SlideShare una empresa de Scribd logo
1 de 30
Huntsman Lake Dam Rehabilitation
Huntsman Lake Dredging and Restoration
Department of Public Works and Environmental Services
Pardon Our Dust Meeting
Fairfax County, VA

A Fairfax County, VA publication, October 2013
Huntsman Lake Dam Rehabilitation
Huntsman Lake Dredging and Restoration
Pardon Our Dust
Outline
•

•

•
•
•

Dam Rehabilitation
– Background
– Project Status
– Sequence of Work
– Major Project Elements
Lake Dredging and Restoration
– Background
– Project Status
– Dredging Phases
– Lake Restoration
Construction Timeline Summary
Safety
Q&A
Huntsman Lake Dam Rehabilitation Project
Background
•

•

•

Huntsman Dam is operating under a
conditional Operation & Maintenance
(O&M) Certificate from the Virginia
Department of Conservation and
Recreation, Division of Dam Safety,
because its auxiliary spillway can only
convey about 50 percent of the flows
from the design storm.
Planning and design for this project
was completed in February 2013, and
Fairfax County and Northern Virginia
Soil and Water Conservation District
(NVSWCD) entered into a cost-share
agreement with the Natural Resources
Conservation Service (NRCS) to
rehabilitate the facility in June, 2013.
Project was advertised for construction
on September 9, 2013.
Huntsman Lake Dam Rehabilitation Project Status
• Bid opening: October 2nd, 2013
• Two bids received; apparent low bidder is ASI
Constructors, Inc.
• Construction contract will be managed by the Utilities
Design and Construction Division (UDCD), Fairfax County
• UDCD is completing safety, qualification and reference
checks
• Target date for contract execution*: November 16, 2013
• Notice to Proceed (NTP): First week of December, 2013
• Performance time: 240 days
* Before

a contract can be awarded, Natural Resources Conservation Service (NRCS) will
review and concur with proposed construction schedule, subcontractors and performance bond.
Huntsman Lake Dam Rehabilitation Project
Summary of rehabilitation plan
Huntsman Lake Dam Rehabilitation Project
Major Design Elements
Dam Rehabilitation
General Sequence of Work
•
•
•
•
•
•
•
•
•
•
•
•

Drawdown lake and flag limits of construction
Install perimeter controls
Clear some trees
Install Erosion and Sedimentation (E&S) controls
Rough-grade the area
Install cofferdam for diversion of water
Demolish the riser
Final-grade the area
Install Articulated Concrete Blocks (ACBs)
Build concrete structures (riser, cutoff wall system)
Lay topsoil and seed the area
Remove E&S controls
Huntsman Lake Dam Rehabilitation Project
Spillway realignment and armoring
Huntsman Lake Dam Rehabilitation Project
Spillway realignment and armoring
Huntsman Lake Dam Rehabilitation Project
Spillway realignment and armoring
Huntsman Lake Dam Rehabilitation Project
Riser replacement
Huntsman Lake Dam Rehabilitation Project
Riser replacement
Dredging and Lake Restoration Project Status
•
•
•
•

Bid advertisement: October 14th, 2013
Mandatory pre-bid meeting: October 30th, 2013
Bid opening: November 13th, 2013
Contract execution: middle of December, 2013 to early
January, 2014
• Notice to Proceed (NTP): typically 2 weeks after contract
execution
• Performance time:
– Phase I : 150 days
– If Phase II is authorized: Additional 120 days
Note: For dredging, contract specifications state that the lake will be fully
drained. The dam rehabilitation contractor will be responsible for lake
drawdown, which is expected to take approximately 4 weeks.
Background
•
•
•
•
•

Drainage area = 1,482 acres (2.3 square miles)
Lake surface area = 28.6 acres
Sediment pool capacity = 295,000 cubic yards (CY)
Current sediment in lake = 65,000 CY
Estimated annual sediment load = 2,970 CY

32.5 feet
65,000 CY
Huntsman Lake Dam Rehabilitation Project
Fish Relocation (May 2013)
Sediment Thickness
Huntsman Lake
Site Access and Staging Area
Huntsman Lake - Forebays
maintenance access

bank stabilization
aquatic bench
forebay berms

forebay
sanitary sewer

Phase I dredging limits (34,500 CY)

dam
embankment
Dry Dredging
Lake Needwood in Montgomery County, MD
Dry Dredging
Dry Dredging
Lake Needwood in Montgomery County, MD

21
Lake Restoration
•
•
•
•
•

In-lake forebay
Shoreline stabilization
Fish habitat
Fish stocking
Reforestation

Fish habitat created from salvaged trees

Lake Barton: Fish stocking by Virginia Game and Inland Fisheries
Shoreline Restoration
Huntsman Lake Existing Conditions
Shoreline Restoration
Shoreline Protection
Reforestation
Huntsman Lake Dam Rehabilitation
Huntsman Lake Dredging and Restoration
Summary of construction timeline

• Lake drawdown and dam rehabilitation construction activities to
start in December, 2013
• Dredging activities to commence after lake is fully drawn down by
January, 2014
• Project duration: 9 months (both projects)
• Lake will remain drained for entire project
• Dam rehabilitation and dredging projects have been coordinated to
minimize the time lake is empty
• Lake filling after project completion is dependent on rainfall
conditions, and it is expected filling will be initiated in September,
2014
Huntsman Lake Dam Rehabilitation
Huntsman Lake Dredging and Restoration
SAFETY
• Contractor is required to comply with Fairfax County’s Construction
Safety Resolution. UDCD performs a review of the contractor’s
safety record during the past 3 years.
• For all residents, keeping safe means following two simple rules:

1. Please stay outside the construction limits at all times!
2. Observe construction activities from a safe distance.
Huntsman Lake Dam Rehabilitation
Huntsman Lake Dredging and Restoration
For more information or questions, call the Stormwater Planning Division at
703-324-5500, TTY 711 or email:
Dipmani Kumar: dkumar@fairfaxcounty.gov
Matt Meyers: mmeye1@fairfaxcounty.gov
Utilities Design and Construction Division
703-324-5111, TTY 711 or email:
Bill Nolan (Dam Rehabilitation): wnolan@fairfaxcounty.gov
Mannan Qureshi (Dredging): mqures@fairfaxcounty.gov

A Fairfax County, Virginia, publication October 2013
To request this information in an alternate format, call 703-324-5500, TTY 711.

Thank you.

Más contenido relacionado

La actualidad más candente

Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Fairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationFairfax County
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationFairfax County
 
Stormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaStormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaFairfax County
 
Flood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFlood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFairfax County
 
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public Meeting
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public MeetingDraft TMDL Action Plans for Sediment, Bacteria, and PCBs Public Meeting
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public MeetingFairfax County
 
Paul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream RestorationPaul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream RestorationFairfax County
 
Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013Fairfax County
 
Autumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit ProjectAutumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit ProjectFairfax County
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectFairfax County
 
Summerton Way Pond Retrofit
Summerton Way Pond RetrofitSummerton Way Pond Retrofit
Summerton Way Pond RetrofitFairfax County
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Fairfax County
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Fairfax County
 
Colvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectColvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectFairfax County
 
Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Fairfax County
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park NorthFairfax County
 
Big Rocky Run Phase II Stream Restoration
Big Rocky Run Phase II Stream RestorationBig Rocky Run Phase II Stream Restoration
Big Rocky Run Phase II Stream RestorationFairfax County
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Fairfax County
 
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020Fairfax County
 
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
 Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali... Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...Fairfax County
 

La actualidad más candente (20)

Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
 
Stormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, ChinaStormwater Management Information Sharing with Shandong Province, China
Stormwater Management Information Sharing with Shandong Province, China
 
Flood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFlood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly Drive
 
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public Meeting
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public MeetingDraft TMDL Action Plans for Sediment, Bacteria, and PCBs Public Meeting
Draft TMDL Action Plans for Sediment, Bacteria, and PCBs Public Meeting
 
Paul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream RestorationPaul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream Restoration
 
Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013Government Center Pond Retrofit - May 2013
Government Center Pond Retrofit - May 2013
 
Autumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit ProjectAutumnwood Park Pond Retrofit Project
Autumnwood Park Pond Retrofit Project
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
 
Summerton Way Pond Retrofit
Summerton Way Pond RetrofitSummerton Way Pond Retrofit
Summerton Way Pond Retrofit
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
 
Colvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration ProjectColvin Run Phase I Lake Fairfax Park Stream Restoration Project
Colvin Run Phase I Lake Fairfax Park Stream Restoration Project
 
Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park North
 
Big Rocky Run Phase II Stream Restoration
Big Rocky Run Phase II Stream RestorationBig Rocky Run Phase II Stream Restoration
Big Rocky Run Phase II Stream Restoration
 
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020Tucker Avenue Neighborhood - Community Meeting 3-11-2020
Tucker Avenue Neighborhood - Community Meeting 3-11-2020
 
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
 
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
 Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali... Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...
 

Similar a Huntsman Lake “Pardon Our Dust”

Babson Court Outfall Restoration
Babson Court Outfall RestorationBabson Court Outfall Restoration
Babson Court Outfall RestorationFairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Fairfax County
 
Lenox Drive Outfall Restoration
Lenox Drive Outfall RestorationLenox Drive Outfall Restoration
Lenox Drive Outfall RestorationFairfax County
 
Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Fairfax County
 
Crestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationCrestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationFairfax County
 
Crestmont circle outfall restoration
Crestmont circle outfall restorationCrestmont circle outfall restoration
Crestmont circle outfall restorationFairfax County
 
Royal Lake Dredging and Restoration
Royal Lake Dredging and RestorationRoyal Lake Dredging and Restoration
Royal Lake Dredging and RestorationFairfax County
 
Newington Commons Pond Improvement
Newington Commons Pond ImprovementNewington Commons Pond Improvement
Newington Commons Pond ImprovementFairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationFairfax County
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationFairfax County
 
Barnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project CompletionBarnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project CompletionFairfax County
 
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018Fairfax County
 
Piney Run Public Meeting 1 October 17, 2018
Piney Run Public Meeting 1 October 17, 2018Piney Run Public Meeting 1 October 17, 2018
Piney Run Public Meeting 1 October 17, 2018Fairfax County
 
Peppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationPeppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationFairfax County
 
Difficult Run at Brittenford Drive Information Meeting May 17, 2017
Difficult Run at Brittenford Drive Information Meeting May 17, 2017Difficult Run at Brittenford Drive Information Meeting May 17, 2017
Difficult Run at Brittenford Drive Information Meeting May 17, 2017Fairfax County
 
Franklin Park Chesterbrook Neighborhood Project Highlights
Franklin Park Chesterbrook Neighborhood Project HighlightsFranklin Park Chesterbrook Neighborhood Project Highlights
Franklin Park Chesterbrook Neighborhood Project HighlightsFairfax County
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond ImprovementFairfax County
 
Hunting Creek at Fairfield Stream Restoration
Hunting Creek at Fairfield Stream RestorationHunting Creek at Fairfield Stream Restoration
Hunting Creek at Fairfield Stream RestorationFairfax County
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration ProjectFairfax County
 

Similar a Huntsman Lake “Pardon Our Dust” (20)

Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014
 
Babson Court Outfall Restoration
Babson Court Outfall RestorationBabson Court Outfall Restoration
Babson Court Outfall Restoration
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Lenox Drive Outfall Restoration
Lenox Drive Outfall RestorationLenox Drive Outfall Restoration
Lenox Drive Outfall Restoration
 
Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014
 
Crestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationCrestleigh Way Outfall Restoration
Crestleigh Way Outfall Restoration
 
Crestmont circle outfall restoration
Crestmont circle outfall restorationCrestmont circle outfall restoration
Crestmont circle outfall restoration
 
Royal Lake Dredging and Restoration
Royal Lake Dredging and RestorationRoyal Lake Dredging and Restoration
Royal Lake Dredging and Restoration
 
Newington Commons Pond Improvement
Newington Commons Pond ImprovementNewington Commons Pond Improvement
Newington Commons Pond Improvement
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream Restoration
 
Barnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project CompletionBarnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project Completion
 
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
Snakeden Branch at Lake Audubon Public Meeting November 13, 2018
 
Piney Run Public Meeting 1 October 17, 2018
Piney Run Public Meeting 1 October 17, 2018Piney Run Public Meeting 1 October 17, 2018
Piney Run Public Meeting 1 October 17, 2018
 
Peppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationPeppercorn Drive Outfall Restoration
Peppercorn Drive Outfall Restoration
 
Difficult Run at Brittenford Drive Information Meeting May 17, 2017
Difficult Run at Brittenford Drive Information Meeting May 17, 2017Difficult Run at Brittenford Drive Information Meeting May 17, 2017
Difficult Run at Brittenford Drive Information Meeting May 17, 2017
 
Franklin Park Chesterbrook Neighborhood Project Highlights
Franklin Park Chesterbrook Neighborhood Project HighlightsFranklin Park Chesterbrook Neighborhood Project Highlights
Franklin Park Chesterbrook Neighborhood Project Highlights
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond Improvement
 
Hunting Creek at Fairfield Stream Restoration
Hunting Creek at Fairfield Stream RestorationHunting Creek at Fairfield Stream Restoration
Hunting Creek at Fairfield Stream Restoration
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration Project
 

Más de Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

Más de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Último

Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationReyMonsales
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerOmarCabrera39
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victoryanjanibaddipudi1
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoSABC News
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsnaxymaxyy
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012ankitnayak356677
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkbhavenpr
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest2
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeAbdulGhani778830
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfauroraaudrey4826
 

Último (13)

Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and information
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert Oppenheimer
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election Manifesto
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the rounds
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpk
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdf
 

Huntsman Lake “Pardon Our Dust”

  • 1. Huntsman Lake Dam Rehabilitation Huntsman Lake Dredging and Restoration Department of Public Works and Environmental Services Pardon Our Dust Meeting Fairfax County, VA A Fairfax County, VA publication, October 2013
  • 2. Huntsman Lake Dam Rehabilitation Huntsman Lake Dredging and Restoration Pardon Our Dust Outline • • • • • Dam Rehabilitation – Background – Project Status – Sequence of Work – Major Project Elements Lake Dredging and Restoration – Background – Project Status – Dredging Phases – Lake Restoration Construction Timeline Summary Safety Q&A
  • 3. Huntsman Lake Dam Rehabilitation Project Background • • • Huntsman Dam is operating under a conditional Operation & Maintenance (O&M) Certificate from the Virginia Department of Conservation and Recreation, Division of Dam Safety, because its auxiliary spillway can only convey about 50 percent of the flows from the design storm. Planning and design for this project was completed in February 2013, and Fairfax County and Northern Virginia Soil and Water Conservation District (NVSWCD) entered into a cost-share agreement with the Natural Resources Conservation Service (NRCS) to rehabilitate the facility in June, 2013. Project was advertised for construction on September 9, 2013.
  • 4. Huntsman Lake Dam Rehabilitation Project Status • Bid opening: October 2nd, 2013 • Two bids received; apparent low bidder is ASI Constructors, Inc. • Construction contract will be managed by the Utilities Design and Construction Division (UDCD), Fairfax County • UDCD is completing safety, qualification and reference checks • Target date for contract execution*: November 16, 2013 • Notice to Proceed (NTP): First week of December, 2013 • Performance time: 240 days * Before a contract can be awarded, Natural Resources Conservation Service (NRCS) will review and concur with proposed construction schedule, subcontractors and performance bond.
  • 5. Huntsman Lake Dam Rehabilitation Project Summary of rehabilitation plan
  • 6. Huntsman Lake Dam Rehabilitation Project Major Design Elements
  • 7. Dam Rehabilitation General Sequence of Work • • • • • • • • • • • • Drawdown lake and flag limits of construction Install perimeter controls Clear some trees Install Erosion and Sedimentation (E&S) controls Rough-grade the area Install cofferdam for diversion of water Demolish the riser Final-grade the area Install Articulated Concrete Blocks (ACBs) Build concrete structures (riser, cutoff wall system) Lay topsoil and seed the area Remove E&S controls
  • 8. Huntsman Lake Dam Rehabilitation Project Spillway realignment and armoring
  • 9. Huntsman Lake Dam Rehabilitation Project Spillway realignment and armoring
  • 10. Huntsman Lake Dam Rehabilitation Project Spillway realignment and armoring
  • 11. Huntsman Lake Dam Rehabilitation Project Riser replacement
  • 12. Huntsman Lake Dam Rehabilitation Project Riser replacement
  • 13. Dredging and Lake Restoration Project Status • • • • Bid advertisement: October 14th, 2013 Mandatory pre-bid meeting: October 30th, 2013 Bid opening: November 13th, 2013 Contract execution: middle of December, 2013 to early January, 2014 • Notice to Proceed (NTP): typically 2 weeks after contract execution • Performance time: – Phase I : 150 days – If Phase II is authorized: Additional 120 days Note: For dredging, contract specifications state that the lake will be fully drained. The dam rehabilitation contractor will be responsible for lake drawdown, which is expected to take approximately 4 weeks.
  • 14. Background • • • • • Drainage area = 1,482 acres (2.3 square miles) Lake surface area = 28.6 acres Sediment pool capacity = 295,000 cubic yards (CY) Current sediment in lake = 65,000 CY Estimated annual sediment load = 2,970 CY 32.5 feet 65,000 CY
  • 15. Huntsman Lake Dam Rehabilitation Project Fish Relocation (May 2013)
  • 17. Huntsman Lake Site Access and Staging Area
  • 18. Huntsman Lake - Forebays maintenance access bank stabilization aquatic bench forebay berms forebay sanitary sewer Phase I dredging limits (34,500 CY) dam embankment
  • 19. Dry Dredging Lake Needwood in Montgomery County, MD
  • 21. Dry Dredging Lake Needwood in Montgomery County, MD 21
  • 22. Lake Restoration • • • • • In-lake forebay Shoreline stabilization Fish habitat Fish stocking Reforestation Fish habitat created from salvaged trees Lake Barton: Fish stocking by Virginia Game and Inland Fisheries
  • 23. Shoreline Restoration Huntsman Lake Existing Conditions
  • 27. Huntsman Lake Dam Rehabilitation Huntsman Lake Dredging and Restoration Summary of construction timeline • Lake drawdown and dam rehabilitation construction activities to start in December, 2013 • Dredging activities to commence after lake is fully drawn down by January, 2014 • Project duration: 9 months (both projects) • Lake will remain drained for entire project • Dam rehabilitation and dredging projects have been coordinated to minimize the time lake is empty • Lake filling after project completion is dependent on rainfall conditions, and it is expected filling will be initiated in September, 2014
  • 28. Huntsman Lake Dam Rehabilitation Huntsman Lake Dredging and Restoration SAFETY • Contractor is required to comply with Fairfax County’s Construction Safety Resolution. UDCD performs a review of the contractor’s safety record during the past 3 years. • For all residents, keeping safe means following two simple rules: 1. Please stay outside the construction limits at all times! 2. Observe construction activities from a safe distance.
  • 29. Huntsman Lake Dam Rehabilitation Huntsman Lake Dredging and Restoration
  • 30. For more information or questions, call the Stormwater Planning Division at 703-324-5500, TTY 711 or email: Dipmani Kumar: dkumar@fairfaxcounty.gov Matt Meyers: mmeye1@fairfaxcounty.gov Utilities Design and Construction Division 703-324-5111, TTY 711 or email: Bill Nolan (Dam Rehabilitation): wnolan@fairfaxcounty.gov Mannan Qureshi (Dredging): mqures@fairfaxcounty.gov A Fairfax County, Virginia, publication October 2013 To request this information in an alternate format, call 703-324-5500, TTY 711. Thank you.

Notas del editor

  1. Built in 1973 as a flood-control dam
  2. 1. Armor the control section 2. Extend the training dikes 3. Change the AS alignment
  3. Built in 1973 as a flood-control dam
  4. Built in 1973 as a flood-control dam
  5. Built in 1973 as a flood-control dam
  6. Built in 1973 as a flood-control dam
  7. Built in 1973 as a flood-control dam
  8. Built in 1973 as a flood-control dam
  9. 65,000 CY/295,000 CY = 22 percent full
  10. Built in 1973 as a flood-control dam
  11. This project was Lake Needwood in Montgomery County, MD (Redland). We dredged 100,000 cy of sediment. We did a partial drawdown. The drawdown took about 2 weeks - they only needed to drawdown the lake about 4 feet; however, the County started the drawdown in September, after the main recreation season, and the pre-construction meeting wasn't until the beginning of November. They wanted to let the sediment naturally dewater as much as possible. Initially, they had a lot of rain and didn't get as much dewatering as desired, but eventually, the sediments dewatered enough to truck them to the disposal area. They did have to mix the sediments with a drier material for placement at the disposal area. There was no real additional dewatering -- they filled the disposal area and the end result was a filled in and mounded area (with slopes of 3:1). The mound ended up being 25 high with a big flat top! Not our design - we had a design that maximized the available land footprint, had 4:1 and 5:1 slopes and kinda blended into the area. We didn't want it to look like a big out of place mound of dirt! The contractor requested a field change for the disposal site which the County finally agreed to. They were lucky they had a big open space available that was used as a fill source for a recent highway construction project. The project pre-construction was November 3, 2010. They actually started dredging right after Christmas are completed the project just after July 4th 2011 -- so it took about 9 months. Marlene MartinFX Browne
  12. Built in 1973 as a flood-control dam
  13. Built in 1973 as a flood-control dam
  14. Built in 1973 as a flood-control dam