SlideShare una empresa de Scribd logo
1 de 20
Dulles Corridor Metrorail Project
Silver Line Phase 2 Implementation
Board Transportation Committee Update
July 17, 2018
Mark Canale, Fairfax County Project Manager
Fairfax County Department of Transportation
2
Project Status
Phase 1
• Old Meadow Road Realignment – 90% design complete.
• Construction completion scheduled for the end of 2018.
• VDOT punch list ongoing – MWAA and Bechtel to complete
• Work on bus bays at Spring Hill and McLean started
• Phase 1 close out - $2.982B (no change)
Phase 2
• Overall Phase 2 – 83% complete
• Package A (Rail line, system, and stations) – 83%
• Sections of the third rail have been energized.
• Package B (Rail yard at Dulles) – 84%
• Contractual Substantial Completion – August 2019
• WMATA Board to establish Revenue Operations Date
3
• Budget
• Total Budget $2.778B
• Total Forecast $2.778B
• Total Expenditures $1.758B
• Contingency Utilization
• Total Contingency $551.5M
• Total Contingency Utilized $236.7M
• Remaining Contingency $314.8M
Phase 2 – Cost Summary
4
• Reston Town Center Station – Mechanical/electrical/plumbing
rough-in, roofing system, and pavilion area work ongoing.
• Herndon Station – Electrical installation, structural steel frame, and
continued work on north and south pavilions.
• Innovation Station – Electrical and plumbing, platform pavers, and
pedestrian bridge touch-up painting.
Phase 2 – Station Construction
5
• Dulles Airport Station – HVAC and roof drain installation, tunnel tie-
in work ongoing, and assembly of TPSS switch gear
• Loudoun Gateway Station – Precast erection, foundation and
support walls, pedestrian bridge assembled, and roof steel
erection.
• Ashburn Station - Station concrete work, precast detailing,
pavilion work, and pedestrian bridge lighting conduits.
Phase 2 – Station Construction
6
• 1598 precast panels provided
• 60 Panels rejected (42 installed 18 not installed). All rejected panels at
the Herndon, Reston, and Innovation Stations have been replaced.
Ashburn and Loudoun Gateway Stations have several panels to be
replaced.
• United States and Commonwealth of Virginia have taken legal
action against UPC in a whistleblower lawsuit claiming UPC
falsified test results and documentation.
• MWAA commenced an independent evaluation of the panels and
final results expected early August. WMATA also conducting a
review of the testing.
• UPC panels are not structure panels but impact the 100 year
durability of the panels.
Phase 2 – Universal Concrete Products (UPC)
7
• Issues with the panels
• High water to cement ratio, air entrainment, insufficient concrete cover
over the rebar, and may not meet non-reactivity to alkali-silica reaction
(unknown until the whistleblower court documents unsealed)
• MWAA proposes a sinking fund to provide money to coat the
panels. This would improve durability and life of the panels to
meet the contract 100 year requirement. WMATA is working with
MWAA on the proposed solution.
• The costs for the “fix” is the responsibility of the Phase 2
contractor
Phase 2 – Universal Concrete Products (UPC) cont.
8
• Aerial guideway finish painting girder bearings and clean up work
• Power and communication lines relocation ongoing
• Completed all 34.5kV cable and conduit installation
• All primary and secondary feeders tested and energized from
Dominion Energy substation to project.
• Rail and switches being installed along the at grade guideway in
the DIAAH median through the Herndon and Reston stations and
along the Greenway median
Phase 2 – Aerial, Track, Utilities, Systems
9
• Interior work for Service and Inspection Building,
Maintenance Way Building, and Transit Police Building.
Construction continues at Train Wash Facility, Warehouse
Facility, and Vehicle Storage Facility.
• Ongoing – Third rail installation and work at the installed
Traction Power Substations
Phase 2 – Rail Yard at Dulles Airport
10
• Total Project Estimate: $44.5M
• Construction Progress: 87% complete
• Existing garage repair work scope and cost under review
Schedule
• Construction Award: October 2016
• Construction (new garage): November 2016 – March 2019
• Construction (existing garage): February 2019 – March 2019
• Ready for Occupancy: April 2019
Herndon Metrorail Garage
11
Herndon Metrorail Garage
Herndon Garage Interior Construction
12
13
• Total Project Estimate: $52 million
• Construction Progress: 62% complete
• Precast Fabrication: October 2017
• Precast Erection: April 5, 2018 (started)
Schedule
• Construction Award: March 2017
• Construction: April 2017
• Ready for Occupancy: April/May 2019
Innovation Metrorail Garage
14
Innovation Metrorail Garage
15
Reston Town Center Station
Reston Town Center Pavilions
16
Herndon Station
Herndon Station Pavilions
Herndon Station South Pavilion
17
Innovation Center Station
Innovation South Pavilion
18
Dulles Airport Station
19
Rail Yard Dulles Airport
20
QUESTIONS?

Más contenido relacionado

La actualidad más candente

La actualidad más candente (20)

Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities Rehabilitation of Three Equalization Basins and Ancillary Facilities
Rehabilitation of Three Equalization Basins and Ancillary Facilities
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
 
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingSpringfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
 
Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020Langley School Pump Station Community Meeting October 22, 2020
Langley School Pump Station Community Meeting October 22, 2020
 
Lakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community MeetingLakevale Sewer Improvements Community Meeting
Lakevale Sewer Improvements Community Meeting
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream Restoration
 
Crook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationCrook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream Restoration
 
Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015Huntsman Lake Dredging January 2015
Huntsman Lake Dredging January 2015
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency Repair
 
Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 

Similar a Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation

Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
Crosstown TO
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
ascemiami-dade
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)
Timothy Nikolai
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Crosstown TO
 

Similar a Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation (20)

Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation : Boar...
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 
Agenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II ImplementationAgenda Item 7: Silver Line Phase II Implementation
Agenda Item 7: Silver Line Phase II Implementation
 
Addison Capital Projects Update
Addison Capital Projects UpdateAddison Capital Projects Update
Addison Capital Projects Update
 
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding UpdateDulles Metrorail Silver Line Phase 2 Status and Funding Update
Dulles Metrorail Silver Line Phase 2 Status and Funding Update
 
Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014Silver Line Phase 1-Status Report: May 6, 2014
Silver Line Phase 1-Status Report: May 6, 2014
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
 
K.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 projectK.1 turkey point units 6 & 7 project
K.1 turkey point units 6 & 7 project
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
 
Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 

Más de Fairfax County

Más de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 

Último

Minto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxMinto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptx
Awaiskhalid96
 
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
Fi L
 

Último (20)

2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
2024 03 13 AZ GOP LD4 Gen Meeting Minutes_FINAL.docx
 
Minto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptxMinto-Morley Reforms 1909 (constitution).pptx
Minto-Morley Reforms 1909 (constitution).pptx
 
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptxLorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
Lorenzo D'Emidio_Lavoro sullaNorth Korea .pptx
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Indirapuram Escorts >༒8448380779 Escort Service
 
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
2024 02 15 AZ GOP LD4 Gen Meeting Minutes_FINAL_20240228.docx
 
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
Nurturing Families, Empowering Lives: TDP's Vision for Family Welfare in Andh...
 
29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdf29042024_First India Newspaper Jaipur.pdf
29042024_First India Newspaper Jaipur.pdf
 
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
Defensa de JOH insiste que testimonio de analista de la DEA es falso y solici...
 
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Greater Noida Escorts >༒8448380779 Escort Service
 
How Europe Underdeveloped Africa_walter.pdf
How Europe Underdeveloped Africa_walter.pdfHow Europe Underdeveloped Africa_walter.pdf
How Europe Underdeveloped Africa_walter.pdf
 
Pakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdfPakistan PMLN Election Manifesto 2024.pdf
Pakistan PMLN Election Manifesto 2024.pdf
 
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
如何办理(BU学位证书)美国贝翰文大学毕业证学位证书
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 135 Noida Escorts >༒8448380779 Escort Service
 
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover BackVerified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
Verified Love Spells in Little Rock, AR (310) 882-6330 Get My Ex-Lover Back
 
28042024_First India Newspaper Jaipur.pdf
28042024_First India Newspaper Jaipur.pdf28042024_First India Newspaper Jaipur.pdf
28042024_First India Newspaper Jaipur.pdf
 
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
2024 04 03 AZ GOP LD4 Gen Meeting Minutes FINAL.docx
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
 
Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort ServiceEnjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
Enjoy Night⚡Call Girls Rajokri Delhi >༒8448380779 Escort Service
 

Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation

  • 1. Dulles Corridor Metrorail Project Silver Line Phase 2 Implementation Board Transportation Committee Update July 17, 2018 Mark Canale, Fairfax County Project Manager Fairfax County Department of Transportation
  • 2. 2 Project Status Phase 1 • Old Meadow Road Realignment – 90% design complete. • Construction completion scheduled for the end of 2018. • VDOT punch list ongoing – MWAA and Bechtel to complete • Work on bus bays at Spring Hill and McLean started • Phase 1 close out - $2.982B (no change) Phase 2 • Overall Phase 2 – 83% complete • Package A (Rail line, system, and stations) – 83% • Sections of the third rail have been energized. • Package B (Rail yard at Dulles) – 84% • Contractual Substantial Completion – August 2019 • WMATA Board to establish Revenue Operations Date
  • 3. 3 • Budget • Total Budget $2.778B • Total Forecast $2.778B • Total Expenditures $1.758B • Contingency Utilization • Total Contingency $551.5M • Total Contingency Utilized $236.7M • Remaining Contingency $314.8M Phase 2 – Cost Summary
  • 4. 4 • Reston Town Center Station – Mechanical/electrical/plumbing rough-in, roofing system, and pavilion area work ongoing. • Herndon Station – Electrical installation, structural steel frame, and continued work on north and south pavilions. • Innovation Station – Electrical and plumbing, platform pavers, and pedestrian bridge touch-up painting. Phase 2 – Station Construction
  • 5. 5 • Dulles Airport Station – HVAC and roof drain installation, tunnel tie- in work ongoing, and assembly of TPSS switch gear • Loudoun Gateway Station – Precast erection, foundation and support walls, pedestrian bridge assembled, and roof steel erection. • Ashburn Station - Station concrete work, precast detailing, pavilion work, and pedestrian bridge lighting conduits. Phase 2 – Station Construction
  • 6. 6 • 1598 precast panels provided • 60 Panels rejected (42 installed 18 not installed). All rejected panels at the Herndon, Reston, and Innovation Stations have been replaced. Ashburn and Loudoun Gateway Stations have several panels to be replaced. • United States and Commonwealth of Virginia have taken legal action against UPC in a whistleblower lawsuit claiming UPC falsified test results and documentation. • MWAA commenced an independent evaluation of the panels and final results expected early August. WMATA also conducting a review of the testing. • UPC panels are not structure panels but impact the 100 year durability of the panels. Phase 2 – Universal Concrete Products (UPC)
  • 7. 7 • Issues with the panels • High water to cement ratio, air entrainment, insufficient concrete cover over the rebar, and may not meet non-reactivity to alkali-silica reaction (unknown until the whistleblower court documents unsealed) • MWAA proposes a sinking fund to provide money to coat the panels. This would improve durability and life of the panels to meet the contract 100 year requirement. WMATA is working with MWAA on the proposed solution. • The costs for the “fix” is the responsibility of the Phase 2 contractor Phase 2 – Universal Concrete Products (UPC) cont.
  • 8. 8 • Aerial guideway finish painting girder bearings and clean up work • Power and communication lines relocation ongoing • Completed all 34.5kV cable and conduit installation • All primary and secondary feeders tested and energized from Dominion Energy substation to project. • Rail and switches being installed along the at grade guideway in the DIAAH median through the Herndon and Reston stations and along the Greenway median Phase 2 – Aerial, Track, Utilities, Systems
  • 9. 9 • Interior work for Service and Inspection Building, Maintenance Way Building, and Transit Police Building. Construction continues at Train Wash Facility, Warehouse Facility, and Vehicle Storage Facility. • Ongoing – Third rail installation and work at the installed Traction Power Substations Phase 2 – Rail Yard at Dulles Airport
  • 10. 10 • Total Project Estimate: $44.5M • Construction Progress: 87% complete • Existing garage repair work scope and cost under review Schedule • Construction Award: October 2016 • Construction (new garage): November 2016 – March 2019 • Construction (existing garage): February 2019 – March 2019 • Ready for Occupancy: April 2019 Herndon Metrorail Garage
  • 12. Herndon Garage Interior Construction 12
  • 13. 13 • Total Project Estimate: $52 million • Construction Progress: 62% complete • Precast Fabrication: October 2017 • Precast Erection: April 5, 2018 (started) Schedule • Construction Award: March 2017 • Construction: April 2017 • Ready for Occupancy: April/May 2019 Innovation Metrorail Garage
  • 15. 15 Reston Town Center Station Reston Town Center Pavilions
  • 16. 16 Herndon Station Herndon Station Pavilions Herndon Station South Pavilion