2. Project Details.
Original Contract Value of the Project- Dhs.-289,927,807
Revised Contract value- Dhs.-
323,560,976
Value Invoiced( May 09)- Dhs.-
219,382,328
Type of Contract-
LumpSum
As per Contract-
Date of Commencement of Project 22 May
2007
Date of Completion of Project- 23
Nov.2008
Current Status-
Date of Completion of Project- 31
Dec.2009
Percentage Completion-
69%
Current Delays-
EOT Claimed - 360
Days