The Herndon Station Metro Garage project provides a new six-level pre-cast parking structure with seven tiers of parking to accommodate over 2,000 added parking spaces. This project addresses the increased parking demand associated with the coming arrival of the Silver Line Metro, and supports the expanded use of public, mass transportation in the area. The project also provides secure bicycle storage for 130 bikes, energy efficient LED lighting fixtures throughout the garage, and vehicular and pedestrian bridge connections to the existing garage. Infrastructure and site improvements include utilities and road widening coordinated with the Silver Line Phase 2 project, direct vehicular garage egress to the Dulles Toll Road to reduce traffic impact on local roads, and enhanced stormwater management serving the site.
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
HERNDON STATION METRO
GARAGE
Project Number: TF-000020-001
Hunter Mill District
April 2019
2. HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
3. HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Project Description
The project site, located at 12530 Sunrise Valley Drive, Herndon, is designated as the location of
the Herndon Metro Station in Silver Line Phase 2. The new Herndon Station Metro Garage
addresses the increased parking demand associated with the arrival of the Silver Line Metro, and
supports the expanded use of public, mass transportation.
The project site is 5.3 acres as part of the overall 28.2 acres site that also houses an existing
garage, a bus loop and connections to the Dulles Toll Road, all of which remained operational
during the construction of the new garage. The project provides:
• A new 6 level pre-cast parking structure with 7 tiers of parking to accommodate 2,006 parking
spaces,
• Secure bicycles storage area for 130 bikes,
• Energy Efficient LED lighting fixtures throughout the garage,
• Vehicular and pedestrian connections to the existing garage by a new steel truss bridge,
• Infrastructure and site improvements, including utilities and road widening as coordinated
with the Silver Line Phase 2 project,
• Enhanced stormwater management serving the site
• Direct vehicular egress to Dulles Toll Road to reduce traffic impact on local roads.
Substantial Completion: April 4, 2019
Total Project Cost: $44,900,000
4. HERNDON STATION METRO GARAGE
DPWES- Building Design and Construction Division:
• Gasim Elfaki, Project Coordinator, Public Private Partnerships Branch
• Mohammed Abdel-Kariem, Construction Manager, Building Construction Branch
• Geoffrey Kimmel, Senior Construction Manager, Building Construction Branch
• Peter Duryea, Building QC Inspector, Building Construction Branch
• Don Buckbee, Building QC Inspector, Building Construction Branch
DPWES- Land Acquisition Division:
• John Zeigler, Land Acquisition Agent
Fairfax County Department of Transportation:
• Mark Canale, Dulles Rail Project Manager, Fairfax County
• Martha Coello, Senior Transportation Planner
• Nathan Wilkinson, Transportation Planner
• Pamela Rittenhouse, Transportation Planner
• Kris Miller, Transportation Planner
Architect: Hammel Green and Abrahamson
General Contractor: Manhattan Construction Company
Department of Public Works and Environmental Services | Building Design and Construction Division
Project Team
5. HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
12530 SUNRISE VALLEY DRIVE, HERNDON, VA 20191
New Garage
Stormwater
Management
Project Location
6. HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Pedestrian and Vehicular Bridge
7. HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Garage Exterior Views
EAST AND NORTH
SOUTH
WEST ELEVATORS AND STAIR TOWER
8. HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Garage Interior Views
4th Level Elevators
West Entrance
Stair Tower
7th Level Elevators
9. HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Garage Interior Views
10. HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Secure Bicycle Storage
11. Before After
Department of Public Works and Environmental Services | Building Design and Construction Division
HERNDON STATION METRO GARAGE
12. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/dpwes
HERNDON STATION METRO GARAGE
Matt Kaiser, Public Information Officer
703-324-8455, TTY 711
Matthew.Kaiser@fairfaxcounty.gov
Department of Public Works and Environmental Services | Building Design and Construction Division