SlideShare una empresa de Scribd logo
1 de 3
Status
• Phase 1
• VDOT, WMATA, Fairfax Punchlist – Ongoing
• Fairfax County - 279 items, 203 closed
• VDOT with majority of remaining punchlist
items
• Project Closeout anticipated at the end of 2015
• Task Order Contract awarded May 7, 2015 to
William M Schlosser Construction Co (2 Yr.)
• Art in Transit Task Order issued
• Final Phase 1 close out - $2.982B
• Wiehle Garage – 100% parking utilization
• Phase 2
• Total Project Status (all bid packages)
• Overall Project – 20%
• Design – 86%
• Construction – 6%
• Highlights
• Tower crane at Innovation Center Station
• Enabling/Utility work – Reston Town Center,
Herndon, Innovation Center Stations
• Aerial Guideway at Dulles Airport under
construction
• Rail Yard at Dulles Airport in design
• Updated schedule for Phase 2 – Fairfax County
adjusted garage schedules to accommodate
MWAA schedule adjustment
• Budget - $2.775B
• Total Contingency - $551.M (Remaining $507.2M)
• Contract extension costs under negotiations
between MWAA and CRC
• County has drawn down $25.8m of its $403.3
million TIFIA loan for payments to MWAA
County Activities – Past 60 Days
• Phase 2 Design Reviews
• County Coordination
• Town of Herndon
• Adjacent Land Owners
• Project Partners (MWAA, VDOT, DRPT, WMATA,
Loudoun County)
• Fairfax Connector
• CIT on land transfer
• Phase 1 Close Out and Punchlist
• 2232 approved at Herndon Station for TPSS 13
• SE for Pavilion at Herndon Station (south side) submitted
• PC – July 22
• BOS – July 28
• Innovation Center Station Joint Infrastructure
Groundbreaking held June 15, 2015, clearing to begin in
September
• Herndon and Innovation Center Stations Garages - Value
Engineering Completed
• Herndon Station Garage – $800K savings
• Innovation Center Station Garage - $4M savings
1
July 14, 2015
2
July 14, 2015
3
July 14, 2015

Más contenido relacionado

La actualidad más candente

Hunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road StudyHunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road StudyFairfax County
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Fairfax County
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Fairfax County
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Fairfax County
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Fairfax County
 
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Fairfax County
 
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsVDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsFairfax County
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Fairfax County
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Fairfax County
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Fairfax County
 
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3Fairfax County
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Fairfax County
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportFairfax County
 
Burke Road Realignment-Citizen Information Meeting: June 1, 2017
Burke Road Realignment-Citizen Information Meeting: June 1, 2017Burke Road Realignment-Citizen Information Meeting: June 1, 2017
Burke Road Realignment-Citizen Information Meeting: June 1, 2017Fairfax County
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the BeltwayFairfax County
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Fairfax County
 
Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyFairfax County
 

La actualidad más candente (20)

Hunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road StudyHunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road Study
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
 
Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015Board Transportation Committee Update: March 17, 2015
Board Transportation Committee Update: March 17, 2015
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
 
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016 Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
Fairfax County Capital Bikeshare - TAC Presentation: June 21, 2016
 
Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014Silver Line Phase 1-Status Report: Feb. 4, 2014
Silver Line Phase 1-Status Report: Feb. 4, 2014
 
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next StepsVDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
VDRPT Route 1 Multimodal Alternatives Analysis: Recommendations for Next Steps
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
 
Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014Silver Line Phase 1 Status Report-Sept. 16, 2014
Silver Line Phase 1 Status Report-Sept. 16, 2014
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
 
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
Burke Road Realignment-Citizen Information Meeting: June 1, 2017
Burke Road Realignment-Citizen Information Meeting: June 1, 2017Burke Road Realignment-Citizen Information Meeting: June 1, 2017
Burke Road Realignment-Citizen Information Meeting: June 1, 2017
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the Beltway
 
Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016Silver Line Update: Board Transportation Committee May 24, 2016
Silver Line Update: Board Transportation Committee May 24, 2016
 
Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning Study
 

Destacado

Discussion of Converting Roads from the Secondary System to the Primary Syste...
Discussion of Converting Roads from the Secondary System to the Primary Syste...Discussion of Converting Roads from the Secondary System to the Primary Syste...
Discussion of Converting Roads from the Secondary System to the Primary Syste...Fairfax County
 
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016Fairfax County
 
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Fairfax County
 
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016Fairfax County
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingFairfax County
 
Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15...
Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15...Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15...
Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15...Fairfax County
 
Transportation Services Group: Employer Services in Fairfax County
Transportation Services Group: Employer Services in Fairfax CountyTransportation Services Group: Employer Services in Fairfax County
Transportation Services Group: Employer Services in Fairfax CountyFairfax County
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare ProgramFairfax County
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County
 
Potential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramPotential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramFairfax County
 
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495Fairfax County
 
Mobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-WayMobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-WayFairfax County
 
Design Public Hearing Presentation for Wiehle Avenue at W&OD Trail
Design Public Hearing Presentation for Wiehle Avenue at W&OD TrailDesign Public Hearing Presentation for Wiehle Avenue at W&OD Trail
Design Public Hearing Presentation for Wiehle Avenue at W&OD TrailFairfax County
 
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016  Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016 Fairfax County
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Fairfax County
 
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Fairfax County
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Fairfax County
 
Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyFairfax County
 
Fairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory CommitteeFairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory CommitteeFairfax County
 

Destacado (20)

Discussion of Converting Roads from the Secondary System to the Primary Syste...
Discussion of Converting Roads from the Secondary System to the Primary Syste...Discussion of Converting Roads from the Secondary System to the Primary Syste...
Discussion of Converting Roads from the Secondary System to the Primary Syste...
 
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
 
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
 
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public Meeting
 
Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15...
Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15...Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15...
Hunter Mill Road and Sunset Hills Road Study: Community Meeting #5 - Sept. 15...
 
Transportation Services Group: Employer Services in Fairfax County
Transportation Services Group: Employer Services in Fairfax CountyTransportation Services Group: Employer Services in Fairfax County
Transportation Services Group: Employer Services in Fairfax County
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare Program
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
 
Potential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramPotential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light Program
 
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
Status of I-66 Corridor Improvement Projects: US Route 15 to I-495
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
Mobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-WayMobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-Way
 
Design Public Hearing Presentation for Wiehle Avenue at W&OD Trail
Design Public Hearing Presentation for Wiehle Avenue at W&OD TrailDesign Public Hearing Presentation for Wiehle Avenue at W&OD Trail
Design Public Hearing Presentation for Wiehle Avenue at W&OD Trail
 
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016  Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
 
Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning Study
 
Fairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory CommitteeFairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory Committee
 

Similar a Dulles Metrorail Silver Line Phase 2 Status and Funding Update

Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingFairfax County
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Fairfax County
 
Dulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateDulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateFairfax County
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Fairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Fairfax County
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationFairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationFairfax County
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Fairfax County
 
Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationFairfax County
 
Dulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and FundingDulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and FundingFairfax County
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects UpdateTownofAddison
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Fairfax County
 
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Fairfax County
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Fairfax County
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Fairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Fairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Fairfax County
 
Clean Water Facility Update
Clean Water Facility UpdateClean Water Facility Update
Clean Water Facility UpdateJackie Dagger
 

Similar a Dulles Metrorail Silver Line Phase 2 Status and Funding Update (20)

Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Dulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and FundingDulles Metrorail Silver Line Phase 2 Status and Funding
Dulles Metrorail Silver Line Phase 2 Status and Funding
 
Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015Silver Line Update: December 1, 2015
Silver Line Update: December 1, 2015
 
Dulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 UpdateDulles Metrorail Silver Line Phase 2 Update
Dulles Metrorail Silver Line Phase 2 Update
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
 
Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II Implementation
 
Dulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and FundingDulles Rail Silver Line Phase 2 Status and Funding
Dulles Rail Silver Line Phase 2 Status and Funding
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
 
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
 
Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013Silver Line Phase 1-Status Report: Sept. 2013
Silver Line Phase 1-Status Report: Sept. 2013
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
 
Clean Water Facility Update
Clean Water Facility UpdateClean Water Facility Update
Clean Water Facility Update
 

Más de Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

Más de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Último

BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKISHAN REDDY OFFICE
 
Pakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdfPakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdfFahimUddin61
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreiebhavenpr
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
28042024_First India Newspaper Jaipur.pdf
28042024_First India Newspaper Jaipur.pdf28042024_First India Newspaper Jaipur.pdf
28042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Pooja Nehwal
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)Delhi Call girls
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPsychicRuben LoveSpells
 
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxjohnandrewcarlos
 
Minto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxMinto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxAwaiskhalid96
 
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...narsireddynannuri1
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docxkfjstone13
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...Axel Bruns
 
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docxkfjstone13
 
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书Fi L
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s LeadershipTDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadershipanjanibaddipudi1
 
Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Krish109503
 

Último (20)

BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
Pakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdfPakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdf
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf30042024_First India Newspaper Jaipur.pdf
30042024_First India Newspaper Jaipur.pdf
 
28042024_First India Newspaper Jaipur.pdf
28042024_First India Newspaper Jaipur.pdf28042024_First India Newspaper Jaipur.pdf
28042024_First India Newspaper Jaipur.pdf
 
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
Call Girls in Mira Road Mumbai ( Neha 09892124323 ) College Escorts Service i...
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptxKAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
KAHULUGAN AT KAHALAGAHAN NG GAWAING PANSIBIKO.pptx
 
Minto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxMinto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptx
 
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
 
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
 
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
 
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s LeadershipTDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
TDP As the Party of Hope For AP Youth Under N Chandrababu Naidu’s Leadership
 
Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!Israel Palestine Conflict, The issue and historical context!
Israel Palestine Conflict, The issue and historical context!
 

Dulles Metrorail Silver Line Phase 2 Status and Funding Update

  • 1. Status • Phase 1 • VDOT, WMATA, Fairfax Punchlist – Ongoing • Fairfax County - 279 items, 203 closed • VDOT with majority of remaining punchlist items • Project Closeout anticipated at the end of 2015 • Task Order Contract awarded May 7, 2015 to William M Schlosser Construction Co (2 Yr.) • Art in Transit Task Order issued • Final Phase 1 close out - $2.982B • Wiehle Garage – 100% parking utilization • Phase 2 • Total Project Status (all bid packages) • Overall Project – 20% • Design – 86% • Construction – 6% • Highlights • Tower crane at Innovation Center Station • Enabling/Utility work – Reston Town Center, Herndon, Innovation Center Stations • Aerial Guideway at Dulles Airport under construction • Rail Yard at Dulles Airport in design • Updated schedule for Phase 2 – Fairfax County adjusted garage schedules to accommodate MWAA schedule adjustment • Budget - $2.775B • Total Contingency - $551.M (Remaining $507.2M) • Contract extension costs under negotiations between MWAA and CRC • County has drawn down $25.8m of its $403.3 million TIFIA loan for payments to MWAA County Activities – Past 60 Days • Phase 2 Design Reviews • County Coordination • Town of Herndon • Adjacent Land Owners • Project Partners (MWAA, VDOT, DRPT, WMATA, Loudoun County) • Fairfax Connector • CIT on land transfer • Phase 1 Close Out and Punchlist • 2232 approved at Herndon Station for TPSS 13 • SE for Pavilion at Herndon Station (south side) submitted • PC – July 22 • BOS – July 28 • Innovation Center Station Joint Infrastructure Groundbreaking held June 15, 2015, clearing to begin in September • Herndon and Innovation Center Stations Garages - Value Engineering Completed • Herndon Station Garage – $800K savings • Innovation Center Station Garage - $4M savings 1 July 14, 2015