Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

Clause No. 4

The Contractor

Sub-Clause No. 4.2

Performance Security






Summary
Performance Security is in the amount as stated in particular conditions of the contract as a guarantee towards
performance of the contractor.
Performance Security is valid and enforceable until the contractor has executed and completed the works, remedied
any defects and has become entitled to receive performance certificate after issue of performance certificate by the
employer.
Performance Security is also linked with failure by the contractor to pay the employer an amount due, as either agreed
by the contractor or determined under employer’s claim, claims, disputes and arbitration and termination by employer.

Content of the FIDIC Clause in Brief
The Contractor shall obtain (at his cost) a Performance Security for proper performance, in the amount and currencies
stated in the Particular Conditions. If an amount is not stated in the Particular Conditions, this Sub-Clause shall not apply.
The Contractor shall deliver the Performance Security to the Employer within 28 days after both Parties have signed the
Contract Agreement. The Performance Security shall be issued by an entity and from within a country (or other
jurisdiction) approved by the Employer, and shall be in the form annexed to the Particular Conditions or in another form
approved by the Employer.
The Contractor shall ensure that the Performance Security is valid and enforceable until the Contractor has executed and
completed the Works and remedied any defects. If the terms of the Performance Security specify its expiry date, and the
Contractor has not become entitled to receive the Performance Certificate by the date 28 days prior to the expiry date, the
Contractor shall extend the validity of the Performance Security until the Works have been completed and any defects
have been remedied.
The Employer shall not make a claim under the Performance Security, except for amounts to which the Employer is
entitled under the Contract in the event of:
(a) failure by the Contractor to extend the validity of the Performance Security as described in the preceding paragraph, in
which event the Employer may claim the full amount of the Performance Security,
(b) failure by the Contractor to pay the Employer an amount due, as either agreed by the Contractor or determined under
Sub-Clause 2.5 [Employer's Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement
or determination,
(c) failure by the Contractor to remedy a default within 42 days after receiving the Employer's notice requiring the default
to be remedied, or
(d) circumstances which entitle the Employer to termination under Sub-Clause 15.2 [Termination by Employer],
irrespective of whether notice of termination has been given.
The Employer shall return the Performance Security to the Contractor within 21 days after the Contractor has become
entitled to receive the Performance Certificate.

Increasing the Amount of Performance Security during the Execution of the Contract
Clause 11 ‘Defect Liability’, Sub-Clause ‘Removal of Defective Work’ (To understand the provision in FIDIC related to
increase amount of Performance Security)
If the defect or damage cannot be remedied expeditiously on the Site and the Employer gives consent, the Contractor may
remove from the Site for the purposes of repair such items of Plant as are defective or damaged. This consent may require
the Contractor to increase the amount of the Performance Security by the full replacement cost of these items, or to
provide other appropriate security.
Pg. 1/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

Guidance for Performance Security
The amount of the performance security shall be ten percent 10% of the contract price stated in the contract agreement.
If the performance security is in the form of a bank guarantee, it shall be issued either (a) by a bank located in the country,
or (b) directly by a foreign bank acceptable to the employer. If the performance security is not in the form of a bank
guarantee, it shall be furnished by a financial entity registered, or licensed to do business, in the country.
Forms of Performance Security
Demand Guarantee: Performance bond or other type of guarantee payable to the employer on demand, often without
the presentation of other documents and without the need to show the demand is in compliance with the terms of the
underlying contract. In effect, it is a substitute for a cash deposit. Under UK law, a demand guarantee is independent of the
underlying contract and is separate from the counter-guarantee (if any) given by the employer’s bank to
the contractor’s bank. Under US law also a demand guarantee enjoys similar protection and is called a standby letter of
credit.
Surety Bond: Formal, legally enforceable contract between the contractor and the employer and a third party (the surety,
such as a bank, bonding company, or insurance company) whereby the surety guarantees payment of a specified
maximum sum, or to otherwise compensate (indemnify), the employer against damage or loss caused by the actions (or
a failure to perform.
Notes:
 It is quite common for the employer to require an ‘on demand’ guarantee. It is however recommended that a ‘surety
bond’ as should be used. ‘On demand’ guarantees are quite a dangerous instrument due to the fact that in principle the
beneficiary becomes entitled to call for payment despite lack of any reason or justification to do so, whereas a ‘surety
bond’ can only be drawn if and when a substantial claim exists which remains unsatisfied.
 The intention behind this security is to have the financial responsibility of the surety standing behind the contractor’s
completion obligations. Thus it is critical to pay as much attention to the language of the performance bond as to the
language of any significant contract. The FIDIC model forms of securities require that the surety indemnify the
employer for the consequences of default or breach of contract.
It is critical to carefully scrutinize the extent of liability under the performance security, in particular because Subclause
4.2 includes an indemnity to the contractor if the employer was not entitled to make the claim.
Applied Clauses of the Performance Security/ Bond for EPC Contracts (FIDIC or Mixed)
(References to the clauses are removed)
Performance Security means the bonds and the parent company guarantee.
Performance Bond means the bond in the form set out in annexure (Performance Bond), issued by a bank or financial
institution reasonably acceptable to the employer with a credit rating of no worse than [A+] (Standard and Poor’s) or [A1]
(Moody’s).
The performance bond shall be the equivalent of 10% of the contract price (or any replacement thereof pursuant to
clause).
In the event of a variation under (Variations and Adjustments), which results in an increase or decrease in the contract
price by an amount equal to or greater than 5% (either by itself or when aggregated with all variations since any previous
adjustment to the amount of the bonds), the maximum amounts available under the bonds pursuant shall be increased or
decreased accordingly, and the contractor shall deliver a replacement bond to cover such increased or decreased maximum
amount issued by an entity meeting the requirements as previously approved by the employer, such approval not to be
unreasonably withheld or delayed and otherwise on the same terms as the replaced bond. Such replacement bond shall be
delivered duly executed to the employer no later than 30 days following the variation. All fees, taxes and expenses
Pg. 2/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

associated with procuring, preparing, completing and stamping (if applicable) each of the bonds and the parent company
guarantee shall be paid by the contractor.
If the contractor fails to provide an extension to a bond or replacement bond, the employer shall have the right to call the
outstanding balance of the bond and use and apply the same as security for compliance by the contractor with its
obligations and liabilities under the contract. The employer shall be entitled to make deductions against any amounts so
held in respect of any claim for which it would have been entitled to call against an extended or replacement bond (had the
contractor provided the same), but shall otherwise return to the contractor the remaining balance of such amounts (without
any interest).
Event of Performance Security in Sequence of Contract Activities as Per FIDIC
Schematic (only symbol
to be considered as time-line)
Signing of
the Contract
Agreement

< 28
Days

Issue of
Performance
Security by
the
Contractor
< 42 Days

Time for
Completion

Tests on
Completion

Issue of
Taking
Over
Certificate

Remedying
of Defects

Commencement
Date



Pg. 3/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC

Defect
Notification
Period

Issue of the
Performance
Certificate

Within
21
Days

Return of
the
Performance
Security by
the
Employer

Más contenido relacionado

La actualidad más candente

Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptxssuserb337ce1
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 

La actualidad más candente (20)

fidic , jct and nec contracts
fidic , jct and nec contractsfidic , jct and nec contracts
fidic , jct and nec contracts
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Bim arabia red fidic
Bim arabia red fidicBim arabia red fidic
Bim arabia red fidic
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Construction contract
Construction contract Construction contract
Construction contract
 

Similar a Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999.

Vietnam Accounting Standards - VAS 19 Insurance Contract
Vietnam Accounting Standards - VAS 19 Insurance ContractVietnam Accounting Standards - VAS 19 Insurance Contract
Vietnam Accounting Standards - VAS 19 Insurance ContractAC&C Consulting Co., Ltd.
 
Mechanics Lien Coverage
Mechanics Lien CoverageMechanics Lien Coverage
Mechanics Lien Coveragedtownsend
 
Calling of a demand guarantee
Calling of a demand guaranteeCalling of a demand guarantee
Calling of a demand guaranteeAndrea Frosinini
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingRHKLegal
 
Avn 99 aircraft finance lease contract continuing liability endorsement
Avn 99 aircraft finance lease contract   continuing liability endorsement Avn 99 aircraft finance lease contract   continuing liability endorsement
Avn 99 aircraft finance lease contract continuing liability endorsement Ridwan Ichsan
 
Avn 67 c airline finance lease contract endorsement hull war
Avn 67 c airline finance lease contract endorsement hull warAvn 67 c airline finance lease contract endorsement hull war
Avn 67 c airline finance lease contract endorsement hull warRidwan Ichsan
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTXRyan Hatton
 
JPMorgan Chase Guaranty Amended 3-24-08
JPMorgan Chase Guaranty Amended 3-24-08JPMorgan Chase Guaranty Amended 3-24-08
JPMorgan Chase Guaranty Amended 3-24-08finance2
 
Avn 67 c airline finance lease contract endorsement
Avn 67 c airline finance lease contract endorsementAvn 67 c airline finance lease contract endorsement
Avn 67 c airline finance lease contract endorsementRidwan Ichsan
 
Guarantee-Backed Lines of Credit
Guarantee-Backed Lines of CreditGuarantee-Backed Lines of Credit
Guarantee-Backed Lines of CreditLuca Bernardinetti
 
Letter of Gurantee
Letter of GuranteeLetter of Gurantee
Letter of GuranteeRaxid Aqeel
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
Risk Management For Contractors
Risk Management For ContractorsRisk Management For Contractors
Risk Management For Contractorsdawnpogue
 
Title Insurance Commitment
Title Insurance CommitmentTitle Insurance Commitment
Title Insurance Commitmentlegal1
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 

Similar a Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999. (20)

Clause 14.docx
Clause 14.docxClause 14.docx
Clause 14.docx
 
Vietnam Accounting Standards - VAS 19 Insurance Contract
Vietnam Accounting Standards - VAS 19 Insurance ContractVietnam Accounting Standards - VAS 19 Insurance Contract
Vietnam Accounting Standards - VAS 19 Insurance Contract
 
Mechanics Lien Coverage
Mechanics Lien CoverageMechanics Lien Coverage
Mechanics Lien Coverage
 
Calling of a demand guarantee
Calling of a demand guaranteeCalling of a demand guarantee
Calling of a demand guarantee
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract Drafting
 
Avn 99 aircraft finance lease contract continuing liability endorsement
Avn 99 aircraft finance lease contract   continuing liability endorsement Avn 99 aircraft finance lease contract   continuing liability endorsement
Avn 99 aircraft finance lease contract continuing liability endorsement
 
Avn 67 c airline finance lease contract endorsement hull war
Avn 67 c airline finance lease contract endorsement hull warAvn 67 c airline finance lease contract endorsement hull war
Avn 67 c airline finance lease contract endorsement hull war
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
 
JPMorgan Chase Guaranty Amended 3-24-08
JPMorgan Chase Guaranty Amended 3-24-08JPMorgan Chase Guaranty Amended 3-24-08
JPMorgan Chase Guaranty Amended 3-24-08
 
Avn 67 c airline finance lease contract endorsement
Avn 67 c airline finance lease contract endorsementAvn 67 c airline finance lease contract endorsement
Avn 67 c airline finance lease contract endorsement
 
Guarantee-Backed Lines of Credit
Guarantee-Backed Lines of CreditGuarantee-Backed Lines of Credit
Guarantee-Backed Lines of Credit
 
IFRS 4
IFRS 4IFRS 4
IFRS 4
 
Surety Bonds
Surety BondsSurety Bonds
Surety Bonds
 
Letter of Gurantee
Letter of GuranteeLetter of Gurantee
Letter of Gurantee
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Business laws
Business lawsBusiness laws
Business laws
 
Risk Management For Contractors
Risk Management For ContractorsRisk Management For Contractors
Risk Management For Contractors
 
Title Insurance Commitment
Title Insurance CommitmentTitle Insurance Commitment
Title Insurance Commitment
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Bonds
BondsBonds
Bonds
 

Más de Divyanshu Dayal

The Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and TrucksThe Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and TrucksDivyanshu Dayal
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Divyanshu Dayal
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Divyanshu Dayal
 
Development of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and ContractsDevelopment of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and ContractsDivyanshu Dayal
 
International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...Divyanshu Dayal
 
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)Divyanshu Dayal
 
Coal Facts 2013 Demand Supply
Coal Facts 2013 Demand SupplyCoal Facts 2013 Demand Supply
Coal Facts 2013 Demand SupplyDivyanshu Dayal
 
Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)Divyanshu Dayal
 
How to Export From India- An Introduction
How to Export From India- An IntroductionHow to Export From India- An Introduction
How to Export From India- An IntroductionDivyanshu Dayal
 
Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.Divyanshu Dayal
 
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...Divyanshu Dayal
 
4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax4. Indian Taxation. Service Tax
4. Indian Taxation. Service TaxDivyanshu Dayal
 
3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)Divyanshu Dayal
 
2. Indian Taxation. Customs Duty.
2. Indian Taxation. Customs Duty.2. Indian Taxation. Customs Duty.
2. Indian Taxation. Customs Duty.Divyanshu Dayal
 

Más de Divyanshu Dayal (20)

incoterms-2010
incoterms-2010incoterms-2010
incoterms-2010
 
RESUME WITH A SOUL
RESUME WITH A SOULRESUME WITH A SOUL
RESUME WITH A SOUL
 
The Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and TrucksThe Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and Trucks
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
 
Development of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and ContractsDevelopment of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and Contracts
 
Purchasing Management
Purchasing ManagementPurchasing Management
Purchasing Management
 
International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...
 
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
 
Coal Facts 2013 Demand Supply
Coal Facts 2013 Demand SupplyCoal Facts 2013 Demand Supply
Coal Facts 2013 Demand Supply
 
Mining Law in Asia
Mining Law in AsiaMining Law in Asia
Mining Law in Asia
 
Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)
 
How to Export From India- An Introduction
How to Export From India- An IntroductionHow to Export From India- An Introduction
How to Export From India- An Introduction
 
Type of Contracts.
Type of Contracts.Type of Contracts.
Type of Contracts.
 
Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.
 
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
 
Resume
ResumeResume
Resume
 
4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax
 
3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)
 
2. Indian Taxation. Customs Duty.
2. Indian Taxation. Customs Duty.2. Indian Taxation. Customs Duty.
2. Indian Taxation. Customs Duty.
 

Último

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...apidays
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelDeepika Singh
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Bhuvaneswari Subramani
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWERMadyBayot
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistandanishmna97
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Orbitshub
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxRustici Software
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdfSandro Moreira
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsNanddeep Nachan
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MIND CTI
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...apidays
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusZilliz
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 

Último (20)

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 

Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999.

  • 1. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 Clause No. 4 The Contractor Sub-Clause No. 4.2 Performance Security    Summary Performance Security is in the amount as stated in particular conditions of the contract as a guarantee towards performance of the contractor. Performance Security is valid and enforceable until the contractor has executed and completed the works, remedied any defects and has become entitled to receive performance certificate after issue of performance certificate by the employer. Performance Security is also linked with failure by the contractor to pay the employer an amount due, as either agreed by the contractor or determined under employer’s claim, claims, disputes and arbitration and termination by employer. Content of the FIDIC Clause in Brief The Contractor shall obtain (at his cost) a Performance Security for proper performance, in the amount and currencies stated in the Particular Conditions. If an amount is not stated in the Particular Conditions, this Sub-Clause shall not apply. The Contractor shall deliver the Performance Security to the Employer within 28 days after both Parties have signed the Contract Agreement. The Performance Security shall be issued by an entity and from within a country (or other jurisdiction) approved by the Employer, and shall be in the form annexed to the Particular Conditions or in another form approved by the Employer. The Contractor shall ensure that the Performance Security is valid and enforceable until the Contractor has executed and completed the Works and remedied any defects. If the terms of the Performance Security specify its expiry date, and the Contractor has not become entitled to receive the Performance Certificate by the date 28 days prior to the expiry date, the Contractor shall extend the validity of the Performance Security until the Works have been completed and any defects have been remedied. The Employer shall not make a claim under the Performance Security, except for amounts to which the Employer is entitled under the Contract in the event of: (a) failure by the Contractor to extend the validity of the Performance Security as described in the preceding paragraph, in which event the Employer may claim the full amount of the Performance Security, (b) failure by the Contractor to pay the Employer an amount due, as either agreed by the Contractor or determined under Sub-Clause 2.5 [Employer's Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement or determination, (c) failure by the Contractor to remedy a default within 42 days after receiving the Employer's notice requiring the default to be remedied, or (d) circumstances which entitle the Employer to termination under Sub-Clause 15.2 [Termination by Employer], irrespective of whether notice of termination has been given. The Employer shall return the Performance Security to the Contractor within 21 days after the Contractor has become entitled to receive the Performance Certificate. Increasing the Amount of Performance Security during the Execution of the Contract Clause 11 ‘Defect Liability’, Sub-Clause ‘Removal of Defective Work’ (To understand the provision in FIDIC related to increase amount of Performance Security) If the defect or damage cannot be remedied expeditiously on the Site and the Employer gives consent, the Contractor may remove from the Site for the purposes of repair such items of Plant as are defective or damaged. This consent may require the Contractor to increase the amount of the Performance Security by the full replacement cost of these items, or to provide other appropriate security. Pg. 1/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
  • 2. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 Guidance for Performance Security The amount of the performance security shall be ten percent 10% of the contract price stated in the contract agreement. If the performance security is in the form of a bank guarantee, it shall be issued either (a) by a bank located in the country, or (b) directly by a foreign bank acceptable to the employer. If the performance security is not in the form of a bank guarantee, it shall be furnished by a financial entity registered, or licensed to do business, in the country. Forms of Performance Security Demand Guarantee: Performance bond or other type of guarantee payable to the employer on demand, often without the presentation of other documents and without the need to show the demand is in compliance with the terms of the underlying contract. In effect, it is a substitute for a cash deposit. Under UK law, a demand guarantee is independent of the underlying contract and is separate from the counter-guarantee (if any) given by the employer’s bank to the contractor’s bank. Under US law also a demand guarantee enjoys similar protection and is called a standby letter of credit. Surety Bond: Formal, legally enforceable contract between the contractor and the employer and a third party (the surety, such as a bank, bonding company, or insurance company) whereby the surety guarantees payment of a specified maximum sum, or to otherwise compensate (indemnify), the employer against damage or loss caused by the actions (or a failure to perform. Notes:  It is quite common for the employer to require an ‘on demand’ guarantee. It is however recommended that a ‘surety bond’ as should be used. ‘On demand’ guarantees are quite a dangerous instrument due to the fact that in principle the beneficiary becomes entitled to call for payment despite lack of any reason or justification to do so, whereas a ‘surety bond’ can only be drawn if and when a substantial claim exists which remains unsatisfied.  The intention behind this security is to have the financial responsibility of the surety standing behind the contractor’s completion obligations. Thus it is critical to pay as much attention to the language of the performance bond as to the language of any significant contract. The FIDIC model forms of securities require that the surety indemnify the employer for the consequences of default or breach of contract. It is critical to carefully scrutinize the extent of liability under the performance security, in particular because Subclause 4.2 includes an indemnity to the contractor if the employer was not entitled to make the claim. Applied Clauses of the Performance Security/ Bond for EPC Contracts (FIDIC or Mixed) (References to the clauses are removed) Performance Security means the bonds and the parent company guarantee. Performance Bond means the bond in the form set out in annexure (Performance Bond), issued by a bank or financial institution reasonably acceptable to the employer with a credit rating of no worse than [A+] (Standard and Poor’s) or [A1] (Moody’s). The performance bond shall be the equivalent of 10% of the contract price (or any replacement thereof pursuant to clause). In the event of a variation under (Variations and Adjustments), which results in an increase or decrease in the contract price by an amount equal to or greater than 5% (either by itself or when aggregated with all variations since any previous adjustment to the amount of the bonds), the maximum amounts available under the bonds pursuant shall be increased or decreased accordingly, and the contractor shall deliver a replacement bond to cover such increased or decreased maximum amount issued by an entity meeting the requirements as previously approved by the employer, such approval not to be unreasonably withheld or delayed and otherwise on the same terms as the replaced bond. Such replacement bond shall be delivered duly executed to the employer no later than 30 days following the variation. All fees, taxes and expenses Pg. 2/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
  • 3. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 associated with procuring, preparing, completing and stamping (if applicable) each of the bonds and the parent company guarantee shall be paid by the contractor. If the contractor fails to provide an extension to a bond or replacement bond, the employer shall have the right to call the outstanding balance of the bond and use and apply the same as security for compliance by the contractor with its obligations and liabilities under the contract. The employer shall be entitled to make deductions against any amounts so held in respect of any claim for which it would have been entitled to call against an extended or replacement bond (had the contractor provided the same), but shall otherwise return to the contractor the remaining balance of such amounts (without any interest). Event of Performance Security in Sequence of Contract Activities as Per FIDIC Schematic (only symbol to be considered as time-line) Signing of the Contract Agreement < 28 Days Issue of Performance Security by the Contractor < 42 Days Time for Completion Tests on Completion Issue of Taking Over Certificate Remedying of Defects Commencement Date  Pg. 3/3 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC Defect Notification Period Issue of the Performance Certificate Within 21 Days Return of the Performance Security by the Employer