The Centreville Green Ponds 1 and 2 are located within the Centreville Green Subdivision; Pond 1 is located off Lee Highway and Pond 2 is located off Canada Goose Court within the Little Rocky Run Watershed. The project consisted of retrofitting the existing two ponds to improve water quality and storage volume. Improvement will increase the residence time of the ponds and provide enhanced water quality benefits. Retrofitting the Centreville Green Ponds allows for the facilities to provide a reduction of 10.7 pounds of total phosphorous, 82.3 pounds of total nitrogen, and 8,622.9 pounds of sediment per year.
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Contract No. CN17125172
Project No. SD-000031-153
District: Sully District
Tax Map No. 055-3
April 20, 2019
Centreville Green Pond 1 (0738DP) & 2 (0739DP)
Pond Retrofits
2. Project Details
Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Description:
• The Centreville Green Pond 1 (LR81-0001-0738DP) and Pond 2 (LR81-0002-0739DP) Retrofit Project has been substantially
completed. The two ponds are located within the Centreville Green Subdivision; Pond 1 is located off Lee Highway and Pond 2
is located off Canada Goose Court within the Little Rocky Run Watershed. The project consisted of retrofitting the existing two
ponds to improve water quality and storage volume. Improvement will increase the residence time of the ponds and provide
enhanced water quality benefits. Retrofitting the Centreville Green Ponds allows for the facilities to provide a reduction of 10.7
pounds of total phosphorous, 82.3 pounds of total nitrogen, and 8,622.9 pounds of sediment per year.
Project Overview:
• Construction of forebays, high and low-marsh, vegetated wetland areas, micro-pools.
• Modification of existing risers with orifice, bmp plates, trash racks.
• Installed floatable trash collection devices at the inflow pipes as a Pilot Program.
• Installation of Maintenance Access Grasscrete.
• Upgrading the existing asphalt trail into 12’ Wide Maintenance Access Asphalt.
• Installation of Standard Entrance Gutter CG-9 and installation of five removable locking bollards at pond 1.
• Installation of Modified Entrance with three removable locking bollards at pond 2.
• Restoring the site with selective seed mix, low marsh plugs, shrubs and trees.
Project Team:
• Project Manager - Suzy Harding / Dave Anglin, Stormwater Planning Division
• Construction Manager - Yousef Rayyan, Utilities Design and Construction Division (UDCD)
• Construction Inspector - Yagya Bhandari, UDCD
• Right of Way Agent - Eric Lefcourt, Land Acquisition
• Land Development Services - Anthony Wall
3. Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Tax Map 055-3, Sully District
Pond No. 1
Pond No. 2
4. Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Pre-Existing Conditions
Pond No. 1 Pond No. 2
5. Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Construction Activities – Pond 1
6. Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Construction Activities – Pond 2
7. Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Maintenance Access
Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Pond No. 1
Post Construction
Pond No. 1
Pre Construction
8. Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Maintenance Access
Pond No. 2
Pre Construction
Pond No. 2
Post Construction
9. Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Pond No. 1 Pond No. 2
Post Construction
10. Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Floatable Trash Collection System - Pilot Program
11. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/dpwes
Centreville Green Pond 1 (0738DP) & 2 (0739DP) Pond Retrofits
Capital Facilities/Utilities Design and Construction/Stormwater Construction Branch
Matthew Kaiser, Public Information Officer