SlideShare una empresa de Scribd logo
1 de 32
Descargar para leer sin conexión
COASTAL STORM RISK
MANAGEMENT
ALTERNATIVE
FORMULATION FOR
JAMAICA BAY
COMMUNITIES
JAMAICA BAY TASK FORCE MEETING
November 1, 2018
Peter Weppler, Chief
Environmental Analysis Branch
Planning Division
New York District
U.S. Army Corps of Engineers
Jamaica Bay, facing South from Brooklyn towards the
Bay, Rockaway Peninsula, and Atlantic Ocean. Source:
Boating Times Long Island, Photo by Jim Mobel
Jamaica Bay, New York City
2
CORPS OF ENGINEERS
PLAN FORMULATION PROCESS
• Identify problems and opportunities
• Inventory and forecast conditions
• Formulate alternatives to manage the risk of flooding from
coastal storms
• Evaluate alternatives
o Plans are screened for completeness, effectiveness, efficiency, and acceptability
o Compare reduced damages of proposed alternatives against without project conditions
to determine benefits
o Perform an initial evaluation of environmental impacts
o Compare benefits to costs for each alternative
 To be economically justified a plan must have a benefit-to-cost ratio (BCR)
greater than one
• Compare alternatives
• Select alternative
ADDRESSING SEA LEVEL RISE
3
• Adapting to sea level rise is NOT optional and it is a
shared responsibility.
• Incorporates the most recent, sound science analyses of
how to adapt coastal storm risk measures to increased
future sea level in their design and analyses.
• This includes assessing risk and uncertainty based on an
uncertain future.
4
EAST ROCKAWAY INLET TO ROCKAWAY INLET AND
JAMAICA BAY – ROCKAWAY BEACH
BACKGROUND ON ROCKAWAY REFORMULATION
Draft Report Released August 2016  wide-ranging public and agency
comments were received
Tentatively Selected Plan in the 2016 Draft Report recommended a
comprehensive $3B plan (which has since been revised) but included:
Storm surge barrier across Jamaica Bay inlet
Atlantic Shorefront seawall dune and beach system with groin
enhancement
Smaller features in the Back-Bay to manage risk for frequent flooding
when the barrier would remain open
The $5B “perimeter plan” of floodwalls and tributary gates around
Jamaica Bay was screened out in favor of the above
Public and Agency Input called for further analysis of proposed storm surge
barrier across Jamaica Bay
Numerous comments requested the inclusion of additional natural and
nature-based features (NNBFs) in Jamaica Bay
Equally, there were many comments requesting that the study be expedited
to construct the Atlantic Shorefront feature earlier than proposed
Draft Revise Report Released August 2018.
Comment period closed October 22, 2018
5
RECOMMENDED PLAN
ATLANTIC SHOREFRONT REACH
• Reinforced
vegetated dune
and beachfill with
structure crest of
+17 ft NAVD88,
dune crest of +18
ft NAVD88 for
35,000 LF from
Beach 9th Street to
Beach 149th
Street, and include
sand tapers at the
ends of the project
• 5 groin extensions,
1 optional groin
rehabilitation
• 13 new groins
• Obtaining sand
from borrow area
located
approximately 2
miles south of the
Rockaway
Peninsula and
about 6 miles east
of the Rockaway
Inlet.
6
TENTATIVELY SELECTED PLAN (CIRCA 2016)
DRAFT BARRIER ALIGNMENT
ALTERNATIVES EVALUATED (CIRCA 2016)
Three alignments of the storm surge barrier originally considered
- Hydrodynamic modeling undertaken for design of openings
- Effects of scour on Gil Hodges Bridge eliminated C-1W
- Impacts to existing utilities considered
C-1E is the preferred alignment, C-2 is close in comparison
HIGH FREQUENCY FLOODING RISK REDUCTION
FEATURES (HFFRRFS)
• Due to the scale, complexity, and cost of the
proposed storm barrier, and the need for
additional study, the barrier was moved to
New York/New Jersey Harbor and Tributaries
Feasibility Study which came out of the
North Atlantic Coast Comprehensive Study
(NACCS)
• High Frequency Flooding Risk Reduction
Features (HFFRRFs, formerly ‘Residual Risk
Features’) are designed to complement a
potential future storm surge barrier
• In order to be recommended, each element
must be justified as stand-alone feature
(without the proposed storm surge barrier)
and have a positive benefit-to-cost ratio
9
New York and New Jersey Harbor and
Tributaries Study Area—The study team is
evaluating a suite of storm surge barriers in
the region to evaluate potential for regional
storm risk management measures
BACK BAY FLOODING
10
3yr RP (2068) Flood Extent Verified
5yr RP (2068) Flood Extent Verified
10yr RP (2068) Flood Extent Verified
Flood extents calculated
only within HFFRRF study
area. Excludes Broad
Channel and areas outside
(west) of storm surge barrier
alignment C-1E
NATURE BASED FEATURES
LOCATIONS ANALYZED
3 Sites at Arverne
1 Site at
Edgemere
1 Site at Norton
Basin
1 Site at
Bayswater
2 Sites at
Mott’s
Basin
NNBF PROTOTYPE
DEVELOPMENT
 NNBFs created to accommodate a
variation in coastal edge conditions.
 Two main variations are distinguished:
 Horizontal space available between the
urban developed edge and the water line
 Existing plant species composition and the
need to either extend the existing
coastline or cut back the existing bank line
to accommodate a suitable habitat for
wetland creation/enhancement
 Rapidly descending bathymetry near
shoreline
 Limited horizontal width between front toe
of new shoreline slope and flood control
structure on back edge
 Already existing living shoreline habitats
performing CSRM function
 Presence of heavy anthropogenic
infrastructure along shoreline (e.g. docks,
piers).
 Gray feature structures set far back from
shoreline…no interactive capacity.
 Combinations of all these factors (most
likely scenario)
 Does not increase risk of wildlife hazards
to planes; habitat type restrictions near
JFK airport
DID NOT SITE NNBFS WHERE
THERE IS…
12
12
OLD HOWARD
BEACH
CANARSIE
HEAD OF BAY
NORTON BASIN
MOTTS BASIN
INWOOD
BAYSWATER
PARK
Flood extents calculated only within
HFFRRF study area. Excludes
Broad Channel and areas outside
(west) of storm surge barrier
alignment C-1E
ROSEDALE
MEADOWMERE
LAWRENCE
BROAD
CHANNEL
STRUCTURAL
SCREENED,
NONSTRUCTURAL
PASSED
MID-ROCKAWAY
BACK-BAY W/
NNBFs
High Frequency Flooding Risk Reduction
Features - SCREENING RESULTS
• 3 sites are in the Final Plan, including 5 NNBFs at the
Mid-Rockaway Back-Bay site
• Non-structural plan for Broad Channel screened using
data and experience from Build it Back
RECOMMENDED PLAN
JAMAICA BAY REACH
13
NNBF considered but not
recommended in this location:
• Existing high quality mudflat and
mussel habitat already
performing NNBF functions
• Avoid habitat exchange
Motts Basin North HFFRRF
RECOMMENDED PLAN
JAMAICA BAY REACH
14
HFFRRF Projects
Mid-Rockaway HFFRRF
Arverne Area/Subreach
(left)
Mid-Rockaway HFFRRF
Edgemere Area/Subreach
• NNBFs are integral features to control erosion
on the berm which will be overtopped
frequently throughout the project life
• NNBF+berm design is more cost effective than
alternative non-erodible floodwall
• BCR underestimates benefits due to “leaving
benefits on the table”
15
New York-New Jersey Harbor and Tributaries
Coastal Storm Risk Management Feasibility Study
ALTERNATIVES OVERVIEW
• Alternative 1: No Action
• Alternative 2: Harbor Wide Gate and Beach Restoration
• Alternative 3A/3B: Multiple Bay/Basin Gate and Floodwalls & Levee Systems
• Alternative 4: Individual Waterbody Gate and Floodwalls & Levees
• Alternative 5: Perimeter Only
New York Harbor.
ALTERNATIVE 1: NO ACTION (FUTURE WITHOUT PROJECT CONDITIONS)
16
ALTERNATIVES 2-5
• Alternative No. is a reference to the scale of solution and general strategy
• Siting and quantities are approximate for screening purposes and will be refined
• Design level 1% event (mean) + RSLC + Wave Run-up (measure and location specific)
• Focus on biggest cost drivers (storm surge barrier) in each alternative
• Nonstructural, NNBF, and perimeter structural placeholders to be refined in future
formulation
17
New York-New Jersey Harbor and Tributaries
Coastal Storm Risk Management Feasibility Study
Alt. 2 Alt. 3A Alt. 3B Alt. 4 Alt. 5
In-Water
Measures
Land-Based
Measures
18
20
21
22
23
New York-New Jersey Harbor and Tributaries
Coastal Storm Risk Management Feasibility Study
Alternatives at AMM
Best performing alternatives
(Draft Interim Report)
TSP and Draft Report
Work needed to identify TSP
Parametric analyses
ADM and optimization
Recommended Plan
FACTORS CONSIDERED - ALTERNATIVE SCREENING
1. Hydrodynamic Modeling
Induced Flooding during Storms
Tidal Influences
2. Relative Sea Level Change
Based on intermediate
3. Period of Analysis
50 year period may limit full evaluation given many measures will
likely have far longer period of utility
4. Operations and Maintenance Assumptions
Storm event condition selected for surge gate operation has
substantial effects on plan selection
5. Benefits Model
24
New York-New Jersey Harbor and Tributaries
Coastal Storm Risk Management Feasibility
Study
25
New York-New Jersey Harbor and Tributaries
Coastal Storm Risk Management Feasibility Study
ENVIRONMENTAL CONSIDERATIONS
 Changes to tidal range/regime, flow velocity, salinity concentrations, sedimentation rates,
scour, and elevation
 Water quality, dissolved oxygen, nutrients, and phytoplankton biomass (i.e.
eutrophication), and pathogenic bacteria
 Anadromous/catadromous fish migration and aquatic species
 Marsh inundation
 Air quality
 Transportation (marine vessels, etc.)
 Aesthetics and recreation
 National Historic Landmarks and
Historic Properties
 Listed species and critical habitat
 Noise and vibration
 Bay bottom impacts, as well as landside impacts
 Location of Superfund, National Priority List, and other contaminated sites
Jamaica Bay, New York City
26
New York-New Jersey Harbor and Tributaries
Coastal Storm Risk Management Feasibility Study
PUBLIC INVOLVEMENT
 Scoping Period through November 5th
 Release of the Draft Interim Report – Winter 2019
 Public/ Agency Reviews with Public Meetings
 Draft Feasibility Report and Tier 1 EIS – Spring 2020
 Public/ Agency Reviews with Public Meetings
 Optimization of the Selected Plan
 Final Feasibility Report and Tier 1 EIS – Spring 2021
 Chief’s Report – Summer 2022
 Public Involvement during Pre-Construction Engineering
and Design Phase –Tier 2 EIS
*The red boxes indicate the best opportunities for the public to
provide input to the study.
The scoping period extends until
November 5, 2018. Comments
and input submitted by this
deadline will be used to develop
the Draft Interim Report.
Comments received after the
deadline are welcome and will be
used to help identify the Tentatively
Selected Plan (TSP) in 2020.
Once the Draft Interim Report is
released, the public and agencies
will have a chance to review and
submit comments and public
meetings will be held as part of the
public review period. The
comments are used to inform the
agency as it moves to identifying
the TSP.
27
New York-New Jersey Harbor and Tributaries
Coastal Storm Risk Management Feasibility Study
STUDY SCHEDULE
Milestones
Milestones Dates*
Draft Interim Report Winter 2018/2019
Draft Feasibility Report and Tier 1 EIS Spring 2020
Final Feasibility Report and Tier 1 EIS Spring 2021
Chief’s Report (for Congress) Summer 2022
* The schedule is contingent upon available funding, non-federal partner
support, and concurrence by Corps higher-authority offices.
28
New York-New Jersey Harbor and Tributaries
Coastal Storm Risk Management Feasibility Study
HOW TO STAY INVOLVED
Project Webpage
http://www.nan.usace.army.mil/Missions/Civ
il-Works/Projects-in-New-York/New-York-
New-Jersey-Harbor-Tributaries-Focus-Area-
Feasibility-Study/
Stakeholder Mailing List
Email
NYNJHarbor.TribStudy@usace.army.mil
if you would like to join our mailing list
and receive periodic updates.
Scoping Comments
Send any questions and/or comments
to
NYNJHarbor.TribStudy@usace.army.
mil
OR
Fill out and submit a comment card at
a scoping meeting
Scoping Comment Period open
through November 5, 2018
29
JAMAICA BAY PLANNING REGION EFFORTS
Elders Point East and
West Marsh Islands
Restoration (Mitigation
for NY Harbor and CAP
Beneficial Use of
Dredged Material):
Constructed 2007 & 2010
Black Wall and
Rulers Bar Marsh
Islands Restoration
(NY Harbor Sand
Placement):
Constructed 2012
and differential cost
paid for by sponsor.
Existing
Rockaway
Project:
Constructed 1977
and Repaired in
2014.
Proposed Ecosystem Restoration Sites
Jamaica Bay
Navigation Channel:
O&M Dredging in 2019
(subject to availability
of funds)
Plumb Beach
CSRM Project
(CAP Beneficial
Use of Dredged
Material):
Constructed
2012/2013
Gerritsen Creek
Restoration (CAP
Section 1135):
Constructed 2011
Hudson Raritan
Estuary (HRE)
Proposed Restoration
Sites
Yellow Bar Hassock
Marsh Island
Restoration (CAP
Beneficial Use of
Dredged Material):
Constructed 2012
East Rockaway
Inlet Navigation
Channel: O&M
Dredging in 2019
(subject to
availability of Funds)
Spring Creek South
CSRM/Restoration
(NYSDEC/FEMA IIS):
60% designs completed
and EA public release
August 2018
Spring Creek North
Restoration (CAP Section
1135): Report approved
Mar 2018 and D&I PPA
scheduled Jul 2018
SPRING CREEK SOUTH
FEMA HAZARD MITIGATION GRANT
PROGRAM (HMGP) PROJECT
Goals
• Manage coastal storm risk with Natural/nature-based features;
Decrease risk of fire
• Align with NPS Gateway National Recreation Area (GNRA)
Management Plan
• Coordinate with complementary Jamaica Bay projects
• Recommended Plan
 Berm - 19 feet NAVD 88; 50-foot-wide path at crest
 Tie-ins at Belt Parkway and Addabbo Bridge
 Freshwater wetlands
 Flap gates
 Local access points; Improved edge aesthetic
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities

Más contenido relacionado

La actualidad más candente

PPL26 Bayou La Loutre Ridge & Marsh Restoration Nomination Fact Sheet for 1_8_16
PPL26 Bayou La Loutre Ridge & Marsh Restoration Nomination Fact Sheet for 1_8_16PPL26 Bayou La Loutre Ridge & Marsh Restoration Nomination Fact Sheet for 1_8_16
PPL26 Bayou La Loutre Ridge & Marsh Restoration Nomination Fact Sheet for 1_8_16
Blaise Pezold
 
Lake Development Authority_CEO
Lake Development Authority_CEOLake Development Authority_CEO
Lake Development Authority_CEO
Ekonnect
 

La actualidad más candente (20)

Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
Long Branch Tributary at Long Branch Falls Park Public Meeting 8-20-2015
 
Royal Lake Dredging and Restoration
Royal Lake Dredging and RestorationRoyal Lake Dredging and Restoration
Royal Lake Dredging and Restoration
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Dead Run Stream Restoration Existing Conditions August 18, 2015
Dead Run Stream Restoration Existing Conditions August 18, 2015Dead Run Stream Restoration Existing Conditions August 18, 2015
Dead Run Stream Restoration Existing Conditions August 18, 2015
 
Amy Wolfe, Trout Unlimited, "A Decade of Progress for the West Branch Susqueh...
Amy Wolfe, Trout Unlimited, "A Decade of Progress for the West Branch Susqueh...Amy Wolfe, Trout Unlimited, "A Decade of Progress for the West Branch Susqueh...
Amy Wolfe, Trout Unlimited, "A Decade of Progress for the West Branch Susqueh...
 
Muskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success StoryMuskegon Lake Restoration: A Success Story
Muskegon Lake Restoration: A Success Story
 
PPL26 Bayou La Loutre Ridge & Marsh Restoration Nomination Fact Sheet for 1_8_16
PPL26 Bayou La Loutre Ridge & Marsh Restoration Nomination Fact Sheet for 1_8_16PPL26 Bayou La Loutre Ridge & Marsh Restoration Nomination Fact Sheet for 1_8_16
PPL26 Bayou La Loutre Ridge & Marsh Restoration Nomination Fact Sheet for 1_8_16
 
Positive Declaration for Pilgrim Pipeline from NY DEC & Thruway Authority
Positive Declaration for Pilgrim Pipeline from NY DEC & Thruway AuthorityPositive Declaration for Pilgrim Pipeline from NY DEC & Thruway Authority
Positive Declaration for Pilgrim Pipeline from NY DEC & Thruway Authority
 
Autumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit ProjectAutumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit Project
 
Lake Development Authority_CEO
Lake Development Authority_CEOLake Development Authority_CEO
Lake Development Authority_CEO
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
 
Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...
Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...
Shawn Rummel, Trout Unlimited, "Recovery of Coldwater Ecosystems Following Tr...
 
Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015
 
Sequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit ProjectSequoia Park Pond Retrofit Project
Sequoia Park Pond Retrofit Project
 
Wetlands_term_paper_2015
Wetlands_term_paper_2015Wetlands_term_paper_2015
Wetlands_term_paper_2015
 
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
 
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
Wolftrap Creek Restoration in Vienna’s Wildwood Park, October 2013
 
Dead Run Stream Restoration Public Meeting May 19, 2015
Dead Run Stream Restoration Public Meeting May 19, 2015Dead Run Stream Restoration Public Meeting May 19, 2015
Dead Run Stream Restoration Public Meeting May 19, 2015
 
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public Meeting
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public MeetingDraft TMDL Action Plans for Sediment, Bacteria, and PCBs Public Meeting
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public Meeting
 

Similar a ACOE Coastal Storm Management Alternative for Jamaica Bay Communities

SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
Erin Vieira
 
Staff Presentation 080311 Gtg
Staff Presentation 080311 GtgStaff Presentation 080311 Gtg
Staff Presentation 080311 Gtg
Greg Gearheart
 
26. Floods Directive & Hydromorpholgy Measures
26. Floods Directive & Hydromorpholgy Measures26. Floods Directive & Hydromorpholgy Measures
26. Floods Directive & Hydromorpholgy Measures
Environmental Protection Agency, Ireland
 

Similar a ACOE Coastal Storm Management Alternative for Jamaica Bay Communities (20)

NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdfNYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
 
Army Corps of Engineers Report on Restoration Planning in Jamaica bay
Army Corps of Engineers Report on Restoration Planning in Jamaica bayArmy Corps of Engineers Report on Restoration Planning in Jamaica bay
Army Corps of Engineers Report on Restoration Planning in Jamaica bay
 
Municipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach CommunitiesMunicipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach Communities
 
Poope and dean 1986
Poope and dean 1986Poope and dean 1986
Poope and dean 1986
 
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
Use of MIKE 21/3 in the Hydraulic Analysis for the Dublin Port ABR Project - ...
 
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptxFall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation final
 
Carullo gsm 111314
Carullo gsm 111314Carullo gsm 111314
Carullo gsm 111314
 
Nam Ngiep Hydropower Dam -- Climate Risk Assessment
Nam Ngiep Hydropower Dam -- Climate Risk Assessment Nam Ngiep Hydropower Dam -- Climate Risk Assessment
Nam Ngiep Hydropower Dam -- Climate Risk Assessment
 
Jamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfJamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdf
 
Orlando 2015
Orlando 2015Orlando 2015
Orlando 2015
 
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
 
Understanding Who is AT RISK - Flood extent modelling
Understanding Who is AT RISK - Flood extent modellingUnderstanding Who is AT RISK - Flood extent modelling
Understanding Who is AT RISK - Flood extent modelling
 
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
 
Staff Presentation 080311 Gtg
Staff Presentation 080311 GtgStaff Presentation 080311 Gtg
Staff Presentation 080311 Gtg
 
James riverpartnership2003
James riverpartnership2003James riverpartnership2003
James riverpartnership2003
 
Coastal Erosion Control_RIFMA2016
Coastal Erosion Control_RIFMA2016Coastal Erosion Control_RIFMA2016
Coastal Erosion Control_RIFMA2016
 
Wetlands and Stormwater Management
Wetlands and Stormwater ManagementWetlands and Stormwater Management
Wetlands and Stormwater Management
 
ACOE Reformulation study for Jamaica Bay
ACOE Reformulation study for Jamaica BayACOE Reformulation study for Jamaica Bay
ACOE Reformulation study for Jamaica Bay
 
26. Floods Directive & Hydromorpholgy Measures
26. Floods Directive & Hydromorpholgy Measures26. Floods Directive & Hydromorpholgy Measures
26. Floods Directive & Hydromorpholgy Measures
 

Más de ecowatchers

Más de ecowatchers (20)

JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdfJBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
JBTF Nov2023 - JBRPC West Pond Living Shoreline.pdf
 
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptxNYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
 
Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf
Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdfBaron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf
Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf
 
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfNPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
 
November 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdfNovember 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdf
 
Baron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdf
 
Jamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdfJamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdf
 
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
 
Ribbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdfRibbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdf
 
Jb task force 2021 1103
Jb task force 2021 1103Jb task force 2021 1103
Jb task force 2021 1103
 
201130 west pond reduced
201130 west pond reduced201130 west pond reduced
201130 west pond reduced
 
Jamaica bay ecowatchers task force presentation 12.9.2020
Jamaica bay ecowatchers task force presentation   12.9.2020Jamaica bay ecowatchers task force presentation   12.9.2020
Jamaica bay ecowatchers task force presentation 12.9.2020
 
Nyc parks marine debris removal
Nyc parks marine debris removalNyc parks marine debris removal
Nyc parks marine debris removal
 
Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020
 
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
 
Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.
 
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodiesNYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
 
Shirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two workShirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two work
 
Sunset cove restoration project -update
Sunset cove restoration project -updateSunset cove restoration project -update
Sunset cove restoration project -update
 
American Littoral Society Jamaica Bay presentation, 5 9-2019
American Littoral Society Jamaica Bay presentation, 5 9-2019 American Littoral Society Jamaica Bay presentation, 5 9-2019
American Littoral Society Jamaica Bay presentation, 5 9-2019
 

Último

Sustainable Packaging
Sustainable PackagingSustainable Packaging
Sustainable Packaging
Dr. Salem Baidas
 
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
rajputriyana310
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
Contact Number Call Girls Service In Goa  9316020077 Goa  Call Girls ServiceContact Number Call Girls Service In Goa  9316020077 Goa  Call Girls Service
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
sexy call girls service in goa
 
E Waste Management
E Waste ManagementE Waste Management
E Waste Management
Dr. Salem Baidas
 

Último (20)

The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
 
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...Call On 6297143586  Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
Call On 6297143586 Pimpri Chinchwad Call Girls In All Pune 24/7 Provide Call...
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
 
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
 
Sustainable Packaging
Sustainable PackagingSustainable Packaging
Sustainable Packaging
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...Booking open Available Pune Call Girls Budhwar Peth  6297143586 Call Hot Indi...
Booking open Available Pune Call Girls Budhwar Peth 6297143586 Call Hot Indi...
 
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
 
Types of Pollution Powerpoint presentation
Types of Pollution Powerpoint presentationTypes of Pollution Powerpoint presentation
Types of Pollution Powerpoint presentation
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
 
CSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayCSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting Day
 
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
 
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...Book Sex Workers Available Pune Call Girls Kondhwa  6297143586 Call Hot India...
Book Sex Workers Available Pune Call Girls Kondhwa 6297143586 Call Hot India...
 
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
Contact Number Call Girls Service In Goa  9316020077 Goa  Call Girls ServiceContact Number Call Girls Service In Goa  9316020077 Goa  Call Girls Service
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
 
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
(NEHA) Call Girls Navi Mumbai Call Now 8250077686 Navi Mumbai Escorts 24x7
 
Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...Booking open Available Pune Call Girls Yewalewadi  6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Yewalewadi 6297143586 Call Hot Indian...
 
E Waste Management
E Waste ManagementE Waste Management
E Waste Management
 

ACOE Coastal Storm Management Alternative for Jamaica Bay Communities

  • 1. COASTAL STORM RISK MANAGEMENT ALTERNATIVE FORMULATION FOR JAMAICA BAY COMMUNITIES JAMAICA BAY TASK FORCE MEETING November 1, 2018 Peter Weppler, Chief Environmental Analysis Branch Planning Division New York District U.S. Army Corps of Engineers Jamaica Bay, facing South from Brooklyn towards the Bay, Rockaway Peninsula, and Atlantic Ocean. Source: Boating Times Long Island, Photo by Jim Mobel Jamaica Bay, New York City
  • 2. 2 CORPS OF ENGINEERS PLAN FORMULATION PROCESS • Identify problems and opportunities • Inventory and forecast conditions • Formulate alternatives to manage the risk of flooding from coastal storms • Evaluate alternatives o Plans are screened for completeness, effectiveness, efficiency, and acceptability o Compare reduced damages of proposed alternatives against without project conditions to determine benefits o Perform an initial evaluation of environmental impacts o Compare benefits to costs for each alternative  To be economically justified a plan must have a benefit-to-cost ratio (BCR) greater than one • Compare alternatives • Select alternative
  • 3. ADDRESSING SEA LEVEL RISE 3 • Adapting to sea level rise is NOT optional and it is a shared responsibility. • Incorporates the most recent, sound science analyses of how to adapt coastal storm risk measures to increased future sea level in their design and analyses. • This includes assessing risk and uncertainty based on an uncertain future.
  • 4. 4 EAST ROCKAWAY INLET TO ROCKAWAY INLET AND JAMAICA BAY – ROCKAWAY BEACH
  • 5. BACKGROUND ON ROCKAWAY REFORMULATION Draft Report Released August 2016  wide-ranging public and agency comments were received Tentatively Selected Plan in the 2016 Draft Report recommended a comprehensive $3B plan (which has since been revised) but included: Storm surge barrier across Jamaica Bay inlet Atlantic Shorefront seawall dune and beach system with groin enhancement Smaller features in the Back-Bay to manage risk for frequent flooding when the barrier would remain open The $5B “perimeter plan” of floodwalls and tributary gates around Jamaica Bay was screened out in favor of the above Public and Agency Input called for further analysis of proposed storm surge barrier across Jamaica Bay Numerous comments requested the inclusion of additional natural and nature-based features (NNBFs) in Jamaica Bay Equally, there were many comments requesting that the study be expedited to construct the Atlantic Shorefront feature earlier than proposed Draft Revise Report Released August 2018. Comment period closed October 22, 2018 5
  • 6. RECOMMENDED PLAN ATLANTIC SHOREFRONT REACH • Reinforced vegetated dune and beachfill with structure crest of +17 ft NAVD88, dune crest of +18 ft NAVD88 for 35,000 LF from Beach 9th Street to Beach 149th Street, and include sand tapers at the ends of the project • 5 groin extensions, 1 optional groin rehabilitation • 13 new groins • Obtaining sand from borrow area located approximately 2 miles south of the Rockaway Peninsula and about 6 miles east of the Rockaway Inlet. 6
  • 8. DRAFT BARRIER ALIGNMENT ALTERNATIVES EVALUATED (CIRCA 2016) Three alignments of the storm surge barrier originally considered - Hydrodynamic modeling undertaken for design of openings - Effects of scour on Gil Hodges Bridge eliminated C-1W - Impacts to existing utilities considered C-1E is the preferred alignment, C-2 is close in comparison
  • 9. HIGH FREQUENCY FLOODING RISK REDUCTION FEATURES (HFFRRFS) • Due to the scale, complexity, and cost of the proposed storm barrier, and the need for additional study, the barrier was moved to New York/New Jersey Harbor and Tributaries Feasibility Study which came out of the North Atlantic Coast Comprehensive Study (NACCS) • High Frequency Flooding Risk Reduction Features (HFFRRFs, formerly ‘Residual Risk Features’) are designed to complement a potential future storm surge barrier • In order to be recommended, each element must be justified as stand-alone feature (without the proposed storm surge barrier) and have a positive benefit-to-cost ratio 9 New York and New Jersey Harbor and Tributaries Study Area—The study team is evaluating a suite of storm surge barriers in the region to evaluate potential for regional storm risk management measures
  • 10. BACK BAY FLOODING 10 3yr RP (2068) Flood Extent Verified 5yr RP (2068) Flood Extent Verified 10yr RP (2068) Flood Extent Verified Flood extents calculated only within HFFRRF study area. Excludes Broad Channel and areas outside (west) of storm surge barrier alignment C-1E
  • 11. NATURE BASED FEATURES LOCATIONS ANALYZED 3 Sites at Arverne 1 Site at Edgemere 1 Site at Norton Basin 1 Site at Bayswater 2 Sites at Mott’s Basin NNBF PROTOTYPE DEVELOPMENT  NNBFs created to accommodate a variation in coastal edge conditions.  Two main variations are distinguished:  Horizontal space available between the urban developed edge and the water line  Existing plant species composition and the need to either extend the existing coastline or cut back the existing bank line to accommodate a suitable habitat for wetland creation/enhancement  Rapidly descending bathymetry near shoreline  Limited horizontal width between front toe of new shoreline slope and flood control structure on back edge  Already existing living shoreline habitats performing CSRM function  Presence of heavy anthropogenic infrastructure along shoreline (e.g. docks, piers).  Gray feature structures set far back from shoreline…no interactive capacity.  Combinations of all these factors (most likely scenario)  Does not increase risk of wildlife hazards to planes; habitat type restrictions near JFK airport DID NOT SITE NNBFS WHERE THERE IS…
  • 12. 12 12 OLD HOWARD BEACH CANARSIE HEAD OF BAY NORTON BASIN MOTTS BASIN INWOOD BAYSWATER PARK Flood extents calculated only within HFFRRF study area. Excludes Broad Channel and areas outside (west) of storm surge barrier alignment C-1E ROSEDALE MEADOWMERE LAWRENCE BROAD CHANNEL STRUCTURAL SCREENED, NONSTRUCTURAL PASSED MID-ROCKAWAY BACK-BAY W/ NNBFs High Frequency Flooding Risk Reduction Features - SCREENING RESULTS • 3 sites are in the Final Plan, including 5 NNBFs at the Mid-Rockaway Back-Bay site • Non-structural plan for Broad Channel screened using data and experience from Build it Back
  • 13. RECOMMENDED PLAN JAMAICA BAY REACH 13 NNBF considered but not recommended in this location: • Existing high quality mudflat and mussel habitat already performing NNBF functions • Avoid habitat exchange Motts Basin North HFFRRF
  • 14. RECOMMENDED PLAN JAMAICA BAY REACH 14 HFFRRF Projects Mid-Rockaway HFFRRF Arverne Area/Subreach (left) Mid-Rockaway HFFRRF Edgemere Area/Subreach • NNBFs are integral features to control erosion on the berm which will be overtopped frequently throughout the project life • NNBF+berm design is more cost effective than alternative non-erodible floodwall • BCR underestimates benefits due to “leaving benefits on the table”
  • 15. 15 New York-New Jersey Harbor and Tributaries Coastal Storm Risk Management Feasibility Study ALTERNATIVES OVERVIEW • Alternative 1: No Action • Alternative 2: Harbor Wide Gate and Beach Restoration • Alternative 3A/3B: Multiple Bay/Basin Gate and Floodwalls & Levee Systems • Alternative 4: Individual Waterbody Gate and Floodwalls & Levees • Alternative 5: Perimeter Only New York Harbor.
  • 16. ALTERNATIVE 1: NO ACTION (FUTURE WITHOUT PROJECT CONDITIONS) 16
  • 17. ALTERNATIVES 2-5 • Alternative No. is a reference to the scale of solution and general strategy • Siting and quantities are approximate for screening purposes and will be refined • Design level 1% event (mean) + RSLC + Wave Run-up (measure and location specific) • Focus on biggest cost drivers (storm surge barrier) in each alternative • Nonstructural, NNBF, and perimeter structural placeholders to be refined in future formulation 17 New York-New Jersey Harbor and Tributaries Coastal Storm Risk Management Feasibility Study Alt. 2 Alt. 3A Alt. 3B Alt. 4 Alt. 5 In-Water Measures Land-Based Measures
  • 18. 18
  • 19.
  • 20. 20
  • 21. 21
  • 22. 22
  • 23. 23 New York-New Jersey Harbor and Tributaries Coastal Storm Risk Management Feasibility Study Alternatives at AMM Best performing alternatives (Draft Interim Report) TSP and Draft Report Work needed to identify TSP Parametric analyses ADM and optimization Recommended Plan
  • 24. FACTORS CONSIDERED - ALTERNATIVE SCREENING 1. Hydrodynamic Modeling Induced Flooding during Storms Tidal Influences 2. Relative Sea Level Change Based on intermediate 3. Period of Analysis 50 year period may limit full evaluation given many measures will likely have far longer period of utility 4. Operations and Maintenance Assumptions Storm event condition selected for surge gate operation has substantial effects on plan selection 5. Benefits Model 24 New York-New Jersey Harbor and Tributaries Coastal Storm Risk Management Feasibility Study
  • 25. 25 New York-New Jersey Harbor and Tributaries Coastal Storm Risk Management Feasibility Study ENVIRONMENTAL CONSIDERATIONS  Changes to tidal range/regime, flow velocity, salinity concentrations, sedimentation rates, scour, and elevation  Water quality, dissolved oxygen, nutrients, and phytoplankton biomass (i.e. eutrophication), and pathogenic bacteria  Anadromous/catadromous fish migration and aquatic species  Marsh inundation  Air quality  Transportation (marine vessels, etc.)  Aesthetics and recreation  National Historic Landmarks and Historic Properties  Listed species and critical habitat  Noise and vibration  Bay bottom impacts, as well as landside impacts  Location of Superfund, National Priority List, and other contaminated sites Jamaica Bay, New York City
  • 26. 26 New York-New Jersey Harbor and Tributaries Coastal Storm Risk Management Feasibility Study PUBLIC INVOLVEMENT  Scoping Period through November 5th  Release of the Draft Interim Report – Winter 2019  Public/ Agency Reviews with Public Meetings  Draft Feasibility Report and Tier 1 EIS – Spring 2020  Public/ Agency Reviews with Public Meetings  Optimization of the Selected Plan  Final Feasibility Report and Tier 1 EIS – Spring 2021  Chief’s Report – Summer 2022  Public Involvement during Pre-Construction Engineering and Design Phase –Tier 2 EIS *The red boxes indicate the best opportunities for the public to provide input to the study. The scoping period extends until November 5, 2018. Comments and input submitted by this deadline will be used to develop the Draft Interim Report. Comments received after the deadline are welcome and will be used to help identify the Tentatively Selected Plan (TSP) in 2020. Once the Draft Interim Report is released, the public and agencies will have a chance to review and submit comments and public meetings will be held as part of the public review period. The comments are used to inform the agency as it moves to identifying the TSP.
  • 27. 27 New York-New Jersey Harbor and Tributaries Coastal Storm Risk Management Feasibility Study STUDY SCHEDULE Milestones Milestones Dates* Draft Interim Report Winter 2018/2019 Draft Feasibility Report and Tier 1 EIS Spring 2020 Final Feasibility Report and Tier 1 EIS Spring 2021 Chief’s Report (for Congress) Summer 2022 * The schedule is contingent upon available funding, non-federal partner support, and concurrence by Corps higher-authority offices.
  • 28. 28 New York-New Jersey Harbor and Tributaries Coastal Storm Risk Management Feasibility Study HOW TO STAY INVOLVED Project Webpage http://www.nan.usace.army.mil/Missions/Civ il-Works/Projects-in-New-York/New-York- New-Jersey-Harbor-Tributaries-Focus-Area- Feasibility-Study/ Stakeholder Mailing List Email NYNJHarbor.TribStudy@usace.army.mil if you would like to join our mailing list and receive periodic updates. Scoping Comments Send any questions and/or comments to NYNJHarbor.TribStudy@usace.army. mil OR Fill out and submit a comment card at a scoping meeting Scoping Comment Period open through November 5, 2018
  • 29. 29 JAMAICA BAY PLANNING REGION EFFORTS Elders Point East and West Marsh Islands Restoration (Mitigation for NY Harbor and CAP Beneficial Use of Dredged Material): Constructed 2007 & 2010 Black Wall and Rulers Bar Marsh Islands Restoration (NY Harbor Sand Placement): Constructed 2012 and differential cost paid for by sponsor. Existing Rockaway Project: Constructed 1977 and Repaired in 2014. Proposed Ecosystem Restoration Sites Jamaica Bay Navigation Channel: O&M Dredging in 2019 (subject to availability of funds) Plumb Beach CSRM Project (CAP Beneficial Use of Dredged Material): Constructed 2012/2013 Gerritsen Creek Restoration (CAP Section 1135): Constructed 2011 Hudson Raritan Estuary (HRE) Proposed Restoration Sites Yellow Bar Hassock Marsh Island Restoration (CAP Beneficial Use of Dredged Material): Constructed 2012 East Rockaway Inlet Navigation Channel: O&M Dredging in 2019 (subject to availability of Funds) Spring Creek South CSRM/Restoration (NYSDEC/FEMA IIS): 60% designs completed and EA public release August 2018 Spring Creek North Restoration (CAP Section 1135): Report approved Mar 2018 and D&I PPA scheduled Jul 2018
  • 30. SPRING CREEK SOUTH FEMA HAZARD MITIGATION GRANT PROGRAM (HMGP) PROJECT Goals • Manage coastal storm risk with Natural/nature-based features; Decrease risk of fire • Align with NPS Gateway National Recreation Area (GNRA) Management Plan • Coordinate with complementary Jamaica Bay projects • Recommended Plan  Berm - 19 feet NAVD 88; 50-foot-wide path at crest  Tie-ins at Belt Parkway and Addabbo Bridge  Freshwater wetlands  Flap gates  Local access points; Improved edge aesthetic