SlideShare una empresa de Scribd logo
1 de 23
Descargar para leer sin conexión
New Madrid Earthquake Catastrophic
            Planning
        Project Overview

                   Presented by:

                  Jim Wilkinson
             Executive Director, CUSEC

                     Derek Estes
      Acting Chief, FEMA Catastrophic Disaster
                   Planning Branch




           EIIP - EMForum.org
              March 25, 2009
Planning Mission
The mission of the New Madrid Seismic
Zone (NMSZ) Catastrophic Planning
Project is to create a comprehensive
preparedness plan for a catastrophic
earthquake in the NMSZ based on the
most advanced impact assessment
techniques and new response and
recovery methodologies.
Catastrophic
              Planning Background
1999 there were four hazards identified by FEMA as catastrophic – LA Earthquake,
Miami Hurricane, New Orleans Hurricane, New Madrid Earthquake

Since 9/11 the National Planning Scenarios list has evolved to 15 catastrophic events
– earthquakes and hurricanes being the only two natural hazards.

2004 New Orleans planning kicked off with Hurricane Pam

2005 New Madrid was scheduled but Katrina caused a delay

2006 New Madrid workshop geared up – contracts, planners, and key organizations
in place
    March 2007 Official kickoff
    Interim-Contingency plan developed
    Interim-

2007 Miami planning got underway
New Madrid Seismic Zone Catastrophic Planning
   What is a Catastrophic Event
A catastrophic event, as defined by the National
Response Plan is:

Any natural or man-made incident, including terrorism, that results in
extraordinary levels of mass casualties, damage, or disruption severely
affecting the population, infrastructure, environment, economy,
national morale, and/or government functions.

A catastrophic event could result in sustained national impacts over a
prolonged period of time; almost immediately exceeds resources
normally available to State, local, tribal, and private-sector authorities
in the impacted area; and significantly interrupts governmental
operations and emergency services to such an extent that national
security could be threatened. All catastrophic incidents are Incidents of
National Significance. These factors drive the urgency for coordinated
national planning to ensure accelerated Federal/National assistance.
What Makes an Earthquake in the
Central US Worthy of a Separate Plan?
Highest seismicity East of the
Rockies – Avg. 150-200 events a
year
Wider reaching effect than quake in
CA
    (See Map insert)
NMSZ → Significant Fault Systems,
High Consequences
44M people live in eight-state region
    12M in high risk area
         1- 3 million in Memphis and
         Saint Louis areas
High percentage of buildings not
designed for earthquakes
Tremendous impact on civil
infrastructure and critical facilities
Significant national impact
 Ripple effect across America
What Makes an Earthquake in the
Central US Worthy of a Separate Plan?
New Madrid Seismic Zone Catastrophic Planning
 Meeting The Challenge
The Federal Government and all levels
of government in the NMSZ recognize
the need for comprehensive
catastrophic planning.

The NMSZ Project addresses this need,
providing:

A Bottom-Up Planning Approach with
participation from all levels of Government
and the Private Sector “All Disasters are
Local”
Comprehensive ON-SITE Project Work:
Plan Development and Enhancement,
establishment of Sustainable Planning
Processes
A template to use in other parts of the
country for all hazard no-notice
catastrophic disasters
NMSZ Planning A Partnership Approach
  Involving Federal, State, Local participants
  Central US Earthquake Consortium (CUSEC)
      AL, AR, IL, IN, KY, MS, MO, TN
      Leading the way with the States
  Mid-America Earthquake Center
  Virginia Tech - Center for Technology, Security, and Policy;
  George Washington University - Institute for Crisis,
  Disaster & Risk Management
  DHS components
  FEMA Hq and Regions IV, V, VI, VII – Response, Recovery &
  Mitigation Directorates
  Federal and Sector Specific Agencies
      Critical Infrastructure
  Emergency Management Assistance Compact (EMAC)
  Tribal and local governments
  Private Sector
  Business, Industry, and Volunteer Organizations
  Innovative Emergency Management and
  Many other
New Madrid Seismic Zone Catastrophic Planning
     Key Goals
A multi-year effort as part of the
Catastrophic Annex to the National
Response Framework (NRF) to:
   Improve response, recovery and
   mitigation planning for a no-notice
   Catastrophic Earthquake.

   To plan for a coordinated response and
   recovery effort for Federal, State, and
   local agencies.

   To incorporate key lessons from the
   Hurricane Katrina response, the
   Southeast Louisiana Catastrophic
   Hurricane Planning, and previous
   earthquake response and recovery
   actions
New Madrid Planning Goals
        Continued

Address areas for improvement
Develop DHS/FEMA Emergency Operations Plan
Procedures to deal with catastrophic events under the
NRP/Framework
Create an environment for continued planning
  Improve modeling tools (HAZUS-MH)
  Develop a methodology for collecting and standardizing data
Develop relationships and contacts
Exercise
NMSZ Scenario Based Planning
    Utilizes HAZUS-MH

Mid America Earthquake Center,
George Washington University are
the lead partners for the modeling
Regional, State, and local models
built around magnitude 7.7 NM
event. 7.0 Wabash
Regional, and state baseline model
provided through CUSEC
New Madrid Seismic Zone Catastrophic Planning:
        Workshop Structure

Three levels of workshops:
  State workshops in all 8 CUSEC States
      Integration of local at-risk communities planning
   Regional Workshops
      Atlanta, GA (R4),
      Indianapolis, IN (R5),
      Little Rock (R6), and
      Jefferson City, MO (R7)
   Final integration workshop includes results
   from all regions
CUSEC Board Established
  Multi-State Priorities
Multi-State Coordination
Communications
Damage Assessment
Search and Rescue
Emergency Medical
Transportation
Post Earthquake Investigation Clearinghouse
(Coordination of research response)
Potential Functional Areas Of
            Emphasis
Command & Control          Access control & reentry
Saving Lives               Power, water & ice
                           distribution
Search & Rescue
                           Volunteer & donations
Temporary Medical Care
                           management
Evacuation including
                           Hazardous materials
Medical/Special Needs
                           External affairs
Transportation/staging &
distribution of critical   BIG partnership
resources                  Private sector
Sheltering                 coordination
Hosting                    Critical infrastructure
Schools
Products
Response Plans Specific to Earthquake
Hazard in the central US
    local, state
    Operational/response plans
    Improved Mitigation plans

  Regional
    Multi-State Coordination Plan
    FEMA Regional plans

  Federal (National)
    National Response Framework – Catastrophic annex
    Federal Interim Contingency Plan
Testing of Plans
 A national Level Exercise (NLE) is set for May
2011 to test the various plans developed over the
course of the planning initiative at the local, state,
                and federal levels.
Initial exercise planning
          achievements
Exercise Working Group established
General Timeline of Events Set
  Up to and including NLE 2011 (May)
Exercise Play
  Five Days
  Three phases (Initial response, extended
  response, short-term recovery)
Long-Term Recovery
Overarching Objectives
Exercise Objectives

Five Overarching Objectives to the 2011
Exercise for the CUSEC States
    Communications
    Critical Resource Logistics and Distribution
    Mass Care (Sheltering, Feeding, and Related
    Services)
    Citizen Evacuation and Shelter-in-Place
    Emergency Public Information and Warning
Summary
NMSZ catastrophic planning is a major
initiative involving countless
organizations and individuals addressing
the risk from all levels of government.

The work is not done - other priorities
need to be addressed
       Secondary Hazards
          Fire
          Landslide/levee/dam failures
          Hazardous material releases
       Social / Economic Impact
       Long term recovery
       And many others
NMSZ Planning Schedule
FY06
  Project coordination with FEMA Regions and States (ongoing)
  Deploy contractor personnel to sites (completed)
FY07
  Complete Interim S-1 Decision Matrix and Playbook
  Develop catastrophic NMSZ earthquake scenarios
  Establish Performance Metrics and outcomes
  Complete existing plans review
  Conduct state/local workshops
  Conduct regional workshops to develop draft catastrophic plans
FY08
  Conduct Final Integration Workshops
  Finalize and disseminate plan
New Madrid Seismic Zone Catastrophic Planning:

                Plan Validation

FY 2010
  Scenario based training and exercise of the plan
  State and local community participation
FY 2011
  Major Command Post exercise
Catastrophic Planning Initiative
       Contact Information

NMSZ Catastrophic planning effort – contact Jim
Wilkinson, 901-544-3570, jwilkinson@cusec.org

FEMA National Catastrophic Planning – Derek
Estes, 202-646-4359, derek.estes@dhs.gov

Scenario model enhancement - Contact Dr. Amr
Elnashai at 217-244-6302 or aelnash@uiuc.edu
Dr. Theresa Jefferson - tjeff@gwu.edu
Questions?

Más contenido relacionado

La actualidad más candente

National Policy on Disaster management 2009
National Policy on Disaster management 2009National Policy on Disaster management 2009
National Policy on Disaster management 2009Vishwa Sharma
 
Ra 9729 Climate Change Act of 2009
Ra 9729 Climate Change Act of 2009Ra 9729 Climate Change Act of 2009
Ra 9729 Climate Change Act of 2009Milka Pioli
 
Insurance in a changing risk landscape
Insurance in a changing risk landscapeInsurance in a changing risk landscape
Insurance in a changing risk landscapeDr Lendy Spires
 
04 draft final_chapter one_20140331
04 draft final_chapter one_2014033104 draft final_chapter one_20140331
04 draft final_chapter one_20140331Tudlo
 
Disaster management in india
Disaster management in indiaDisaster management in india
Disaster management in indiaDevyani Wanjari
 
California Geological Survey – “Probabilistic Tsunami Modeling and Public Pol...
California Geological Survey – “Probabilistic Tsunami Modeling and Public Pol...California Geological Survey – “Probabilistic Tsunami Modeling and Public Pol...
California Geological Survey – “Probabilistic Tsunami Modeling and Public Pol...EERI
 
Grand Challenges for Disaster Reduction
Grand Challenges for Disaster ReductionGrand Challenges for Disaster Reduction
Grand Challenges for Disaster ReductionFrancisYee1
 
Chapter 5 global assessment report
Chapter 5   global assessment reportChapter 5   global assessment report
Chapter 5 global assessment reportMahendra Poudel
 
National policy on disaster management 2009
National policy on disaster management 2009National policy on disaster management 2009
National policy on disaster management 2009MOHAMED HUDAIF T
 
Disaster risk management in cambodia
Disaster risk management in cambodiaDisaster risk management in cambodia
Disaster risk management in cambodiaThành Nguyễn
 
Phases Of An Event Of Scale
Phases Of An Event Of ScalePhases Of An Event Of Scale
Phases Of An Event Of ScaleBob Prieto
 
Chapter 6 UNISDR Initiative
Chapter 6 UNISDR InitiativeChapter 6 UNISDR Initiative
Chapter 6 UNISDR InitiativeMahendra Poudel
 
Lessons learned from autonomous and planned adaptation experiences en central...
Lessons learned from autonomous and planned adaptation experiences en central...Lessons learned from autonomous and planned adaptation experiences en central...
Lessons learned from autonomous and planned adaptation experiences en central...PROVIA
 
Disaster Management In INDIA.
Disaster Management In INDIA.Disaster Management In INDIA.
Disaster Management In INDIA.Urvesh Prajapati
 
Chapter 2 unisdr from 1960
Chapter 2   unisdr from 1960Chapter 2   unisdr from 1960
Chapter 2 unisdr from 1960Mahendra Poudel
 
H mdm operations protocol 20140331
H mdm operations protocol 20140331H mdm operations protocol 20140331
H mdm operations protocol 20140331Tudlo
 
Decision support system for Local Level Agencies and Communities Disaster Ris...
Decision support system for Local Level Agencies and Communities Disaster Ris...Decision support system for Local Level Agencies and Communities Disaster Ris...
Decision support system for Local Level Agencies and Communities Disaster Ris...Janathakshan Gte Ltd
 
03 executive summary 20140331
03 executive summary 2014033103 executive summary 20140331
03 executive summary 20140331Tudlo
 

La actualidad más candente (20)

National Policy on Disaster management 2009
National Policy on Disaster management 2009National Policy on Disaster management 2009
National Policy on Disaster management 2009
 
Ra 9729 Climate Change Act of 2009
Ra 9729 Climate Change Act of 2009Ra 9729 Climate Change Act of 2009
Ra 9729 Climate Change Act of 2009
 
Insurance in a changing risk landscape
Insurance in a changing risk landscapeInsurance in a changing risk landscape
Insurance in a changing risk landscape
 
04 draft final_chapter one_20140331
04 draft final_chapter one_2014033104 draft final_chapter one_20140331
04 draft final_chapter one_20140331
 
Disaster management in india
Disaster management in indiaDisaster management in india
Disaster management in india
 
National Disaster management Policy
National Disaster management PolicyNational Disaster management Policy
National Disaster management Policy
 
California Geological Survey – “Probabilistic Tsunami Modeling and Public Pol...
California Geological Survey – “Probabilistic Tsunami Modeling and Public Pol...California Geological Survey – “Probabilistic Tsunami Modeling and Public Pol...
California Geological Survey – “Probabilistic Tsunami Modeling and Public Pol...
 
Grand Challenges for Disaster Reduction
Grand Challenges for Disaster ReductionGrand Challenges for Disaster Reduction
Grand Challenges for Disaster Reduction
 
Chapter 5 global assessment report
Chapter 5   global assessment reportChapter 5   global assessment report
Chapter 5 global assessment report
 
National policy on disaster management 2009
National policy on disaster management 2009National policy on disaster management 2009
National policy on disaster management 2009
 
Disaster risk management in cambodia
Disaster risk management in cambodiaDisaster risk management in cambodia
Disaster risk management in cambodia
 
Phases Of An Event Of Scale
Phases Of An Event Of ScalePhases Of An Event Of Scale
Phases Of An Event Of Scale
 
Chapter 6 UNISDR Initiative
Chapter 6 UNISDR InitiativeChapter 6 UNISDR Initiative
Chapter 6 UNISDR Initiative
 
Lessons learned from autonomous and planned adaptation experiences en central...
Lessons learned from autonomous and planned adaptation experiences en central...Lessons learned from autonomous and planned adaptation experiences en central...
Lessons learned from autonomous and planned adaptation experiences en central...
 
Disaster Management In INDIA.
Disaster Management In INDIA.Disaster Management In INDIA.
Disaster Management In INDIA.
 
Chapter 2 unisdr from 1960
Chapter 2   unisdr from 1960Chapter 2   unisdr from 1960
Chapter 2 unisdr from 1960
 
Policy and Insititutional Arrangement for Disaster Management
Policy and Insititutional Arrangement for Disaster ManagementPolicy and Insititutional Arrangement for Disaster Management
Policy and Insititutional Arrangement for Disaster Management
 
H mdm operations protocol 20140331
H mdm operations protocol 20140331H mdm operations protocol 20140331
H mdm operations protocol 20140331
 
Decision support system for Local Level Agencies and Communities Disaster Ris...
Decision support system for Local Level Agencies and Communities Disaster Ris...Decision support system for Local Level Agencies and Communities Disaster Ris...
Decision support system for Local Level Agencies and Communities Disaster Ris...
 
03 executive summary 20140331
03 executive summary 2014033103 executive summary 20140331
03 executive summary 20140331
 

Similar a Nmsz Earthquake Planning

Ian Noble: Lessons from the PPCR and GFDRR
Ian Noble: Lessons from the PPCR and GFDRRIan Noble: Lessons from the PPCR and GFDRR
Ian Noble: Lessons from the PPCR and GFDRRNAPExpo 2014
 
Malawi and the LDCF
Malawi and the LDCFMalawi and the LDCF
Malawi and the LDCFNAP Events
 
WMO-role-in-disaster-mitigation (1).ppt
WMO-role-in-disaster-mitigation (1).pptWMO-role-in-disaster-mitigation (1).ppt
WMO-role-in-disaster-mitigation (1).pptAbdihakimAdan3
 
National disaster operation, kenya office of the president - regional consu...
National disaster operation, kenya   office of the president - regional consu...National disaster operation, kenya   office of the president - regional consu...
National disaster operation, kenya office of the president - regional consu...Strengthening Climate Resilience
 
mitigation strategies.pptx
mitigation strategies.pptxmitigation strategies.pptx
mitigation strategies.pptxmark269336
 
City Of Capitola Hazard Mitigation 2010
City Of Capitola Hazard Mitigation 2010City Of Capitola Hazard Mitigation 2010
City Of Capitola Hazard Mitigation 2010toddmayer
 
Order 866663 emergency planning in the uk public services
Order 866663 emergency planning in the uk public servicesOrder 866663 emergency planning in the uk public services
Order 866663 emergency planning in the uk public servicesKimberly Williams
 
Des inventar methodology
Des inventar methodologyDes inventar methodology
Des inventar methodologyIzzaAsshofi1
 
Disaster Management in india
Disaster Management in indiaDisaster Management in india
Disaster Management in indiaKaran Patel
 
Turning Black into Green - Incorporating DRR into Social and Economic Develop...
Turning Black into Green - Incorporating DRR into Social and Economic Develop...Turning Black into Green - Incorporating DRR into Social and Economic Develop...
Turning Black into Green - Incorporating DRR into Social and Economic Develop...Global Risk Forum GRFDavos
 
DM Basic Concepts.ppt
DM Basic Concepts.pptDM Basic Concepts.ppt
DM Basic Concepts.pptVinIta546343
 
Running head the recovery phase of the disaster recovery cycle .docx
Running head the recovery phase of the disaster recovery cycle   .docxRunning head the recovery phase of the disaster recovery cycle   .docx
Running head the recovery phase of the disaster recovery cycle .docxtoltonkendal
 
drrm roles.pptx
drrm roles.pptxdrrm roles.pptx
drrm roles.pptxmark269336
 
resilient measures strategies.pptx
resilient measures strategies.pptxresilient measures strategies.pptx
resilient measures strategies.pptxmark269336
 

Similar a Nmsz Earthquake Planning (20)

Ian Noble: Lessons from the PPCR and GFDRR
Ian Noble: Lessons from the PPCR and GFDRRIan Noble: Lessons from the PPCR and GFDRR
Ian Noble: Lessons from the PPCR and GFDRR
 
Malawi and the LDCF
Malawi and the LDCFMalawi and the LDCF
Malawi and the LDCF
 
WMO-role-in-disaster-mitigation (1).ppt
WMO-role-in-disaster-mitigation (1).pptWMO-role-in-disaster-mitigation (1).ppt
WMO-role-in-disaster-mitigation (1).ppt
 
National disaster operation, kenya office of the president - regional consu...
National disaster operation, kenya   office of the president - regional consu...National disaster operation, kenya   office of the president - regional consu...
National disaster operation, kenya office of the president - regional consu...
 
Mitigation Action Plan
Mitigation Action PlanMitigation Action Plan
Mitigation Action Plan
 
mitigation strategies.pptx
mitigation strategies.pptxmitigation strategies.pptx
mitigation strategies.pptx
 
City Of Capitola Hazard Mitigation 2010
City Of Capitola Hazard Mitigation 2010City Of Capitola Hazard Mitigation 2010
City Of Capitola Hazard Mitigation 2010
 
Disaster Management
 Disaster Management  Disaster Management
Disaster Management
 
Order 866663 emergency planning in the uk public services
Order 866663 emergency planning in the uk public servicesOrder 866663 emergency planning in the uk public services
Order 866663 emergency planning in the uk public services
 
Cambodia coordination and policy
Cambodia coordination and policyCambodia coordination and policy
Cambodia coordination and policy
 
Des inventar methodology
Des inventar methodologyDes inventar methodology
Des inventar methodology
 
Essay On Coping With Disaster
Essay On Coping With DisasterEssay On Coping With Disaster
Essay On Coping With Disaster
 
Disaster Management in india
Disaster Management in indiaDisaster Management in india
Disaster Management in india
 
Turning Black into Green - Incorporating DRR into Social and Economic Develop...
Turning Black into Green - Incorporating DRR into Social and Economic Develop...Turning Black into Green - Incorporating DRR into Social and Economic Develop...
Turning Black into Green - Incorporating DRR into Social and Economic Develop...
 
DM Basic Concepts.ppt
DM Basic Concepts.pptDM Basic Concepts.ppt
DM Basic Concepts.ppt
 
Running head the recovery phase of the disaster recovery cycle .docx
Running head the recovery phase of the disaster recovery cycle   .docxRunning head the recovery phase of the disaster recovery cycle   .docx
Running head the recovery phase of the disaster recovery cycle .docx
 
JMM_Panama_Peru_2009
JMM_Panama_Peru_2009JMM_Panama_Peru_2009
JMM_Panama_Peru_2009
 
Mike Alagna
Mike AlagnaMike Alagna
Mike Alagna
 
drrm roles.pptx
drrm roles.pptxdrrm roles.pptx
drrm roles.pptx
 
resilient measures strategies.pptx
resilient measures strategies.pptxresilient measures strategies.pptx
resilient measures strategies.pptx
 

Último

Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 

Último (20)

Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 

Nmsz Earthquake Planning

  • 1. New Madrid Earthquake Catastrophic Planning Project Overview Presented by: Jim Wilkinson Executive Director, CUSEC Derek Estes Acting Chief, FEMA Catastrophic Disaster Planning Branch EIIP - EMForum.org March 25, 2009
  • 2. Planning Mission The mission of the New Madrid Seismic Zone (NMSZ) Catastrophic Planning Project is to create a comprehensive preparedness plan for a catastrophic earthquake in the NMSZ based on the most advanced impact assessment techniques and new response and recovery methodologies.
  • 3. Catastrophic Planning Background 1999 there were four hazards identified by FEMA as catastrophic – LA Earthquake, Miami Hurricane, New Orleans Hurricane, New Madrid Earthquake Since 9/11 the National Planning Scenarios list has evolved to 15 catastrophic events – earthquakes and hurricanes being the only two natural hazards. 2004 New Orleans planning kicked off with Hurricane Pam 2005 New Madrid was scheduled but Katrina caused a delay 2006 New Madrid workshop geared up – contracts, planners, and key organizations in place March 2007 Official kickoff Interim-Contingency plan developed Interim- 2007 Miami planning got underway
  • 4. New Madrid Seismic Zone Catastrophic Planning What is a Catastrophic Event A catastrophic event, as defined by the National Response Plan is: Any natural or man-made incident, including terrorism, that results in extraordinary levels of mass casualties, damage, or disruption severely affecting the population, infrastructure, environment, economy, national morale, and/or government functions. A catastrophic event could result in sustained national impacts over a prolonged period of time; almost immediately exceeds resources normally available to State, local, tribal, and private-sector authorities in the impacted area; and significantly interrupts governmental operations and emergency services to such an extent that national security could be threatened. All catastrophic incidents are Incidents of National Significance. These factors drive the urgency for coordinated national planning to ensure accelerated Federal/National assistance.
  • 5. What Makes an Earthquake in the Central US Worthy of a Separate Plan? Highest seismicity East of the Rockies – Avg. 150-200 events a year Wider reaching effect than quake in CA (See Map insert) NMSZ → Significant Fault Systems, High Consequences 44M people live in eight-state region 12M in high risk area 1- 3 million in Memphis and Saint Louis areas High percentage of buildings not designed for earthquakes Tremendous impact on civil infrastructure and critical facilities Significant national impact Ripple effect across America
  • 6. What Makes an Earthquake in the Central US Worthy of a Separate Plan?
  • 7. New Madrid Seismic Zone Catastrophic Planning Meeting The Challenge The Federal Government and all levels of government in the NMSZ recognize the need for comprehensive catastrophic planning. The NMSZ Project addresses this need, providing: A Bottom-Up Planning Approach with participation from all levels of Government and the Private Sector “All Disasters are Local” Comprehensive ON-SITE Project Work: Plan Development and Enhancement, establishment of Sustainable Planning Processes A template to use in other parts of the country for all hazard no-notice catastrophic disasters
  • 8. NMSZ Planning A Partnership Approach Involving Federal, State, Local participants Central US Earthquake Consortium (CUSEC) AL, AR, IL, IN, KY, MS, MO, TN Leading the way with the States Mid-America Earthquake Center Virginia Tech - Center for Technology, Security, and Policy; George Washington University - Institute for Crisis, Disaster & Risk Management DHS components FEMA Hq and Regions IV, V, VI, VII – Response, Recovery & Mitigation Directorates Federal and Sector Specific Agencies Critical Infrastructure Emergency Management Assistance Compact (EMAC) Tribal and local governments Private Sector Business, Industry, and Volunteer Organizations Innovative Emergency Management and Many other
  • 9. New Madrid Seismic Zone Catastrophic Planning Key Goals A multi-year effort as part of the Catastrophic Annex to the National Response Framework (NRF) to: Improve response, recovery and mitigation planning for a no-notice Catastrophic Earthquake. To plan for a coordinated response and recovery effort for Federal, State, and local agencies. To incorporate key lessons from the Hurricane Katrina response, the Southeast Louisiana Catastrophic Hurricane Planning, and previous earthquake response and recovery actions
  • 10. New Madrid Planning Goals Continued Address areas for improvement Develop DHS/FEMA Emergency Operations Plan Procedures to deal with catastrophic events under the NRP/Framework Create an environment for continued planning Improve modeling tools (HAZUS-MH) Develop a methodology for collecting and standardizing data Develop relationships and contacts Exercise
  • 11. NMSZ Scenario Based Planning Utilizes HAZUS-MH Mid America Earthquake Center, George Washington University are the lead partners for the modeling Regional, State, and local models built around magnitude 7.7 NM event. 7.0 Wabash Regional, and state baseline model provided through CUSEC
  • 12. New Madrid Seismic Zone Catastrophic Planning: Workshop Structure Three levels of workshops: State workshops in all 8 CUSEC States Integration of local at-risk communities planning Regional Workshops Atlanta, GA (R4), Indianapolis, IN (R5), Little Rock (R6), and Jefferson City, MO (R7) Final integration workshop includes results from all regions
  • 13. CUSEC Board Established Multi-State Priorities Multi-State Coordination Communications Damage Assessment Search and Rescue Emergency Medical Transportation Post Earthquake Investigation Clearinghouse (Coordination of research response)
  • 14. Potential Functional Areas Of Emphasis Command & Control Access control & reentry Saving Lives Power, water & ice distribution Search & Rescue Volunteer & donations Temporary Medical Care management Evacuation including Hazardous materials Medical/Special Needs External affairs Transportation/staging & distribution of critical BIG partnership resources Private sector Sheltering coordination Hosting Critical infrastructure Schools
  • 15. Products Response Plans Specific to Earthquake Hazard in the central US local, state Operational/response plans Improved Mitigation plans Regional Multi-State Coordination Plan FEMA Regional plans Federal (National) National Response Framework – Catastrophic annex Federal Interim Contingency Plan
  • 16. Testing of Plans A national Level Exercise (NLE) is set for May 2011 to test the various plans developed over the course of the planning initiative at the local, state, and federal levels.
  • 17. Initial exercise planning achievements Exercise Working Group established General Timeline of Events Set Up to and including NLE 2011 (May) Exercise Play Five Days Three phases (Initial response, extended response, short-term recovery) Long-Term Recovery Overarching Objectives
  • 18. Exercise Objectives Five Overarching Objectives to the 2011 Exercise for the CUSEC States Communications Critical Resource Logistics and Distribution Mass Care (Sheltering, Feeding, and Related Services) Citizen Evacuation and Shelter-in-Place Emergency Public Information and Warning
  • 19. Summary NMSZ catastrophic planning is a major initiative involving countless organizations and individuals addressing the risk from all levels of government. The work is not done - other priorities need to be addressed Secondary Hazards Fire Landslide/levee/dam failures Hazardous material releases Social / Economic Impact Long term recovery And many others
  • 20. NMSZ Planning Schedule FY06 Project coordination with FEMA Regions and States (ongoing) Deploy contractor personnel to sites (completed) FY07 Complete Interim S-1 Decision Matrix and Playbook Develop catastrophic NMSZ earthquake scenarios Establish Performance Metrics and outcomes Complete existing plans review Conduct state/local workshops Conduct regional workshops to develop draft catastrophic plans FY08 Conduct Final Integration Workshops Finalize and disseminate plan
  • 21. New Madrid Seismic Zone Catastrophic Planning: Plan Validation FY 2010 Scenario based training and exercise of the plan State and local community participation FY 2011 Major Command Post exercise
  • 22. Catastrophic Planning Initiative Contact Information NMSZ Catastrophic planning effort – contact Jim Wilkinson, 901-544-3570, jwilkinson@cusec.org FEMA National Catastrophic Planning – Derek Estes, 202-646-4359, derek.estes@dhs.gov Scenario model enhancement - Contact Dr. Amr Elnashai at 217-244-6302 or aelnash@uiuc.edu Dr. Theresa Jefferson - tjeff@gwu.edu