Georgetown Pike Walkway Phase IV
Task Order No. 79
Contract No. CN19124133
Project No. 2G40-088-036
Dranesville District
Tax Map No. 6-4
October 16, 2019
Georgetown Pike Walkway Phase IV
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Project Details
Georgetown Pike Walkway Phase IV
Description:
The Georgetown Pike Walkway Phase IV Project was substantially completed on time on
October 04, 2019. This project consisted of construction of asphalt sidewalk, reconstruction of
driveways, and some other related items.
Project Overview:
• New Asphalt walkway
• New Handicap Ramp
• Drainage Improvement
Project Team:
• Department of Transportation – John Dresser, Brook Khorashadi
• Land Acquisition Division – John R. Honnick
• Utilities Design and Construction Division (UDCD) – Ben Samiyi
• Fairfax County Project Inspector – Keith Ferrell
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Cinder Bed Road Realignment
Dranesville District, Tax Map No. 6-4
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Georgetown Pike Walkway Phase IV
Project
Location
Existing Conditions
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Georgetown Pike Walkway Phase IV
Preparation of the Aggregate Base for Asphalt Walkway
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Georgetown Pike Walkway Phase IV
Installation of Soil Stabilization Mats
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Georgetown Pike Walkway Phase IV
Georgetown Pike Walkway Phase IV
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Before After
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Georgetown Pike Walkway Phase IV
Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Matthew Kaiser, Public Information Officer
703-324-8455, TTY 711
Matthew.Kaiser@fairfaxcounty.gov
Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
Georgetown Pike Walkway Phase IV

Más contenido relacionado

La actualidad más candente

Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingFairfax County
 
Jermantown Vehicle Services Maintenance Facility Upgrades
Jermantown Vehicle Services Maintenance Facility UpgradesJermantown Vehicle Services Maintenance Facility Upgrades
Jermantown Vehicle Services Maintenance Facility UpgradesFairfax County
 
Route 50 Sidewalk - Patrick Henry to Olin Dr.
Route 50 Sidewalk - Patrick Henry to Olin Dr.Route 50 Sidewalk - Patrick Henry to Olin Dr.
Route 50 Sidewalk - Patrick Henry to Olin Dr.Fairfax County
 
Brown's Chapel Property Pond and Outfall Improvement
Brown's Chapel Property Pond and Outfall ImprovementBrown's Chapel Property Pond and Outfall Improvement
Brown's Chapel Property Pond and Outfall ImprovementFairfax County
 
Portland Place Phase II
Portland Place Phase IIPortland Place Phase II
Portland Place Phase IIFairfax County
 
MSI Developer Council Presentation - February 2017: Regional Transportation D...
MSI Developer Council Presentation - February 2017: Regional Transportation D...MSI Developer Council Presentation - February 2017: Regional Transportation D...
MSI Developer Council Presentation - February 2017: Regional Transportation D...Brad Howard
 
Jefferson Fire Station #18
Jefferson Fire Station #18Jefferson Fire Station #18
Jefferson Fire Station #18Fairfax County
 
NCDOT Master Plan Presentation
NCDOT Master Plan PresentationNCDOT Master Plan Presentation
NCDOT Master Plan PresentationCub Berrian
 
Bus Stop Safety and Accessibility Improvements
Bus Stop Safety and Accessibility ImprovementsBus Stop Safety and Accessibility Improvements
Bus Stop Safety and Accessibility ImprovementsFairfax County
 
Great Falls St. Sidewalk Improvements December 2020
Great Falls St. Sidewalk Improvements December 2020Great Falls St. Sidewalk Improvements December 2020
Great Falls St. Sidewalk Improvements December 2020Fairfax County
 
VDOT Proposal to Address McLean Cut Through Traffic Problems
VDOT Proposal to Address McLean Cut Through Traffic ProblemsVDOT Proposal to Address McLean Cut Through Traffic Problems
VDOT Proposal to Address McLean Cut Through Traffic ProblemsFairfax County
 
Ben Franklin Park Section 1 January 2021
Ben Franklin Park Section 1 January 2021Ben Franklin Park Section 1 January 2021
Ben Franklin Park Section 1 January 2021Fairfax County
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Fairfax County
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Fairfax County
 
Reston Transit Station Areas Development and Transportation Projects
Reston Transit Station Areas Development and Transportation Projects Reston Transit Station Areas Development and Transportation Projects
Reston Transit Station Areas Development and Transportation Projects Fairfax County
 
Georgetown Pike Walkway Phase III & Phase IV
Georgetown Pike Walkway Phase III & Phase IVGeorgetown Pike Walkway Phase III & Phase IV
Georgetown Pike Walkway Phase III & Phase IVFairfax County
 

La actualidad más candente (20)

Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
 
Jermantown Vehicle Services Maintenance Facility Upgrades
Jermantown Vehicle Services Maintenance Facility UpgradesJermantown Vehicle Services Maintenance Facility Upgrades
Jermantown Vehicle Services Maintenance Facility Upgrades
 
FDOT SR-997/Krome Avenue Safety Improvement Projects Status Update
FDOT SR-997/Krome Avenue Safety Improvement Projects Status UpdateFDOT SR-997/Krome Avenue Safety Improvement Projects Status Update
FDOT SR-997/Krome Avenue Safety Improvement Projects Status Update
 
Route 50 Sidewalk - Patrick Henry to Olin Dr.
Route 50 Sidewalk - Patrick Henry to Olin Dr.Route 50 Sidewalk - Patrick Henry to Olin Dr.
Route 50 Sidewalk - Patrick Henry to Olin Dr.
 
Brown's Chapel Property Pond and Outfall Improvement
Brown's Chapel Property Pond and Outfall ImprovementBrown's Chapel Property Pond and Outfall Improvement
Brown's Chapel Property Pond and Outfall Improvement
 
Portland Place Phase II
Portland Place Phase IIPortland Place Phase II
Portland Place Phase II
 
MSI Developer Council Presentation - February 2017: Regional Transportation D...
MSI Developer Council Presentation - February 2017: Regional Transportation D...MSI Developer Council Presentation - February 2017: Regional Transportation D...
MSI Developer Council Presentation - February 2017: Regional Transportation D...
 
Jefferson Fire Station #18
Jefferson Fire Station #18Jefferson Fire Station #18
Jefferson Fire Station #18
 
March 17, 2021 TARC Virtual Workshop
March 17, 2021 TARC Virtual Workshop March 17, 2021 TARC Virtual Workshop
March 17, 2021 TARC Virtual Workshop
 
NCDOT Master Plan Presentation
NCDOT Master Plan PresentationNCDOT Master Plan Presentation
NCDOT Master Plan Presentation
 
Bus Stop Safety and Accessibility Improvements
Bus Stop Safety and Accessibility ImprovementsBus Stop Safety and Accessibility Improvements
Bus Stop Safety and Accessibility Improvements
 
TMC Meeting - SMART Plan Corridors Update
TMC Meeting - SMART Plan Corridors UpdateTMC Meeting - SMART Plan Corridors Update
TMC Meeting - SMART Plan Corridors Update
 
Great Falls St. Sidewalk Improvements December 2020
Great Falls St. Sidewalk Improvements December 2020Great Falls St. Sidewalk Improvements December 2020
Great Falls St. Sidewalk Improvements December 2020
 
VDOT Proposal to Address McLean Cut Through Traffic Problems
VDOT Proposal to Address McLean Cut Through Traffic ProblemsVDOT Proposal to Address McLean Cut Through Traffic Problems
VDOT Proposal to Address McLean Cut Through Traffic Problems
 
FPC Meeting - SMART Plan Corridors Update presentation
FPC Meeting - SMART Plan Corridors Update presentationFPC Meeting - SMART Plan Corridors Update presentation
FPC Meeting - SMART Plan Corridors Update presentation
 
Ben Franklin Park Section 1 January 2021
Ben Franklin Park Section 1 January 2021Ben Franklin Park Section 1 January 2021
Ben Franklin Park Section 1 January 2021
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
 
Reston Transit Station Areas Development and Transportation Projects
Reston Transit Station Areas Development and Transportation Projects Reston Transit Station Areas Development and Transportation Projects
Reston Transit Station Areas Development and Transportation Projects
 
Georgetown Pike Walkway Phase III & Phase IV
Georgetown Pike Walkway Phase III & Phase IVGeorgetown Pike Walkway Phase III & Phase IV
Georgetown Pike Walkway Phase III & Phase IV
 

Similar a Georgetown Pike Walkway Phase IV

Georgetown Pike Walkway Phase III
Georgetown Pike Walkway Phase IIIGeorgetown Pike Walkway Phase III
Georgetown Pike Walkway Phase IIIFairfax County
 
Substantial Completion: Franconia Road Sidewalk
Substantial Completion: Franconia Road SidewalkSubstantial Completion: Franconia Road Sidewalk
Substantial Completion: Franconia Road SidewalkFairfax County
 
Pohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian ImprovementsPohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian ImprovementsFairfax County
 
Old Mount Vernon Road Walkway
Old Mount Vernon Road WalkwayOld Mount Vernon Road Walkway
Old Mount Vernon Road WalkwayFairfax County
 
PowerPoint Westmoreland Street Bike Lanes - substantial completion
PowerPoint   Westmoreland Street Bike Lanes - substantial completionPowerPoint   Westmoreland Street Bike Lanes - substantial completion
PowerPoint Westmoreland Street Bike Lanes - substantial completionFairfax County
 
Parcher Avenue Pedestrian Access Improvement
Parcher Avenue Pedestrian Access ImprovementParcher Avenue Pedestrian Access Improvement
Parcher Avenue Pedestrian Access ImprovementFairfax County
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsFairfax County
 
Gallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsGallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsFairfax County
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road WalkwayFairfax County
 
Chichester Lane at Lismore Lane Walkway
Chichester Lane at Lismore Lane WalkwayChichester Lane at Lismore Lane Walkway
Chichester Lane at Lismore Lane WalkwayFairfax County
 
Sunrise Valley Drive from Hitchcock Drive to Colts Neck Drive
Sunrise Valley Drive from Hitchcock Drive to Colts Neck DriveSunrise Valley Drive from Hitchcock Drive to Colts Neck Drive
Sunrise Valley Drive from Hitchcock Drive to Colts Neck DriveFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Chesterbrook Road Walkway Improvement Project August 2020
Chesterbrook Road Walkway Improvement Project August 2020Chesterbrook Road Walkway Improvement Project August 2020
Chesterbrook Road Walkway Improvement Project August 2020Fairfax County
 
Workhouse Arts Foundation Cross-County Trail
Workhouse Arts Foundation Cross-County TrailWorkhouse Arts Foundation Cross-County Trail
Workhouse Arts Foundation Cross-County TrailFairfax County
 
Glade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank WayGlade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank WayFairfax County
 
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...Fairfax County
 
Workhouse Arts Foundation Access Road
Workhouse Arts Foundation Access RoadWorkhouse Arts Foundation Access Road
Workhouse Arts Foundation Access RoadFairfax County
 
Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...
Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...
Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...Fairfax County
 
Herndon Station Metro Garage
Herndon Station Metro GarageHerndon Station Metro Garage
Herndon Station Metro GarageFairfax County
 

Similar a Georgetown Pike Walkway Phase IV (20)

Georgetown Pike Walkway Phase III
Georgetown Pike Walkway Phase IIIGeorgetown Pike Walkway Phase III
Georgetown Pike Walkway Phase III
 
Substantial Completion: Franconia Road Sidewalk
Substantial Completion: Franconia Road SidewalkSubstantial Completion: Franconia Road Sidewalk
Substantial Completion: Franconia Road Sidewalk
 
Pohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian ImprovementsPohick Road - South Run Road Walkway Pedestrian Improvements
Pohick Road - South Run Road Walkway Pedestrian Improvements
 
Old Mount Vernon Road Walkway
Old Mount Vernon Road WalkwayOld Mount Vernon Road Walkway
Old Mount Vernon Road Walkway
 
Center Road sidewalk
Center Road sidewalkCenter Road sidewalk
Center Road sidewalk
 
PowerPoint Westmoreland Street Bike Lanes - substantial completion
PowerPoint   Westmoreland Street Bike Lanes - substantial completionPowerPoint   Westmoreland Street Bike Lanes - substantial completion
PowerPoint Westmoreland Street Bike Lanes - substantial completion
 
Parcher Avenue Pedestrian Access Improvement
Parcher Avenue Pedestrian Access ImprovementParcher Avenue Pedestrian Access Improvement
Parcher Avenue Pedestrian Access Improvement
 
North Shore Sidewalk Improvements
North Shore Sidewalk ImprovementsNorth Shore Sidewalk Improvements
North Shore Sidewalk Improvements
 
Gallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsGallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue Improvements
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
Chichester Lane at Lismore Lane Walkway
Chichester Lane at Lismore Lane WalkwayChichester Lane at Lismore Lane Walkway
Chichester Lane at Lismore Lane Walkway
 
Sunrise Valley Drive from Hitchcock Drive to Colts Neck Drive
Sunrise Valley Drive from Hitchcock Drive to Colts Neck DriveSunrise Valley Drive from Hitchcock Drive to Colts Neck Drive
Sunrise Valley Drive from Hitchcock Drive to Colts Neck Drive
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Chesterbrook Road Walkway Improvement Project August 2020
Chesterbrook Road Walkway Improvement Project August 2020Chesterbrook Road Walkway Improvement Project August 2020
Chesterbrook Road Walkway Improvement Project August 2020
 
Workhouse Arts Foundation Cross-County Trail
Workhouse Arts Foundation Cross-County TrailWorkhouse Arts Foundation Cross-County Trail
Workhouse Arts Foundation Cross-County Trail
 
Glade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank WayGlade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank Way
 
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
 
Workhouse Arts Foundation Access Road
Workhouse Arts Foundation Access RoadWorkhouse Arts Foundation Access Road
Workhouse Arts Foundation Access Road
 
Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...
Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...
Bus Stop Safety and Accessibility Improvements: Hunter Mill, Braddock and Lee...
 
Herndon Station Metro Garage
Herndon Station Metro GarageHerndon Station Metro Garage
Herndon Station Metro Garage
 

Más de Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
 

Más de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 

Último

sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfSERUDS INDIA
 
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...kumargunjan9515
 
Honasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdfHonasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdfSocial Samosa
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Global Network
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...gajnagarg
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)NAP Global Network
 
74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptxpiyushsinghrajput913
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberSareena Khatun
 
Private Call Girls Bidar 9332606886Call Girls Advance Cash On Delivery Service
Private Call Girls Bidar  9332606886Call Girls Advance Cash On Delivery ServicePrivate Call Girls Bidar  9332606886Call Girls Advance Cash On Delivery Service
Private Call Girls Bidar 9332606886Call Girls Advance Cash On Delivery Servicekumargunjan9515
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Partito democratico
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfScottMeyers35
 
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...kumargunjan9515
 
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...Sareena Khatun
 
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...kajalverma014
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processNAP Global Network
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learningNAP Global Network
 
Russian Escorts in Abu Dhabi 0508644382 Abu Dhabi Escorts
Russian Escorts in Abu Dhabi 0508644382 Abu Dhabi EscortsRussian Escorts in Abu Dhabi 0508644382 Abu Dhabi Escorts
Russian Escorts in Abu Dhabi 0508644382 Abu Dhabi EscortsMonica Sydney
 
NGO working for orphan children’s education
NGO working for orphan children’s educationNGO working for orphan children’s education
NGO working for orphan children’s educationSERUDS INDIA
 

Último (20)

sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
Delivery in 20 Mins Call Girls Malappuram { 9332606886 } VVIP NISHA Call Girl...
 
Honasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdfHonasa Consumer Limited Impact Report 2024.pdf
Honasa Consumer Limited Impact Report 2024.pdf
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptx
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
 
Private Call Girls Bidar 9332606886Call Girls Advance Cash On Delivery Service
Private Call Girls Bidar  9332606886Call Girls Advance Cash On Delivery ServicePrivate Call Girls Bidar  9332606886Call Girls Advance Cash On Delivery Service
Private Call Girls Bidar 9332606886Call Girls Advance Cash On Delivery Service
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
 
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
 
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
Russian Escorts in Abu Dhabi 0508644382 Abu Dhabi Escorts
Russian Escorts in Abu Dhabi 0508644382 Abu Dhabi EscortsRussian Escorts in Abu Dhabi 0508644382 Abu Dhabi Escorts
Russian Escorts in Abu Dhabi 0508644382 Abu Dhabi Escorts
 
NGO working for orphan children’s education
NGO working for orphan children’s educationNGO working for orphan children’s education
NGO working for orphan children’s education
 

Georgetown Pike Walkway Phase IV

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Georgetown Pike Walkway Phase IV Task Order No. 79 Contract No. CN19124133 Project No. 2G40-088-036 Dranesville District Tax Map No. 6-4 October 16, 2019
  • 2. Georgetown Pike Walkway Phase IV Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  • 3. Project Details Georgetown Pike Walkway Phase IV Description: The Georgetown Pike Walkway Phase IV Project was substantially completed on time on October 04, 2019. This project consisted of construction of asphalt sidewalk, reconstruction of driveways, and some other related items. Project Overview: • New Asphalt walkway • New Handicap Ramp • Drainage Improvement Project Team: • Department of Transportation – John Dresser, Brook Khorashadi • Land Acquisition Division – John R. Honnick • Utilities Design and Construction Division (UDCD) – Ben Samiyi • Fairfax County Project Inspector – Keith Ferrell Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  • 4. Cinder Bed Road Realignment Dranesville District, Tax Map No. 6-4 Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Georgetown Pike Walkway Phase IV Project Location
  • 5. Existing Conditions Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Georgetown Pike Walkway Phase IV
  • 6. Preparation of the Aggregate Base for Asphalt Walkway Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Georgetown Pike Walkway Phase IV
  • 7. Installation of Soil Stabilization Mats Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Georgetown Pike Walkway Phase IV
  • 8. Georgetown Pike Walkway Phase IV Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch
  • 9. Before After Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Georgetown Pike Walkway Phase IV
  • 10. Additional Information For additional Information, please call www.fairfaxcounty.gov/publicworks Matthew Kaiser, Public Information Officer 703-324-8455, TTY 711 Matthew.Kaiser@fairfaxcounty.gov Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Georgetown Pike Walkway Phase IV