Transportation Improvement Status Report - 2012
PIONEER VALLEY PROJECTS NEEDS
$1,469,471,644 (173 Projects)
2
Costs
Despite the beneficial effects of the 2009 reforms, statewide
road and bridge funding gap has increased from $10.5 Billion
to at least $11.3 Billion, a 7% increase since 2007.
Highway Projects
Transportation Improvement Status Report - 2012
Estimated Cost
$796,464,188 (103 Projects)
3
Bridge Projects
Transportation Improvement Status Report - 2012
Estimated Cost
$304,364,334 (42 Projects)
4
Transit/Intermodal Projects
Transportation Improvement Status Report - 2012
Estimated Cost
$196,480,850 (11 Projects)
5
Bicycle/Pedestrian Projects
Transportation Improvement Status Report - 2012
Estimated Cost
$33,162,272 (12 Projects)
6
Rail Projects
Transportation Improvement Status Report - 2012
Estimated Cost
$139,000,000 + (8 Projects)*
* Several Projects are in the planning phase, project cost has not yet been determined
7
Transportation Improvement Status Report - 2012
Source: http://www.massdot.state.ma.us/
8
Strategies
Transportation reforms the Legislature enacted in 2009 have
resulted in cost savings estimated at $120 Million per year.
Transportation Improvement Status Report - 2012
As part of the reforms MassDOT has streamlined the design
and construction process in order to reduce the amount of
time between project initiation and construction, the
streamlined process includes:
1. Project Needs Form (PNF) – This new form identifies
needs of the proposed project location prior to start of
design.
2. Rehabilitation of roadways in place of reconstruction
3. Flagmen in place of Police Officers where appropriate.
9
Additional federal resources are no longer anticipated with
level funding now widely viewed as the very best case
scenario out of Washington along with a continuing ban on
earmarks.
Transportation Improvement Status Report - 2012
$0
$5,000,000
$10,000,000
$15,000,000
$20,000,000
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Regional Funding 2004-2013
Regional Funding
10
Funding
A public consensus that more resources are needed to
maintain our transportation infrastructure will be needed in
order to make further progress on long term solutions.
Transportation Improvement Status Report - 2012
$139,830,212
$219,031,869
$260,151,977
$355,115,493
$298,501,051
$363,981,681
$453,753,771
$498,603,095
$607,087,064 $609,149,070
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Axis Title
Project Backlog Vs. Targets
Regional TIP Target Estimated Total TIP Project Backlog
11
Transportation Improvement Status Report - 2012
New and alternative transportation revenue sources (not
tolls) need to be seriously considered and debated including:
1. A regional, place based revenue option that would
require voter-approval to implement; or
2. A vehicle miles travelled (VMT) tax.
12
Transportation Improvement Status Report - 2012
QUESTIONS?
13

Más contenido relacionado

La actualidad más candente

Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...
JumpingJaq
 
22 nov re estabilishing pms
22 nov re estabilishing pms22 nov re estabilishing pms
22 nov re estabilishing pms
Hamid62
 

La actualidad más candente (20)

Fairfax County Parking Ordinance Revsions July 2016
Fairfax County Parking Ordinance Revsions July 2016Fairfax County Parking Ordinance Revsions July 2016
Fairfax County Parking Ordinance Revsions July 2016
 
Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...Integration of mega projects into the existing network – the critical role of...
Integration of mega projects into the existing network – the critical role of...
 
mpo fiscal priorities committee - building the future transportation system p...
mpo fiscal priorities committee - building the future transportation system p...mpo fiscal priorities committee - building the future transportation system p...
mpo fiscal priorities committee - building the future transportation system p...
 
Reston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost AllocationsReston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost Allocations
 
22 nov re estabilishing pms
22 nov re estabilishing pms22 nov re estabilishing pms
22 nov re estabilishing pms
 
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
 
Reston Funding Plan: Rates/Contributions Discussion
Reston Funding Plan: Rates/Contributions DiscussionReston Funding Plan: Rates/Contributions Discussion
Reston Funding Plan: Rates/Contributions Discussion
 
Fixing America's Surface Transportation (FAST) Act
Fixing America's Surface Transportation (FAST) ActFixing America's Surface Transportation (FAST) Act
Fixing America's Surface Transportation (FAST) Act
 
I-395 Express Lanes Extension
I-395 Express Lanes ExtensionI-395 Express Lanes Extension
I-395 Express Lanes Extension
 
Investing in Washington State Transportation: Driving Economic Growth
Investing in Washington State Transportation: Driving Economic GrowthInvesting in Washington State Transportation: Driving Economic Growth
Investing in Washington State Transportation: Driving Economic Growth
 
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of CountywideDialogue on Transportation:Project SelectionA Si...Continuation of CountywideDialogue on Transportation:Project SelectionA Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
 
Dulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationDulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study Investigation
 
Agenda Item 6: Update Intelligent Transportation Systems (ITS) for Fairfax Co...
Agenda Item 6: Update Intelligent Transportation Systems (ITS) for Fairfax Co...Agenda Item 6: Update Intelligent Transportation Systems (ITS) for Fairfax Co...
Agenda Item 6: Update Intelligent Transportation Systems (ITS) for Fairfax Co...
 
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
 
Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...
Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...
Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...
 

Destacado (8)

Mapd65versionpublicfinance.revised by ag
Mapd65versionpublicfinance.revised by agMapd65versionpublicfinance.revised by ag
Mapd65versionpublicfinance.revised by ag
 
Effective Graphical Web Development
Effective Graphical Web DevelopmentEffective Graphical Web Development
Effective Graphical Web Development
 
Bsces rtgma presentation for mapd conference060712
Bsces rtgma presentation for mapd conference060712Bsces rtgma presentation for mapd conference060712
Bsces rtgma presentation for mapd conference060712
 
River overview 2012
River overview 2012River overview 2012
River overview 2012
 
International Design Agency - our Creation your success
International Design Agency - our Creation your successInternational Design Agency - our Creation your success
International Design Agency - our Creation your success
 
Wifc presentation mapc june 2012
Wifc presentation   mapc june 2012Wifc presentation   mapc june 2012
Wifc presentation mapc june 2012
 
Use mapd intro to preservation powerpoint presentation
Use  mapd intro to preservation powerpoint presentationUse  mapd intro to preservation powerpoint presentation
Use mapd intro to preservation powerpoint presentation
 
Amherst fbc mapd 2012 presentation
Amherst fbc mapd 2012 presentationAmherst fbc mapd 2012 presentation
Amherst fbc mapd 2012 presentation
 

Similar a Roscoe mapd 6.7.12

PLAN 2040 RTP Update Overview
PLAN 2040 RTP Update OverviewPLAN 2040 RTP Update Overview
PLAN 2040 RTP Update Overview
MelissaARC
 

Similar a Roscoe mapd 6.7.12 (20)

Transit in the Charlotte Region
Transit in the Charlotte RegionTransit in the Charlotte Region
Transit in the Charlotte Region
 
City Manager's Recommended 2015 Investment Plan
City Manager's Recommended 2015 Investment PlanCity Manager's Recommended 2015 Investment Plan
City Manager's Recommended 2015 Investment Plan
 
Moving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and BeyondMoving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and Beyond
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
FY 21 Debt Issuance
FY 21 Debt IssuanceFY 21 Debt Issuance
FY 21 Debt Issuance
 
Governor’s Infrastructure Funding Plan
Governor’s Infrastructure Funding PlanGovernor’s Infrastructure Funding Plan
Governor’s Infrastructure Funding Plan
 
DOPWIC Program Year 2018 Applicant Workshop
DOPWIC Program Year 2018 Applicant WorkshopDOPWIC Program Year 2018 Applicant Workshop
DOPWIC Program Year 2018 Applicant Workshop
 
Analyst breakfast: North American consultancy business - 19 March 2015
Analyst breakfast: North American consultancy business - 19 March 2015Analyst breakfast: North American consultancy business - 19 March 2015
Analyst breakfast: North American consultancy business - 19 March 2015
 
UDOT Presentation to 2019 Legislature
UDOT Presentation to 2019 LegislatureUDOT Presentation to 2019 Legislature
UDOT Presentation to 2019 Legislature
 
Transportation Funding Discussion: Board Retreat 2012
Transportation Funding Discussion: Board Retreat 2012Transportation Funding Discussion: Board Retreat 2012
Transportation Funding Discussion: Board Retreat 2012
 
07 steve healow
07 steve healow07 steve healow
07 steve healow
 
Crpc
CrpcCrpc
Crpc
 
Surface Transportation - Finance Context & Issues
Surface Transportation - Finance Context & IssuesSurface Transportation - Finance Context & Issues
Surface Transportation - Finance Context & Issues
 
PLAN 2040 RTP Update Overview
PLAN 2040 RTP Update OverviewPLAN 2040 RTP Update Overview
PLAN 2040 RTP Update Overview
 
DTPW's Rapid Transit Corridors Conceptual Financial Plan Proposal
DTPW's Rapid Transit Corridors Conceptual Financial Plan ProposalDTPW's Rapid Transit Corridors Conceptual Financial Plan Proposal
DTPW's Rapid Transit Corridors Conceptual Financial Plan Proposal
 
State and Local Road Project Updates: Part 3
State and Local Road Project Updates: Part 3State and Local Road Project Updates: Part 3
State and Local Road Project Updates: Part 3
 
North Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement StudyNorth Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement Study
 
A New Vision for State Rail “Transportation Action Plans”
A New Vision for State Rail “Transportation Action Plans”A New Vision for State Rail “Transportation Action Plans”
A New Vision for State Rail “Transportation Action Plans”
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentation
 
Colchester Capital Budget Presentation Updated
Colchester Capital Budget Presentation UpdatedColchester Capital Budget Presentation Updated
Colchester Capital Budget Presentation Updated
 

Más de Christopher Hayes

Mapd conservation development presentation 6 7-12
Mapd conservation development presentation 6 7-12Mapd conservation development presentation 6 7-12
Mapd conservation development presentation 6 7-12
Christopher Hayes
 
Mapd innovative zoning amherst
Mapd innovative zoning   amherstMapd innovative zoning   amherst
Mapd innovative zoning amherst
Christopher Hayes
 
Mapd conference tropical storm irene
Mapd conference tropical storm ireneMapd conference tropical storm irene
Mapd conference tropical storm irene
Christopher Hayes
 
Mapd flier re anthony flint talk
Mapd flier re anthony flint talkMapd flier re anthony flint talk
Mapd flier re anthony flint talk
Christopher Hayes
 
Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12
Christopher Hayes
 
Limited development projects final 6 8-2012
Limited development projects  final 6 8-2012Limited development projects  final 6 8-2012
Limited development projects final 6 8-2012
Christopher Hayes
 
Anthony flint mapd june 7 2012[1]
Anthony flint mapd june 7 2012[1]Anthony flint mapd june 7 2012[1]
Anthony flint mapd june 7 2012[1]
Christopher Hayes
 

Más de Christopher Hayes (12)

Solid waste mapd 2012
Solid waste mapd 2012Solid waste mapd 2012
Solid waste mapd 2012
 
Mapd 060412
Mapd 060412Mapd 060412
Mapd 060412
 
Mapd panel re fbc 2012
Mapd panel re fbc   2012Mapd panel re fbc   2012
Mapd panel re fbc 2012
 
Mapd conservation development presentation 6 7-12
Mapd conservation development presentation 6 7-12Mapd conservation development presentation 6 7-12
Mapd conservation development presentation 6 7-12
 
Mapd innovative zoning amherst
Mapd innovative zoning   amherstMapd innovative zoning   amherst
Mapd innovative zoning amherst
 
Mapd conference tropical storm irene
Mapd conference tropical storm ireneMapd conference tropical storm irene
Mapd conference tropical storm irene
 
Mapd flier re anthony flint talk
Mapd flier re anthony flint talkMapd flier re anthony flint talk
Mapd flier re anthony flint talk
 
Mapd ethics session 6.2012
Mapd ethics session 6.2012Mapd ethics session 6.2012
Mapd ethics session 6.2012
 
Mapd june 2012 - test
Mapd   june 2012 - testMapd   june 2012 - test
Mapd june 2012 - test
 
Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12
 
Limited development projects final 6 8-2012
Limited development projects  final 6 8-2012Limited development projects  final 6 8-2012
Limited development projects final 6 8-2012
 
Anthony flint mapd june 7 2012[1]
Anthony flint mapd june 7 2012[1]Anthony flint mapd june 7 2012[1]
Anthony flint mapd june 7 2012[1]
 

Último

Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Victor Rentea
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 

Último (20)

Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 

Roscoe mapd 6.7.12

  • 1. Focusing on the Transportation Infrastructure of the Pioneer Valley of Western Massachusetts Pioneer Valley Planning Commission 60 Congress Street Springfield, Massachusetts 01104 www.pvpc.org Public Infrastructure in Massachusetts: Costs, Strategies, Funding
  • 2. Transportation Improvement Status Report - 2012 THE REGION: PVPC’ REGIONAL PLANNING DISTRICT 1
  • 3. Transportation Improvement Status Report - 2012 PIONEER VALLEY PROJECTS NEEDS $1,469,471,644 (173 Projects) 2 Costs Despite the beneficial effects of the 2009 reforms, statewide road and bridge funding gap has increased from $10.5 Billion to at least $11.3 Billion, a 7% increase since 2007.
  • 4. Highway Projects Transportation Improvement Status Report - 2012 Estimated Cost $796,464,188 (103 Projects) 3
  • 5. Bridge Projects Transportation Improvement Status Report - 2012 Estimated Cost $304,364,334 (42 Projects) 4
  • 6. Transit/Intermodal Projects Transportation Improvement Status Report - 2012 Estimated Cost $196,480,850 (11 Projects) 5
  • 7. Bicycle/Pedestrian Projects Transportation Improvement Status Report - 2012 Estimated Cost $33,162,272 (12 Projects) 6
  • 8. Rail Projects Transportation Improvement Status Report - 2012 Estimated Cost $139,000,000 + (8 Projects)* * Several Projects are in the planning phase, project cost has not yet been determined 7
  • 9. Transportation Improvement Status Report - 2012 Source: http://www.massdot.state.ma.us/ 8 Strategies Transportation reforms the Legislature enacted in 2009 have resulted in cost savings estimated at $120 Million per year.
  • 10. Transportation Improvement Status Report - 2012 As part of the reforms MassDOT has streamlined the design and construction process in order to reduce the amount of time between project initiation and construction, the streamlined process includes: 1. Project Needs Form (PNF) – This new form identifies needs of the proposed project location prior to start of design. 2. Rehabilitation of roadways in place of reconstruction 3. Flagmen in place of Police Officers where appropriate. 9
  • 11. Additional federal resources are no longer anticipated with level funding now widely viewed as the very best case scenario out of Washington along with a continuing ban on earmarks. Transportation Improvement Status Report - 2012 $0 $5,000,000 $10,000,000 $15,000,000 $20,000,000 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Regional Funding 2004-2013 Regional Funding 10 Funding
  • 12. A public consensus that more resources are needed to maintain our transportation infrastructure will be needed in order to make further progress on long term solutions. Transportation Improvement Status Report - 2012 $139,830,212 $219,031,869 $260,151,977 $355,115,493 $298,501,051 $363,981,681 $453,753,771 $498,603,095 $607,087,064 $609,149,070 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Axis Title Project Backlog Vs. Targets Regional TIP Target Estimated Total TIP Project Backlog 11
  • 13. Transportation Improvement Status Report - 2012 New and alternative transportation revenue sources (not tolls) need to be seriously considered and debated including: 1. A regional, place based revenue option that would require voter-approval to implement; or 2. A vehicle miles travelled (VMT) tax. 12
  • 14. Transportation Improvement Status Report - 2012 QUESTIONS? 13