1.0 Introduction
1.1 Jalan Tuanku Abdul Rahman 3
1.2 Community Library Floor Plans 4
2.0 Precedent Studies & Analysis
2.1 Structural Steel Frame – The Spring House 5 – 7
2.2 Composite Floor System – The Spring House 8 – 9
2.3 Roof System – Discovery Centre 10 – 13
2.4 Operable Blinds Facade System – Apartment Building CASP 74 14 – 16
2.5 Double Skin Facade System – Weill Cornell Medical College
Belfer Research Building 17 – 20
3.0 Alternative Design Scheme
3.1 Operable Blinds Facade Scheme 21 – 22
3.2 Double Skin Facade Scheme 23 – 24
4.0 Sectional Perspectives
4.1 Ground Floor 25
4.2 3rd and 4th Floor 26
4.3 Detailing 27
2Building Technology 1: Construction Solutions |
Table of Contents
Site Plan | Scale 1:500
1.0 Introduction | 1.1 Jalan Tuanku Abdul Rahman
3Building Technology 1: Construction Solutions |
The community library sits on two existing shophouses
of total lot area of 392.2m2 in Jalan Tuanku Abdul
Rahman, Kuala Lumpur. The building is fronting to the
east while the rear to the west, and sits within a row of
traditional and modern shophouses.
This community library designed within an urban infill
site serves as a centre for the existing local community
to share similar interests and exchange ideas, addressing
the fading cultural heritage of the site.
Ground Floor Level
Scale 1:200
1.0 Introduction | 1.2 Community Library Floor Plans
4Building Technology 1: Construction Solutions |
Ground Mezzanine Level
Scale 1:200
First Floor Level
Scale 1:200
Second Floor Level
Scale 1:200
Third Floor Level
Scale 1:200
2.0 Precedent Studies | 2.1 Structural Steel Frame
5
The Spring House | Wu & Liu Architects
The Spring House is located in Guiren Tainan, Taiwan.
The design combines the client’s unique personal living
space and for her special friends. The building combines
steel, bricks, concrete and metal plates to form the
framework of traditional architecture and spatial order
to reinterpret modern residential construction. This
residential building uses both steel frame structures and
composite metal decking for its floors.
Building Technology 1: Construction Solutions |
6
Advantages
1. Fast to build at site, as the majority of work can be
pre-fabricated at the factory.
2. Steel structures are flexible and good at resisting
wind and earthquake forces.
3. Strong and durable, and does not warp or expand
unlike traditional wood framing.
4. A wide range of pre-made structural sections are
available and they are suitable to clad with any
material.
5. Able to span long distances.
6. Has a variety of joining methods including bolting,
welding and riveting.
Disadvantages
1. Lose strength at high temperatures and susceptible
to fire so coatings are required.
2. Prone to corrosion in tropical and humid
environments.
Integration to Community Library
Steel frame constructions allow a larger structural spans
and efficient when laid out along a regular grid,
especially when the site has a long distance from front
to rear.
The brick structure combined with the modern steel
structure to produce a unique local architectural type.
This brings a sense of locality with the neighbouring
shoplots which are of solid masses as well. Masonry also
possess good insulation properties for acoustics needed
in the community library. Salvaged bricks from the
existing building can be reused for the new library.
Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.1 Structural Steel Frame
Steel Frame Structures
Steel construction has an immense strength which
is an advantage to buildings. It can bend with
cracking and can flex when wind or earthquake
forces acting on it. Various connection joints are
concurrently used throughout the steel system to
further strengthen the connections between
structural members and the masonry walls.
7
Construction Process
1. After the concrete foundation has set up, steel base plates are anchored and attached to
the foundation with four anchoring bolts. The plates are levelled on a bed of non-shrinking
grout.
2. The steel columns are lowered and welded to these base plates. The plates are used to
transfer concentrated load from the columns to the ground.
3. Primary ground floor beams are connected to the columns via fin plates. The plates are
welded with the column and bolted to the web of the beams.
4. Secondary floor beams are connected to the primary beams through a similar method.
5. The ground flooring is prepared through composite decking. The composite process is
done by welding sheer studs through the steel decking to the supporting steel beam
below. [See Composite Floor System] Infill brick walls are then placed.
6. For the upper floors, more columns are erected and connected through splices. The splices
provide strength and stiffness to both the columns. The splices are bolted to both the
columns.
7. The process is repeated for the flooring system.
Building Technology 1: Construction Solutions |
Brick wall
Steel columns
Composite steel flooring
Steel beam
Concrete foundation
Reinforced concrete
Master bedroom
Entrance
Sectional detail of The Spring House
Steel column is welded to its
steel base plate after the
plate is levelled on a bed of
non-shrinking grout.
Steel beams are connected
to columns via fin plates
through welding and bolting.
Composite flooring system by
welding sheer stuffs to the
supporting steel beam below.
More columns are
connected through
splices by using bolts.
4321
2.0 Precedent Studies | 2.1 Structural Steel Frame
8Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.2 Composite Floor System
Advantages
1. No evidence of nails and has a nice flat finish.
2. Steel and concrete may be arranged to produce
ideal combination of strength, with concrete
efficient in compression and steel in tension.
3. The construction time is reduced since casting of
additional floors may proceed without having to
wait for the previously cast floors to gain strength.
4. The construction of composite floor does not
require highly skilled labour. The steel decking acts
as a permanent form work.
5. Composite decking offers excellent resistance to
corrosion, chemical attack and outdoor weathering.
Disadvantages
1. Temperature sensitive and expands and contracts
with temperature change.
2. If damaged or faded, the material must be
replaced.
3. A soft material and wears easily.
Integration to Community Library
The lightweight properties of composite decking allows
the sizes of other structural components to be greatly
reduced, permitting smaller interiors and the possibility
for open floor plans.
Composite flooring has a much smaller depth compared
to reinforced concrete floor slabs. This allows flexibility
in design and at the same to withstand greater loads.
Ceiling heights can be significantly increased.
Composite Flooring
Composite decking serves as a tensile
reinforcement for the concrete slab to
which it is bonded with embossed rib
patterns.
9
Construction Process
1. Trapezoidal steel decking is placed and spanned in a direction transverse to the secondary
floor beams.
2. The decking is rigidly connected to the primary and secondary beams by shear studs,
which are connected through deck-welding techniques.
3. Steel mesh reinforcement, i.e. rebars, is placed above the steel decking to provide
bending resistance and reduce cracking at the supports. The mesh also aids the
distribution of the effects of localised point and line loads.
4. The profiled steel decking acts as a formwork during construction and additional external
reinforcement at the final stage of construction when reinforced concrete is cast on top of
it.
Building Technology 1: Construction Solutions |
Trapezoidal steel deck profiles
Reinforced concrete cast in-situ
Mesh reinforcement
Trapezoidal steel deck profile
19mm⌀ x 95mm shear stud
Edge trim and restraint strap
End cap
Fixings to suit project
specifications
50mm min. bearing
50mm min. bearing
Downstand edge beam
Composite floor components
• 1-1/2” (38) spanning 4’ to 8’ (1220 to 2440)
• 2” (51) spanning to 8’ to 12’ (2440 to 3660)
• 3” (75) spanning 8’ to 15’ (2440 to 4570)
Composite decking span
2.0 Precedent Studies | 2.2 Composite Floor System
10Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.3 Roof System
Discovery Centre | Architecture Discipline
This city town hall located in Karnataka, India serves as a
office/sales office and the design brief demanded the
exploration of sustainable design and development.
The exposed roof structure utilizes longitudinal steel
trusses for the long building span and topped with
polycarbonate sheeting to allow diffused lighting into
the interior.
11
Advantages
1. The simple mechanism of longitudinal steel trusses
of the roof allows simple and fast construction.
2. The lightweight of the roof truss members reduces
the typical bulkiness of structural members.
3. Steel roof trusses allow larger spans, which
contributes to the need of lesser columns. An open
floor plan can be achieved and it is economical.
4. Lightweight polycarbonate sheet is lightweight and
reduces the sizes of columns supporting the roof.
5. Using a truss system aids in keeping the roof light,
brings light inside and enables controlled
surrounding views of the site.
6. The fabric louvers arranged in angular between the
trusses allows soft and diffused light to penetrate
into the interior spaces. Thus, exposed ceiling can
be achieved.
Disadvantages
1. Skilled labour is required to install these steel roof
trusses.
2. Rust can be a problem when the metal is cut, drilled
and welded if no proper coating is done on the
structural members.
Integration to Community Library
Longitudinal steel roof trusses are encouraged to be
used as the roof system in the community library as it
can span long distances especially when our site is long
in length. The installation of steel trusses also means
that lesser and smaller sized columns can be used to
support the roof structure. This allows an open floor
plan of the community library which contributes to more
interior spaces.
The ceiling can be left exposed as it is as steel trusses
can be aesthetically pleasing when viewed. The
lightweight fabric louvers installed on the structural
members bring in soft and diffused light into the interior
spaces.
Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.3 Roof System
12Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.3 Roof System
1. Primary steel truss – 18m wide span
2. Perforated fabric louvers
3. Translucent fabric layer
4. Steel roof purlins
5. Milky white polycarbonate sheet
6. Rain water to ground storage
7. Composite fascia
Cross-sectional detail of the roof system
Longitudinal section of the building
Construction Process
1. The steel trusses are pre-fabricated in the factory. The diagonal web
members are welded and bolted to both top and bottom chords of the steel
trusses.
2. The primary steel trusses are brought to site and assembled to the structural
steel beams through welding. Both beams and trusses sit on the round
columns of the building.
3. Roof purlins are laid on the trusses of varying heights to allow a small
degree of roof pitch. The purlins are then fasten through bolting and
welding to the top chord of the steel trusses.
4. Polycarbonate sheeting is laid and nailed with fastening plates on the
purlins.
5. The translucent fabric layer is installed right below the top chord of the truss
and secured onto the structural steel beams.
6. Perforated fabric louvers are aligned and angled between the trusses. Some
layers are overlapped with one another to allow natural light to diffuse into
the interior spaces below.
13Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.3 Roof System
[Top] Angular perforated fabric louvers
[Bottom] Diffused natural light into the spaces below
Longitudinal steel roof trusses installed onto the structural steel beams
2.0 Precedent Studies | 2.4 Operable Blinds Facade System
14Building Technology 1: Construction Solutions |
CASP 74 | Bach Arquitectes
The CASP 74 apartment is located in Barcelona, Spain.
The design of the building responds to the necessity of
the modern era and the facade is composed as a
dialogue between fixed panels formed by steel framed
vertical ceramic planks, and sliding aluminium blinds
providing the necessary privacy and lighting control.
15Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.4 Operable Blinds Facade System
Advantages
1. The changing façade provides solar protection and
privacy.
2. Folding aluminium blinds creates dynamics when is
viewed from the street and allows lighting control.
3. The façade prevents heat from getting into the
interior spaces during summer due to the ceramic
planks, so it seals to keep warmth.
4. Aluminium is a lightweight material which makes
the blinds easy to handle and less expensive to
transport.
5. The blinds are durable and less susceptible to
corrosion as aluminium has its own naturally
occurring oxide film.
Disadvantages
1. The blinds can be noisy at the window when it is
operated because they are metal.
2. Tendency to accumulate dust over time, which is
most noticeable on darker coloured vanes.
Integration to Community Library
The implementation of vertical blinds especially with
aluminium as the material is perfect for controlling light
in accordance to the time of the day. It is modern
looking yet classic which fits the ambience of the site of
Jalan Tuanku Abdul Rahman – the mix of classic and
contemporary.
The blinds can be obtained in a wide range of colours
to complement with the surrounding building facade
and interior spaces perfectly. While the vertical blinds
offer different levels of privacy which is needed for the
library spaces, it can be remote control operated by the
librarians.
16Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.4 Operable Blinds Facade System
Sectional detail of facade
Continuous plate along the slab
Würth insulating metallic fabric
UPN 160 channel
Fixed frame to fasten ceramic planks
Grey lead colour lacquered aluminium sliding formed
by vertical rectangular profiles
Special ceramic plank 120x80x680mm by Bach Arquitectes,
the long faces of some pieces are enamelled
3mm neoprene between the separation of ceramic plank
50x30x3mm galvanized steel profile for supporting
ceramic planks
Double plates, fixed with high screws
Lateral drilling profile to allow internal welding with
the supporting flange, allows ventilation in the
event of water entry
Sliding window, grey lacquered aluminium leadFront elevation and horizontal section of facade
Isometric sketch of facadeFixed ceramic planks during construction
17Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.4 Double Skin Facade System
Weill Cornell Medical College
Belfer Research Building | Todd Schliemann & Ennead Architects
The Belfer Research Building of Weill Cornell Medical College is a medical research
facility in New York, United States. The building envelope features a high-
performance double-skinned, fritted-glass curtain wall that maximizes energy
efficiency. The passively vented system is designed to promote controlled convection
within the wall cavity to mitigate extreme temperatures and enhance thermal comfort
within the building.
18
Advantages
1. The double-skinned facade helps to promote
energy efficiency.
2. Passive vented system promotes controlled
convection within the wall cavity, mitigating
extreme temperatures on the exterior of the
building, and significantly reduces temperatures on
the interior glass.
3. Openings and sun-shading devices enhance visual
and thermal comfort within the interior spaces,
reducing the carbon footprint of the building.
4. Curtain wall design provides an economically
sensitive sustainable solution.
Disadvantages
1. The view to the exterior from the building may be
obstructed.
2. The wall cavity results in a decrease in usable floor
space.
3. The construction of a second skin presents a
significant increase in materials and design costs.
Integration to Community Library
Introducing the double-skinned facade in a community
library is feasible as the wall cavity acts as a buffer zone
to tackle noise coming from the street to allow quiet
interior spaces. For a tropical country, the facade
reduces solar heat gain in the interior spaces and
promotes thermal comfort for the users.
This double building envelope approach offers glare
protection which is helpful for reading activities and
promotes good daylighting method which subsequently
minimizes the need of artificial lighting.
Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.4 Double Skin Facade System
3D render of double curtain wall
19Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.4 Double Skin Facade System
GL-1 Insulated Glass Unit:
- 3/8” low-iron outer lite
- Low-E coating #2 surface
- 1/2” air space with argon gas fill
- 1/4” low-iron inner lite
GL-2 Laminated Spandrel Glass:
- 5/8” low-iron laminated w/ 50% coverage frit pat.
#2 surf. and opaque white interlayer
GL-6 Laminated Fritted Glass Screen:
- 5/8” low-iron laminated w/ 75% coverage frit pat.
#2 surf. (black & white double pass frit)
GL-7 Laminated Fritted Glass Screen:
- 5/8” low-iron laminated w/ 50% coverage frit pattern
#2 surf. (black & white double pass frit)
1. Not used
2. Not used
3. Painted aluminium 4-sided structurally glazed curtain
wall w/ laminated glass panels
4. 16 gauge stainless steel cable @ 2” O.C. horizontal
spacing. Wires tensioned across opening
5. Painted steel catwalk grating, 50% open supported on
painted steel catwalk structure anchored to building
structure
6. Curtain wall gravity load connection
7. Interior painted GYP BD finish
8. Intermediate ventilated cavity
9. Radiant ceiling panel
10. Concealed roller shade pocket
11. Painted aluminium 4-sided structurally glazed curtain
wall w/ insulated glass panels
12. Painted aluminium sill cover (1/8” thk.)
13. 4” semi-rigid mineral wool insulation w/ galv. steel
backpan assembly
14. Typical office partition with painted aluminium
partition enclosures at vertical curtain wall mullion
interface
Sectional detail of double curtain wall
20Building Technology 1: Construction Solutions |
2.0 Precedent Studies | 2.4 Double Skin Facade System
Front elevation of building facade Energy efficient building with sun shading properties
21Building Technology 1: Construction Solutions |
3.0 Alternative Design Scheme | 3.1 Operable Blinds Facade Scheme
Front Elevation | Scale 1:100
22Building Technology 1: Construction Solutions |
3.0 Alternative Design Scheme | 3.1 Operable Blinds Facade Scheme
Rear Elevation | Scale 1:100
23Building Technology 1: Construction Solutions |
3.0 Alternative Design Scheme | 3.2 Double Skin Facade Scheme
Front Elevation | Scale 1:100
24Building Technology 1: Construction Solutions |
3.0 Alternative Design Scheme | 3.2 Double Skin Facade Scheme
Rear Elevation | Scale 1:100
25Building Technology 1: Construction Solutions |
4.0 Sectional Perspectives | 4.1 Ground Floor Level
Sectional Perspective | Ground Floor
R.C. pad footing
R.C. column stump
R.C. ground beam
150mm R.C. floor slab
Composite steel decking
with trapezoidal profile
200x200mm steel I-column,
powder coated black
165x305mm steel I-beam,
powder coated black
Concrete slab with mesh
reinforcement
900mm pipe railing
Operable blinds
facade system
DETAIL A
DETAIL B
26Building Technology 1: Construction Solutions |
4.0 Sectional Perspectives | 4.2 2nd and 3rd Floor Level
Composite steel decking
with trapezoidal profile
200x200mm steel I-column,
powder coated black
165x305mm steel I-beam,
powder coated black
Z-channel galvanized
roof purlin
Milky white polycarbonate sheet
Concrete slab with mesh
reinforcement
900mm pipe railing
7m wide span primary steel truss
Operable blinds
facade system
150mm brick wall with
25mm plaster on both sides
Sectional Perspective | 2nd and 3rd Floor Level
DETAIL C
27Building Technology 1: Construction Solutions |
4.0 Sectional Perspectives | 4.3 Detailing
Detail C | Scale 1:30
UPN 160 channel
Fixed frame to fasten ceramic planks
Grey lead colour lacquered aluminium sliding formed
by vertical rectangular profiles
Ceramic plank 120x80x680mm, the long
faces of some pieces are enamelled
Ceramic plank 120x80x680mm, the long
faces of some pieces are enamelled
165x305mm steel I-beam, powder
coated black
200x200mm steel I-column,
powder coated black
Detail A | Scale 1:30 Detail B | Scale 1:30
165x305mm steel I-beam, powder
coated black
200x200mm steel I-column,
powder coated black
Composite steel decking
with trapezoidal profile
25mm ceramic floor tile
150mm thk brick wall
Concrete floor slab
165x305mm steel I-beam, powder
coated black
200x200mm steel I-column,
powder coated black
7m wide span primary steel
truss
Z-channel galvanized roof
purlin
Milky white polycarbonate
sheet

Más contenido relacionado

La actualidad más candente

Hearst Tower
Hearst TowerHearst Tower
Hearst Towermisschand
 
Kinetic structures | B.arch
Kinetic structures | B.archKinetic structures | B.arch
Kinetic structures | B.archAs Per Design
 
Swiss re building london
Swiss re building londonSwiss re building london
Swiss re building londonAda Darmon
 
Curtain wall system
Curtain wall systemCurtain wall system
Curtain wall systembee_by
 
Bank of china tower isaac
Bank of china tower isaacBank of china tower isaac
Bank of china tower isaaccraigh99
 
Aluminum partition wall
Aluminum partition wallAluminum partition wall
Aluminum partition wallZuber Memon
 
A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'Abheek Khajuria
 
Report on high rise (2020) leading university
Report on high rise (2020) leading universityReport on high rise (2020) leading university
Report on high rise (2020) leading universityJubelTalukder
 

La actualidad más candente (20)

Tensile structures
Tensile structuresTensile structures
Tensile structures
 
Hearst Tower
Hearst TowerHearst Tower
Hearst Tower
 
Kinetic structures | B.arch
Kinetic structures | B.archKinetic structures | B.arch
Kinetic structures | B.arch
 
The tents structure system
The tents structure systemThe tents structure system
The tents structure system
 
JOHN HANCOCK CENTER
JOHN HANCOCK CENTERJOHN HANCOCK CENTER
JOHN HANCOCK CENTER
 
FOLDED PLATES TYPES
FOLDED PLATES TYPES FOLDED PLATES TYPES
FOLDED PLATES TYPES
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
Swiss re building london
Swiss re building londonSwiss re building london
Swiss re building london
 
Curtain wall system
Curtain wall systemCurtain wall system
Curtain wall system
 
Curtain walls
Curtain wallsCurtain walls
Curtain walls
 
Bank of china tower isaac
Bank of china tower isaacBank of china tower isaac
Bank of china tower isaac
 
Richard Rogers
Richard RogersRichard Rogers
Richard Rogers
 
Aluminum partition wall
Aluminum partition wallAluminum partition wall
Aluminum partition wall
 
A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'A building with a difference 'Taipei 101'
A building with a difference 'Taipei 101'
 
Report on high rise (2020) leading university
Report on high rise (2020) leading universityReport on high rise (2020) leading university
Report on high rise (2020) leading university
 
Curtain walls
Curtain wallsCurtain walls
Curtain walls
 
Turning torso
Turning torsoTurning torso
Turning torso
 
Facade Research Document
Facade Research DocumentFacade Research Document
Facade Research Document
 
The cables structure system
The cables structure systemThe cables structure system
The cables structure system
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 

Destacado

plastic Facade- PLOYCARBONATE AND PTFE
plastic Facade- PLOYCARBONATE AND PTFE plastic Facade- PLOYCARBONATE AND PTFE
plastic Facade- PLOYCARBONATE AND PTFE Revathy Royer
 
Building Technology 1 Project 2
Building Technology 1 Project 2Building Technology 1 Project 2
Building Technology 1 Project 2Tan Jaden
 
BUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORTBUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORTJoyeeLee0131
 
Building Technology 1 Assignment 2 - Construction Solutions
Building Technology 1 Assignment 2 - Construction SolutionsBuilding Technology 1 Assignment 2 - Construction Solutions
Building Technology 1 Assignment 2 - Construction SolutionsJoe Onn Lim
 
Grid Systems
Grid SystemsGrid Systems
Grid SystemsBas Leurs
 

Destacado (7)

plastic Facade- PLOYCARBONATE AND PTFE
plastic Facade- PLOYCARBONATE AND PTFE plastic Facade- PLOYCARBONATE AND PTFE
plastic Facade- PLOYCARBONATE AND PTFE
 
INTEGRATION
INTEGRATIONINTEGRATION
INTEGRATION
 
Btechfinal
BtechfinalBtechfinal
Btechfinal
 
Building Technology 1 Project 2
Building Technology 1 Project 2Building Technology 1 Project 2
Building Technology 1 Project 2
 
BUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORTBUILDING TECHNOLOGY PROJECT 2 REPORT
BUILDING TECHNOLOGY PROJECT 2 REPORT
 
Building Technology 1 Assignment 2 - Construction Solutions
Building Technology 1 Assignment 2 - Construction SolutionsBuilding Technology 1 Assignment 2 - Construction Solutions
Building Technology 1 Assignment 2 - Construction Solutions
 
Grid Systems
Grid SystemsGrid Systems
Grid Systems
 

Similar a Building Technology 1 Construction Solutions Report

Building Technology I : Project 2 : Construction Solutions
Building Technology I : Project 2 : Construction SolutionsBuilding Technology I : Project 2 : Construction Solutions
Building Technology I : Project 2 : Construction SolutionsJing Fan Koh
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Soh Shing
 
Building Technology Design Solution
Building Technology Design SolutionBuilding Technology Design Solution
Building Technology Design SolutionJia Xin Chee
 
Building technology report
Building technology reportBuilding technology report
Building technology reportChong Yi Hui
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1Gertrude Lee
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartmentJy Chong
 
Building Technology I
Building Technology IBuilding Technology I
Building Technology IOng Shi Hui
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building Systemjisunfoo
 
Project 1 - Industrialised Building System
Project 1 - Industrialised Building SystemProject 1 - Industrialised Building System
Project 1 - Industrialised Building Systemhilmanaqil1
 
Building tech Project 2
Building tech Project 2Building tech Project 2
Building tech Project 2zerospaces_
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Nekumi Kida
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyQuinn Liew
 
Building Technology Project 1 Report
Building Technology Project 1 ReportBuilding Technology Project 1 Report
Building Technology Project 1 ReportBolin Loong
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSJing Fan Koh
 
Building Technology I Project 1
Building Technology I Project 1Building Technology I Project 1
Building Technology I Project 1DavidJPCChai
 
B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsCarmen Chan
 

Similar a Building Technology 1 Construction Solutions Report (20)

Building Technology I : Project 2 : Construction Solutions
Building Technology I : Project 2 : Construction SolutionsBuilding Technology I : Project 2 : Construction Solutions
Building Technology I : Project 2 : Construction Solutions
 
Building Technology 1 (Project 1)
Building Technology 1 (Project 1)Building Technology 1 (Project 1)
Building Technology 1 (Project 1)
 
Building Technology Design Solution
Building Technology Design SolutionBuilding Technology Design Solution
Building Technology Design Solution
 
Building technology report
Building technology reportBuilding technology report
Building technology report
 
Building Technology 1
Building Technology 1Building Technology 1
Building Technology 1
 
IBS design proposal of apartment
IBS design proposal of apartmentIBS design proposal of apartment
IBS design proposal of apartment
 
Building Technology I
Building Technology IBuilding Technology I
Building Technology I
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building System
 
Project 1 - Industrialised Building System
Project 1 - Industrialised Building SystemProject 1 - Industrialised Building System
Project 1 - Industrialised Building System
 
Building tech Project 2
Building tech Project 2Building tech Project 2
Building tech Project 2
 
BUILDING TECH 5_04.pptx
BUILDING TECH 5_04.pptxBUILDING TECH 5_04.pptx
BUILDING TECH 5_04.pptx
 
Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)Building Technology 1_Report_IBS (Industralized Building System)
Building Technology 1_Report_IBS (Industralized Building System)
 
Building Technology : Industrialize Building Technology
Building Technology : Industrialize Building TechnologyBuilding Technology : Industrialize Building Technology
Building Technology : Industrialize Building Technology
 
Building Technology Project 1 Report
Building Technology Project 1 ReportBuilding Technology Project 1 Report
Building Technology Project 1 Report
 
Btech report
Btech reportBtech report
Btech report
 
Steel frame work
Steel frame workSteel frame work
Steel frame work
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBS
 
Precast-concrete Details
Precast-concrete DetailsPrecast-concrete Details
Precast-concrete Details
 
Building Technology I Project 1
Building Technology I Project 1Building Technology I Project 1
Building Technology I Project 1
 
B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building Systems
 

Más de douglasloon

Architecture Design Project Presentation Slides
Architecture Design Project Presentation SlidesArchitecture Design Project Presentation Slides
Architecture Design Project Presentation Slidesdouglasloon
 
Architecture Design Project Report
Architecture Design Project ReportArchitecture Design Project Report
Architecture Design Project Reportdouglasloon
 
Titiwangsa Cultural Centre Project Management Report
Titiwangsa Cultural Centre Project Management ReportTitiwangsa Cultural Centre Project Management Report
Titiwangsa Cultural Centre Project Management Reportdouglasloon
 
Recreation Blocks Project Management Report
Recreation Blocks Project Management ReportRecreation Blocks Project Management Report
Recreation Blocks Project Management Reportdouglasloon
 
Theories of Architecture and Urbanism Comparative Analysis Essay
Theories of Architecture and Urbanism Comparative Analysis EssayTheories of Architecture and Urbanism Comparative Analysis Essay
Theories of Architecture and Urbanism Comparative Analysis Essaydouglasloon
 
Theories of Architecture and Urbanism Reaction Papers
Theories of Architecture and Urbanism Reaction PapersTheories of Architecture and Urbanism Reaction Papers
Theories of Architecture and Urbanism Reaction Papersdouglasloon
 
Building Technology 1 Industralised Building System (IBS) Report
Building Technology 1 Industralised Building System (IBS) ReportBuilding Technology 1 Industralised Building System (IBS) Report
Building Technology 1 Industralised Building System (IBS) Reportdouglasloon
 
Building Science II Integration Project Report
Building Science II Integration Project ReportBuilding Science II Integration Project Report
Building Science II Integration Project Reportdouglasloon
 
An Acoustic Case Study on Calvary Convention Centre Report
An Acoustic Case Study on Calvary Convention Centre ReportAn Acoustic Case Study on Calvary Convention Centre Report
An Acoustic Case Study on Calvary Convention Centre Reportdouglasloon
 
An Acoustic Case Study on Calvary Convention Centre Presentation Slides
An Acoustic Case Study on Calvary Convention Centre Presentation SlidesAn Acoustic Case Study on Calvary Convention Centre Presentation Slides
An Acoustic Case Study on Calvary Convention Centre Presentation Slidesdouglasloon
 
Structural Analysis of a Bungalow Report
Structural Analysis of a Bungalow ReportStructural Analysis of a Bungalow Report
Structural Analysis of a Bungalow Reportdouglasloon
 
Roof Truss System (Truss Analysis)
Roof Truss System (Truss Analysis)Roof Truss System (Truss Analysis)
Roof Truss System (Truss Analysis)douglasloon
 
Asian Architecture: 8D House Paper Presentation
Asian Architecture: 8D House Paper PresentationAsian Architecture: 8D House Paper Presentation
Asian Architecture: 8D House Paper Presentationdouglasloon
 
Asian Architecture: 8D House Topic Proposal
Asian Architecture: 8D House Topic ProposalAsian Architecture: 8D House Topic Proposal
Asian Architecture: 8D House Topic Proposaldouglasloon
 
Asian Architecture: 8D House Case Study Paper
Asian Architecture: 8D House Case Study PaperAsian Architecture: 8D House Case Study Paper
Asian Architecture: 8D House Case Study Paperdouglasloon
 
Building Services in Public Buildings Report
Building Services in Public Buildings ReportBuilding Services in Public Buildings Report
Building Services in Public Buildings Reportdouglasloon
 
Mapping the Townscape (Petaling Street & Central Market) Presentation Slides
Mapping the Townscape (Petaling Street & Central Market) Presentation SlidesMapping the Townscape (Petaling Street & Central Market) Presentation Slides
Mapping the Townscape (Petaling Street & Central Market) Presentation Slidesdouglasloon
 
Tropical Cities: George Town, Penang Presentation Slides
Tropical Cities: George Town, Penang Presentation SlidesTropical Cities: George Town, Penang Presentation Slides
Tropical Cities: George Town, Penang Presentation Slidesdouglasloon
 
Sun Yat Sen Museum Penang Report
Sun Yat Sen Museum Penang ReportSun Yat Sen Museum Penang Report
Sun Yat Sen Museum Penang Reportdouglasloon
 
Sun Yat Sen Museum Penang Measured Drawings
Sun Yat Sen Museum Penang Measured DrawingsSun Yat Sen Museum Penang Measured Drawings
Sun Yat Sen Museum Penang Measured Drawingsdouglasloon
 

Más de douglasloon (20)

Architecture Design Project Presentation Slides
Architecture Design Project Presentation SlidesArchitecture Design Project Presentation Slides
Architecture Design Project Presentation Slides
 
Architecture Design Project Report
Architecture Design Project ReportArchitecture Design Project Report
Architecture Design Project Report
 
Titiwangsa Cultural Centre Project Management Report
Titiwangsa Cultural Centre Project Management ReportTitiwangsa Cultural Centre Project Management Report
Titiwangsa Cultural Centre Project Management Report
 
Recreation Blocks Project Management Report
Recreation Blocks Project Management ReportRecreation Blocks Project Management Report
Recreation Blocks Project Management Report
 
Theories of Architecture and Urbanism Comparative Analysis Essay
Theories of Architecture and Urbanism Comparative Analysis EssayTheories of Architecture and Urbanism Comparative Analysis Essay
Theories of Architecture and Urbanism Comparative Analysis Essay
 
Theories of Architecture and Urbanism Reaction Papers
Theories of Architecture and Urbanism Reaction PapersTheories of Architecture and Urbanism Reaction Papers
Theories of Architecture and Urbanism Reaction Papers
 
Building Technology 1 Industralised Building System (IBS) Report
Building Technology 1 Industralised Building System (IBS) ReportBuilding Technology 1 Industralised Building System (IBS) Report
Building Technology 1 Industralised Building System (IBS) Report
 
Building Science II Integration Project Report
Building Science II Integration Project ReportBuilding Science II Integration Project Report
Building Science II Integration Project Report
 
An Acoustic Case Study on Calvary Convention Centre Report
An Acoustic Case Study on Calvary Convention Centre ReportAn Acoustic Case Study on Calvary Convention Centre Report
An Acoustic Case Study on Calvary Convention Centre Report
 
An Acoustic Case Study on Calvary Convention Centre Presentation Slides
An Acoustic Case Study on Calvary Convention Centre Presentation SlidesAn Acoustic Case Study on Calvary Convention Centre Presentation Slides
An Acoustic Case Study on Calvary Convention Centre Presentation Slides
 
Structural Analysis of a Bungalow Report
Structural Analysis of a Bungalow ReportStructural Analysis of a Bungalow Report
Structural Analysis of a Bungalow Report
 
Roof Truss System (Truss Analysis)
Roof Truss System (Truss Analysis)Roof Truss System (Truss Analysis)
Roof Truss System (Truss Analysis)
 
Asian Architecture: 8D House Paper Presentation
Asian Architecture: 8D House Paper PresentationAsian Architecture: 8D House Paper Presentation
Asian Architecture: 8D House Paper Presentation
 
Asian Architecture: 8D House Topic Proposal
Asian Architecture: 8D House Topic ProposalAsian Architecture: 8D House Topic Proposal
Asian Architecture: 8D House Topic Proposal
 
Asian Architecture: 8D House Case Study Paper
Asian Architecture: 8D House Case Study PaperAsian Architecture: 8D House Case Study Paper
Asian Architecture: 8D House Case Study Paper
 
Building Services in Public Buildings Report
Building Services in Public Buildings ReportBuilding Services in Public Buildings Report
Building Services in Public Buildings Report
 
Mapping the Townscape (Petaling Street & Central Market) Presentation Slides
Mapping the Townscape (Petaling Street & Central Market) Presentation SlidesMapping the Townscape (Petaling Street & Central Market) Presentation Slides
Mapping the Townscape (Petaling Street & Central Market) Presentation Slides
 
Tropical Cities: George Town, Penang Presentation Slides
Tropical Cities: George Town, Penang Presentation SlidesTropical Cities: George Town, Penang Presentation Slides
Tropical Cities: George Town, Penang Presentation Slides
 
Sun Yat Sen Museum Penang Report
Sun Yat Sen Museum Penang ReportSun Yat Sen Museum Penang Report
Sun Yat Sen Museum Penang Report
 
Sun Yat Sen Museum Penang Measured Drawings
Sun Yat Sen Museum Penang Measured DrawingsSun Yat Sen Museum Penang Measured Drawings
Sun Yat Sen Museum Penang Measured Drawings
 

Último

Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701bronxfugly43
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxcallscotland1987
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 

Último (20)

Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 

Building Technology 1 Construction Solutions Report

  • 1. School of Architecture, Building and Design (SABD) Bachelor of Science (Hons) in Architecture Building Technology 1 (BLD614013 / ARC3514 / ARC3512) Assignment 2: Construction Solutions of Jalan Tuanku Abdul Rahman Community Library Lee Xiang Loon (0322090) Tutor: Mr. Mohamed Rizal
  • 2. Table of Contents 1.0 Introduction 1.1 Jalan Tuanku Abdul Rahman 3 1.2 Community Library Floor Plans 4 2.0 Precedent Studies & Analysis 2.1 Structural Steel Frame – The Spring House 5 – 7 2.2 Composite Floor System – The Spring House 8 – 9 2.3 Roof System – Discovery Centre 10 – 13 2.4 Operable Blinds Facade System – Apartment Building CASP 74 14 – 16 2.5 Double Skin Facade System – Weill Cornell Medical College Belfer Research Building 17 – 20 3.0 Alternative Design Scheme 3.1 Operable Blinds Facade Scheme 21 – 22 3.2 Double Skin Facade Scheme 23 – 24 4.0 Sectional Perspectives 4.1 Ground Floor 25 4.2 3rd and 4th Floor 26 4.3 Detailing 27 2Building Technology 1: Construction Solutions | Table of Contents
  • 3. Site Plan | Scale 1:500 1.0 Introduction | 1.1 Jalan Tuanku Abdul Rahman 3Building Technology 1: Construction Solutions | The community library sits on two existing shophouses of total lot area of 392.2m2 in Jalan Tuanku Abdul Rahman, Kuala Lumpur. The building is fronting to the east while the rear to the west, and sits within a row of traditional and modern shophouses. This community library designed within an urban infill site serves as a centre for the existing local community to share similar interests and exchange ideas, addressing the fading cultural heritage of the site.
  • 4. Ground Floor Level Scale 1:200 1.0 Introduction | 1.2 Community Library Floor Plans 4Building Technology 1: Construction Solutions | Ground Mezzanine Level Scale 1:200 First Floor Level Scale 1:200 Second Floor Level Scale 1:200 Third Floor Level Scale 1:200
  • 5. 2.0 Precedent Studies | 2.1 Structural Steel Frame 5 The Spring House | Wu & Liu Architects The Spring House is located in Guiren Tainan, Taiwan. The design combines the client’s unique personal living space and for her special friends. The building combines steel, bricks, concrete and metal plates to form the framework of traditional architecture and spatial order to reinterpret modern residential construction. This residential building uses both steel frame structures and composite metal decking for its floors. Building Technology 1: Construction Solutions |
  • 6. 6 Advantages 1. Fast to build at site, as the majority of work can be pre-fabricated at the factory. 2. Steel structures are flexible and good at resisting wind and earthquake forces. 3. Strong and durable, and does not warp or expand unlike traditional wood framing. 4. A wide range of pre-made structural sections are available and they are suitable to clad with any material. 5. Able to span long distances. 6. Has a variety of joining methods including bolting, welding and riveting. Disadvantages 1. Lose strength at high temperatures and susceptible to fire so coatings are required. 2. Prone to corrosion in tropical and humid environments. Integration to Community Library Steel frame constructions allow a larger structural spans and efficient when laid out along a regular grid, especially when the site has a long distance from front to rear. The brick structure combined with the modern steel structure to produce a unique local architectural type. This brings a sense of locality with the neighbouring shoplots which are of solid masses as well. Masonry also possess good insulation properties for acoustics needed in the community library. Salvaged bricks from the existing building can be reused for the new library. Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.1 Structural Steel Frame Steel Frame Structures Steel construction has an immense strength which is an advantage to buildings. It can bend with cracking and can flex when wind or earthquake forces acting on it. Various connection joints are concurrently used throughout the steel system to further strengthen the connections between structural members and the masonry walls.
  • 7. 7 Construction Process 1. After the concrete foundation has set up, steel base plates are anchored and attached to the foundation with four anchoring bolts. The plates are levelled on a bed of non-shrinking grout. 2. The steel columns are lowered and welded to these base plates. The plates are used to transfer concentrated load from the columns to the ground. 3. Primary ground floor beams are connected to the columns via fin plates. The plates are welded with the column and bolted to the web of the beams. 4. Secondary floor beams are connected to the primary beams through a similar method. 5. The ground flooring is prepared through composite decking. The composite process is done by welding sheer studs through the steel decking to the supporting steel beam below. [See Composite Floor System] Infill brick walls are then placed. 6. For the upper floors, more columns are erected and connected through splices. The splices provide strength and stiffness to both the columns. The splices are bolted to both the columns. 7. The process is repeated for the flooring system. Building Technology 1: Construction Solutions | Brick wall Steel columns Composite steel flooring Steel beam Concrete foundation Reinforced concrete Master bedroom Entrance Sectional detail of The Spring House Steel column is welded to its steel base plate after the plate is levelled on a bed of non-shrinking grout. Steel beams are connected to columns via fin plates through welding and bolting. Composite flooring system by welding sheer stuffs to the supporting steel beam below. More columns are connected through splices by using bolts. 4321 2.0 Precedent Studies | 2.1 Structural Steel Frame
  • 8. 8Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.2 Composite Floor System Advantages 1. No evidence of nails and has a nice flat finish. 2. Steel and concrete may be arranged to produce ideal combination of strength, with concrete efficient in compression and steel in tension. 3. The construction time is reduced since casting of additional floors may proceed without having to wait for the previously cast floors to gain strength. 4. The construction of composite floor does not require highly skilled labour. The steel decking acts as a permanent form work. 5. Composite decking offers excellent resistance to corrosion, chemical attack and outdoor weathering. Disadvantages 1. Temperature sensitive and expands and contracts with temperature change. 2. If damaged or faded, the material must be replaced. 3. A soft material and wears easily. Integration to Community Library The lightweight properties of composite decking allows the sizes of other structural components to be greatly reduced, permitting smaller interiors and the possibility for open floor plans. Composite flooring has a much smaller depth compared to reinforced concrete floor slabs. This allows flexibility in design and at the same to withstand greater loads. Ceiling heights can be significantly increased. Composite Flooring Composite decking serves as a tensile reinforcement for the concrete slab to which it is bonded with embossed rib patterns.
  • 9. 9 Construction Process 1. Trapezoidal steel decking is placed and spanned in a direction transverse to the secondary floor beams. 2. The decking is rigidly connected to the primary and secondary beams by shear studs, which are connected through deck-welding techniques. 3. Steel mesh reinforcement, i.e. rebars, is placed above the steel decking to provide bending resistance and reduce cracking at the supports. The mesh also aids the distribution of the effects of localised point and line loads. 4. The profiled steel decking acts as a formwork during construction and additional external reinforcement at the final stage of construction when reinforced concrete is cast on top of it. Building Technology 1: Construction Solutions | Trapezoidal steel deck profiles Reinforced concrete cast in-situ Mesh reinforcement Trapezoidal steel deck profile 19mm⌀ x 95mm shear stud Edge trim and restraint strap End cap Fixings to suit project specifications 50mm min. bearing 50mm min. bearing Downstand edge beam Composite floor components • 1-1/2” (38) spanning 4’ to 8’ (1220 to 2440) • 2” (51) spanning to 8’ to 12’ (2440 to 3660) • 3” (75) spanning 8’ to 15’ (2440 to 4570) Composite decking span 2.0 Precedent Studies | 2.2 Composite Floor System
  • 10. 10Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.3 Roof System Discovery Centre | Architecture Discipline This city town hall located in Karnataka, India serves as a office/sales office and the design brief demanded the exploration of sustainable design and development. The exposed roof structure utilizes longitudinal steel trusses for the long building span and topped with polycarbonate sheeting to allow diffused lighting into the interior.
  • 11. 11 Advantages 1. The simple mechanism of longitudinal steel trusses of the roof allows simple and fast construction. 2. The lightweight of the roof truss members reduces the typical bulkiness of structural members. 3. Steel roof trusses allow larger spans, which contributes to the need of lesser columns. An open floor plan can be achieved and it is economical. 4. Lightweight polycarbonate sheet is lightweight and reduces the sizes of columns supporting the roof. 5. Using a truss system aids in keeping the roof light, brings light inside and enables controlled surrounding views of the site. 6. The fabric louvers arranged in angular between the trusses allows soft and diffused light to penetrate into the interior spaces. Thus, exposed ceiling can be achieved. Disadvantages 1. Skilled labour is required to install these steel roof trusses. 2. Rust can be a problem when the metal is cut, drilled and welded if no proper coating is done on the structural members. Integration to Community Library Longitudinal steel roof trusses are encouraged to be used as the roof system in the community library as it can span long distances especially when our site is long in length. The installation of steel trusses also means that lesser and smaller sized columns can be used to support the roof structure. This allows an open floor plan of the community library which contributes to more interior spaces. The ceiling can be left exposed as it is as steel trusses can be aesthetically pleasing when viewed. The lightweight fabric louvers installed on the structural members bring in soft and diffused light into the interior spaces. Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.3 Roof System
  • 12. 12Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.3 Roof System 1. Primary steel truss – 18m wide span 2. Perforated fabric louvers 3. Translucent fabric layer 4. Steel roof purlins 5. Milky white polycarbonate sheet 6. Rain water to ground storage 7. Composite fascia Cross-sectional detail of the roof system Longitudinal section of the building Construction Process 1. The steel trusses are pre-fabricated in the factory. The diagonal web members are welded and bolted to both top and bottom chords of the steel trusses. 2. The primary steel trusses are brought to site and assembled to the structural steel beams through welding. Both beams and trusses sit on the round columns of the building. 3. Roof purlins are laid on the trusses of varying heights to allow a small degree of roof pitch. The purlins are then fasten through bolting and welding to the top chord of the steel trusses. 4. Polycarbonate sheeting is laid and nailed with fastening plates on the purlins. 5. The translucent fabric layer is installed right below the top chord of the truss and secured onto the structural steel beams. 6. Perforated fabric louvers are aligned and angled between the trusses. Some layers are overlapped with one another to allow natural light to diffuse into the interior spaces below.
  • 13. 13Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.3 Roof System [Top] Angular perforated fabric louvers [Bottom] Diffused natural light into the spaces below Longitudinal steel roof trusses installed onto the structural steel beams
  • 14. 2.0 Precedent Studies | 2.4 Operable Blinds Facade System 14Building Technology 1: Construction Solutions | CASP 74 | Bach Arquitectes The CASP 74 apartment is located in Barcelona, Spain. The design of the building responds to the necessity of the modern era and the facade is composed as a dialogue between fixed panels formed by steel framed vertical ceramic planks, and sliding aluminium blinds providing the necessary privacy and lighting control.
  • 15. 15Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.4 Operable Blinds Facade System Advantages 1. The changing façade provides solar protection and privacy. 2. Folding aluminium blinds creates dynamics when is viewed from the street and allows lighting control. 3. The façade prevents heat from getting into the interior spaces during summer due to the ceramic planks, so it seals to keep warmth. 4. Aluminium is a lightweight material which makes the blinds easy to handle and less expensive to transport. 5. The blinds are durable and less susceptible to corrosion as aluminium has its own naturally occurring oxide film. Disadvantages 1. The blinds can be noisy at the window when it is operated because they are metal. 2. Tendency to accumulate dust over time, which is most noticeable on darker coloured vanes. Integration to Community Library The implementation of vertical blinds especially with aluminium as the material is perfect for controlling light in accordance to the time of the day. It is modern looking yet classic which fits the ambience of the site of Jalan Tuanku Abdul Rahman – the mix of classic and contemporary. The blinds can be obtained in a wide range of colours to complement with the surrounding building facade and interior spaces perfectly. While the vertical blinds offer different levels of privacy which is needed for the library spaces, it can be remote control operated by the librarians.
  • 16. 16Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.4 Operable Blinds Facade System Sectional detail of facade Continuous plate along the slab Würth insulating metallic fabric UPN 160 channel Fixed frame to fasten ceramic planks Grey lead colour lacquered aluminium sliding formed by vertical rectangular profiles Special ceramic plank 120x80x680mm by Bach Arquitectes, the long faces of some pieces are enamelled 3mm neoprene between the separation of ceramic plank 50x30x3mm galvanized steel profile for supporting ceramic planks Double plates, fixed with high screws Lateral drilling profile to allow internal welding with the supporting flange, allows ventilation in the event of water entry Sliding window, grey lacquered aluminium leadFront elevation and horizontal section of facade Isometric sketch of facadeFixed ceramic planks during construction
  • 17. 17Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.4 Double Skin Facade System Weill Cornell Medical College Belfer Research Building | Todd Schliemann & Ennead Architects The Belfer Research Building of Weill Cornell Medical College is a medical research facility in New York, United States. The building envelope features a high- performance double-skinned, fritted-glass curtain wall that maximizes energy efficiency. The passively vented system is designed to promote controlled convection within the wall cavity to mitigate extreme temperatures and enhance thermal comfort within the building.
  • 18. 18 Advantages 1. The double-skinned facade helps to promote energy efficiency. 2. Passive vented system promotes controlled convection within the wall cavity, mitigating extreme temperatures on the exterior of the building, and significantly reduces temperatures on the interior glass. 3. Openings and sun-shading devices enhance visual and thermal comfort within the interior spaces, reducing the carbon footprint of the building. 4. Curtain wall design provides an economically sensitive sustainable solution. Disadvantages 1. The view to the exterior from the building may be obstructed. 2. The wall cavity results in a decrease in usable floor space. 3. The construction of a second skin presents a significant increase in materials and design costs. Integration to Community Library Introducing the double-skinned facade in a community library is feasible as the wall cavity acts as a buffer zone to tackle noise coming from the street to allow quiet interior spaces. For a tropical country, the facade reduces solar heat gain in the interior spaces and promotes thermal comfort for the users. This double building envelope approach offers glare protection which is helpful for reading activities and promotes good daylighting method which subsequently minimizes the need of artificial lighting. Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.4 Double Skin Facade System
  • 19. 3D render of double curtain wall 19Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.4 Double Skin Facade System GL-1 Insulated Glass Unit: - 3/8” low-iron outer lite - Low-E coating #2 surface - 1/2” air space with argon gas fill - 1/4” low-iron inner lite GL-2 Laminated Spandrel Glass: - 5/8” low-iron laminated w/ 50% coverage frit pat. #2 surf. and opaque white interlayer GL-6 Laminated Fritted Glass Screen: - 5/8” low-iron laminated w/ 75% coverage frit pat. #2 surf. (black & white double pass frit) GL-7 Laminated Fritted Glass Screen: - 5/8” low-iron laminated w/ 50% coverage frit pattern #2 surf. (black & white double pass frit) 1. Not used 2. Not used 3. Painted aluminium 4-sided structurally glazed curtain wall w/ laminated glass panels 4. 16 gauge stainless steel cable @ 2” O.C. horizontal spacing. Wires tensioned across opening 5. Painted steel catwalk grating, 50% open supported on painted steel catwalk structure anchored to building structure 6. Curtain wall gravity load connection 7. Interior painted GYP BD finish 8. Intermediate ventilated cavity 9. Radiant ceiling panel 10. Concealed roller shade pocket 11. Painted aluminium 4-sided structurally glazed curtain wall w/ insulated glass panels 12. Painted aluminium sill cover (1/8” thk.) 13. 4” semi-rigid mineral wool insulation w/ galv. steel backpan assembly 14. Typical office partition with painted aluminium partition enclosures at vertical curtain wall mullion interface Sectional detail of double curtain wall
  • 20. 20Building Technology 1: Construction Solutions | 2.0 Precedent Studies | 2.4 Double Skin Facade System Front elevation of building facade Energy efficient building with sun shading properties
  • 21. 21Building Technology 1: Construction Solutions | 3.0 Alternative Design Scheme | 3.1 Operable Blinds Facade Scheme Front Elevation | Scale 1:100
  • 22. 22Building Technology 1: Construction Solutions | 3.0 Alternative Design Scheme | 3.1 Operable Blinds Facade Scheme Rear Elevation | Scale 1:100
  • 23. 23Building Technology 1: Construction Solutions | 3.0 Alternative Design Scheme | 3.2 Double Skin Facade Scheme Front Elevation | Scale 1:100
  • 24. 24Building Technology 1: Construction Solutions | 3.0 Alternative Design Scheme | 3.2 Double Skin Facade Scheme Rear Elevation | Scale 1:100
  • 25. 25Building Technology 1: Construction Solutions | 4.0 Sectional Perspectives | 4.1 Ground Floor Level Sectional Perspective | Ground Floor R.C. pad footing R.C. column stump R.C. ground beam 150mm R.C. floor slab Composite steel decking with trapezoidal profile 200x200mm steel I-column, powder coated black 165x305mm steel I-beam, powder coated black Concrete slab with mesh reinforcement 900mm pipe railing Operable blinds facade system DETAIL A DETAIL B
  • 26. 26Building Technology 1: Construction Solutions | 4.0 Sectional Perspectives | 4.2 2nd and 3rd Floor Level Composite steel decking with trapezoidal profile 200x200mm steel I-column, powder coated black 165x305mm steel I-beam, powder coated black Z-channel galvanized roof purlin Milky white polycarbonate sheet Concrete slab with mesh reinforcement 900mm pipe railing 7m wide span primary steel truss Operable blinds facade system 150mm brick wall with 25mm plaster on both sides Sectional Perspective | 2nd and 3rd Floor Level DETAIL C
  • 27. 27Building Technology 1: Construction Solutions | 4.0 Sectional Perspectives | 4.3 Detailing Detail C | Scale 1:30 UPN 160 channel Fixed frame to fasten ceramic planks Grey lead colour lacquered aluminium sliding formed by vertical rectangular profiles Ceramic plank 120x80x680mm, the long faces of some pieces are enamelled Ceramic plank 120x80x680mm, the long faces of some pieces are enamelled 165x305mm steel I-beam, powder coated black 200x200mm steel I-column, powder coated black Detail A | Scale 1:30 Detail B | Scale 1:30 165x305mm steel I-beam, powder coated black 200x200mm steel I-column, powder coated black Composite steel decking with trapezoidal profile 25mm ceramic floor tile 150mm thk brick wall Concrete floor slab 165x305mm steel I-beam, powder coated black 200x200mm steel I-column, powder coated black 7m wide span primary steel truss Z-channel galvanized roof purlin Milky white polycarbonate sheet