Understanding and Managing Risk
within Complex Supply Chain Projects


         CILT Supply Chain Network
                London, UK
          Monday 15th June 2009
Duracell and Corus suffer
  due to steel conflict




            (Source: headlines from national newspapers)
Car transporter vessel
 sinks after collision




          (Source: headlines from national newspapers)
Recall of Mercedes ML
        Models




          (Source: headlines from national newspapers)
More takeovers and mergers
  in the transport sector




            (Source: headlines from national newspapers)
Strikes in Austria, France
         and Italy




            (Source: headlines from national newspapers)
Distribution halted by IT
      system fault




            (Source: headlines from national newspapers)
EC requires traceability of
food, feed and ingredients
 throughout supply chain




             (Source: headlines from national newspapers)
Research center studies
terrorism's impact on supply
            chain




             (Source: headlines from national newspapers)
Risk is unavoidable
Derek Hill
                     w
                A rro
           cy
       g en
   ntin
Co
Life before Logistex…
Interesting projects…
Risk
Not a ment
M an age
 Exp ert
Agenda
• Understanding different types of risks
• Identifying and evaluating risks
• FKI Logistex risk processes and governance
Objective of Risk
 Management
• Not to remove risk
• To raise awareness and visibility of risks
• To manage risks by mitigation actions to
  prevent major impact
• To prepare for contingency
Improve the predictability
      of a project!
Project Predictability
                   250%


                   200%
Planned Cost (%)




                   150%
                                      Project Cost
                   100%




                                                                                        Project End
                   50%


                    0%
                          0   1   2   3   4   5      6     7    8   9    10   11   12                 13   14   15   16
                                                         Time (months)

                                                               Planned
Project Predictability
                   250%


                   200%
Planned Cost (%)




                   150%
                                      Project Cost
                   100%




                                                                                         Project End
                   50%


                    0%
                          0   1   2   3   4   5      6     7    8   9    10    11   12                 13   14   15   16
                                                         Time (months)

                                          Planned                             Risk Managed
Project Predictability
                   250%

                                                Project Cost
                   200%
Planned Cost (%)




                   150%




                                                                                                                           Project End
                                       Project Cost
                   100%




                                                                                         Project End
                   50%


                    0%
                          0   1   2    3   4    5     6     7    8   9    10   11   12                 13   14   15   16
                                                          Time (months)

                                      Planned                Risk Managed                   Freestyle
1.
Understanding different
    types of risks
What Is A Risk?
• A potential event with negative consequences that has not
  happened yet
   – However a risk could also be defined as the event with unforeseen
     positive consequences; an Opportunity
• A possibility of loss — not the loss itself!
   – A source of problem during a project
   – Avoid labeling the cost of a risk as a risk (e.g. Schedule slippage). Find
     the sources!
   – Strike at the root of the problem, not the leaves!
• Something that makes the project special
• In the widest sense everything is a risk
• There are better ways of handling recurrent problems!
Two Basic Classifications
• Known unknowns
  – Things that we know we don’t know
• Unknown unknowns
  – Risks that surface despite our best efforts
Types of Risk
Financial     (e.g. gearing/interest rates, liquidity, foreign exchange,
              commodity prices, systemic risks etc)
Credit        (e.g. customer default, failure of key partner/supplier)
Operational   (e.g. business continuity, service quality)
Strategic     (e.g. changes in markets, customers, products, M&A, major
              capital investments/projects)
Legislative   (e.g. HSE, anti-competitive practices, stock market rules)
Political     (e.g. Country risk, civil commotions, nationalisation)
Environment   (e.g. natural disasters, pollution, global warming impacts,
              diseases/pandemics)
3rd Party     (e.g. risks of being let down by partners, key suppliers, outsource
              providers etc)
Logistex Corporate Risk Register
Business                              Projects
•   M&A                               •   Technology
•   Capital expenditures              •   New roles
•   Factory moves/closures            •   Ill defined specifications
•   New product development           •   Sourcing and supply chain
•   Supply chain development          •   Terms and Conditions
•   Organizational restructuring      •   People
•   Corporate Social Responsibility   •   Organisational
•   HSE                               •   Estimation
•   Environment
•   Currency
•   Competencies
2.
Identifying and evaluating risks
Context
• Project objectives
• Scope, terms costs conditions, an guarantees
• Schedule, location, and plan of project
• Assumptions
• Interfaces and stakeholders
• Definitions
Expectations
                     GAP
                     = Difference in expectations
End-User             = Increased risk




                               Provider
Influences

                   External




End-User




                              Provider



           Complexity
Project Risk Profile
• Profiling output
  determines weight of
  Bid Approval and
  Project Execution
  Process
Risk Mapping
• Hold a Risk Workshop for
  key members of project,
  stakeholder, suppliers etc.




                                               HGIH
• Brainstorm types of risk and




                                 PROBABILITY
  categorise in terms of size




                                               MEDIUM
  of impact.
• Then assess probability of
  occurrence and populate

                                               LOW
  Prioritising Risk Matrix
  opposite.
                                                        LOW   MEDIUM   HGIH
• Risks should be owned and
  tracked.                                                    IMPACT
NASA's illustration showing high impact risk areas for the International Space Station
Method
• Describe the Risks
  – Brainstorming potential risks
  – Walkthrough of the risk identification checklist
Method
• Common language
  – Clear and accurate description
  – Formulated as an “IF..THEN…” statement
• Example 1
  – “The equipment will arrive late and we will incur liquidated
    damages.”
• Example 2
  – “IF customs requires additional paperwork and this delays
    the release of the equipment, which delays the installation,
    THEN we will incur liquidated damages.”
Method
• Analyze and Prioritize Risks
  – Walkthrough risk sheet and estimate the
    probability and cost impact of each risk
  – Calculate risk rating of each risk (e.g. probability *
    impact)
  – Concentrate on Key Risks
Probability
                      What Is the Probability the Risk Will Happen?

Level                           Your Approach and Processes...

  1     Not Likely:             …will effectively avoid or mitigate this risk based on
                                standard practices.
  2     Low Likelihood:         …have usually mitigated this type of risk with minimal
                                oversight in similar cases.
  3     Likely:                 …may mitigate this risk, but workarounds will be
                                required.
  4     Highly Likely:          ...cannot mitigate this risk, but a different approach
                                might
  5     Near Certainty:         ...cannot mitigate this type of risk; no known processes
                                or workarounds are available
Impact
        Given the risk is realised, what would be the magnitude of the Impact?

Level    Technical                   Schedule                Cost

  1      Minimal or no impact        Minimal or no impact    Minimal or no impact

  2      Minor pert shortfall,       Additional activities  Budget increase of less
         same approach retained      required; able to meet than 1%
                                     key dates
  3      Mod pert shortfall, but     Minor schedule slip;    Budget increase of less
         workarounds available       will miss need date     than 5%
  4      Unacceptable; but           Program critical path   Budget increase of less
         workarounds available       affected                than 10%
  5      Unacceptable; no            Cannot achieve key      Budget increase of less
         alternatives exist          program milestone       than 10%
RISK

 Reject /   Transfer /     Reduce      Reduce
                                                Accept
Eliminate     Insure     Probability   Impact




                         Actions
Mitigation and Contingency Planning
• List Mitigation Actions
  – Start with most severe risks
  – List possible actions to reduce probability and/or
    cost
  – Some risks can be avoided
• Contingency Planning
  – Only for the most severe risks that cannot be
    mitigated
  – List actions to take should the risk mature
Risk Provisions
• Provision = (Probability x Impact) + Mitigation cost
• Mitigation cost may out way the Impact cost
   – Manage to the Risk
Project Risk Register
Key Risk
• A Key Risk Overview (KRO) is required
• Detailed plan of mitigation actions
• Embed responsiveness
Key Risk Overview
Risks require active
management
• Eliminate the risk NOW - scope, terms & conditions, reject.
• Do something NOW to transfer the risks - Insurer, customer,
  supplier.
• Do something NOW to reduce the probability of the risks
  occurring.
• Plan contingency actions NOW to reduce the impact if the
  risk occurs.
• Set up fallback plans NOW to limit the impact for
  implementation before the risk occurs.
• Get everybody’s agreement if you will just accept the risk.
3.
Processes and governance
Probability Impact Grid (PIG)

                                                             1
                                                  2
               HGIH
                                      8
                                                             3
 PROBABILITY




                                      12         5
                                            11                   4
               MEDIUM




                                10
                                      14             6
                                13          9

                         10
                        OTHER          15
                                                         7
               LOW




                        RISKS



                        LOW          MEDIUM      HGIH


                                     IMPACT
Monitor
• Re-Assess Risks regularly
  – Has probability and damage of controlled risks
    changed?
  – New risks identified? Analyse them
Stage-Gate Process
Continuity and Consistency
• Monthly and Gate Based Reviews




                                                                1
                                                     2
                HGIH




                                         8
                                                                3
  PROBABILITY




                                         12         5
                                               11                   4
                MEDIUM




                                   10
                                         14             6
                                   13          9

                            10
                           OTHER          15
                                                            7
                LOW




                           RISKS



                           LOW          MEDIUM      HGIH


                                        IMPACT
Who is involved in Risk Management?
• Customer
• End-user
• Project Team
• Management
• Product Management
• Related Projects
• Subcontractors and Suppliers
Roles in Risk Management
• Business Unit
• Project Team
• Risk Action Owner
• Risk Coordinator
• Steering Group
Risk Roll up & Action Flow-down
                                Corporate
    Risk Action                                         Risk Roll-up
    Flow-down                 Business Unit
                                 Business
                                  Project
                                   Task


• Risk Escalation
   – Risks outside the control of the area or affecting next levels objectives
• Risk Action Flow-down
   – Actions to ensure business objectives are met (Business Plan
     Deployment)
(Near the end….)
Risk management should…
• be an integral part of organisational processes
• be systematic and structured
• be based on the best available information
• take into account human factors
• be transparent and inclusive
• be dynamic, and responsive to change
• be tailored
• deliver better projects
derek.hill@fkilogistex.com
      07940 764844
Discussion…
• What risks does your business or team face?
• How do you deal with them?
• What lessons (good or bad) can you share?

Más contenido relacionado

Similar a Understanding and Managing Risk in Complex Supply Chain Projects

Win Friends and Influence People... with DSLs
Win Friends and Influence People... with DSLsWin Friends and Influence People... with DSLs
Win Friends and Influence People... with DSLsVladimir Bacvanski, PhD
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementBiju Nair
 
AACE Presentation Final 2007
AACE Presentation Final 2007AACE Presentation Final 2007
AACE Presentation Final 2007janknopfler
 
P&msp2010 07 risk-and-change-management
P&msp2010 07 risk-and-change-managementP&msp2010 07 risk-and-change-management
P&msp2010 07 risk-and-change-managementEmanuele Della Valle
 
Risk analysis and management
Risk analysis and managementRisk analysis and management
Risk analysis and managementgnitu
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learningVanita Ahuja
 
Project Management Risks Review
Project Management Risks ReviewProject Management Risks Review
Project Management Risks ReviewDavid Tennant
 
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen... Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...Lviv Startup Club
 
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»Lviv Startup Club
 
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...Project Controls Expo
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacPMA Consultants
 
Critical Chain Basics
Critical Chain BasicsCritical Chain Basics
Critical Chain BasicsJakub Linhart
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptxKamranKhan353531
 
Planificación del proyecto análisis de riesgo
Planificación del proyecto   análisis de riesgoPlanificación del proyecto   análisis de riesgo
Planificación del proyecto análisis de riesgoProColombia
 

Similar a Understanding and Managing Risk in Complex Supply Chain Projects (20)

Risk balanced portfolios Jim Morrison
Risk balanced portfolios   Jim MorrisonRisk balanced portfolios   Jim Morrison
Risk balanced portfolios Jim Morrison
 
Win Friends and Influence People... with DSLs
Win Friends and Influence People... with DSLsWin Friends and Influence People... with DSLs
Win Friends and Influence People... with DSLs
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
APM Edinburgh risk management january 2017 final
APM Edinburgh risk management january 2017 finalAPM Edinburgh risk management january 2017 final
APM Edinburgh risk management january 2017 final
 
AACE Presentation Final 2007
AACE Presentation Final 2007AACE Presentation Final 2007
AACE Presentation Final 2007
 
P&msp2010 07 risk-and-change-management
P&msp2010 07 risk-and-change-managementP&msp2010 07 risk-and-change-management
P&msp2010 07 risk-and-change-management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk analysis and management
Risk analysis and managementRisk analysis and management
Risk analysis and management
 
Risk-Cube Teaser Presentation
Risk-Cube Teaser PresentationRisk-Cube Teaser Presentation
Risk-Cube Teaser Presentation
 
Risk management concepts and learning
Risk management   concepts and learningRisk management   concepts and learning
Risk management concepts and learning
 
Project Management Risks Review
Project Management Risks ReviewProject Management Risks Review
Project Management Risks Review
 
Risk Management
Risk Management Risk Management
Risk Management
 
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen... Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
Андрій Мудрий “Risk managemnt: Welcome to Risk World” Lviv Project Managemen...
 
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»Андрій Мудрий «Risk managemnt: Welcome to Risk World»
Андрій Мудрий «Risk managemnt: Welcome to Risk World»
 
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
Project Controls Expo - 31st Oct 2012 - Schedule Risk Analysis: An Overview (...
 
Risk Management Processes from Jerry Klanac
Risk Management Processes from Jerry KlanacRisk Management Processes from Jerry Klanac
Risk Management Processes from Jerry Klanac
 
Critical Chain Basics
Critical Chain BasicsCritical Chain Basics
Critical Chain Basics
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptx
 
Planificación del proyecto análisis de riesgo
Planificación del proyecto   análisis de riesgoPlanificación del proyecto   análisis de riesgo
Planificación del proyecto análisis de riesgo
 
Project mngmnt risks3.2
Project mngmnt risks3.2Project mngmnt risks3.2
Project mngmnt risks3.2
 

Understanding and Managing Risk in Complex Supply Chain Projects

  • 1. Understanding and Managing Risk within Complex Supply Chain Projects CILT Supply Chain Network London, UK Monday 15th June 2009
  • 2. Duracell and Corus suffer due to steel conflict (Source: headlines from national newspapers)
  • 3. Car transporter vessel sinks after collision (Source: headlines from national newspapers)
  • 4. Recall of Mercedes ML Models (Source: headlines from national newspapers)
  • 5. More takeovers and mergers in the transport sector (Source: headlines from national newspapers)
  • 6. Strikes in Austria, France and Italy (Source: headlines from national newspapers)
  • 7. Distribution halted by IT system fault (Source: headlines from national newspapers)
  • 8. EC requires traceability of food, feed and ingredients throughout supply chain (Source: headlines from national newspapers)
  • 9. Research center studies terrorism's impact on supply chain (Source: headlines from national newspapers)
  • 11. Derek Hill w A rro cy g en ntin Co
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 19.
  • 20.
  • 21.
  • 22.
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30. Risk Not a ment M an age Exp ert
  • 32. • Understanding different types of risks • Identifying and evaluating risks • FKI Logistex risk processes and governance
  • 33. Objective of Risk Management
  • 34. • Not to remove risk • To raise awareness and visibility of risks • To manage risks by mitigation actions to prevent major impact • To prepare for contingency
  • 35. Improve the predictability of a project!
  • 36.
  • 37. Project Predictability 250% 200% Planned Cost (%) 150% Project Cost 100% Project End 50% 0% 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Time (months) Planned
  • 38. Project Predictability 250% 200% Planned Cost (%) 150% Project Cost 100% Project End 50% 0% 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Time (months) Planned Risk Managed
  • 39. Project Predictability 250% Project Cost 200% Planned Cost (%) 150% Project End Project Cost 100% Project End 50% 0% 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Time (months) Planned Risk Managed Freestyle
  • 40. 1. Understanding different types of risks
  • 41. What Is A Risk? • A potential event with negative consequences that has not happened yet – However a risk could also be defined as the event with unforeseen positive consequences; an Opportunity • A possibility of loss — not the loss itself! – A source of problem during a project – Avoid labeling the cost of a risk as a risk (e.g. Schedule slippage). Find the sources! – Strike at the root of the problem, not the leaves! • Something that makes the project special • In the widest sense everything is a risk • There are better ways of handling recurrent problems!
  • 42. Two Basic Classifications • Known unknowns – Things that we know we don’t know • Unknown unknowns – Risks that surface despite our best efforts
  • 43. Types of Risk Financial (e.g. gearing/interest rates, liquidity, foreign exchange, commodity prices, systemic risks etc) Credit (e.g. customer default, failure of key partner/supplier) Operational (e.g. business continuity, service quality) Strategic (e.g. changes in markets, customers, products, M&A, major capital investments/projects) Legislative (e.g. HSE, anti-competitive practices, stock market rules) Political (e.g. Country risk, civil commotions, nationalisation) Environment (e.g. natural disasters, pollution, global warming impacts, diseases/pandemics) 3rd Party (e.g. risks of being let down by partners, key suppliers, outsource providers etc)
  • 44. Logistex Corporate Risk Register Business Projects • M&A • Technology • Capital expenditures • New roles • Factory moves/closures • Ill defined specifications • New product development • Sourcing and supply chain • Supply chain development • Terms and Conditions • Organizational restructuring • People • Corporate Social Responsibility • Organisational • HSE • Estimation • Environment • Currency • Competencies
  • 46. Context • Project objectives • Scope, terms costs conditions, an guarantees • Schedule, location, and plan of project • Assumptions • Interfaces and stakeholders • Definitions
  • 47. Expectations GAP = Difference in expectations End-User = Increased risk Provider
  • 48.
  • 49. Influences External End-User Provider Complexity
  • 50.
  • 51.
  • 52. Project Risk Profile • Profiling output determines weight of Bid Approval and Project Execution Process
  • 53.
  • 54. Risk Mapping • Hold a Risk Workshop for key members of project, stakeholder, suppliers etc. HGIH • Brainstorm types of risk and PROBABILITY categorise in terms of size MEDIUM of impact. • Then assess probability of occurrence and populate LOW Prioritising Risk Matrix opposite. LOW MEDIUM HGIH • Risks should be owned and tracked. IMPACT
  • 55. NASA's illustration showing high impact risk areas for the International Space Station
  • 56. Method • Describe the Risks – Brainstorming potential risks – Walkthrough of the risk identification checklist
  • 57. Method • Common language – Clear and accurate description – Formulated as an “IF..THEN…” statement • Example 1 – “The equipment will arrive late and we will incur liquidated damages.” • Example 2 – “IF customs requires additional paperwork and this delays the release of the equipment, which delays the installation, THEN we will incur liquidated damages.”
  • 58.
  • 59. Method • Analyze and Prioritize Risks – Walkthrough risk sheet and estimate the probability and cost impact of each risk – Calculate risk rating of each risk (e.g. probability * impact) – Concentrate on Key Risks
  • 60. Probability What Is the Probability the Risk Will Happen? Level Your Approach and Processes... 1 Not Likely: …will effectively avoid or mitigate this risk based on standard practices. 2 Low Likelihood: …have usually mitigated this type of risk with minimal oversight in similar cases. 3 Likely: …may mitigate this risk, but workarounds will be required. 4 Highly Likely: ...cannot mitigate this risk, but a different approach might 5 Near Certainty: ...cannot mitigate this type of risk; no known processes or workarounds are available
  • 61. Impact Given the risk is realised, what would be the magnitude of the Impact? Level Technical Schedule Cost 1 Minimal or no impact Minimal or no impact Minimal or no impact 2 Minor pert shortfall, Additional activities Budget increase of less same approach retained required; able to meet than 1% key dates 3 Mod pert shortfall, but Minor schedule slip; Budget increase of less workarounds available will miss need date than 5% 4 Unacceptable; but Program critical path Budget increase of less workarounds available affected than 10% 5 Unacceptable; no Cannot achieve key Budget increase of less alternatives exist program milestone than 10%
  • 62.
  • 63. RISK Reject / Transfer / Reduce Reduce Accept Eliminate Insure Probability Impact Actions
  • 64. Mitigation and Contingency Planning • List Mitigation Actions – Start with most severe risks – List possible actions to reduce probability and/or cost – Some risks can be avoided • Contingency Planning – Only for the most severe risks that cannot be mitigated – List actions to take should the risk mature
  • 65. Risk Provisions • Provision = (Probability x Impact) + Mitigation cost • Mitigation cost may out way the Impact cost – Manage to the Risk
  • 66.
  • 68. Key Risk • A Key Risk Overview (KRO) is required • Detailed plan of mitigation actions • Embed responsiveness
  • 71. • Eliminate the risk NOW - scope, terms & conditions, reject. • Do something NOW to transfer the risks - Insurer, customer, supplier. • Do something NOW to reduce the probability of the risks occurring. • Plan contingency actions NOW to reduce the impact if the risk occurs. • Set up fallback plans NOW to limit the impact for implementation before the risk occurs. • Get everybody’s agreement if you will just accept the risk.
  • 73.
  • 74. Probability Impact Grid (PIG) 1 2 HGIH 8 3 PROBABILITY 12 5 11 4 MEDIUM 10 14 6 13 9 10 OTHER 15 7 LOW RISKS LOW MEDIUM HGIH IMPACT
  • 75. Monitor • Re-Assess Risks regularly – Has probability and damage of controlled risks changed? – New risks identified? Analyse them
  • 77. Continuity and Consistency • Monthly and Gate Based Reviews 1 2 HGIH 8 3 PROBABILITY 12 5 11 4 MEDIUM 10 14 6 13 9 10 OTHER 15 7 LOW RISKS LOW MEDIUM HGIH IMPACT
  • 78. Who is involved in Risk Management? • Customer • End-user • Project Team • Management • Product Management • Related Projects • Subcontractors and Suppliers
  • 79. Roles in Risk Management • Business Unit • Project Team • Risk Action Owner • Risk Coordinator • Steering Group
  • 80. Risk Roll up & Action Flow-down Corporate Risk Action Risk Roll-up Flow-down Business Unit Business Project Task • Risk Escalation – Risks outside the control of the area or affecting next levels objectives • Risk Action Flow-down – Actions to ensure business objectives are met (Business Plan Deployment)
  • 82.
  • 83. Risk management should… • be an integral part of organisational processes • be systematic and structured • be based on the best available information • take into account human factors • be transparent and inclusive • be dynamic, and responsive to change • be tailored • deliver better projects
  • 85. Discussion… • What risks does your business or team face? • How do you deal with them? • What lessons (good or bad) can you share?