3. Where will EMPHASIS work?
• Nepal-India route
– Source area (Accham and Kanchanpur)
– Transit area (Gaddachouki / Gaurifanta)
– Destination area (Delhi - National Capital Region)(Mumbai)
Gaddachouki
/ Banbasa
Dhangadi /
Gourifanta
4. Where will EMPHASIS work?
• Bangladesh-India route
– Source area (Jessore and Satkhira)
– Transit area (Petropole and adjoining areas)
– Destination area (Kolkata, Howrah and adjoining areas) (Mumbai)
Source
point
Transit
point
Destination
point
5. First Year of the Programme
• Knowledge Building Phase
– Build knowledge, information, and analysis while
supporting existing services for the target group.
– Using analysis, clarify assumptions about services for
each of the two migration routes: Inputs → Outputs →
Outcomes → Impact
6. Key Processes – Staff Recruitment
Staff Recruitment process started in September,2009 and
all staff were recruited by January, 2010.
Staff Name Designation Place
Essa Mohammad Rafique Team Leader New Delhi
Nabesh Bohidar Manager (M-E-D) New Delhi
Sandhya Saxena Admn Assistant New Delhi
Anupam Das Partnership Coordinator Kolkata
Surajit Chakraborty Partnership Coordinator Bahraich
Moushumi Kundu Partnership Coordinator New Delhi
Manoranjan Routray Finance Officer (part time) New Delhi
7. Key Processes – Workshops for
Common Understanding
• Induction Workshop (New Delhi-October 2009)
• Inception Workshop (Kathmandu-Oct/Nov 2009)
• NGO pre-orientation workshop (New Delhi-Dec 2009)
• CARE Staff Induction workshop (Lucknow-February
2010)
• NGO Induction Workshop (New Delhi-Feb 2010) for
NGO staff of Delhi/NCR
• NGO Induction Workshop (Kolkata-March 2010) for
NGO staff of West Bengal
• NGO Induction Workshop – (Bahraich – March 2010)
for staff of Uttar Pradesh
8. Key Processes – NGO Partners
Contracted
• As the NGO partners were pre-selected, a
process of NGO assessment was carried
out with all the five NGOs. (Nov-Dec 2009)
• The NGO assessment was carried out by a
team comprising of both programme staff
and finance staff of CARE.
• Draft NGO contracts were sent to BIG
through the Secretariat.
• Approval of the contracts were received in
late February.
• NGO contracts were signed from the first
of March
• Six NGO Partners on board (Rationalisation
and new partners)
9. Key Processes – Current activities
of the NGO partners
• Mapping / Stakeholder analysis / Line Listing
• Developed a common methodology, tools and required outputs
through a consultative process for destination and transit sites.
• Status:
– Mapping completed.
– Stakeholder Analysis Completed
– Line Listing Continuing
10. Estimates of Mobile population (combined-
both transit sites for 3 months)
Total Going % to Going % to Going % to
Mobile Delhi Delhi Mumbai Mumbai Others Others
Source -
Accham 3253 407 13 1606 49 1240 38
Source -
Kanchanp
ur 6543 2265 35 411 6 3867 59
Source -
Others 15252 3919 26 3859 25 7474 49
Total 25048 6591 26.3 5876 23.5 12581 50.2
• Those from Accham, more people go to Mumbai than Delhi.
• Those from Kanchanpur, more people go to Delhi than Mumbai
• More number of people go to Delhi than to Mumbai from the two
source districts
11. Estimates of Bangladeshi Mobile
population
• Approximately 7000 people cross over the
border undocumented.
• Approximately 65000 people from Bangladesh
are found in the locations mapped.
• Approximate number of people who have come
from Jessore and Satkhira is 9750
• If we relax the criteria, approximate impact
population would be 10,000.
12. Key Processes – Overcoming the
communication divide across countries
• Communication & KM - Ning
• One Stop Shop
– Chat, Forum, Tele, Google-docs, Blog, Events,
Calendar, Map, Groups, Photos, videos, audios,
Transliteration, Archives, Intra, Google-search, SMS-
web, Wiki
• Status
– Started in Dec 09, Analytics show high usage
– Will require dedicated facilitator support
13. Milestones in the First Year - India
S. Milestone Outcome New Remarks
N. time
3 Establishment of 1 DIC in NP, BD and IN 1 Q2 IN On Schedule
7 First cross border learning visit of partner 1,2 Q1 India-Bangladesh on schedule
NGOs (from Bangladesh and India to
Nepal)
10 Establishment of first condom outlet/ 1 Q3 On Schedule
vending machine at transit and destination
in India
24 First capacity building session with at 1, 2 Q2 On Schedule
least 4 service providers in India
32 Publication of first set of leaflets and 1,3 Qr 2 On Schedule (will depend upon the
posters in India and Bangladesh Baseline study and BCC strategy)
34 Capacity assessment of selected 2 Qr 3 On Schedule
NGO/CBOs in all three countries
35 Development of curricula for capacity 2 Qr 3 On Schedule
building session with NGOs and CBOs
14. Milestones in the First Year - India
S. Milestone Outcom New Remarks
N. e time
36 First capacity building session with at least 2 Qr 3 On Schedule
5 NGOs/ CBOs each in all countries
37 Develop Curriculum for capacity building 2 Q3 On Schedule
for security /police in India and Nepal
38 First capacity building session with border 2 Q3 On Schedule
security/ police in India and Nepal
46 Establishment of 11th drop in centre in 1 Q3 Possible addition of Mumbai as
India destination will delay establishment
47 Appointment of all Peer Educators India 1 Q3 Possible addition of Mumbai as
destination will delay appointment
50 First Radio broadcast in India 1 Will depend upon the BCC strategy
51 Formation and training of at least once 1 Q4 On Schedule
community support group in India
55 Second Cross Border visit of partner NGOs 1, 2 Q3 On Schedule
(from Nepal and Bangladesh to India)
59 Establishing learning site in India 1, 2 Q4 On Schedule
15. Who will EMPHASIS work with?
Impact population (revised draft Oct 2010):
People from Bangladesh or Nepal who cross into India for
the purpose of work:
• Minimum 3 months to maximum 5 years
• Age group 15-49 years
• Men living at destination without spouse
• Women living at destination with or without family
(Nuclear family)
• The families at source and destination of the above.
We will be flexible in service provision on a case by case.
16. Budget Scenario if Mumbai included (with interventions for
both Nepali and Bangladeshis )
Overall for 5 years (GBP)
Original As per S1 Delta
P1 544,056 576,874 (32,818)
P2 32,475 93,410 (60,935)
P3 15,272 15,888 (616)
Mgt & Operation 669,161 687,738 (18,577)
1,260,964 1,373,911 (112,947)
SPC 75,658 82,435 (6,777)
Total 1,336,622 1,456,346 (119,723)
17. Budget Scenario if Mumbai included (with interventions for
only Nepalis)
Overall for 5 Years (GBP)
Original As per S1 Delta
P1 544,056 520,263 23,793
P2 32,475 93,410 (60,935)
P3 15,272 15,888 (616)
Mgt & Operation 669,161 683,631 (14,469)
1,260,964 1,313,192 (52,228)
SPC 75,658 78,792 (3,134)
Total 1,336,622 1,391,984 (55,362)
19. Discussion: Program
• Get Inputs from Team by including one
rep
• Liaison EMPHASIS with other programs
– RAKS THAI (CARE Thailand)
– ISOFI (CARE Gender and Sexuality)
RAB (FHI India, Nepal)
– NACO Mobility programs
ACP (AIDS Competence Process)
20. Transit-Destination Paradigm
Population of Delhi is 11,954,217 (2001 census).
New Delhi is the second-largest metropolis in India,
and the eighth largest metropolis in the world by population
21. Source, Transit, Destination
(STD)
Mumbai as Destination:
• Budget for Mumbai
• Advocacy to work with Bangladeshis in
Mumbai
• Starting Mapping of Nepali & Bangladeshi
Delhi as Transit/Destination:
• Do we map & work with Bangladeshis in
Delhi?
22. Region & Sharing
• Regionalism of the program directly
dependent on sharing across the region
• Vital: a share facilitator - TOR shared
• Other Suggestions:
– Host Archives and workspace on CARE India
web space till EMPHASIS has its own
– Share all field visit reports as Blog in Ning
– 1 comment by ACD/day in Ning – 1 minute!
– e-mails to e-group hosted on CARE India list
23. Immediate Attention
• Internal Interim PD and Internal post
• Correcting all milestone deficit by mid Yr 2
• Complete Baseline asap
• BCC Strategy in place after Baseline
• Dream Team at the Secretariat
• Improve Communication across Countries
24. Conclusion
• Need to relax limiting Impact population criteria
• In tune with revised NACO strategy
• Makes intervention feasible.
• Broaden intervention to reach all
Nepalis/Bangladeshi in a destination/transit site,
while also focusing on the continuum.