SlideShare una empresa de Scribd logo
1 de 12
A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
HERNDON STATION METRO
GARAGE
Project Number: TF-000020-001
Hunter Mill District
April 2019
HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Project Description
The project site, located at 12530 Sunrise Valley Drive, Herndon, is designated as the location of
the Herndon Metro Station in Silver Line Phase 2. The new Herndon Station Metro Garage
addresses the increased parking demand associated with the arrival of the Silver Line Metro, and
supports the expanded use of public, mass transportation.
The project site is 5.3 acres as part of the overall 28.2 acres site that also houses an existing
garage, a bus loop and connections to the Dulles Toll Road, all of which remained operational
during the construction of the new garage. The project provides:
• A new 6 level pre-cast parking structure with 7 tiers of parking to accommodate 2,006 parking
spaces,
• Secure bicycles storage area for 130 bikes,
• Energy Efficient LED lighting fixtures throughout the garage,
• Vehicular and pedestrian connections to the existing garage by a new steel truss bridge,
• Infrastructure and site improvements, including utilities and road widening as coordinated
with the Silver Line Phase 2 project,
• Enhanced stormwater management serving the site
• Direct vehicular egress to Dulles Toll Road to reduce traffic impact on local roads.
Substantial Completion: April 4, 2019
Total Project Cost: $44,900,000
HERNDON STATION METRO GARAGE
DPWES- Building Design and Construction Division:
• Gasim Elfaki, Project Coordinator, Public Private Partnerships Branch
• Mohammed Abdel-Kariem, Construction Manager, Building Construction Branch
• Geoffrey Kimmel, Senior Construction Manager, Building Construction Branch
• Peter Duryea, Building QC Inspector, Building Construction Branch
• Don Buckbee, Building QC Inspector, Building Construction Branch
DPWES- Land Acquisition Division:
• John Zeigler, Land Acquisition Agent
Fairfax County Department of Transportation:
• Mark Canale, Dulles Rail Project Manager, Fairfax County
• Martha Coello, Senior Transportation Planner
• Nathan Wilkinson, Transportation Planner
• Pamela Rittenhouse, Transportation Planner
• Kris Miller, Transportation Planner
Architect: Hammel Green and Abrahamson
General Contractor: Manhattan Construction Company
Department of Public Works and Environmental Services | Building Design and Construction Division
Project Team
HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
12530 SUNRISE VALLEY DRIVE, HERNDON, VA 20191
New Garage
Stormwater
Management
Project Location
HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Pedestrian and Vehicular Bridge
HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Garage Exterior Views
EAST AND NORTH
SOUTH
WEST ELEVATORS AND STAIR TOWER
HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Garage Interior Views
4th Level Elevators
West Entrance
Stair Tower
7th Level Elevators
HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Garage Interior Views
HERNDON STATION METRO GARAGE
Department of Public Works and Environmental Services | Building Design and Construction Division
Secure Bicycle Storage
Before After
Department of Public Works and Environmental Services | Building Design and Construction Division
HERNDON STATION METRO GARAGE
Additional Information
For additional Information, please call
www.fairfaxcounty.gov/dpwes
HERNDON STATION METRO GARAGE
Matt Kaiser, Public Information Officer
703-324-8455, TTY 711
Matthew.Kaiser@fairfaxcounty.gov
Department of Public Works and Environmental Services | Building Design and Construction Division

Más contenido relacionado

La actualidad más candente

Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Crosstown TO
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)
Crosstown TO
 
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
Crosstown TO
 
Western Segment Open House - spring 2019
Western Segment Open House - spring 2019 Western Segment Open House - spring 2019
Western Segment Open House - spring 2019
Crosstown TO
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Crosstown TO
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
Crosstown TO
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
Crosstown TO
 

La actualidad más candente (20)

Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampReston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
 
Edsall Road Walkway Pedestrian Improvements
Edsall Road Walkway Pedestrian ImprovementsEdsall Road Walkway Pedestrian Improvements
Edsall Road Walkway Pedestrian Improvements
 
Center Road sidewalk
Center Road sidewalkCenter Road sidewalk
Center Road sidewalk
 
Brookfield Park Wet Pond Construction
Brookfield Park Wet Pond ConstructionBrookfield Park Wet Pond Construction
Brookfield Park Wet Pond Construction
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)
 
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
East Open House - East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station...
 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
 
Western Segment Open House - spring 2019
Western Segment Open House - spring 2019 Western Segment Open House - spring 2019
Western Segment Open House - spring 2019
 
McLean Hunt Estates Pond Improvement Project
McLean Hunt Estates Pond Improvement ProjectMcLean Hunt Estates Pond Improvement Project
McLean Hunt Estates Pond Improvement Project
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
McLean Metro Gravity Sewer Capacity Improvements
McLean Metro Gravity Sewer Capacity ImprovementsMcLean Metro Gravity Sewer Capacity Improvements
McLean Metro Gravity Sewer Capacity Improvements
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open House
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
 
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
  High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project  High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
High Ridge Lakevale Estates Langley Oaks and Weid Pump Stations Project
 
Belcrest Road Phasing Program
Belcrest Road Phasing ProgramBelcrest Road Phasing Program
Belcrest Road Phasing Program
 
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project - Silver Line Phase 2 Implementation
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 

Similar a Herndon Station Metro Garage

Similar a Herndon Station Metro Garage (20)

Franconia at Westchester Drive Median Refuge
Franconia at Westchester Drive Median RefugeFranconia at Westchester Drive Median Refuge
Franconia at Westchester Drive Median Refuge
 
Hunter Village Drive Shoulder Improvements
Hunter Village Drive Shoulder ImprovementsHunter Village Drive Shoulder Improvements
Hunter Village Drive Shoulder Improvements
 
Gallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue ImprovementsGallows Road and Prosperity Avenue Improvements
Gallows Road and Prosperity Avenue Improvements
 
Quander Road Walkway
Quander Road WalkwayQuander Road Walkway
Quander Road Walkway
 
Vesper St. Shared Use Path
Vesper St. Shared Use PathVesper St. Shared Use Path
Vesper St. Shared Use Path
 
Substantial Completion: Franconia Road Sidewalk
Substantial Completion: Franconia Road SidewalkSubstantial Completion: Franconia Road Sidewalk
Substantial Completion: Franconia Road Sidewalk
 
Glade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank WayGlade Drive Walkway - Middle Creek Lane to Glade Bank Way
Glade Drive Walkway - Middle Creek Lane to Glade Bank Way
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
Oakton Community Park Phase 2A
Oakton Community Park Phase 2AOakton Community Park Phase 2A
Oakton Community Park Phase 2A
 
PowerPoint Westmoreland Street Bike Lanes - substantial completion
PowerPoint   Westmoreland Street Bike Lanes - substantial completionPowerPoint   Westmoreland Street Bike Lanes - substantial completion
PowerPoint Westmoreland Street Bike Lanes - substantial completion
 
Lanier St. Bicycle and Pedestrian Connection
Lanier St. Bicycle and Pedestrian ConnectionLanier St. Bicycle and Pedestrian Connection
Lanier St. Bicycle and Pedestrian Connection
 
Huntington Levee
Huntington LeveeHuntington Levee
Huntington Levee
 
Parcher Avenue Pedestrian Access Improvement
Parcher Avenue Pedestrian Access ImprovementParcher Avenue Pedestrian Access Improvement
Parcher Avenue Pedestrian Access Improvement
 
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
Richmond Highway Bus Stop Safety and Accessibility Improvement at Six Bus Sto...
 
South Lakes Drive Sidewalk
South Lakes Drive Sidewalk South Lakes Drive Sidewalk
South Lakes Drive Sidewalk
 
Tysons Boulevard and Galleria Drive Pedestrian Access Improvements
Tysons Boulevard and Galleria Drive Pedestrian Access ImprovementsTysons Boulevard and Galleria Drive Pedestrian Access Improvements
Tysons Boulevard and Galleria Drive Pedestrian Access Improvements
 
Fairfax County Glade Dr. Walkway Improvements August 2020
Fairfax County Glade Dr. Walkway Improvements August 2020Fairfax County Glade Dr. Walkway Improvements August 2020
Fairfax County Glade Dr. Walkway Improvements August 2020
 
Old Mount Vernon Road Walkway
Old Mount Vernon Road WalkwayOld Mount Vernon Road Walkway
Old Mount Vernon Road Walkway
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 

Más de Fairfax County

Más de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 

Último

Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
HyderabadDolls
 
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Menggugurkan Kandungan 087776558899
 

Último (20)

Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Genuine Call Girls in Salem 9332606886 HOT & SEXY Models beautiful and charm...
Genuine Call Girls in Salem  9332606886 HOT & SEXY Models beautiful and charm...Genuine Call Girls in Salem  9332606886 HOT & SEXY Models beautiful and charm...
Genuine Call Girls in Salem 9332606886 HOT & SEXY Models beautiful and charm...
 
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
Call Girls Koregaon Park - 8250092165 Our call girls are sure to provide you ...
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
Call Girls AS Rao Nagar - 8250092165 Our call girls are sure to provide you w...
 
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girlsPakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
 
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Morena [ 7014168258 ] Call Me For Genuine Models We...
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptx
 
Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019Contributi dei parlamentari del PD - Contributi L. 3/2019
Contributi dei parlamentari del PD - Contributi L. 3/2019
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
tOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTRtOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTR
 
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No 📞 9352988975 📞 Elite Escort Service Av...
 
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
 

Herndon Station Metro Garage

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! HERNDON STATION METRO GARAGE Project Number: TF-000020-001 Hunter Mill District April 2019
  • 2. HERNDON STATION METRO GARAGE Department of Public Works and Environmental Services | Building Design and Construction Division
  • 3. HERNDON STATION METRO GARAGE Department of Public Works and Environmental Services | Building Design and Construction Division Project Description The project site, located at 12530 Sunrise Valley Drive, Herndon, is designated as the location of the Herndon Metro Station in Silver Line Phase 2. The new Herndon Station Metro Garage addresses the increased parking demand associated with the arrival of the Silver Line Metro, and supports the expanded use of public, mass transportation. The project site is 5.3 acres as part of the overall 28.2 acres site that also houses an existing garage, a bus loop and connections to the Dulles Toll Road, all of which remained operational during the construction of the new garage. The project provides: • A new 6 level pre-cast parking structure with 7 tiers of parking to accommodate 2,006 parking spaces, • Secure bicycles storage area for 130 bikes, • Energy Efficient LED lighting fixtures throughout the garage, • Vehicular and pedestrian connections to the existing garage by a new steel truss bridge, • Infrastructure and site improvements, including utilities and road widening as coordinated with the Silver Line Phase 2 project, • Enhanced stormwater management serving the site • Direct vehicular egress to Dulles Toll Road to reduce traffic impact on local roads. Substantial Completion: April 4, 2019 Total Project Cost: $44,900,000
  • 4. HERNDON STATION METRO GARAGE DPWES- Building Design and Construction Division: • Gasim Elfaki, Project Coordinator, Public Private Partnerships Branch • Mohammed Abdel-Kariem, Construction Manager, Building Construction Branch • Geoffrey Kimmel, Senior Construction Manager, Building Construction Branch • Peter Duryea, Building QC Inspector, Building Construction Branch • Don Buckbee, Building QC Inspector, Building Construction Branch DPWES- Land Acquisition Division: • John Zeigler, Land Acquisition Agent Fairfax County Department of Transportation: • Mark Canale, Dulles Rail Project Manager, Fairfax County • Martha Coello, Senior Transportation Planner • Nathan Wilkinson, Transportation Planner • Pamela Rittenhouse, Transportation Planner • Kris Miller, Transportation Planner Architect: Hammel Green and Abrahamson General Contractor: Manhattan Construction Company Department of Public Works and Environmental Services | Building Design and Construction Division Project Team
  • 5. HERNDON STATION METRO GARAGE Department of Public Works and Environmental Services | Building Design and Construction Division 12530 SUNRISE VALLEY DRIVE, HERNDON, VA 20191 New Garage Stormwater Management Project Location
  • 6. HERNDON STATION METRO GARAGE Department of Public Works and Environmental Services | Building Design and Construction Division Pedestrian and Vehicular Bridge
  • 7. HERNDON STATION METRO GARAGE Department of Public Works and Environmental Services | Building Design and Construction Division Garage Exterior Views EAST AND NORTH SOUTH WEST ELEVATORS AND STAIR TOWER
  • 8. HERNDON STATION METRO GARAGE Department of Public Works and Environmental Services | Building Design and Construction Division Garage Interior Views 4th Level Elevators West Entrance Stair Tower 7th Level Elevators
  • 9. HERNDON STATION METRO GARAGE Department of Public Works and Environmental Services | Building Design and Construction Division Garage Interior Views
  • 10. HERNDON STATION METRO GARAGE Department of Public Works and Environmental Services | Building Design and Construction Division Secure Bicycle Storage
  • 11. Before After Department of Public Works and Environmental Services | Building Design and Construction Division HERNDON STATION METRO GARAGE
  • 12. Additional Information For additional Information, please call www.fairfaxcounty.gov/dpwes HERNDON STATION METRO GARAGE Matt Kaiser, Public Information Officer 703-324-8455, TTY 711 Matthew.Kaiser@fairfaxcounty.gov Department of Public Works and Environmental Services | Building Design and Construction Division