County of Fairfax, Virginia
1
Citizens Information Meeting
Sleepy Hollow Road Walkway
April 23, 2018, 7:30 P.M. Presentation
Fairfax County - Mason District
County of Fairfax, Virginia
2
Department of Transportation
Fairfax County Team
• Department of Transportation
– Transportation Design Division
• Jacobs Engineering Group
– Capital Projects Division
• Department of Public Works
– Land Acquisition Division
– Construction Division
County of Fairfax, Virginia
3
Agenda
• Purpose & Need
• Summary of Scope Modifications
• Next Steps
• General Q&A - Community Feedback
• Open House
Department of Transportation
County of Fairfax, Virginia
4
• Pedestrian Improvements
– Provide Pedestrian Connectivity
• Add 4,400LF of new walkway
– ADA Compliance
– Safety – Improved Crossings
Purpose & Need
Department of Transportation
County of Fairfax, Virginia
5
Project Update
• Community Meeting #1 – March 2017
– Written responses, calls, and emails received
through May 2017 in addition to public meeting.
• Comments Included:
– Loss of Trees
– Driveway/Grading Issues
– Impacts on Eastside of Sleepy Hollow Road between
Eppard Street and Aspen Lane. Can we utilize
parking lane for sidewalk?
– Pedestrian Crossings
– General Speed/Traffic concerns
Department of Transportation
County of Fairfax, Virginia
6
Project Update
• Major Activities since May 2017
– June/July – Comment Analysis & Internal
Project Scope Review
– July to September – Project Redesign, Parking
Study, Additional Survey, Utility Designation
– October – Internal presentation of revised
project plans.
– December to March – Advance plans to 60%
stage with VDOT submittal.
Department of Transportation
County of Fairfax, Virginia
7
What are the changes?
• Shift sidewalk location between Eppard Street and
Aspen Lane
Department of Transportation
March 2017 Typical Section
County of Fairfax, Virginia
8
Department of Transportation
March 2017
Sidewalk Locations
(West/East)
Aspen Ln
Eppard St
Marlo Dr
Valley Brook Dr
Dearborn Dr
County of Fairfax, Virginia
9
What are the changes?
Department of Transportation
• Shift sidewalk location between Eppard Street and
Aspen Lane
• Utilize Parking Lane for sidewalk between Holmes
Run Road and Aspen Lane
County of Fairfax, Virginia
10
What are the changes?
Department of Transportation
Pedestrian crossing modifications near Bay Tree Lane
County of Fairfax, Virginia
11
What are the changes?
Expected Utility Impacts
Department of Transportation
County of Fairfax, Virginia
12
What are the changes?
Refuge Island Modifications
– Removed crossings at Eppard Street and Aspen
Lane
– Determined Design Vehicles/Turning Radius
Checks
Department of Transportation
County of Fairfax, Virginia
13
What are the changes?
Refuge Island
Modifications
Department of Transportation
County of Fairfax, Virginia
14
Department of Transportation
What are the changes?
Retaining wall type change near
Dearborne Drive: Post & Panel
County of Fairfax, Virginia
15
What has stayed the same?
– Retaining Walls between Valley Brook Drive and
Church Entrance
– Form Liner Options for Walls
Department of Transportation
County of Fairfax, Virginia
16
What has stayed the same?
– Improved Pedestian Crossing at Kerns (Existing
Signalized Intersection)
– Refuge Islands
• Dearborn Drive
• Kennedy Lane
• Castle Place
Department of Transportation
County of Fairfax, Virginia
17
What has stayed the same?
– Sidewalk design South of Holmes Run Road
– Sidewalk design North of Aspen Lane
Department of Transportation
County of Fairfax, Virginia
18
What has stayed the same?
– Landrights will still be necessary on the project.
• Temporary Construction Easements
• Right of Way for VDOT Maintenance
Department of Transportation
County of Fairfax, Virginia
19
Department of Transportation
Potential Issues
– Grading behind walkway
– Driveways
– Trees
– Utilities
County of Fairfax, Virginia
20
Schedule
• Review Community Feedback & Finalize Project
Scope – May 2018
• 90% Design Plans – Fall 2018
• Utility Review/Design & Plat Development –
Winter 2018
• Initiate Land Acquisition – Summer 2019
• Complete Land Acquisition – Spring 2020
• Apply for VDOT Construction Permit – Fall 2020
Department of Transportation
County of Fairfax, Virginia
21
General Questions?
Department of Transportation
Mark.VanZandt@fairfaxcounty.gov
Project Website:
https://www.fairfaxcounty.gov/transportation/projects/sleepy
-hollow-walkway/
Comment forms available at sign-in station.

Más contenido relacionado

La actualidad más candente

La actualidad más candente (20)

Fairfax County Parkway Corridor Study
Fairfax County Parkway Corridor StudyFairfax County Parkway Corridor Study
Fairfax County Parkway Corridor Study
 
Agenda Item 4:I-66 Outside the Beltway
Agenda Item 4:I-66 Outside the BeltwayAgenda Item 4:I-66 Outside the Beltway
Agenda Item 4:I-66 Outside the Beltway
 
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
 
Reston Network Analysis: 2030 Results and Roadway Classifications
Reston Network Analysis: 2030 Results and Roadway ClassificationsReston Network Analysis: 2030 Results and Roadway Classifications
Reston Network Analysis: 2030 Results and Roadway Classifications
 
Springfield Community Business Center Commuter Parking Garage: Design Public ...
Springfield Community Business Center Commuter Parking Garage: Design Public ...Springfield Community Business Center Commuter Parking Garage: Design Public ...
Springfield Community Business Center Commuter Parking Garage: Design Public ...
 
Balls Hill Road & Old Dominion Drive Roadway Spot Improvement - Community Inf...
Balls Hill Road & Old Dominion Drive Roadway Spot Improvement - Community Inf...Balls Hill Road & Old Dominion Drive Roadway Spot Improvement - Community Inf...
Balls Hill Road & Old Dominion Drive Roadway Spot Improvement - Community Inf...
 
Hunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road StudyHunter Mill Road and Sunset Hills Road Study
Hunter Mill Road and Sunset Hills Road Study
 
Burke Road Corridor Community Meeting : June 18, 2018
Burke Road Corridor Community Meeting : June 18, 2018Burke Road Corridor Community Meeting : June 18, 2018
Burke Road Corridor Community Meeting : June 18, 2018
 
Kirby Road Sidewalk Presentation
Kirby Road Sidewalk PresentationKirby Road Sidewalk Presentation
Kirby Road Sidewalk Presentation
 
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy Circle
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy CircleSunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy Circle
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy Circle
 
Backlick Road Walkway Citizens Information Meeting: Nov. 9, 2017
Backlick Road Walkway Citizens Information Meeting: Nov. 9, 2017Backlick Road Walkway Citizens Information Meeting: Nov. 9, 2017
Backlick Road Walkway Citizens Information Meeting: Nov. 9, 2017
 
Clairemont CPG ad hoc subcommittee presentation 1/18/18
Clairemont CPG ad hoc subcommittee presentation 1/18/18Clairemont CPG ad hoc subcommittee presentation 1/18/18
Clairemont CPG ad hoc subcommittee presentation 1/18/18
 
Pedestrian Access Improvements: Burke Lake Road at Coffer Woods Road
Pedestrian Access Improvements: Burke Lake Road at Coffer Woods RoadPedestrian Access Improvements: Burke Lake Road at Coffer Woods Road
Pedestrian Access Improvements: Burke Lake Road at Coffer Woods Road
 
Clairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee MeetingClairemont CPG Ad Hoc Subcommittee Meeting
Clairemont CPG Ad Hoc Subcommittee Meeting
 
Fairfax Connector Service Planning
Fairfax Connector Service PlanningFairfax Connector Service Planning
Fairfax Connector Service Planning
 
EIR Scoping Meeting 7 18-17 presentation
EIR Scoping Meeting 7 18-17 presentationEIR Scoping Meeting 7 18-17 presentation
EIR Scoping Meeting 7 18-17 presentation
 
Bus Stop Safety and Accessibility Improvements
Bus Stop Safety and Accessibility ImprovementsBus Stop Safety and Accessibility Improvements
Bus Stop Safety and Accessibility Improvements
 
Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016
 
GROC 2014 Year End Review
GROC 2014 Year End ReviewGROC 2014 Year End Review
GROC 2014 Year End Review
 
2015 member meeting presentation
2015 member meeting presentation2015 member meeting presentation
2015 member meeting presentation
 

Similar a Citizens Information Meeting: Sleepy Hollow Road Walkway - April 23, 2018

Similar a Citizens Information Meeting: Sleepy Hollow Road Walkway - April 23, 2018 (20)

Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017
Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017
Citizens Information Meeting: Sleepy Hollow Road Walkway-March 29, 2017
 
Burke Centre VRE Connector Ph. IV: Community Meeting for Bicycle and Pedestri...
Burke Centre VRE Connector Ph. IV: Community Meeting for Bicycle and Pedestri...Burke Centre VRE Connector Ph. IV: Community Meeting for Bicycle and Pedestri...
Burke Centre VRE Connector Ph. IV: Community Meeting for Bicycle and Pedestri...
 
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
 
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
Great Falls Street Sidewalk Citizens Information Meeting: Sept. 13, 2016
 
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
Little River Turnpike Bicycle Corridor Study: Public Meeting #2: Sept. 26, 2016
 
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving: Mount Vernon District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving: Mount Vernon DistrictProposed Bicycle Facilities-VDOT Summer 2015 Repaving: Mount Vernon District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving: Mount Vernon District
 
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictProposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
 
Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495Braddock Road Multimodal Study: Guinea Road to I-495
Braddock Road Multimodal Study: Guinea Road to I-495
 
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
 
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
 
Lee District 2017 VDOT Repaving
Lee District 2017 VDOT RepavingLee District 2017 VDOT Repaving
Lee District 2017 VDOT Repaving
 
Citizens Information Meeting: Baron Road Walkway: Oct. 20, 2016
Citizens Information Meeting: Baron Road Walkway: Oct. 20, 2016Citizens Information Meeting: Baron Road Walkway: Oct. 20, 2016
Citizens Information Meeting: Baron Road Walkway: Oct. 20, 2016
 
Citizens Information Meeting: North West Street and Great Falls Street Sidewalks
Citizens Information Meeting: North West Street and Great Falls Street SidewalksCitizens Information Meeting: North West Street and Great Falls Street Sidewalks
Citizens Information Meeting: North West Street and Great Falls Street Sidewalks
 
Fairfax County Parkway/Franconia-Springfield Parkway: Alternatives Analysis a...
Fairfax County Parkway/Franconia-Springfield Parkway: Alternatives Analysis a...Fairfax County Parkway/Franconia-Springfield Parkway: Alternatives Analysis a...
Fairfax County Parkway/Franconia-Springfield Parkway: Alternatives Analysis a...
 
Braddock Road Second Pedestrian Bridge Workshop -- Nov. 8, 2018
Braddock Road Second Pedestrian Bridge Workshop -- Nov. 8, 2018Braddock Road Second Pedestrian Bridge Workshop -- Nov. 8, 2018
Braddock Road Second Pedestrian Bridge Workshop -- Nov. 8, 2018
 
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
 
Braddock Road Pedestrian Bridge Workshop: June 20, 2018
Braddock Road Pedestrian Bridge Workshop: June 20, 2018Braddock Road Pedestrian Bridge Workshop: June 20, 2018
Braddock Road Pedestrian Bridge Workshop: June 20, 2018
 
Citizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road WalkwayCitizens Information Meeting: Lee Chapel Road Walkway
Citizens Information Meeting: Lee Chapel Road Walkway
 
Braddock Road Pedestrian Bridge Workshop - June 20, 2018
Braddock Road Pedestrian Bridge Workshop - June 20, 2018Braddock Road Pedestrian Bridge Workshop - June 20, 2018
Braddock Road Pedestrian Bridge Workshop - June 20, 2018
 
Citizens Information Meeting-Pedestrian Improvements: Center Road from Rollin...
Citizens Information Meeting-Pedestrian Improvements: Center Road from Rollin...Citizens Information Meeting-Pedestrian Improvements: Center Road from Rollin...
Citizens Information Meeting-Pedestrian Improvements: Center Road from Rollin...
 

Más de Fairfax County

Más de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Último

Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
PsychicRuben LoveSpells
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
Faga1939
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
hyt3577
 

Último (20)

Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
 
Group_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the tradeGroup_5_US-China Trade War to understand the trade
Group_5_US-China Trade War to understand the trade
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 47 (Gurgaon)
 
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
Transformative Leadership: N Chandrababu Naidu and TDP's Vision for Innovatio...
 
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
AI as Research Assistant: Upscaling Content Analysis to Identify Patterns of ...
 
Julius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the TableJulius Randle's Injury Status: Surgery Not Off the Table
Julius Randle's Injury Status: Surgery Not Off the Table
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 143 Noida Escorts >༒8448380779 Escort Service
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
THE OBSTACLES THAT IMPEDE THE DEVELOPMENT OF BRAZIL IN THE CONTEMPORARY ERA A...
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
Kishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdfKishan Reddy Report To People (2019-24).pdf
Kishan Reddy Report To People (2019-24).pdf
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
 

Citizens Information Meeting: Sleepy Hollow Road Walkway - April 23, 2018

  • 1. County of Fairfax, Virginia 1 Citizens Information Meeting Sleepy Hollow Road Walkway April 23, 2018, 7:30 P.M. Presentation Fairfax County - Mason District
  • 2. County of Fairfax, Virginia 2 Department of Transportation Fairfax County Team • Department of Transportation – Transportation Design Division • Jacobs Engineering Group – Capital Projects Division • Department of Public Works – Land Acquisition Division – Construction Division
  • 3. County of Fairfax, Virginia 3 Agenda • Purpose & Need • Summary of Scope Modifications • Next Steps • General Q&A - Community Feedback • Open House Department of Transportation
  • 4. County of Fairfax, Virginia 4 • Pedestrian Improvements – Provide Pedestrian Connectivity • Add 4,400LF of new walkway – ADA Compliance – Safety – Improved Crossings Purpose & Need Department of Transportation
  • 5. County of Fairfax, Virginia 5 Project Update • Community Meeting #1 – March 2017 – Written responses, calls, and emails received through May 2017 in addition to public meeting. • Comments Included: – Loss of Trees – Driveway/Grading Issues – Impacts on Eastside of Sleepy Hollow Road between Eppard Street and Aspen Lane. Can we utilize parking lane for sidewalk? – Pedestrian Crossings – General Speed/Traffic concerns Department of Transportation
  • 6. County of Fairfax, Virginia 6 Project Update • Major Activities since May 2017 – June/July – Comment Analysis & Internal Project Scope Review – July to September – Project Redesign, Parking Study, Additional Survey, Utility Designation – October – Internal presentation of revised project plans. – December to March – Advance plans to 60% stage with VDOT submittal. Department of Transportation
  • 7. County of Fairfax, Virginia 7 What are the changes? • Shift sidewalk location between Eppard Street and Aspen Lane Department of Transportation March 2017 Typical Section
  • 8. County of Fairfax, Virginia 8 Department of Transportation March 2017 Sidewalk Locations (West/East) Aspen Ln Eppard St Marlo Dr Valley Brook Dr Dearborn Dr
  • 9. County of Fairfax, Virginia 9 What are the changes? Department of Transportation • Shift sidewalk location between Eppard Street and Aspen Lane • Utilize Parking Lane for sidewalk between Holmes Run Road and Aspen Lane
  • 10. County of Fairfax, Virginia 10 What are the changes? Department of Transportation Pedestrian crossing modifications near Bay Tree Lane
  • 11. County of Fairfax, Virginia 11 What are the changes? Expected Utility Impacts Department of Transportation
  • 12. County of Fairfax, Virginia 12 What are the changes? Refuge Island Modifications – Removed crossings at Eppard Street and Aspen Lane – Determined Design Vehicles/Turning Radius Checks Department of Transportation
  • 13. County of Fairfax, Virginia 13 What are the changes? Refuge Island Modifications Department of Transportation
  • 14. County of Fairfax, Virginia 14 Department of Transportation What are the changes? Retaining wall type change near Dearborne Drive: Post & Panel
  • 15. County of Fairfax, Virginia 15 What has stayed the same? – Retaining Walls between Valley Brook Drive and Church Entrance – Form Liner Options for Walls Department of Transportation
  • 16. County of Fairfax, Virginia 16 What has stayed the same? – Improved Pedestian Crossing at Kerns (Existing Signalized Intersection) – Refuge Islands • Dearborn Drive • Kennedy Lane • Castle Place Department of Transportation
  • 17. County of Fairfax, Virginia 17 What has stayed the same? – Sidewalk design South of Holmes Run Road – Sidewalk design North of Aspen Lane Department of Transportation
  • 18. County of Fairfax, Virginia 18 What has stayed the same? – Landrights will still be necessary on the project. • Temporary Construction Easements • Right of Way for VDOT Maintenance Department of Transportation
  • 19. County of Fairfax, Virginia 19 Department of Transportation Potential Issues – Grading behind walkway – Driveways – Trees – Utilities
  • 20. County of Fairfax, Virginia 20 Schedule • Review Community Feedback & Finalize Project Scope – May 2018 • 90% Design Plans – Fall 2018 • Utility Review/Design & Plat Development – Winter 2018 • Initiate Land Acquisition – Summer 2019 • Complete Land Acquisition – Spring 2020 • Apply for VDOT Construction Permit – Fall 2020 Department of Transportation
  • 21. County of Fairfax, Virginia 21 General Questions? Department of Transportation Mark.VanZandt@fairfaxcounty.gov Project Website: https://www.fairfaxcounty.gov/transportation/projects/sleepy -hollow-walkway/ Comment forms available at sign-in station.