SlideShare una empresa de Scribd logo
1 de 9
Earned Value Analysis 
Concept and Application 
Presented by 
Ahmed Rami Elsherif 
27/12/2012
Concept 
Earned Value Analysis (EVA). Is a Project Management 
control technique which integrates Scope, Schedule 
and Cost data for objectively measuring project 
performance and progress. 
Performance is measured by determining the budgeted 
cost of work performed (i.e., earned value) and 
comparing it to the actual cost of work performed (i.e., 
actual cost) and the planned cost of work performed 
(i.e. planned cost).
Definitions 
Concept 
Abbre 
viation 
Description 
Budget at Completion BAC Baseline cost of 100% of the project. 
Actual Cost AC Total costs actually incurred so far. 
Earned Value EV 
Amount of budget earned so far based on 
physical work accomplished, without 
reference to actual costs. 
Planned Value PV 
The budget for the physical work scheduled 
to be completed by the end of the time 
period.
Metrics 
Concept 
Abbre 
viation 
Description 
Cost Variance CV 
Measure of cost overrun. 
CV = EV – AC 
Schedule Variance SV 
Measure schedule slippage. 
SV = EV – PV 
Cost Performance Index CPI 
Cost efficiency ratio. 
CPI = EV/AC 
Scheduled Performance 
Index 
SPI 
Schedule efficiency ratio. 
SPI = EV/PV 
Estimate at Completion EAC 
Expected total cost based on the current 
cost and schedule efficiency ratios. 
EAC = AC+((BAC-EV)/(CPI*SPI))
For example 
The project is to build a 4 wall room. The cost per wall is 100 SAR 
and it will take 1 day to construct 1 wall. At the end of the 3 day we 
have finished 2.5 walls and our actual cost is 280 SAR then our 
values are : 
Budget at Completion (BAC) = 400 SAR 
Actual Cost (AC ) = 280 SAR 
Earned Value (EV) = 250 SAR 
Planned Value (PV) = 300 SAR 
And based on the above data we can calculate the following:
Calculated Metrics 
Cost Variance is CV = EV – AC = 250 – 280 = -30 
we are over budget by 30 SAR 
Scheduled Variance is SV = EV – PV = 250 – 300 = -50 
we behind scheduled by 50 SAR 
Cost Performance Index is CPI = EV / AC = 250 / 280 = .89 
For each 1 SAR we spend we gain .89 halalas 
Schedule Performance Index is SPI = EV / PV = 250 / 300 = .83 
We are behind schedule by 17 %. 
Estimate at Completion is EAC = AC+((BAC-EV)/(CPI*SPI)) = 483 
If we continue with the same efficiency rates, we might end up with 
a total cost of 483 SAR.
Proposal 
Recent research studies have shown that the tools and 
techniques of Earned Value Analysis have positive impact on 
improving project controls on Scope, Cost and Schedule and 
are good predictors of project success. 
Popularity of EVA has grown significantly in recent years for 
which we would like to recommend using it for ATCO 
projects (i.e. construction, big projects in EWE, EWF). 
For that we have developed a simple module in the EIS 
where project managers will enter the EV parameters which 
the system will combine with data booked in accounts and 
calculates the EV metrics. 
Data from RAS ALKHER project is entered in the system for 
testing.
Steps in EIS 
1. Login to EIS by assigned operational staff. 
2. Process the EV report of his particular division. 
3. Enter the EV values of the Month and any comments 
regarding the variances. 
Graphical 
Presentations 
4. Use the data and reports in the monthly project status 
reporting. 
Project EV data entered 
by Operations on a 
monthly basis 
Projects status 
dashboard report
Proposed Plan 
1. Agree with you if this is a suitable solution. 
We can discuss this by taking RAS ALKHER 
project data which is already entered in the 
system as an example. 
2. If Yes share it with operations for feedback 
on possible enhancements or 
improvements. 
3. Identify users in each divisions and do 
training. 
4. Start using the new process.

Más contenido relacionado

La actualidad más candente

Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
Harinadh Karimikonda
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
nazi2020
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
Shenin Hassan
 

La actualidad más candente (20)

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost Estimation
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 

Destacado (8)

Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
 
Cocomo
CocomoCocomo
Cocomo
 
COCOMO MODEL
COCOMO MODELCOCOMO MODEL
COCOMO MODEL
 
Software reliability
Software reliabilitySoftware reliability
Software reliability
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 

Similar a Earned Value Analysis

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
Nita Cristian
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
ejlp12
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 

Similar a Earned Value Analysis (20)

Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
Earned value management
Earned value managementEarned value management
Earned value management
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 

Más de Ahmed Rami Elsherif, PMP, ITBMC

Más de Ahmed Rami Elsherif, PMP, ITBMC (20)

Leading change
Leading changeLeading change
Leading change
 
Liderando el Cambio
Liderando el CambioLiderando el Cambio
Liderando el Cambio
 
Ahmed Rami Elsherif, CV
Ahmed Rami Elsherif, CVAhmed Rami Elsherif, CV
Ahmed Rami Elsherif, CV
 
Bolivia decide presentacion
Bolivia decide presentacionBolivia decide presentacion
Bolivia decide presentacion
 
Invoicing your client with wikiprojects
Invoicing your client with wikiprojectsInvoicing your client with wikiprojects
Invoicing your client with wikiprojects
 
Wikiprojects: Una Introducción
Wikiprojects: Una Introducción Wikiprojects: Una Introducción
Wikiprojects: Una Introducción
 
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014ATCO-BaasKaar Roadmap to SAP Quality Award 2014
ATCO-BaasKaar Roadmap to SAP Quality Award 2014
 
ATCO-SAP ERP Implementation
ATCO-SAP ERP ImplementationATCO-SAP ERP Implementation
ATCO-SAP ERP Implementation
 
Ahmed's 1 Page CV
Ahmed's 1 Page CVAhmed's 1 Page CV
Ahmed's 1 Page CV
 
ATCO Engineering - Process Evaluation
ATCO Engineering - Process EvaluationATCO Engineering - Process Evaluation
ATCO Engineering - Process Evaluation
 
Process groups and knowledge areas PMBOK 5th Edition
Process groups and knowledge areas PMBOK 5th EditionProcess groups and knowledge areas PMBOK 5th Edition
Process groups and knowledge areas PMBOK 5th Edition
 
dotProject Tutorial
dotProject TutorialdotProject Tutorial
dotProject Tutorial
 
Building your company's vision
Building your company's visionBuilding your company's vision
Building your company's vision
 
Introduction to dotProject
Introduction to dotProjectIntroduction to dotProject
Introduction to dotProject
 
Wikiprojects
WikiprojectsWikiprojects
Wikiprojects
 
HR Transformation
HR TransformationHR Transformation
HR Transformation
 
Introduction to ERP
Introduction to ERPIntroduction to ERP
Introduction to ERP
 
Sap Reporting
Sap ReportingSap Reporting
Sap Reporting
 
Sap Integrations
Sap IntegrationsSap Integrations
Sap Integrations
 
Sap Downstream web interfaces
Sap Downstream web interfacesSap Downstream web interfaces
Sap Downstream web interfaces
 

Último

Call Girls in Yamuna Vihar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in  Yamuna Vihar  (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in  Yamuna Vihar  (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Yamuna Vihar (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Último (20)

Benefits & Risk Of Stock Loans
Benefits & Risk Of Stock LoansBenefits & Risk Of Stock Loans
Benefits & Risk Of Stock Loans
 
Fixed exchange rate and flexible exchange rate.pptx
Fixed exchange rate and flexible exchange rate.pptxFixed exchange rate and flexible exchange rate.pptx
Fixed exchange rate and flexible exchange rate.pptx
 
Significant AI Trends for the Financial Industry in 2024 and How to Utilize Them
Significant AI Trends for the Financial Industry in 2024 and How to Utilize ThemSignificant AI Trends for the Financial Industry in 2024 and How to Utilize Them
Significant AI Trends for the Financial Industry in 2024 and How to Utilize Them
 
7 steps to achieve financial freedom.pdf
7 steps to achieve financial freedom.pdf7 steps to achieve financial freedom.pdf
7 steps to achieve financial freedom.pdf
 
Vip Call Girls Rasulgada😉 Bhubaneswar 9777949614 Housewife Call Girls Servic...
Vip Call Girls Rasulgada😉  Bhubaneswar 9777949614 Housewife Call Girls Servic...Vip Call Girls Rasulgada😉  Bhubaneswar 9777949614 Housewife Call Girls Servic...
Vip Call Girls Rasulgada😉 Bhubaneswar 9777949614 Housewife Call Girls Servic...
 
Seeman_Fiintouch_LLP_Newsletter_May-2024.pdf
Seeman_Fiintouch_LLP_Newsletter_May-2024.pdfSeeman_Fiintouch_LLP_Newsletter_May-2024.pdf
Seeman_Fiintouch_LLP_Newsletter_May-2024.pdf
 
Lion One Corporate Presentation May 2024
Lion One Corporate Presentation May 2024Lion One Corporate Presentation May 2024
Lion One Corporate Presentation May 2024
 
Pension dashboards forum 1 May 2024 (1).pdf
Pension dashboards forum 1 May 2024 (1).pdfPension dashboards forum 1 May 2024 (1).pdf
Pension dashboards forum 1 May 2024 (1).pdf
 
Escorts Indore Call Girls-9155612368-Vijay Nagar Decent Fantastic Call Girls ...
Escorts Indore Call Girls-9155612368-Vijay Nagar Decent Fantastic Call Girls ...Escorts Indore Call Girls-9155612368-Vijay Nagar Decent Fantastic Call Girls ...
Escorts Indore Call Girls-9155612368-Vijay Nagar Decent Fantastic Call Girls ...
 
Call Girls in Yamuna Vihar (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in  Yamuna Vihar  (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in  Yamuna Vihar  (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in Yamuna Vihar (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Call Girls Howrah ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Howrah ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Howrah ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Howrah ( 8250092165 ) Cheap rates call girls | Get low budget
 
✂️ 👅 Independent Bhubaneswar Escorts Odisha Call Girls With Room Bhubaneswar ...
✂️ 👅 Independent Bhubaneswar Escorts Odisha Call Girls With Room Bhubaneswar ...✂️ 👅 Independent Bhubaneswar Escorts Odisha Call Girls With Room Bhubaneswar ...
✂️ 👅 Independent Bhubaneswar Escorts Odisha Call Girls With Room Bhubaneswar ...
 
Kopar Khairane Cheapest Call Girls✔✔✔9833754194 Nerul Premium Call Girls-Navi...
Kopar Khairane Cheapest Call Girls✔✔✔9833754194 Nerul Premium Call Girls-Navi...Kopar Khairane Cheapest Call Girls✔✔✔9833754194 Nerul Premium Call Girls-Navi...
Kopar Khairane Cheapest Call Girls✔✔✔9833754194 Nerul Premium Call Girls-Navi...
 
7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator Options7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator Options
 
Technology industry / Finnish economic outlook
Technology industry / Finnish economic outlookTechnology industry / Finnish economic outlook
Technology industry / Finnish economic outlook
 
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot GirlsMahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
 
Toronto dominion bank investor presentation.pdf
Toronto dominion bank investor presentation.pdfToronto dominion bank investor presentation.pdf
Toronto dominion bank investor presentation.pdf
 
Strategic Resources May 2024 Corporate Presentation
Strategic Resources May 2024 Corporate PresentationStrategic Resources May 2024 Corporate Presentation
Strategic Resources May 2024 Corporate Presentation
 
Premium Call Girls Bangalore Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
Premium Call Girls Bangalore Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...Premium Call Girls Bangalore Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
Premium Call Girls Bangalore Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...
Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...
Famous No1 Amil Baba Love marriage Astrologer Specialist Expert In Pakistan a...
 

Earned Value Analysis

  • 1. Earned Value Analysis Concept and Application Presented by Ahmed Rami Elsherif 27/12/2012
  • 2. Concept Earned Value Analysis (EVA). Is a Project Management control technique which integrates Scope, Schedule and Cost data for objectively measuring project performance and progress. Performance is measured by determining the budgeted cost of work performed (i.e., earned value) and comparing it to the actual cost of work performed (i.e., actual cost) and the planned cost of work performed (i.e. planned cost).
  • 3. Definitions Concept Abbre viation Description Budget at Completion BAC Baseline cost of 100% of the project. Actual Cost AC Total costs actually incurred so far. Earned Value EV Amount of budget earned so far based on physical work accomplished, without reference to actual costs. Planned Value PV The budget for the physical work scheduled to be completed by the end of the time period.
  • 4. Metrics Concept Abbre viation Description Cost Variance CV Measure of cost overrun. CV = EV – AC Schedule Variance SV Measure schedule slippage. SV = EV – PV Cost Performance Index CPI Cost efficiency ratio. CPI = EV/AC Scheduled Performance Index SPI Schedule efficiency ratio. SPI = EV/PV Estimate at Completion EAC Expected total cost based on the current cost and schedule efficiency ratios. EAC = AC+((BAC-EV)/(CPI*SPI))
  • 5. For example The project is to build a 4 wall room. The cost per wall is 100 SAR and it will take 1 day to construct 1 wall. At the end of the 3 day we have finished 2.5 walls and our actual cost is 280 SAR then our values are : Budget at Completion (BAC) = 400 SAR Actual Cost (AC ) = 280 SAR Earned Value (EV) = 250 SAR Planned Value (PV) = 300 SAR And based on the above data we can calculate the following:
  • 6. Calculated Metrics Cost Variance is CV = EV – AC = 250 – 280 = -30 we are over budget by 30 SAR Scheduled Variance is SV = EV – PV = 250 – 300 = -50 we behind scheduled by 50 SAR Cost Performance Index is CPI = EV / AC = 250 / 280 = .89 For each 1 SAR we spend we gain .89 halalas Schedule Performance Index is SPI = EV / PV = 250 / 300 = .83 We are behind schedule by 17 %. Estimate at Completion is EAC = AC+((BAC-EV)/(CPI*SPI)) = 483 If we continue with the same efficiency rates, we might end up with a total cost of 483 SAR.
  • 7. Proposal Recent research studies have shown that the tools and techniques of Earned Value Analysis have positive impact on improving project controls on Scope, Cost and Schedule and are good predictors of project success. Popularity of EVA has grown significantly in recent years for which we would like to recommend using it for ATCO projects (i.e. construction, big projects in EWE, EWF). For that we have developed a simple module in the EIS where project managers will enter the EV parameters which the system will combine with data booked in accounts and calculates the EV metrics. Data from RAS ALKHER project is entered in the system for testing.
  • 8. Steps in EIS 1. Login to EIS by assigned operational staff. 2. Process the EV report of his particular division. 3. Enter the EV values of the Month and any comments regarding the variances. Graphical Presentations 4. Use the data and reports in the monthly project status reporting. Project EV data entered by Operations on a monthly basis Projects status dashboard report
  • 9. Proposed Plan 1. Agree with you if this is a suitable solution. We can discuss this by taking RAS ALKHER project data which is already entered in the system as an example. 2. If Yes share it with operations for feedback on possible enhancements or improvements. 3. Identify users in each divisions and do training. 4. Start using the new process.