This document provides details about the Chain Bridge Road Walkway Improvements project in Fairfax County, VA. The project involved constructing approximately 3,300 feet of new 5-foot wide sidewalk along the east side of Chain Bridge Road between Niblick Drive and Horse Shoe Drive. It also included stormwater drainage, curb and gutter works, and signal modifications. The project was substantially completed on September 24, 2019.
Chain Bridge Road Walkway from Niblick Drive to Horse Shoe Drive
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Task Order No. 10
Contract No. CN19124125
Project No. 2G40-088-014
Providence District
Tax Map No. 38-2, 39-1
November 13, 2019
CHAIN BRIDGE ROAD WALKWAY
FROM NIBLICK DRIVE TO HORSE SHOE DRIVE
2. Chain Bridge Road Walkway Improvements
(from Niblick Drive to Horse Shoe Drive)
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
3. Project Details
Chain Bridge Road Walkway Improvements
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Description:
The Chain Bridge Road Walkway Improvements Project was substantially completed on
September 24, 2019. This project is part of commercial and industrial (C&I) revenue projects
and consists of the construction of approximately 3,300 ft long, 5 ft. wide, sidewalk with
associated stormwater drainage, curb and gutter works, and signal modifications along the east
side of Chain Bridge Road between Niblick Drive and Horse Shoe Drive.
Project Team:
Department of Transportation - James Beall (PM); Eldar Yusufoglu (Utility Coordinator)
Utilities Design and Construction Division (UDCD) - Abul M. Syed (CM)
UDCD Inspections - Kenneth Giles and Jim Cooper
Capital Facilities Survey- Gregory Harper
Engineer - Whitman, Requardt & Associates, LLP
Contractor - Finley Asphalt & Sealing, Inc.
4. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Providence, Tax Map 38-2, 39-1
Limits of Improvements,
Project No. 2G40-088-014
PROJECT SITE
Chain Bridge Road Walkway Improvements
5. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Pre-Existing Conditions
Chain Bridge Road Walkway Improvements
6. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Pre-Existing Conditions
Chain Bridge Road Walkway Improvements
7. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Chain Bridge Road Walkway Improvements
Installation of Storm Drainage Pipe
8. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Chain Bridge Road Walkway Improvements
Installation of Concrete Sidewalk
9. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Installation of Soil Stabilization Mats
Chain Bridge Road Walkway Improvements
10. Chain Bridge Road Walkway Improvements
(from Niblick Drive to Horse Shoe Drive)
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
11. Chain Bridge Road Walkway Improvements
(from Niblick Drive to Horse Shoe Drive)
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
12. Chain Bridge Road Walkway Improvements
(from Niblick Drive to Horse Shoe Drive)
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
13. Before After
Chain Bridge Road Walkway Improvements
(from Niblick Drive to Horse Shoe Drive)
Capital Facilities/Utilities Design and Construction Division, Transportation Construction Branch
14. Before After
Capital Facilities/Utilities Design and Construction Division, Transportation Construction Branch
Chain Bridge Road Walkway Improvements
(from Niblick Drive to Horse Shoe Drive)
15. Before After
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Chain Bridge Road Walkway Improvements
(from Niblick Drive to Horse Shoe Drive)
16. Before After
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Chain Bridge Road Walkway Improvements
(from Niblick Drive to Horse Shoe Drive)
17. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Matthew Kaiser, Public Information Officer
703-324-8455, TTY 711
Matthew.Kaiser@fairfaxcounty.gov
Chain Bridge Road Walkway Improvements