SPILLWAYS
• When the water in the reservoir increases, the large accumulation of
water endangers the stability of the dam structure. To avoid this a
structure is provided in the body of a dam or near the dam or
periphery of the reservoir. This structure is called as spillway.
• Mainly used to discharge water during flood period.
Requirements:
• Provide structural stability to the dam under all condition
• Should able to pass the designed flood without raising the reservoir
level above H.F.L.
• Should have an efficient operation
• Should be economical
FUNCTION
• The spillway has the function of
discharging all the water not utilized for
generation. The maximum discharge
capacity of the spillway is 62.2 thousand
m3/s; 40 times greater than the mean
discharge of the Iguaçu Falls.
LOCATION OF SPILLWAY
• Generally, the spillways are provided at
the following places
• Spillways may be provided within the
body of the dam.
• Spillways may sometimes be provided at
one side or both sides of the dam.
• Sometimes by-pass spillway is provided
which is completely separate from the
dam.
Component parts of
Spillway :
Approach channel
Control structure
Discharge carrier
Discharge channel
Energy dissipators.
APPROACH
CHANNEL
Control
structure
Major component of spillway provided with bridge and
gates.
Regulates and controls the surplus water from the reservoir.
It does not allow discharge of water below the fixed
reservoir level.
Control
structure
Discharge
carrier
It is the waterway provided to convey the flows released
from the control structure to the downstream side of
spillway.
The cross section may be rectangular, trapezoidal or of
other shape.
Waterway may be wide or narrow, long or short.
Discharge
carrie
r
Discharge channel
Provided to convey the water from bottom of the
discharge carrier to the downstream flowing river.
It may be the downstream face of spillway itself.
The width of discharge channel depends on amount of
water to be conveyed.
Discharge
channel
Energy
dissipators
At the end of discharge carrier, the water released from
control structure has great velocities enough to cause scour.
Thus, energy dissipators are provided to avoid the scouring
of downstream side of spillway.
These are to be provided before water entering the discharge
channel.
The following are the different types of dissipators:
1. Bucket type energy dissipators
2. Stilling basin type dissipators
3. Baffle type dissipators.
Bucket type
dissipators
 The high kinetic energy of water is reduced by providing
a hydraulic jump at the end of spillway.
The hydraulic jump can be achieved by providing bucket
type dissipators.
By hydraulic jump of water some part of energy is
dissipated by aeration.
Bucket type
dissipator
Stilling
basin
Stilling basins are usually provided after the buckets.
Due to the hydraulic jump of water, the water falling on
the ground may cause cavitations on the ground.
These cavitations can be avoided by providing the stilling
basin.
The stilling basin consists of water which reduces some
part of energy of water.
Stilling
basin
Baffle type
dissipators
After passing the stilling basin water has still some energy.
If any amount of energy exist, it can be fully dissipated by
providing baffle dissipators.
In this, baffle type structures are provided in a number of
series depending on the amount of energy.
Baffle type dissipators
TYPES OF SPILLWAYS
 Overfall spillway
 Chute spillway
 Saddle spillway
 Shaft spillway
 Side channel spillway
 Emergency spillway
 siphon spillway
FIGURES
Overfall spillways
Chute spillways:
In this type water is conveyed from the
reservoir to the river or to nalla below
the dam through an excavated open
channel, through fairly steep slope
Overfall spillway:
• that allows water to pass over its crest
widely used on gravity, arch, &
buttress dam
• This is a simplest type
SADDLE SPILLWAYS
This type is mainly used when other types are not
favourable.
In some basins formed by a dam, there may be
one or more natural depressions or saddles in the
rim of the basin, which can be used as spillway.
It is essential that the bottom of the depression should
be at full reservoir level.
It is usually necessary for the saddle to be on firm
rock.
 The shape is just like a funnel .
 water drops through a vertical shaft in a the foundation material toa
horizontal conduit that conveys the water past the dam.
 Lower end of shaft is turned at right angle and then water taken out
below the dam horizontally.
 Also called as glory hole spillway.
SHAFT SPILLWAY
SIDE CHANNEL SPILLWAY
 When the dam is not rigid and it is undesirable to pass flood water
over the dam , this type of spillway is used.
 After passing crossing over the spillway crest ,water flows parallel to
the crest.
SIPHON SPILLWAYS
It is designed by the principle of a siphon.
When water rises over the FRL then water startspilling.
There is a air vent for removing the entrapped pressure from the
water.
EMERGENCY SPILLWAY
• This type is rarely used .
• Extra spillways provided on a project in rare case of
extreme floods(emergency)
• Used to convey frequently occurring outflow rates.
ADVANTAGES
• Very stable. The likelihood of serious structural
damage is less than for other types of structures.
• The rectangular weir is less likely to be clogged
by debri,s than the openings or other structures
of comparative discharge capacities.
• They are relatively easy to construct. The
concrete block type can be built with farm labor,
while the reinforced concrete or steel sheet
piling type usually requires the services of
a contractor.
DISADVANTAGES
• It is more costly than some other types of
structures where the required discharge
capacity is less than 100 c.f.s. and the
total head or drop is greater than 10 feet.
• It is not a favorable structure where
temporary spillway storage is needed to
obtain a large reduction in discharge.
• A stable grade below the structure is
essential.
ENERGY DISSIPATION
• As water passes over a spillway and down
the chute, potential energy converts into
increasing kinetic energy capacity of its
power plant.
• The energy can be dissipated by
addressing one or more parts of a
spillway's design
ENERGY DISSIPATION
SAFETY
• Spillway gates may operate suddenly without warning, under remote
control. Trespassers within the spillway run the risk of drowning.
Spillways are usually fenced and equipped with locked gates to
prevent casual trespassing within the structure. Warning signs,
sirens, and other measures may be in place to warn users of the
downstream area of sudden release of water. Operating protocols
may require "cracking" a gate to release a small amount of water to
warn persons downstream.
• The sudden closure of a spillway gate can result in the stranding of
fish, and this is also usually avoided.

Más contenido relacionado

La actualidad más candente

Dams arvind gupta-12march13 (2)
Dams   arvind gupta-12march13 (2)Dams   arvind gupta-12march13 (2)
Dams arvind gupta-12march13 (2)
Arvind Gupta
 

La actualidad más candente (20)

Spillway and its types
Spillway and its typesSpillway and its types
Spillway and its types
 
Cross Drainage Work
Cross Drainage Work Cross Drainage Work
Cross Drainage Work
 
types of dam
types of damtypes of dam
types of dam
 
Gravity dam
Gravity damGravity dam
Gravity dam
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
 
Design of barrages
Design of barragesDesign of barrages
Design of barrages
 
Laying, jointing and testing of pipes
Laying, jointing and testing of pipesLaying, jointing and testing of pipes
Laying, jointing and testing of pipes
 
Spillway gates
Spillway gatesSpillway gates
Spillway gates
 
Dams arvind gupta-12march13 (2)
Dams   arvind gupta-12march13 (2)Dams   arvind gupta-12march13 (2)
Dams arvind gupta-12march13 (2)
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
Gravity Dam
Gravity DamGravity Dam
Gravity Dam
 
Intake structures in wwwe
Intake structures in wwweIntake structures in wwwe
Intake structures in wwwe
 
Earthen Dam
Earthen DamEarthen Dam
Earthen Dam
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Gallery in Concrete Gravity Dam
Gallery in Concrete Gravity DamGallery in Concrete Gravity Dam
Gallery in Concrete Gravity Dam
 
River engineering
River engineeringRiver engineering
River engineering
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
 
River training works lecture
River training works lectureRiver training works lecture
River training works lecture
 

Similar a Spillways, Spillway capacity, flood routing through spillways, different types of spillways and gates, energy dissipation below spillways

Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01
saibabu48
 

Similar a Spillways, Spillway capacity, flood routing through spillways, different types of spillways and gates, energy dissipation below spillways (20)

Spillway
Spillway Spillway
Spillway
 
Spillway
SpillwaySpillway
Spillway
 
Unit 3 spillway
Unit 3 spillwayUnit 3 spillway
Unit 3 spillway
 
seminar presentation report on spillway
 seminar presentation report on spillway seminar presentation report on spillway
seminar presentation report on spillway
 
Spillway 140901101155-phpapp02
Spillway 140901101155-phpapp02Spillway 140901101155-phpapp02
Spillway 140901101155-phpapp02
 
4. Spillways.ppt
4. Spillways.ppt4. Spillways.ppt
4. Spillways.ppt
 
Spillways and Diversion Headwork's
Spillways and Diversion Headwork'sSpillways and Diversion Headwork's
Spillways and Diversion Headwork's
 
Canal MASONRY WORK
Canal MASONRY WORKCanal MASONRY WORK
Canal MASONRY WORK
 
Canal structures
Canal structuresCanal structures
Canal structures
 
Canal structures
Canal structuresCanal structures
Canal structures
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
 
UNIT 4.pptx
UNIT 4.pptxUNIT 4.pptx
UNIT 4.pptx
 
UNIT 4.pptx
UNIT 4.pptxUNIT 4.pptx
UNIT 4.pptx
 
MODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptx
MODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptxMODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptx
MODULE 4 REGULATING AND CROSS DRAINAGE WORKS.pptx
 
Hydroelectric Power Plant
Hydroelectric Power PlantHydroelectric Power Plant
Hydroelectric Power Plant
 
5. DAMS AND SPILLWAYS.pdf
5. DAMS AND SPILLWAYS.pdf5. DAMS AND SPILLWAYS.pdf
5. DAMS AND SPILLWAYS.pdf
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage Works
 
Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01
 

Más de Denish Jangid

WRED Water Resources Engineering Design lab Record work by Mr.Denish Jangid
WRED Water Resources Engineering Design lab Record work by Mr.Denish JangidWRED Water Resources Engineering Design lab Record work by Mr.Denish Jangid
WRED Water Resources Engineering Design lab Record work by Mr.Denish Jangid
Denish Jangid
 
All FLUID MECHANICS (FM) Notes by Mr. Denish Jangid
All FLUID MECHANICS (FM) Notes by Mr. Denish JangidAll FLUID MECHANICS (FM) Notes by Mr. Denish Jangid
All FLUID MECHANICS (FM) Notes by Mr. Denish Jangid
Denish Jangid
 
Complete all notes WATER RESOURCE ENGINEERING (WRE)
Complete all notes WATER RESOURCE ENGINEERING (WRE)Complete all notes WATER RESOURCE ENGINEERING (WRE)
Complete all notes WATER RESOURCE ENGINEERING (WRE)
Denish Jangid
 

Más de Denish Jangid (20)

Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
surveying_module-3-trigonometric-leveling by Denis Jangeed.pdf
surveying_module-3-trigonometric-leveling by Denis Jangeed.pdfsurveying_module-3-trigonometric-leveling by Denis Jangeed.pdf
surveying_module-3-trigonometric-leveling by Denis Jangeed.pdf
 
Total Station by Denis Jangeed.pdf
Total Station by Denis Jangeed.pdfTotal Station by Denis Jangeed.pdf
Total Station by Denis Jangeed.pdf
 
EDM-Electronic Distance Measurement by Denis Jangeed.pptx
EDM-Electronic Distance Measurement by Denis Jangeed.pptxEDM-Electronic Distance Measurement by Denis Jangeed.pptx
EDM-Electronic Distance Measurement by Denis Jangeed.pptx
 
Curve Surveying by DJ Sir.pptx
Curve Surveying by DJ Sir.pptxCurve Surveying by DJ Sir.pptx
Curve Surveying by DJ Sir.pptx
 
Surveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdf
Surveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdfSurveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdf
Surveying Levelling & Contouring Unit 2 Notes updating.pptx (1).pdf
 
A Complete Guidance How to do Summer Industrial Training after 4th & 6th Seme...
A Complete Guidance How to do Summer Industrial Training after 4th & 6th Seme...A Complete Guidance How to do Summer Industrial Training after 4th & 6th Seme...
A Complete Guidance How to do Summer Industrial Training after 4th & 6th Seme...
 
Wind and Seismic Analysis WASA or Building Design Notes.pdf
Wind and Seismic Analysis WASA or Building Design Notes.pdfWind and Seismic Analysis WASA or Building Design Notes.pdf
Wind and Seismic Analysis WASA or Building Design Notes.pdf
 
Surveying Complete Notes of Unit 1.pptx
Surveying Complete Notes of Unit 1.pptxSurveying Complete Notes of Unit 1.pptx
Surveying Complete Notes of Unit 1.pptx
 
WRED Water Resources Engineering Design lab Record work by Mr.Denish Jangid
WRED Water Resources Engineering Design lab Record work by Mr.Denish JangidWRED Water Resources Engineering Design lab Record work by Mr.Denish Jangid
WRED Water Resources Engineering Design lab Record work by Mr.Denish Jangid
 
WRE water resources engineering lab work by Mr. Denish Jangid
WRE water resources engineering lab work by Mr. Denish JangidWRE water resources engineering lab work by Mr. Denish Jangid
WRE water resources engineering lab work by Mr. Denish Jangid
 
All FLUID MECHANICS (FM) Notes by Mr. Denish Jangid
All FLUID MECHANICS (FM) Notes by Mr. Denish JangidAll FLUID MECHANICS (FM) Notes by Mr. Denish Jangid
All FLUID MECHANICS (FM) Notes by Mr. Denish Jangid
 
Complete all notes WATER RESOURCE ENGINEERING (WRE)
Complete all notes WATER RESOURCE ENGINEERING (WRE)Complete all notes WATER RESOURCE ENGINEERING (WRE)
Complete all notes WATER RESOURCE ENGINEERING (WRE)
 
Introduction of WATER RESOURCE ENGINEERING Unit 1 Definitions functions and a...
Introduction of WATER RESOURCE ENGINEERING Unit 1 Definitions functions and a...Introduction of WATER RESOURCE ENGINEERING Unit 1 Definitions functions and a...
Introduction of WATER RESOURCE ENGINEERING Unit 1 Definitions functions and a...
 
M sand difference between river sand and m sand & Manufactured sand- properti...
M sand difference between river sand and m sand & Manufactured sand- properti...M sand difference between river sand and m sand & Manufactured sand- properti...
M sand difference between river sand and m sand & Manufactured sand- properti...
 
water distribution system & warabandi by Denish Jangid unit 2 Water Resources...
water distribution system & warabandi by Denish Jangid unit 2 Water Resources...water distribution system & warabandi by Denish Jangid unit 2 Water Resources...
water distribution system & warabandi by Denish Jangid unit 2 Water Resources...
 
Water Resources Engineering types of wells with figures Denish Jangid Open we...
Water Resources Engineering types of wells with figures Denish Jangid Open we...Water Resources Engineering types of wells with figures Denish Jangid Open we...
Water Resources Engineering types of wells with figures Denish Jangid Open we...
 
Waterlogging Types & Causes of Waterlogging Effects & its control Salinity Ef...
Waterlogging Types & Causes of Waterlogging Effects & its control Salinity Ef...Waterlogging Types & Causes of Waterlogging Effects & its control Salinity Ef...
Waterlogging Types & Causes of Waterlogging Effects & its control Salinity Ef...
 
unit 4 vsem cross drainage works & srturcture water resource engineering Siph...
unit 4 vsem cross drainage works & srturcture water resource engineering Siph...unit 4 vsem cross drainage works & srturcture water resource engineering Siph...
unit 4 vsem cross drainage works & srturcture water resource engineering Siph...
 
Hydrology by Denish Jangid sir
Hydrology by Denish Jangid sirHydrology by Denish Jangid sir
Hydrology by Denish Jangid sir
 

Último

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Último (20)

Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 

Spillways, Spillway capacity, flood routing through spillways, different types of spillways and gates, energy dissipation below spillways

  • 1. Subject- WRE-II By Mr. Denish Jangid Assistant Professor Civil Engineering Department Topic- SPILLWAYS
  • 2. SPILLWAYS • When the water in the reservoir increases, the large accumulation of water endangers the stability of the dam structure. To avoid this a structure is provided in the body of a dam or near the dam or periphery of the reservoir. This structure is called as spillway. • Mainly used to discharge water during flood period. Requirements: • Provide structural stability to the dam under all condition • Should able to pass the designed flood without raising the reservoir level above H.F.L. • Should have an efficient operation • Should be economical
  • 3. FUNCTION • The spillway has the function of discharging all the water not utilized for generation. The maximum discharge capacity of the spillway is 62.2 thousand m3/s; 40 times greater than the mean discharge of the Iguaçu Falls.
  • 4. LOCATION OF SPILLWAY • Generally, the spillways are provided at the following places • Spillways may be provided within the body of the dam. • Spillways may sometimes be provided at one side or both sides of the dam. • Sometimes by-pass spillway is provided which is completely separate from the dam.
  • 5. Component parts of Spillway : Approach channel Control structure Discharge carrier Discharge channel Energy dissipators.
  • 7. Control structure Major component of spillway provided with bridge and gates. Regulates and controls the surplus water from the reservoir. It does not allow discharge of water below the fixed reservoir level.
  • 9. Discharge carrier It is the waterway provided to convey the flows released from the control structure to the downstream side of spillway. The cross section may be rectangular, trapezoidal or of other shape. Waterway may be wide or narrow, long or short.
  • 11. Discharge channel Provided to convey the water from bottom of the discharge carrier to the downstream flowing river. It may be the downstream face of spillway itself. The width of discharge channel depends on amount of water to be conveyed.
  • 13. Energy dissipators At the end of discharge carrier, the water released from control structure has great velocities enough to cause scour. Thus, energy dissipators are provided to avoid the scouring of downstream side of spillway. These are to be provided before water entering the discharge channel. The following are the different types of dissipators: 1. Bucket type energy dissipators 2. Stilling basin type dissipators 3. Baffle type dissipators.
  • 14. Bucket type dissipators  The high kinetic energy of water is reduced by providing a hydraulic jump at the end of spillway. The hydraulic jump can be achieved by providing bucket type dissipators. By hydraulic jump of water some part of energy is dissipated by aeration.
  • 16. Stilling basin Stilling basins are usually provided after the buckets. Due to the hydraulic jump of water, the water falling on the ground may cause cavitations on the ground. These cavitations can be avoided by providing the stilling basin. The stilling basin consists of water which reduces some part of energy of water.
  • 18. Baffle type dissipators After passing the stilling basin water has still some energy. If any amount of energy exist, it can be fully dissipated by providing baffle dissipators. In this, baffle type structures are provided in a number of series depending on the amount of energy.
  • 20. TYPES OF SPILLWAYS  Overfall spillway  Chute spillway  Saddle spillway  Shaft spillway  Side channel spillway  Emergency spillway  siphon spillway
  • 21. FIGURES Overfall spillways Chute spillways: In this type water is conveyed from the reservoir to the river or to nalla below the dam through an excavated open channel, through fairly steep slope Overfall spillway: • that allows water to pass over its crest widely used on gravity, arch, & buttress dam • This is a simplest type
  • 22. SADDLE SPILLWAYS This type is mainly used when other types are not favourable. In some basins formed by a dam, there may be one or more natural depressions or saddles in the rim of the basin, which can be used as spillway. It is essential that the bottom of the depression should be at full reservoir level. It is usually necessary for the saddle to be on firm rock.
  • 23.  The shape is just like a funnel .  water drops through a vertical shaft in a the foundation material toa horizontal conduit that conveys the water past the dam.  Lower end of shaft is turned at right angle and then water taken out below the dam horizontally.  Also called as glory hole spillway. SHAFT SPILLWAY
  • 24. SIDE CHANNEL SPILLWAY  When the dam is not rigid and it is undesirable to pass flood water over the dam , this type of spillway is used.  After passing crossing over the spillway crest ,water flows parallel to the crest.
  • 25. SIPHON SPILLWAYS It is designed by the principle of a siphon. When water rises over the FRL then water startspilling. There is a air vent for removing the entrapped pressure from the water.
  • 26.
  • 27. EMERGENCY SPILLWAY • This type is rarely used . • Extra spillways provided on a project in rare case of extreme floods(emergency) • Used to convey frequently occurring outflow rates.
  • 28. ADVANTAGES • Very stable. The likelihood of serious structural damage is less than for other types of structures. • The rectangular weir is less likely to be clogged by debri,s than the openings or other structures of comparative discharge capacities. • They are relatively easy to construct. The concrete block type can be built with farm labor, while the reinforced concrete or steel sheet piling type usually requires the services of a contractor.
  • 29. DISADVANTAGES • It is more costly than some other types of structures where the required discharge capacity is less than 100 c.f.s. and the total head or drop is greater than 10 feet. • It is not a favorable structure where temporary spillway storage is needed to obtain a large reduction in discharge. • A stable grade below the structure is essential.
  • 30. ENERGY DISSIPATION • As water passes over a spillway and down the chute, potential energy converts into increasing kinetic energy capacity of its power plant. • The energy can be dissipated by addressing one or more parts of a spillway's design
  • 32. SAFETY • Spillway gates may operate suddenly without warning, under remote control. Trespassers within the spillway run the risk of drowning. Spillways are usually fenced and equipped with locked gates to prevent casual trespassing within the structure. Warning signs, sirens, and other measures may be in place to warn users of the downstream area of sudden release of water. Operating protocols may require "cracking" a gate to release a small amount of water to warn persons downstream. • The sudden closure of a spillway gate can result in the stranding of fish, and this is also usually avoided.