  1. Memorandum of Understanding for 2017-18 onwards CHENNAI 19th November, 2016 Department of Public Enterprises Ministry of Heavy Industries & Public Enterprises Government of India 1
  2. Outline of Presentation • Proposals for MoU Guidelines 2017-18 • MoU Negotiation 2016-17 • MoU Performance Evaluation 2015-16 2
  3. Memorandum of Understanding (MoU) MoU is a negotiated agreement and contract between the Administrative Ministry/ Department/ Holding CPSE i.e. majority shareholder and the Management of the Central Public Sector Enterprise (CPSE) on selected parameters having targets decided normally before the start of a new financial year and results evaluated at the end of the year to measure the performance. For carrying out this exercise, CPSEs would provide brief about it. 3
  4. Purpose of MoU The purpose of the MoU is to measure the performance of the management of the CPSEs on key selected parameters against the targets set so as to increase the improvements of the critical financial indicators of the organisation. 4
  5. Scope All CPSEs (Holding as well as Subsidiaries) are required to sign MoUs. The Apex/Holding companies will sign MoUs with their administrative Ministries/ Departments, while the Subsidiary companies will sign MoUs with their respective Apex/ Holding companies. 5
  6. Exemption from MoU Following CPSEs may be exempted from MoU system by the Inter-Ministerial Committee (IMC): • CPSEs under liquidation where Liquidator has already been appointed. However administrative ministry would provide the list of such CPSEs to DPE along-with brief write-up. • CPSE which is not in operation or having no employees or on any other ground on the recommendation of administrative Ministry. 6
  7. Parameters CPSEs work in various sectors under different conditions and therefore uniform parameters cannot be prescribed. In view of this, the following guidelines are laid down:- • There should be uniform parameters for measuring financial performances such as revenue from operations, operating profit and ratio of PAT/Net-worth. This would be applicable to all the CPSEs, except CPSEs which are dependent on government grant or performing functions of distribution of grant etc. e.g. Biotechnology Industry Research Assistance Council (BIRAC). Hence, 3 financial parameters have been prescribed for all the CPSEs with total weightage of 50% except for CPSEs like BIRAC. 7
  8. Parameters…… contd. • For the remaining 50% weightage, a list of parameters have been suggested for selection depending on the sector in which the CPSE is operating. The parameters most appropriate and relevant for measuring performance shall be suggested by the Pre-Negotiation Committee (PNC) to the Inter-Ministerial Committee (IMC). However there are some CPSEs which have specific role to play or are covered under specific regulatory authority e.g. ECGC which is covered under IRDA or are performing regulatory functions e.g. POSCO. In all the cases IMC shall take appropriate decision on the suggestions made by PNC. 8
  9. Parameters…… contd. • For CPSEs under closure/ under construction/ under reconstruction, no parameters have been suggested leaving it to the PNC to suggest the most appropriate parameter along with targets for IMC to take decisions. For such CPSEs, the emphasis should be to suggest parameters and fix targets for starting commercial operations as early as possible. For CPSEs under closure, the targets would be for ensuring time bound closure. • Definition and basis for suggesting the parameters have been given in Annex. 9
  10. Proposed MoU parameters for 2017-18 (Suggestions invited) 10
  11. Time-Lines for MoU 2017-18 11 Documents Prescribed Date The draft MoU to administrative Ministry/ Department 21st November, 2016 The draft MoU to DPE after the approval of administrative Ministry/ Department 5th December, 2016 Signing of MoU as per Minutes of IMC meeting 31st March, 2017 or 21 days from issue of minutes whichever is later. Performance evaluation reports to DPE after approval of the Board and through the administrative Ministries/ Departments 30th September, 2017
  12. MoU Score and Rating Consolidated Score Rating More than Equal to or less than 90 100 Excellent 70 90 Very Good 50 70 Good 33 50 Fair 0 33 Poor 12
  13. Additional eligibility criteria (1) CPSEs have to essentially comply with the following conditions, failing which its MoU rating would be downgraded by one step except CPSEs in poor rating e.g. CPSEs with ‘Excellent rating’ would be treated as ‘Very Good’ and composite score shall be read as 90.00 and CPSEs with ‘Very Good rating’ would be treated as ‘Good’ and composite score shall be read as 70.00 and so on: i. Compliance of Provisions of The Companies Act, 2013 or the relevant Act under which they have been regulated (To the extent compliances are within the ambit of CPSEs). ii. In case of listed CPSEs, compliance of provisions of Listing Agreement (To the extent compliances are within the ambit of CPSEs). 13
  14. Additional eligibility criteria (1)……contd. iii. Compliance of DPE Guidelines having financial implications. iv. No adverse observations by CAG on Annual Accounts pointing out misappropriation of funds of any amount or Over/ under statement of profit/ loss (surplus/ deficit)/ assets/ liabilities amounting to 5% of Revenue from Operation. v. Holding of AGM without seeking extension of time. vi. Submission of Draft MoU/ MoU evaluation through administrative ministry/ department to DPE by prescribed date. vii. Signing of MoU as prescribed without deviation from minutes of the IMC meeting. 14
  15. Additional eligibility criteria (2) CPSEs have also to essentially comply with the following conditions, failing which its MoU rating would be reduced by score of 1 from the composite score for non- compliance of each condition. • Compliance of Public Procurement Policy for Micro and Small Enterprises issued by M/o Micro Small and Medium Enterprises. 15
  16. Mandatory Parameters Sl. Financial Performance Criteria Unit Wt i Turnover Revenue from Operations (Net) Rs. crore 10 ii Operating Profit/Loss (Profit/ Surplus before Tax excluding other Income, Extraordinary and Exceptional Items): CPSEs with operating profit :- Operating profit/ surplus as a percentage of Revenue from operations (net). % 20 CPSEs with operating Loss:- Reduction in operating Loss over previous year. iii Return on investment: Profit Earning CPSEs : PAT or Surplus / Average Net Worth % 20 Loss making CPSEs : Reduction in Total Expenses as a percentage of Total Income as compared to previous year. 16
  17. Turnover (Revenue from Operations) Where price of product is regulated by statutory authorities/ international transparent mechanism, adjustment in revenue from operations may be allowed for variation in price. As per schedule III In respect of a company other than finance company revenue from operations consist of: (a) Sale of products; (b) Sale of services; (c) Other operating revenues; Less: (d) Excise duty. In respect of a finance company, revenue from operations shall include revenue from (a) Interest income; and (b) Other income from financial services 17
  18. Other Parameters……contd. Sl. Performance Criteria Unit Wt i Capacity Utilisation Production/ Generation/ Transmission, etc. Orders Received during the year % 0-15 May not apply to CPSEs in trading, heavy engineering etc. ii CAPEX: a. with own funds and by loan by leveraging net-worth Rs. crore 0-20 a. with Budgetary Support 0-10 iii Percentages of value of CAPEX contracts/ projects running/ completed during the year without time/ cost overrun to total value of CAPEX contracts running/ completed during the year % 0-10 May not apply to CPSEs in consultancy, trading, marketing etc. 18
  19. Other Parameters……contd. Sl. Performance Criteria Unit Wt iv Completion of clients orders milestone without time overrun 0-30 May apply to CPSEs in Consultancy, Heavy Engineering, Defence Production, Pharmaceutical Sectors v Inventory of finished goods and work in progress to Revenue from operations (Net) % 0-10 May apply to CPSEs in Manufacturing, Trading, Fertilizers, Heavy Engineering, Consumer Goods Sectors vi Reduction in Inventory of more than one year old % 0-10 May apply to CPSEs in Trading, Marketing Sectors vii. Trade receivables (Net) as number of days of Revenue from Operations (gross) Days 0-10 May apply to CPSEs in all Sectors except where Trade Receivables are negligible 19
  20. Other Parameters……contd. Sl. Performance Criteria Unit Wt viii. Contingent liabilities: Reduction in claims against the Company not acknowledged as debt % 0-10 May apply to CPSEs having substantial amount of contingent liabilities ix. Return (share of profit/loss) on Investment in Joint Ventures- CPSEs having Joint Ventures % 0-10 May apply to CPSEs having joint ventures x. Milestones with respect to subsidiary CPSEs not signing MoUs separately 0-10 May apply to CPSEs having subsidiary CPSEs not having joint ventures xi. Any other sector specific result-oriented measurable parameters (upto 4 parameters). 0-20 May apply to CPSEs in all sectors 20
  21. Other Parameters (Finance CPSEs) Sl. Performance Criteria Unit Wt i. Loans Sanctioned during the year 5 ii. Loans disbursed/ Loans sanctioned during the year 10 iii. Loans disbursed/ Total Funds Available 0-10 iv. Overdue loans/ Total loans (Net) % 10 v. NPA/ Total loans (Net) % 10 vi. Cost of raising loans as compared to similarly rated CPSEs/ entities 0-10 21
  22. Other Parameters (Finance CPSEs)….contd. Sl. Performance Criteria Unit Wt vii. Contingent liabilities: Reduction in claims against the Company not acknowledged as debt % 0-10 viii. Return on Investment (share of profit/loss) in Joint Ventures- CPSEs having Joint Ventures % 0-10 ix. Milestones with respect to subsidiary CPSEs not signing MoUs separately 0-10 x. Any other sector specific result-oriented measurable parameters (upto 4 parameters). 0-15 22
  23. MoU Negotiation 2016-17 23
  24. MoU Negotiation 2016-17 - Status Particulars No of CPSEs No. of CPSEs 382 Pre-negotiation meetings held 259 MoU negotiation (IMC) meetings held 259 Targets given 234 CPSEs exempted 143 MoU not submitted by CPSE 5 MoU Authenticated 182 MoU signed 119
  25. MoU Evaluation 2015-16 25
  26. MoU Evaluation 2015-16 - Status Particulars No of CPSEs No. of CPSEs 293 CPSEs exempted 78 Targets given 215 MoU submitted by CPSE for Evaluation 110
  27. MoU Evaluation 2015-16 Particulars Response Complying Non-complying Public Procurement policy 89 3 86 DPE guidelines 62 34 28 Survey 80 CSR 82 Corporate Governance 27
  28. Supporting Documents Where achievements are not verifiable from annual report, CPSE may submit the same by way of resolution from Board of Directors. 28
  29. 29
  30. Thank You 30
  31. MoU Evaluation 2015-16 31
  32. Self Performance Evaluation Report by CPSEs • CPSEs are required to submit Self evaluation Sheet on the basis of audited data along with Annual Accounts/Report, other documentary evidences in support of achievement of financial and non-financial parameters, etc. within the target date of 30 th September, 2016; Documents submitted should be authenticated and conclusive; Mandatory compliances of various Guidelines and entry of data as prescribed in MoU guidelines for negative marking ; Submit actual performance of the CPSE as per the Minutes or MoU negotiation meeting . • Self evaluation sheet should be approved by Board of the CPSE and is to be submitted through its Administrative Ministry/Department by the due date; • Self Evaluation sheet includes, composite score as well as rating, as calculated by CPSE; 32
  33. The following documents are to be considered by DPE during MoU Evaluation; • Minutes of the MoU Negotiation Meeting; • Signed MoU along with Annexure; • Self Evaluation Sheet submitted by CPSE through Administrative ministry/Holding CPSE ; • Following documents are required along with the self evaluation sheet ; Annual Report & Financial statements ; External Certificates. Internal certificates signed by appropriate authority • Report on commitment and assistance by Admin ministry/ Department • Besides CPSE should have timely reported to the concerned for : - Report on compliance of Corporate Governance; - Compliance of DPE guidelines. - Compliance of MSME guidelines. - Compliance of CSR guidelines - Online entry for PE survey - Online entry of MoSPI (wherever applicable). Documents to be considered in MoU Evaluation 2015-16 33
  34. • Computation of financial achievements should be as per definitions given in MoU Guidelines issued by DPE and Generally Accepted Accounting Principles & rules and as per Audited Annual Accounts. • Performance against a parameter would be considered after making suitable adjustments in the target as per specific comment / recommendations as mentioned in the minutes of Negotiation meeting versus actual achievement against the parameter . • Example: Adjustment for Plant Shutdown, change in policy during the year for subsidy calculation, valuation of stock, foreign exchange rate variation etc. • If there is any inconsistency between signed MoU and Minutes of Negotiation meeting, generally minutes of negotiation meeting is considered for Evaluation . Internal Evaluation by DPE: Financial Parameter 34
  35. Internal Evaluation by DPE: Non-Financial Parameter • Non-Financial achievements should be as per the MoU Guidelines issued by DPE and as mentioned in Minutes or MoU, so that actual performance reported is in line with as considered in MoU targets; • To the extent possible, the documents submitted in support of non-financial achievements should be independently verifiable and conclusive; • Where achievements are not verifiable from annual report, CPSE may submit the same by way of resolution from Board of Directors. • In absence of the supporting documents for Non-financial achievements, this may entail an automatic downgrading by at least one notch from the rating claimed by CPSEs in respect of the parameters for which documentary evidence have not been submitted to DPE. 35
  36. MoU Evaluation by the IMC • DPE evaluates Self Evaluation score sheets submitted by CPSEs through Administrative Ministry/Holding CPSE and the observations and comments will be placed before IMC members; • IMC may accept the view of CPSE or Ministry or DPE or in specific circumstances may take decision independently; • Down grading :If the rating of CPSEs gets adversely affected during internal evaluation (i.e. downgrading of rating from self assessed score of CPSE and tentative score calculated by DPE), then opportunity by way of written/oral re-presentation is given to the concerned CPSE through administrative Ministry/Department. 36
  37. MoU Evaluation by the IMC Contd ….. • Offsets: Non achievement of specific targets by CPSEs for reasons beyond the control of CPSEs with specific recommendation of the Administrative ministry, if qualified , will be examined by IMC and shall be recommended for approval of HPC. The power to permit offsets in MoU evaluation for reasons beyond the control of the CPSE (force majeure), is with the High Power Committee on MoU . • Over-achievement of Targets: It has been observed that some CPSEs under-pitch their projected targets for the coming year during MoU negotiation meeting so as to plead for soft/low targets. In such cases, during MoU evaluation DPE/ IMC may call upon the CMD of the CPSE to explain plausible reasons for such over-achievement due to under pitching of targets. • Finalization of Score & Rating :IMC shall finalize the Minutes of Evaluation Meeting and recommend MoU Scores and Ratings for approval of HPC. 37
  38. Penal Provision (Negative marking) in MoU • Following mandatory compliances and non submission of data may be penalized up to 1 mark depending on the degree and seriousness of non-compliance. – Non-compliance of Corporate Governance – Non-Compliance for procurement as prescribed in Public Procurement policy issued by MSME – Non-Compliance to DPE Guidelines – Non-Compliance to provisions as prescribed in CSR guidelines – Non-compliance to submission of data for Public Enterprises (PE) survey, – Non-compliance to submission of data for MOSPI (if applicable) 38
  39. Negative Marking: Corporate Governance in MoU Evaluation 2015-16 • Non-Compliance of Corporate Governance will be penalized by way of negative marking and MoU score will be increased in the following manner in accordance with DPE OM 18(8)/2005-GM, dated 22nd June, 2011. • Status of Negative Marking : – 2013-14 : 70 – 2014-15 : Nil – 2015-16 : CG Rating under Finalization Sl Annual Score Grading Penalty Marks 1 85% and Above Excellent 0 2 75%-84% V. Good 0 3 60%-74% Good 0.5 4 50%-59% Fair 0.5 5 Below 50% Poor 1.0 39
  40. Negative Marking : Compliance to Public Procurement guidelines by MSME • CPSEs have to adhere to 20% procurement from MSE and 4% from SC/ST MSEs . • Status of Negative Marking : – 2013-14 : Not Applicable – 2014-15 : Nil – 2015-16 : 89 CPSE’s have submitted data 44 CPSEs have complied to 20% out of which only 03 CPSEs complied to 4% of SC/ST entrepreneurs 40
  41. Negative Marking : Compliance to DPE guidelines MoU 2015-16 • CPSEs have to give a Certificate regarding implementation of Guidelines issued by DPE as per OM No.-DPE/14(38)/10-Fin dated 28th June, 2011. – Non compliance of DPE guidelines on the basis of certificate submitted will be penalized up to 1 mark . • Status of Negative Marking : – 2013-14 : 65 – 2014-15 : 78 – 2015-16 : 62 CPSE’s have submitted data out of which 28 have reported non compliance 41
  42. Negative Marking : Compliance to CSR guidelines • CPSEs have to adhere to provision of CSR guidelines as per section 135 of the Companies Act 2013 . • Status of Negative Marking : – 2013-14 : Not Applicable – 2014-15 : Not Applicable – 2015-16 : 82 CPSE’s have submitted online data 42
  43. Negative Marking : Compliance to Survey Data Entry for 2015-16 • CPSEs have to enter data for PE Survey by 30th September 2016 • Status of Negative Marking : – 2013-14 : Nil – 2014-15 : Nil – 2015-16 : 80 CPSE’s have not submitted survey data 43
  44. Negative Marking : Compliance to Project Monitoring Data for 2015-16 • CPSEs have to enter online data every month for Rs 150 crores and above projects in OCMS system under MoSPI as per prescribed timelines . • Status of Negative Marking : – 2013-14 : Nil – 2014-15 : Nil – 2015-16 : Under Compilation 44
  45. Receipt of MoU self evaluation report 2015-16 Particulars No of CPSEs MoU Signed: 215 - Holding 143 - Subsidiary 72 Self Evaluation Report received: - Through Admin. ministry 110 - From CPSE 34
  46. Timelines for MoU 2015-16 Evaluation • CPSEs were to submit self evaluation report latest by 30th September, 2016 through Administrative Ministry/Department to DPE; • Alongwith Self Evaluation the CPSEs are required to submit the following mandatory compliances : • Corporate governance to Management division of DPE; • Compliance to DPE guidelines to Finance division of DPE; • Compliance to CSR guidelines to CSR division of DPE; • Submission of online survey data by 30th September 2016; • Compliance to Public procurement guidelines issued by MSME to JS or DC (MSME) ; • Submission of online project monitoring data as per prescribed timelines , if applicable; OCMS system of MoSPI 46