
able to support an airplane during an aborted takeoff without causing
structural damage to the airplane.
Stopway must not be used for landing calculations.
DEFINITIONS
CLEARWAY: An area beyond the takeoff runway that is under the
control of airport authorities where terrain or fixed obstacles may not
extend above specified limits. It is not required to be able to support
the weight of the aeroplane, it must only be free of obstacles.
min 250 ft
α = 1.25º26 inches
DEFINITIONS
500 ft
α = 1.25º
DECLARED DISTANCES
Field lengths available for takeoff and landing are known as declared
distances:
 TORA: Takeoff Run Available
 TODA: Takeoff Distance Available. (TORA + CWY)
 ASDA: Accelerate-Stop Distance Available. (TORA + SWY)
 LDA: Landing Distance Available. (TORA – DT)
DECLARED DISTANCES
RWY
CWY
SWYDT
TORA
ASDA
TODA
LDA
TORA
TORA: The length of runway which is declared available by the
appropriate authority and suitable for the ground run of an aeroplane
taking off.
TORA is equal to the distance from the threshold to the Departure End
of Runway (DER).
TORA
TORA
TODA
TODA: The length of the takeoff run available plus the length of the
clearway available.
The maximum length of the clearway is half the TORA.
TORA CWY (1/2 TORA MAX)
TODA
ASDA
ASDA: The length of the takeoff run available plus the length of the
stopway, if such stopway is declared available by the appropriate
authority and is capable of bearing the mass of the aeroplane under
the prevailing operating conditions.
TORA SWY
ASDA
DECLARED DISTANCES
According to JAR-OPS 1.490, “[…] an operator must take account of
the loss, if any, of runway length due to alignment of the aeroplane
prior to takeoff.”
Line-up corrections should be made when computing takeoff
performance, anytime runway access does not permit positioning the
airplane at the threshold.
DECLARED DISTANCES
Effective ASDA
Effective TODA
Runway length
A B
A: Adjustment to takeoff distance
B: Adjustment to accelerate-stop distance
DECLARED DISTANCES
There are different corrections based on 90º turns and 180º turns.
180º turn
DECLARED DISTANCES
DECLARED DISTANCES
DECLARED DISTANCES
The line-up distance will increase if the runway is not wide enough.
DECLARED DISTANCES
Depending on the length of the stopway and/or the clearway (if
available), ASDA may be equal, longer or shorter than TODA.
DECLARED DISTANCES
DECLARED DISTANCES
Declared distances can be found in the AIP, although they are included
in the charts.
REQUIRED DISTANCES
Field lengths required for takeoff are:
 TORR: Takeoff Run Required
 TODR: Takeoff Distance Required.
 ASDR: Accelerate-Stop Distance Required.
TORR
Takeoff Run Required is the longest of:
a) The distance from start of ground roll to a point halfway between
the lift-off point and the point at 35 ft, assuming that the critical
engine has failed at Vef.
b) 115% of the distance from start of ground roll to a point halfway
between the lift-off point and the point at 35 ft, with all the engines
running.
Therefore, the TOR will be only limitative when using a clearway.
The maximum usable clearway is then half the distance between
the lift-off point and the point at 35 ft.
TORR
TORR
ASDR
Accelerate-stop Distance Required is the longest of:
a) The distance taken to accelerate to Vef, continue accelerating to V1
with one engine inoperative, accelerate for 2 more seconds, and
come to a full stop.
b) The distance taken to accelerate to V1, accelerate for 2 more
seconds, and come to a full stop. (With all engines operating)
 Reverse thrust is NOT taken into account.
 The most effective braking sequence is: brakes, thrust idle, spoilers.
ASDR
TODR
Takeoff Distance Required is the longest of:
a) The distance from the start of ground roll to the point where the
aeroplane reaches a height of 35 ft and the V2 speed with engine
failure having occurred at Vef.
b) 115% of the distance between start of ground roll and the point
where the aeroplane reaches a height of 35 ft and the V2 speed with
all engines operating.
 Distance “a)” will be usually longer with twin-engine aeroplanes.
TODR
CONSIDERATIONS
 If V1 is reduced ASD will decrease and TOD will increase, and vice
versa.
 In general terms, acceleration is more affected than braking when
the same condition affects both of them (for instance, runway slope).
BALANCED FIELD LENGHT
If the V1 is calculated in such a way that both the ASDR and the TODR
are of equal length, the takeoff is said to be a balanced field length
takeoff. This situation is given when neither stopway nor clearway
exist, or if both are available.
In that case the V1 is known as balanced V1.
TOD = ASD
35 ft
Balanced V1
BALANCED FIELD LENGHT
V1
m
TODRASDR
V1 BALANCED
BALANCED FIELD LENGHT
V1
m
TODRASDR
V1 increases with weight
100.000 Kg
120.000 Kg
UNBALANCED FIELD LENGTH
If the TORA is not enough to takeoff with our ATOW and a stopway or
a clearway is available, we can take advantage of them, changing the
balanced V1 value.
Thus, ASDR <> TODR, but the situation will meet the requirements
because of that clearway or stopway.
Even with enough TORA, we may operate with unbalanced V1 if the
balanced V1 is below the Vmcg or if it is above Vmbe.
UNBALANCED FIELD LENGTH
CLEARWAY AVAILABLE (NO STOPWAY)
If we decrease the balanced V1 value, the ASDR will decrease and the
TODR will increase.
In this case TODR > ASDR, and ASDR = ASDA = TORA.
TORA = ASDA = ASDR CWY
TODR
V1 < Balanced V1
35 ft
UNBALANCED FIELD LENGTH
STOPWAY AVAILABLE (NO CLEARWAY)
If we increase the balanced V1 value, the ASDR will increase and the
TODR will decrease.
In this case ASDR > TODR, and TODR = TODA = TORA.
TORA = TODA = TODR SWY
ASDR
V1 > Balanced V1
35 ft
UNBALANCED FIELD LENGTH
We have seen how changing the value of V1 we can increase our
OTOW, if a clearway or a stopway is available.
But if BOTH of them are available, then we can operate with a balanced
V1, since both ASDA and TODA are increased with those clearway and
stopway.

Más contenido relacionado

La actualidad más candente

Cat i;ii;iii operations jakub muransky
Cat i;ii;iii operations jakub muranskyCat i;ii;iii operations jakub muransky
Cat i;ii;iii operations jakub muranskyJakub Muransky
 
Aircraft performance 2
Aircraft performance 2Aircraft performance 2
Aircraft performance 2Nazmul Alam
 
Ramp safety
Ramp safetyRamp safety
Ramp safetymahchu12
 
Annex 14 ppt cheng
Annex 14 ppt chengAnnex 14 ppt cheng
Annex 14 ppt chengguestb793fe2
 
Traffic Alert and collision avoidance system (TCAS)
Traffic Alert and collision avoidance system (TCAS)Traffic Alert and collision avoidance system (TCAS)
Traffic Alert and collision avoidance system (TCAS)ARVIND KUMAR SINGH
 
V.o.r ppt
V.o.r pptV.o.r ppt
V.o.r pptbtinus
 
GROUND HANDLING QUICK GUIDE
GROUND HANDLING QUICK GUIDEGROUND HANDLING QUICK GUIDE
GROUND HANDLING QUICK GUIDETranos Matezhure
 
Instrument landing system (ils)
Instrument landing system (ils)Instrument landing system (ils)
Instrument landing system (ils)Divya Chopra
 
Distance Measuring Equipment (DME) power point Presentation for aircraft
Distance Measuring Equipment (DME) power point Presentation for aircraftDistance Measuring Equipment (DME) power point Presentation for aircraft
Distance Measuring Equipment (DME) power point Presentation for aircraftPrabhat K.C.
 
AIRSEDE OPERATION
AIRSEDE OPERATIONAIRSEDE OPERATION
AIRSEDE OPERATIONAiDY
 
Implementation of RNP_PBN Instrument Approach Procedure.pptx
Implementation of RNP_PBN Instrument Approach Procedure.pptxImplementation of RNP_PBN Instrument Approach Procedure.pptx
Implementation of RNP_PBN Instrument Approach Procedure.pptxARVIND KUMAR SINGH
 
Lecture+3 air+traffic+control+(atc)+tower
Lecture+3 air+traffic+control+(atc)+towerLecture+3 air+traffic+control+(atc)+tower
Lecture+3 air+traffic+control+(atc)+towertitu11
 

La actualidad más candente (20)

Airside Hazards And Risks
Airside Hazards And RisksAirside Hazards And Risks
Airside Hazards And Risks
 
Cat i;ii;iii operations jakub muransky
Cat i;ii;iii operations jakub muranskyCat i;ii;iii operations jakub muransky
Cat i;ii;iii operations jakub muransky
 
Aircraft performance 2
Aircraft performance 2Aircraft performance 2
Aircraft performance 2
 
Theory of flight final
Theory of flight finalTheory of flight final
Theory of flight final
 
Aerodrome Operating Minima
Aerodrome Operating MinimaAerodrome Operating Minima
Aerodrome Operating Minima
 
Ramp safety
Ramp safetyRamp safety
Ramp safety
 
ILS
ILSILS
ILS
 
Annex 14 ppt cheng
Annex 14 ppt chengAnnex 14 ppt cheng
Annex 14 ppt cheng
 
Traffic Alert and collision avoidance system (TCAS)
Traffic Alert and collision avoidance system (TCAS)Traffic Alert and collision avoidance system (TCAS)
Traffic Alert and collision avoidance system (TCAS)
 
V.o.r ppt
V.o.r pptV.o.r ppt
V.o.r ppt
 
GROUND HANDLING QUICK GUIDE
GROUND HANDLING QUICK GUIDEGROUND HANDLING QUICK GUIDE
GROUND HANDLING QUICK GUIDE
 
Instrument landing system (ils)
Instrument landing system (ils)Instrument landing system (ils)
Instrument landing system (ils)
 
Aircraft marshalling
Aircraft marshallingAircraft marshalling
Aircraft marshalling
 
Distance Measuring Equipment (DME) power point Presentation for aircraft
Distance Measuring Equipment (DME) power point Presentation for aircraftDistance Measuring Equipment (DME) power point Presentation for aircraft
Distance Measuring Equipment (DME) power point Presentation for aircraft
 
AIRSEDE OPERATION
AIRSEDE OPERATIONAIRSEDE OPERATION
AIRSEDE OPERATION
 
Implementation of RNP_PBN Instrument Approach Procedure.pptx
Implementation of RNP_PBN Instrument Approach Procedure.pptxImplementation of RNP_PBN Instrument Approach Procedure.pptx
Implementation of RNP_PBN Instrument Approach Procedure.pptx
 
1 -efis
1  -efis1  -efis
1 -efis
 
ILS paperwork air traffic control
ILS paperwork air traffic controlILS paperwork air traffic control
ILS paperwork air traffic control
 
Avionics
AvionicsAvionics
Avionics
 
Lecture+3 air+traffic+control+(atc)+tower
Lecture+3 air+traffic+control+(atc)+towerLecture+3 air+traffic+control+(atc)+tower
Lecture+3 air+traffic+control+(atc)+tower
 

Similar a 2. jar 25 distances

Performance presentation 2013
Performance presentation 2013Performance presentation 2013
Performance presentation 2013alsats
 
Presentation1
Presentation1Presentation1
Presentation1alsats
 
Air port presentation 6th unit
Air port presentation 6th unitAir port presentation 6th unit
Air port presentation 6th unitT.Naga Anusha
 
Proposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIAProposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIAKozarni Koko
 
Terminal Part 2
Terminal Part 2Terminal Part 2
Terminal Part 2tomrickard
 
C-130 Weight Limits April 2002
C-130 Weight Limits April 2002C-130 Weight Limits April 2002
C-130 Weight Limits April 20021st_TSG_Airborne
 
237034070 study-guide
237034070 study-guide237034070 study-guide
237034070 study-guidehomeworkping3
 
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdfFLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdfssuser1edd921
 
A320 ILS (CAT II inc.).ppt
A320 ILS (CAT II inc.).pptA320 ILS (CAT II inc.).ppt
A320 ILS (CAT II inc.).pptUditSharma76602
 
10. contaminated runways
10. contaminated runways10. contaminated runways
10. contaminated runwayschococrispis37
 
Airbusa320aircraftoperationmanual
Airbusa320aircraftoperationmanualAirbusa320aircraftoperationmanual
Airbusa320aircraftoperationmanualPedro Viegas
 

Similar a 2. jar 25 distances (20)

Performance presentation 2013
Performance presentation 2013Performance presentation 2013
Performance presentation 2013
 
Basic runway length
Basic runway lengthBasic runway length
Basic runway length
 
Presentation1
Presentation1Presentation1
Presentation1
 
Airpot design
Airpot designAirpot design
Airpot design
 
Air port presentation 6th unit
Air port presentation 6th unitAir port presentation 6th unit
Air port presentation 6th unit
 
Proposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIAProposed RWY21 RESA at YIA
Proposed RWY21 RESA at YIA
 
Terminal Part 2
Terminal Part 2Terminal Part 2
Terminal Part 2
 
C-130 Weight Limits April 2002
C-130 Weight Limits April 2002C-130 Weight Limits April 2002
C-130 Weight Limits April 2002
 
237034070 study-guide
237034070 study-guide237034070 study-guide
237034070 study-guide
 
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdfFLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
 
A320 ILS (CAT II inc.).ppt
A320 ILS (CAT II inc.).pptA320 ILS (CAT II inc.).ppt
A320 ILS (CAT II inc.).ppt
 
runway orientation.pdf
runway orientation.pdfrunway orientation.pdf
runway orientation.pdf
 
Airspace_Training.ppt
Airspace_Training.pptAirspace_Training.ppt
Airspace_Training.ppt
 
10. contaminated runways
10. contaminated runways10. contaminated runways
10. contaminated runways
 
shubham ppt.pptx
shubham ppt.pptxshubham ppt.pptx
shubham ppt.pptx
 
Atc unit 2
Atc unit 2Atc unit 2
Atc unit 2
 
Lvp pdf
Lvp  pdfLvp  pdf
Lvp pdf
 
Air traffic management
Air traffic managementAir traffic management
Air traffic management
 
2 -dme
2  -dme2  -dme
2 -dme
 
Airbusa320aircraftoperationmanual
Airbusa320aircraftoperationmanualAirbusa320aircraftoperationmanual
Airbusa320aircraftoperationmanual
 

Más de chococrispis37

Más de chococrispis37 (8)

Power graphs intro
Power graphs introPower graphs intro
Power graphs intro
 
034 performance
034   performance034   performance
034 performance
 
032 aeroplane performance
032 aeroplane performance032 aeroplane performance
032 aeroplane performance
 
8. descent
8. descent8. descent
8. descent
 
7. cruise ii
7. cruise ii7. cruise ii
7. cruise ii
 
6. cruise i
6. cruise i6. cruise i
6. cruise i
 
5. climb
5. climb5. climb
5. climb
 
3. jar 25 weights
3. jar 25 weights3. jar 25 weights
3. jar 25 weights
 

2. jar 25 distances

  • 2. DISTANCES  Screen height  Definitions  Declared distances  Required distances  Balanced field length  Unbalanced field length
  • 3. SCREEN HEIGHT Screen height is different depending on the type of aeroplane: JAR 23: 50 ft JAR 25: 35 ft JAR 25 (WET RUNWAY): 15 ft 35 ft JAR 25 Screen height
  • 4. DEFINITIONS RUNWAY: Defined rectangular area on a land airport that is prepared for the landing and takeoff run of aircraft along its length. STOPWAY: An area beyond the takeoff runway that is at least as wide as the runway, is centred upon the extended runway centreline, and is able to support an airplane during an aborted takeoff without causing structural damage to the airplane. Stopway must not be used for landing calculations.
  • 5. DEFINITIONS CLEARWAY: An area beyond the takeoff runway that is under the control of airport authorities where terrain or fixed obstacles may not extend above specified limits. It is not required to be able to support the weight of the aeroplane, it must only be free of obstacles. min 250 ft α = 1.25º26 inches
  • 7. DECLARED DISTANCES Field lengths available for takeoff and landing are known as declared distances:  TORA: Takeoff Run Available  TODA: Takeoff Distance Available. (TORA + CWY)  ASDA: Accelerate-Stop Distance Available. (TORA + SWY)  LDA: Landing Distance Available. (TORA – DT)
  • 9. TORA TORA: The length of runway which is declared available by the appropriate authority and suitable for the ground run of an aeroplane taking off. TORA is equal to the distance from the threshold to the Departure End of Runway (DER).
  • 11. TODA TODA: The length of the takeoff run available plus the length of the clearway available. The maximum length of the clearway is half the TORA. TORA CWY (1/2 TORA MAX) TODA
  • 12. ASDA ASDA: The length of the takeoff run available plus the length of the stopway, if such stopway is declared available by the appropriate authority and is capable of bearing the mass of the aeroplane under the prevailing operating conditions. TORA SWY ASDA
  • 13. DECLARED DISTANCES According to JAR-OPS 1.490, “[…] an operator must take account of the loss, if any, of runway length due to alignment of the aeroplane prior to takeoff.” Line-up corrections should be made when computing takeoff performance, anytime runway access does not permit positioning the airplane at the threshold.
  • 14. DECLARED DISTANCES Effective ASDA Effective TODA Runway length A B A: Adjustment to takeoff distance B: Adjustment to accelerate-stop distance
  • 15. DECLARED DISTANCES There are different corrections based on 90º turns and 180º turns. 180º turn
  • 18. DECLARED DISTANCES The line-up distance will increase if the runway is not wide enough.
  • 19. DECLARED DISTANCES Depending on the length of the stopway and/or the clearway (if available), ASDA may be equal, longer or shorter than TODA.
  • 21. DECLARED DISTANCES Declared distances can be found in the AIP, although they are included in the charts.
  • 22. REQUIRED DISTANCES Field lengths required for takeoff are:  TORR: Takeoff Run Required  TODR: Takeoff Distance Required.  ASDR: Accelerate-Stop Distance Required.
  • 23. TORR Takeoff Run Required is the longest of: a) The distance from start of ground roll to a point halfway between the lift-off point and the point at 35 ft, assuming that the critical engine has failed at Vef. b) 115% of the distance from start of ground roll to a point halfway between the lift-off point and the point at 35 ft, with all the engines running. Therefore, the TOR will be only limitative when using a clearway. The maximum usable clearway is then half the distance between the lift-off point and the point at 35 ft.
  • 24. TORR
  • 25. TORR
  • 26. ASDR Accelerate-stop Distance Required is the longest of: a) The distance taken to accelerate to Vef, continue accelerating to V1 with one engine inoperative, accelerate for 2 more seconds, and come to a full stop. b) The distance taken to accelerate to V1, accelerate for 2 more seconds, and come to a full stop. (With all engines operating)  Reverse thrust is NOT taken into account.  The most effective braking sequence is: brakes, thrust idle, spoilers.
  • 27. ASDR
  • 28. TODR Takeoff Distance Required is the longest of: a) The distance from the start of ground roll to the point where the aeroplane reaches a height of 35 ft and the V2 speed with engine failure having occurred at Vef. b) 115% of the distance between start of ground roll and the point where the aeroplane reaches a height of 35 ft and the V2 speed with all engines operating.  Distance “a)” will be usually longer with twin-engine aeroplanes.
  • 29. TODR
  • 30. CONSIDERATIONS  If V1 is reduced ASD will decrease and TOD will increase, and vice versa.  In general terms, acceleration is more affected than braking when the same condition affects both of them (for instance, runway slope).
  • 31. BALANCED FIELD LENGHT If the V1 is calculated in such a way that both the ASDR and the TODR are of equal length, the takeoff is said to be a balanced field length takeoff. This situation is given when neither stopway nor clearway exist, or if both are available. In that case the V1 is known as balanced V1. TOD = ASD 35 ft Balanced V1
  • 33. BALANCED FIELD LENGHT V1 m TODRASDR V1 increases with weight 100.000 Kg 120.000 Kg
  • 34. UNBALANCED FIELD LENGTH If the TORA is not enough to takeoff with our ATOW and a stopway or a clearway is available, we can take advantage of them, changing the balanced V1 value. Thus, ASDR <> TODR, but the situation will meet the requirements because of that clearway or stopway. Even with enough TORA, we may operate with unbalanced V1 if the balanced V1 is below the Vmcg or if it is above Vmbe.
  • 35. UNBALANCED FIELD LENGTH CLEARWAY AVAILABLE (NO STOPWAY) If we decrease the balanced V1 value, the ASDR will decrease and the TODR will increase. In this case TODR > ASDR, and ASDR = ASDA = TORA. TORA = ASDA = ASDR CWY TODR V1 < Balanced V1 35 ft
  • 36. UNBALANCED FIELD LENGTH STOPWAY AVAILABLE (NO CLEARWAY) If we increase the balanced V1 value, the ASDR will increase and the TODR will decrease. In this case ASDR > TODR, and TODR = TODA = TORA. TORA = TODA = TODR SWY ASDR V1 > Balanced V1 35 ft
  • 37. UNBALANCED FIELD LENGTH We have seen how changing the value of V1 we can increase our OTOW, if a clearway or a stopway is available. But if BOTH of them are available, then we can operate with a balanced V1, since both ASDA and TODA are increased with those clearway and stopway.