Dulles Rail Silver Line Phase 2 Status and Funding
1. Status of MWAA Bid Packages
• Package A – Design and construction of aerial guideway,
stations, systems, and wayside facilities
• Clark Construction and Kiewit Infrastructure South
Joint Venture
• Currently in design with 51% of the design
packages submitted (30%, 60%, 90%, IFC)
• Construction ongoing at Dulles International
Airport (aerial guideway, foundations,
substructures etc.)
• Geotechnical subsurface investigations, site
survey activities going on all along Phase 2
• Acquisition of property rights underway
• Package B – Design and construction WMATA Rail Yard
and Maintenance Facility
• Hensel Phelps Construction Company
• Notice to proceed issued August 18, 2014
with construction to being in early 2015
• Completed the 30% Design Development
submittal
• Package S – Site preparation for WMATA Rail Yard and
Maintenance Facility at Dulles International Airport
• Atlantic Contracting and Material Company
• 100% of existing soil stockpile removed
with contract work near completion
County Activities
• Phase 2 Design Reviews
• County Coordination
• Town of Herndon
• Adjacent Land Owners
• Project Partners (MWAA, VDOT, DRPT, WMATA,
Loudoun County)
• Herndon ($58.7M) & Innovation Center Garages ($57M)
• DPWES lead for design and construction
• Land use approvals completed (2232 and Rezoning)
• Design team onboard
• Scheduled design completion - Summer 2015
• Scheduled construction completion – March 2018
• TIFIA Loan
• Reston Town Center Parkway Funding Agreement Signed
• Phase 1 Close Out and Punchlist
Budget
• Project Budget: $2.778B (includes contingency amount of
$551M)
• Approximately 14% of project budget expended
1
December 9, 2014