SlideShare una empresa de Scribd logo
1 de 22
STUDY & DESIGN OF 66/33/25KV
GIS SUBSTATION
DMRC NEW DELHI
PROJECT REPORT
BACHELOR OF ENGINEERING
IN
ELECTRICAL ENGINEERING
UNDER THE SUPERVISION OF
SHEERAZ KIRMANI
ASST. PROFFESOR
FACULTY OF ENGG.&TECHNOLOGY
JAMIA MILLIA ISLAMIA PRESENTED BY
NEW DELHI-110025 DEEPAK KUMAR(11BE108)
GANESH KUMAR (11BE116)
INTRODUCTION
GAS INSULATED SUBSTATIONS
• GAS INSULATED USES SULFUR HEXAFLUORIDE (SF6)
• WHICH HAS A SUPERIOR DIELECTRIC PROPERTIES USED AT
MODERATE PRESSURE.
• IN GAS INSULATED SUBSTATION THE HIGH VOLTAGE
CONDUCTORS, CIRCUIT BREAKER
INTERRUPTERS,SWITCHES,CURRENT TRANSFORMER ,VOLTAGE
TRANFORMER AND LIGHTINING ARRESTERS ARE
ENCAPSULATED IN SF6 GAS INSIDE GROUNDED METAL
ENCLOSURES.
• THE GAS INSULATED SUBSTATION IS PREFERRED FOR
LOCATIONS SUCH AS LARGE CITIES AND TOWNS,
• UNDER GROUND STATIONS,AND MOUNTAINS AND VALLEY
REGIONS
It consist of
• Bus Bars
• Circuit Breakers
• Disconnecting Switches
• Earthing Switches
• Current Transformers
• Voltage Transformers
• Cable and Boxes
• Gas Supply and Gas Monitoring Equipment
• Local Control
Circuit Breaker
Under short circuit
conditions, however,
the current may reach
tens of thousands of
amperes at a power
factor as low as 0.1. It
is duty of a circuit
breaker to interrupt
such currents as soon
as possible to avoid
equipment damage.
Disconnectors
•Disconnectors or isolators
are used for electrical
isolation of circuit parts
•They are slow acting and
operating at off load
•Disconnectors must be
carefully designed and tested
to be able to break small
charging current without
generating too-high over
voltage,
Earthing Switch
Earthing switch is used to earth the
live parts during maintenance and
during testing.
During maintenance although
circuit is open still there are some
voltages on line , due to
which capacitance between line
and earth is charged.
Before proceeding to maintenance
work the voltage is discharged to
earth, by closing the earth switch.
Voltage Transformer
Voltage transformer is connected to
switchgear with the connecting flanges
with a barrier insulator.
 primary winding is insulated with
SF6 gas & connected to high voltage
terminal.
The primary winding is wounded
on the top of the core & secondary
windings.
secondary winding is connected to the
terminals in the external terminal box
through a gas tight multiple bushing.
Current Transformer
In the single phase enclosed
Core of CT is located outside
the enclosure inside for three
phase
Gas compartment to reduce
access of moisture and to
suppress gas-tight bushings for
secondary connections.
Cables Compartment
1. Optimized solution for
plug-in type power
cable connection.
2. Adjustable support
structures for minimum
requirements for the
GIS floor.
3. Fixation to the GIS
floor by cemented
anchor bolts, no need
for special foundation
(steel beams….etc)
TECHNICAL SPECIFICATION
ENCLOSURE TYPE : THREE PHASE ENCLOSURE
RATED VOLTAGE : 72.5 KV RMS
RATED FREQUENCY : 50HZ
RATED CURRENT OF 2500 A RMS
BUS BAR
RATED SHORT TIME : 40 KA RMS,3 SEC
CURRENT
GUARANTED SF6 GAS : LESS THAN 1%
LOSSES PER YEAR
SINGLE LINE DIAGRAM OF 66/33/25 KV GIS SUBSTATION
AUXILIARY MAIN TRANSFORMER(66/33
KV,30/45 MVA)
DESCRIP
TION
UNIT ONAN ONAF
RATING MVA 30 45
RATED
PRIMARY
VOLTAGE
KV 66 66
RATED
SECONDARY
VOLTAGE
KV 33 33
RATED
PRIMARY
CURRENT AT
66 KV
A 262.43 393.65
RATED
SECONDARY
CURRENT AT
33 KV
A 524.86 787.30
TRACTION TRANSFORMER(66/25 KV,40/50 MVA)
DESCRIPTION UNIT ONAN ONAF
RATING MVA 40 50
RATED PRIMARY VOLTAGE KV 66 66
RATED SECONDARY VOLTAGE KV 25 25
RATED PRIMARY CURRENT
AT 66 KV
A 606.06 757.58
RATED SECONDARY CURRENT
AT 33 KV
A 1600.00 2000.00
66 KV LINE CKT BREAKER
DESCRIPTION UNIT CALCULATED SELECTED
RATED VOLTAGE KV 66 66
RATED PRIMARY
CURRENT AT 66
KV
A 1151.22 2000
66 KV LINE ISOLATOR
DESCRIPTION UNIT CALCULATED SELECTED
RATED
VOLTAGE
KV 66 66
RATED PRIMARY
CURRENT AT 66
KV
A 1151.22 2000
PROPERTIES OF SF6
•SF6 does not harm to
the ozone layer.
•Sf6 gas is chemically stable
•Non poisonous
•Colourless & heavier than air
•Almost water insoluble
•Non inflammable
Comparison bw Gis & Ais
ADVANTAGES
• Main advantage of GIS over AIS is its phase to phase
spacing decreases significantly. This is more effective
in urban environment where land and its size is at a
premium
• Gis have no risks for fire & explosion.
• They generate no noise & have no radio interference
• It offer solutions including
-In industrial areas where space & pollution problems
-Mountain areas where ice & snow are major problems
DISADVANTAGES
 GIS installations tend to be much more
expensive that air-insulated installations
with the same rating.
 VFTO during switching operations or earth
faults and transient enclosure voltages
and particle contamination
 The Damage Effect Will Also Be Severe
Whenever Internal Fault occurs.
APPLICATIONS
• High voltage installations.
• Urban installations
• Indoor installations
FUTURE TRENDS IN GAS INSULATED
SUBSTATIONS
 Compact design of switch gear.
 Use of SF6 circuit breaker cells in the medium
high voltage GIS and fewer brakes per pole in
high voltage circuit breakers
 Optimization of GIS design to allow easier
maintenance
CONCLUSION
• GIS are necessary for EHV & UHV
• some important areas to be studied
include.
• more conservative designs.
• improved gas handling .
• Achieving & maintaining high levels of
availability requires a more integrated
approach to quality control by both
users and manufactures

Más contenido relacionado

La actualidad más candente

GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONsujitmandalsk
 
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,Sameer Kumar
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSoumya Raj Poddar
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationsharique_64
 
Gas insulated sub station 4
Gas insulated sub station 4Gas insulated sub station 4
Gas insulated sub station 4Ronal Parmar
 
Gas insulated sub station 3
Gas insulated sub station 3Gas insulated sub station 3
Gas insulated sub station 3Ronal Parmar
 
Gas insulated substation 2
Gas insulated substation 2Gas insulated substation 2
Gas insulated substation 2naga pooja
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationAjay Kuriakose
 
GSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURGSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURHARISH KUMAR
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationhimanshu kumar
 
Gis turnkey substation applications good quality (rev 2)
Gis turnkey substation applications good quality (rev 2)Gis turnkey substation applications good quality (rev 2)
Gis turnkey substation applications good quality (rev 2)MANASB72
 
Gas insulated transmission lines(gil)
Gas insulated transmission lines(gil)Gas insulated transmission lines(gil)
Gas insulated transmission lines(gil)sujay sahu
 
Gas insulated transmission line
Gas insulated transmission lineGas insulated transmission line
Gas insulated transmission lineitsmerahuliluvu
 
Modern substation design
Modern substation designModern substation design
Modern substation designrajesh18001 R
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...Ali Sepehri
 

La actualidad más candente (20)

GIS-NESCL-6
GIS-NESCL-6GIS-NESCL-6
GIS-NESCL-6
 
GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATION
 
Ppt
PptPpt
Ppt
 
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated Substation
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
Gas insulated sub station 4
Gas insulated sub station 4Gas insulated sub station 4
Gas insulated sub station 4
 
Gas insulated sub station 3
Gas insulated sub station 3Gas insulated sub station 3
Gas insulated sub station 3
 
GIS(GAS INSULATED SUBSTATION)
GIS(GAS  INSULATED  SUBSTATION) GIS(GAS  INSULATED  SUBSTATION)
GIS(GAS INSULATED SUBSTATION)
 
Gas insulated substation 2
Gas insulated substation 2Gas insulated substation 2
Gas insulated substation 2
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
GSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURGSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPUR
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
Gis turnkey substation applications good quality (rev 2)
Gis turnkey substation applications good quality (rev 2)Gis turnkey substation applications good quality (rev 2)
Gis turnkey substation applications good quality (rev 2)
 
GIS 400kv substation
GIS  400kv substationGIS  400kv substation
GIS 400kv substation
 
Gagan
GaganGagan
Gagan
 
Gas insulated transmission lines(gil)
Gas insulated transmission lines(gil)Gas insulated transmission lines(gil)
Gas insulated transmission lines(gil)
 
Gas insulated transmission line
Gas insulated transmission lineGas insulated transmission line
Gas insulated transmission line
 
Modern substation design
Modern substation designModern substation design
Modern substation design
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
 

Destacado

Sub stations-air insulated substations
Sub stations-air insulated substationsSub stations-air insulated substations
Sub stations-air insulated substationsbhanu lucky
 
Make heritage fun!
Make heritage fun!Make heritage fun!
Make heritage fun!GoUNESCO
 
American Academy of Pain Management 25th Annual Clinical Meeting-Phoenix, AZ ...
American Academy of Pain Management 25th Annual Clinical Meeting-Phoenix, AZ ...American Academy of Pain Management 25th Annual Clinical Meeting-Phoenix, AZ ...
American Academy of Pain Management 25th Annual Clinical Meeting-Phoenix, AZ ...American Academy of Pain Management
 
Codice di deontologia professionale
Codice di deontologia professionaleCodice di deontologia professionale
Codice di deontologia professionaleMichele Borsoi
 
Presentazione due diligence assicurativa sas
Presentazione due diligence assicurativa sasPresentazione due diligence assicurativa sas
Presentazione due diligence assicurativa sasMichele Borsoi
 
My time brochure april 2014 web
My time brochure april 2014 webMy time brochure april 2014 web
My time brochure april 2014 webmytimemk
 
What clients expect from a hotel marketing agency.
What clients expect from a hotel marketing agency.What clients expect from a hotel marketing agency.
What clients expect from a hotel marketing agency.Tambourine
 
How to increase email conversion rates
How to increase email conversion ratesHow to increase email conversion rates
How to increase email conversion ratesTambourine
 

Destacado (9)

Sub stations-air insulated substations
Sub stations-air insulated substationsSub stations-air insulated substations
Sub stations-air insulated substations
 
Make heritage fun!
Make heritage fun!Make heritage fun!
Make heritage fun!
 
American Academy of Pain Management 25th Annual Clinical Meeting-Phoenix, AZ ...
American Academy of Pain Management 25th Annual Clinical Meeting-Phoenix, AZ ...American Academy of Pain Management 25th Annual Clinical Meeting-Phoenix, AZ ...
American Academy of Pain Management 25th Annual Clinical Meeting-Phoenix, AZ ...
 
Codice di deontologia professionale
Codice di deontologia professionaleCodice di deontologia professionale
Codice di deontologia professionale
 
Presentazione due diligence assicurativa sas
Presentazione due diligence assicurativa sasPresentazione due diligence assicurativa sas
Presentazione due diligence assicurativa sas
 
My time brochure april 2014 web
My time brochure april 2014 webMy time brochure april 2014 web
My time brochure april 2014 web
 
What clients expect from a hotel marketing agency.
What clients expect from a hotel marketing agency.What clients expect from a hotel marketing agency.
What clients expect from a hotel marketing agency.
 
How to increase email conversion rates
How to increase email conversion ratesHow to increase email conversion rates
How to increase email conversion rates
 
Helsinki
HelsinkiHelsinki
Helsinki
 

Similar a Deepak kumar

Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationRaushanKumar582
 
Substation_fundamental.pptx
Substation_fundamental.pptxSubstation_fundamental.pptx
Substation_fundamental.pptxSatish Pydimarla
 
substation 101
substation 101substation 101
substation 101danica11
 
Jmv Presentation Airport and JMV LPS LTD
Jmv Presentation Airport and JMV LPS LTDJmv Presentation Airport and JMV LPS LTD
Jmv Presentation Airport and JMV LPS LTDMahesh Chandra Manav
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxborapring
 
Internship ppt(santhosh).pptx
Internship ppt(santhosh).pptxInternship ppt(santhosh).pptx
Internship ppt(santhosh).pptxBasavarajbanakar6
 
Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstationraja sukumar
 
Ac Test Transformer
Ac Test TransformerAc Test Transformer
Ac Test Transformerkennypowerhv
 
Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?Torben Haagh
 
Gas insulated transmission lines
Gas insulated transmission linesGas insulated transmission lines
Gas insulated transmission linesRahul Mehra
 
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...
Electrical safety presentation by jmv railway and invitation ireee2019 at ...Mahesh Chandra Manav
 
Hts transformer
Hts transformerHts transformer
Hts transformerARGHA SAHA
 

Similar a Deepak kumar (20)

Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
Substation_fundamental.pptx
Substation_fundamental.pptxSubstation_fundamental.pptx
Substation_fundamental.pptx
 
substation 101
substation 101substation 101
substation 101
 
GIS PRESENTATION.pdf
GIS PRESENTATION.pdfGIS PRESENTATION.pdf
GIS PRESENTATION.pdf
 
Jmv Presentation Airport and JMV LPS LTD
Jmv Presentation Airport and JMV LPS LTDJmv Presentation Airport and JMV LPS LTD
Jmv Presentation Airport and JMV LPS LTD
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
 
Internship ppt(santhosh).pptx
Internship ppt(santhosh).pptxInternship ppt(santhosh).pptx
Internship ppt(santhosh).pptx
 
Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstation
 
Gis91
Gis91Gis91
Gis91
 
Breaker Operation & Maintenance
Breaker Operation & MaintenanceBreaker Operation & Maintenance
Breaker Operation & Maintenance
 
Ac Test Transformer
Ac Test TransformerAc Test Transformer
Ac Test Transformer
 
Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?Moving to 66kV: Are current switchgears and transformers adequate?
Moving to 66kV: Are current switchgears and transformers adequate?
 
SF6 circuit breaker
SF6 circuit breakerSF6 circuit breaker
SF6 circuit breaker
 
RPS-SF6LBS-PKE
RPS-SF6LBS-PKERPS-SF6LBS-PKE
RPS-SF6LBS-PKE
 
Gas insulated transmission lines
Gas insulated transmission linesGas insulated transmission lines
Gas insulated transmission lines
 
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...Electrical safety  presentation by jmv   railway and invitation ireee2019 at ...
Electrical safety presentation by jmv railway and invitation ireee2019 at ...
 
Hts transformer
Hts transformerHts transformer
Hts transformer
 
5 power house
5 power house5 power house
5 power house
 
Jmv presentation solar
Jmv  presentation solarJmv  presentation solar
Jmv presentation solar
 

Último

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Último (20)

The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 

Deepak kumar

  • 1. STUDY & DESIGN OF 66/33/25KV GIS SUBSTATION DMRC NEW DELHI PROJECT REPORT BACHELOR OF ENGINEERING IN ELECTRICAL ENGINEERING UNDER THE SUPERVISION OF SHEERAZ KIRMANI ASST. PROFFESOR FACULTY OF ENGG.&TECHNOLOGY JAMIA MILLIA ISLAMIA PRESENTED BY NEW DELHI-110025 DEEPAK KUMAR(11BE108) GANESH KUMAR (11BE116)
  • 2. INTRODUCTION GAS INSULATED SUBSTATIONS • GAS INSULATED USES SULFUR HEXAFLUORIDE (SF6) • WHICH HAS A SUPERIOR DIELECTRIC PROPERTIES USED AT MODERATE PRESSURE. • IN GAS INSULATED SUBSTATION THE HIGH VOLTAGE CONDUCTORS, CIRCUIT BREAKER INTERRUPTERS,SWITCHES,CURRENT TRANSFORMER ,VOLTAGE TRANFORMER AND LIGHTINING ARRESTERS ARE ENCAPSULATED IN SF6 GAS INSIDE GROUNDED METAL ENCLOSURES. • THE GAS INSULATED SUBSTATION IS PREFERRED FOR LOCATIONS SUCH AS LARGE CITIES AND TOWNS, • UNDER GROUND STATIONS,AND MOUNTAINS AND VALLEY REGIONS
  • 3. It consist of • Bus Bars • Circuit Breakers • Disconnecting Switches • Earthing Switches • Current Transformers • Voltage Transformers • Cable and Boxes • Gas Supply and Gas Monitoring Equipment • Local Control
  • 4. Circuit Breaker Under short circuit conditions, however, the current may reach tens of thousands of amperes at a power factor as low as 0.1. It is duty of a circuit breaker to interrupt such currents as soon as possible to avoid equipment damage.
  • 5. Disconnectors •Disconnectors or isolators are used for electrical isolation of circuit parts •They are slow acting and operating at off load •Disconnectors must be carefully designed and tested to be able to break small charging current without generating too-high over voltage,
  • 6. Earthing Switch Earthing switch is used to earth the live parts during maintenance and during testing. During maintenance although circuit is open still there are some voltages on line , due to which capacitance between line and earth is charged. Before proceeding to maintenance work the voltage is discharged to earth, by closing the earth switch.
  • 7. Voltage Transformer Voltage transformer is connected to switchgear with the connecting flanges with a barrier insulator.  primary winding is insulated with SF6 gas & connected to high voltage terminal. The primary winding is wounded on the top of the core & secondary windings. secondary winding is connected to the terminals in the external terminal box through a gas tight multiple bushing.
  • 8. Current Transformer In the single phase enclosed Core of CT is located outside the enclosure inside for three phase Gas compartment to reduce access of moisture and to suppress gas-tight bushings for secondary connections.
  • 9. Cables Compartment 1. Optimized solution for plug-in type power cable connection. 2. Adjustable support structures for minimum requirements for the GIS floor. 3. Fixation to the GIS floor by cemented anchor bolts, no need for special foundation (steel beams….etc)
  • 10. TECHNICAL SPECIFICATION ENCLOSURE TYPE : THREE PHASE ENCLOSURE RATED VOLTAGE : 72.5 KV RMS RATED FREQUENCY : 50HZ RATED CURRENT OF 2500 A RMS BUS BAR RATED SHORT TIME : 40 KA RMS,3 SEC CURRENT GUARANTED SF6 GAS : LESS THAN 1% LOSSES PER YEAR
  • 11. SINGLE LINE DIAGRAM OF 66/33/25 KV GIS SUBSTATION
  • 12. AUXILIARY MAIN TRANSFORMER(66/33 KV,30/45 MVA) DESCRIP TION UNIT ONAN ONAF RATING MVA 30 45 RATED PRIMARY VOLTAGE KV 66 66 RATED SECONDARY VOLTAGE KV 33 33 RATED PRIMARY CURRENT AT 66 KV A 262.43 393.65 RATED SECONDARY CURRENT AT 33 KV A 524.86 787.30
  • 13. TRACTION TRANSFORMER(66/25 KV,40/50 MVA) DESCRIPTION UNIT ONAN ONAF RATING MVA 40 50 RATED PRIMARY VOLTAGE KV 66 66 RATED SECONDARY VOLTAGE KV 25 25 RATED PRIMARY CURRENT AT 66 KV A 606.06 757.58 RATED SECONDARY CURRENT AT 33 KV A 1600.00 2000.00
  • 14. 66 KV LINE CKT BREAKER DESCRIPTION UNIT CALCULATED SELECTED RATED VOLTAGE KV 66 66 RATED PRIMARY CURRENT AT 66 KV A 1151.22 2000
  • 15. 66 KV LINE ISOLATOR DESCRIPTION UNIT CALCULATED SELECTED RATED VOLTAGE KV 66 66 RATED PRIMARY CURRENT AT 66 KV A 1151.22 2000
  • 16. PROPERTIES OF SF6 •SF6 does not harm to the ozone layer. •Sf6 gas is chemically stable •Non poisonous •Colourless & heavier than air •Almost water insoluble •Non inflammable
  • 18. ADVANTAGES • Main advantage of GIS over AIS is its phase to phase spacing decreases significantly. This is more effective in urban environment where land and its size is at a premium • Gis have no risks for fire & explosion. • They generate no noise & have no radio interference • It offer solutions including -In industrial areas where space & pollution problems -Mountain areas where ice & snow are major problems
  • 19. DISADVANTAGES  GIS installations tend to be much more expensive that air-insulated installations with the same rating.  VFTO during switching operations or earth faults and transient enclosure voltages and particle contamination  The Damage Effect Will Also Be Severe Whenever Internal Fault occurs.
  • 20. APPLICATIONS • High voltage installations. • Urban installations • Indoor installations
  • 21. FUTURE TRENDS IN GAS INSULATED SUBSTATIONS  Compact design of switch gear.  Use of SF6 circuit breaker cells in the medium high voltage GIS and fewer brakes per pole in high voltage circuit breakers  Optimization of GIS design to allow easier maintenance
  • 22. CONCLUSION • GIS are necessary for EHV & UHV • some important areas to be studied include. • more conservative designs. • improved gas handling . • Achieving & maintaining high levels of availability requires a more integrated approach to quality control by both users and manufactures