Citizens Information Meeting-Pedestrian Improvements: Center Road from Rolling Spring Court to Reza Court
1. County of Fairfax, Virginia
1
Citizens Information Meeting
Pedestrian Improvements:
Center Road from Rolling Spring
Court to Reza Court
September 23, 2015
Fairfax County
Springfield District
2. County of Fairfax, Virginia
2
Department of Transportation
Project Team
• FCDOT
– Transportation Design (TDD)
– Capital Projects and Operations
(CPOD)
– Department of Public Works &
Environmental Services (DPWES)
• Land Acquisition (LAD)
– Design Consultant
• Volkert, Inc.
3. County of Fairfax, Virginia
3
Agenda
• Purpose & Need
• Summary of Current Design
• Schedule
• Q & A
• Open House
– Project Display Boards
– Comment Sheet
– Sign-In Sheet
Department of Transportation
5. County of Fairfax, Virginia
5
Existing Conditions
Department of Transportation
6. County of Fairfax, Virginia
6
Existing Conditions
Department of Transportation
7. County of Fairfax, Virginia
7
• Pedestrian Improvements
– Sidewalk Connectivity to
School
– ADA Compliance
– Enhanced Safety
• Other Improvements
– Providing Standard Roadway
Width
– New Curb & Gutter
– Drainage Pipes and Inlets
Purpose & Need
Department of Transportation
8. County of Fairfax, Virginia
8
Design Details
Department of Transportation
• Typical Sections
9. County of Fairfax, Virginia
9
Design Details
Department of Transportation
• 5-foot Wide Concrete Sidewalk w/ 4-foot Buffer
• 6-foot Curb Abutted Sidewalk along Retaining Wall
• Curb Ramps (VDOT Std. CG-12)
• Retaining Wall
• Drainage
• Roadway Improvements
10. County of Fairfax, Virginia
10
• Adjacent Property Owners
Temporary Construction Easements
Proposed Right of Way
• Adjustment to On-Site Utilities
Relocate Telephone Duct Cabinets
Relocate Utility Pole
Department of Transportation
11. County of Fairfax, Virginia
11
Maintenance of Traffic
Department of Transportation
• Flagging Operation
• One Work Zone at a Time
• Hours of Construction
– Monday – Thursday:
9:00am – 3:30pm
– Friday:
9:00am – 2:00pm
12. County of Fairfax, Virginia
12
Anticipated Schedule
• Begin Land Acquisition – Spring 2016
• End Land Acquisition – Fall 2016
• Final Plans – Spring 2017
• Construction – Summer 2017
Department of Transportation