SlideShare una empresa de Scribd logo
1 de 32
A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
June 12, 2018
Community Meeting
Sherwood Regional Library
Paul Spring Branch Segment 1 @ Hollin Hills
Stream Restoration Project
Little Hunting Creek Watershed Plan Implementation
DPWES Stormwater Planning Division
Design Team
• Design Team includes:
– Members of the Hollin Hills Civic Association
– Members of the Hollin Hills community
– County staff: Project Manager, Construction Manager, Wastewater,
Urban Forester, Stormwater Ecologist
– Design Engineers: Stantec
– History Commission
– Northern Virginia Soil and Water Conservation District
2
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Meeting Outline
3
• Status and General Schedule
• Site Location and Project Limits
• Existing Conditions
• Design Goals
• Proposed Alignment and Access
• Example Projects
• Q&A
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Status and General Schedule
• Data Collection (Completed)
• Stream Restoration Design Process (In progress)
– Pre-Concept Plan Development (Completed)
– Concept (35%) Design Plan Development (Completed)
– Field Walk (Completed)
– Obtaining Easements (In progress)
– Preliminary (65%) Design Plan Development (After easement)
– Final Design Plan Development (After 65%)
– Construction Documents (After final design and permits)
4
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Status and General Schedule (continued)
• Construction (± 12 months)
– Construction date dependent on future funding
– Bidding and Contract Award
– Community Meeting
– Construction Begins
5
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Project Limits
6
Storm Drainage and
Floodplain Easement,
pending
Hollin Hills Stream Restoration
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Existing Conditions Storm Sewer Outfall
7
DPWES Stormwater Planning Division
Existing Conditions Eroding Banks
8
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Existing Conditions Eroding Banks
9
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Existing Conditions Path Flooding
10
Hollin Hills Stream Restoration
11
Existing Conditions Undermined Trees
DPWES Stormwater Planning Division
Hollin Hills Stream Restoration
Erosion undermines tree.
Tree becomes unstable and pulls out
bank.
12
Existing Infrastructure
DPWES Stormwater Planning Division
Hollin Hills Stream Restoration
Road downstream Sanitary sewer
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Design Goals
13
What are the design goals?
• Stabilize 1600 LF of stream and storm sewer outfall
• Reduce excess sediment from being transported downstream
• Reduce excess nutrients from entering the waterway
• This concept estimates saving at least 103 lb/yr TP and 223.6 lb/yr
TN from waterway
• Improve aesthetics
• Reduce hazards (steep, eroding banks)
• Reconnect stream to floodplain
• Improve riparian buffers
• Protect valuable infrastructure
DPWES Stormwater Planning Division
Hollin Hills Stream Restoration
Example In-Stream Structures
14
Reinforced Bed
Rock Steps
Boulder Riffle
DPWES Stormwater Planning Division
Hollin Hills Stream Restoration
Stream Bank Reinforcement
15
Native Vegetation
In-Stream Log SillToe-Slope Protection
DPWES Stormwater Planning Division
Hollin Hills Stream Restoration
Stormwater Pipe
16
Drop Structure Flared End Section
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Design
17
Upper
Middle
Lower
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Design – Proposed Alignment (Upper)
18
• Hand-work
• Minimum
disturbance
• Minimizing tree
removal
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Design – Proposed Alignment (Middle)
19
• Follow the existing alignment, grading the banks to remove
instability
• Add storm sewer pipe and drop structures to connect storm
sewer to main channel
• Add stabilization structures above and below confluence
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Design – Proposed Alignment (Lower, private property)
20
• Lower alignment includes work on private property
• Several alignment options, dependent on easements
• All will have positive drainage
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Design – Proposed Alignment (Lower, HHCA)
21
• Lower portion to shift alignment
• Construction staging area/access
• Abandoned Well
DPWES Stormwater Planning Division
Hoolin Hills Stream Restoration
Pre-Restoration
22
DPWES Stormwater Planning Division
Hollin Hills Stream Restoration
Post-restoration
23
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Design – Tree Preservation
24
• Surveyed 293 Trees
• This plan would remove 42 trees 12” or greater
• Up to 30 of these trees could be reused on site
Brush Habitat
Large Log Habitat
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Design – Proposed Alignment (Lower)
25
• Option 1: Stop project
upstream
• Does not address path
flooding
• Does not address
bank erosion
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Design – Proposed Alignment (Lower)
26
• Option 2: Re-align stream
(example only, not yet
designed)
• Adds to construction
timeline
• Large disturbance
footprint
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division 27
Construction Example
Pre-Construction 6 months post-Construction
28DPWES Stormwater Planning Division
Hollin Hills Stream Restoration
Examples – Quander Road Outfall
Pre-Construction
6 months post-Construction
Pre-Construction Construction
Post Construction After plant establishmentPost-Construction
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Examples – Big Rocky Run Tributary
29
DPWES Stormwater Planning Division
Highlights & Next Steps
• Stream project requested by the community as storm
sewer erosion is degrading
• Evaluation and design will improve the stream condition
and prevent further degradation
• Civic Association will provide easements to access property
• Extensive replanting and non-native invasive control will be
incorporated in later design phases
• Ecological monitoring to take place in June (informs
replanting & management goals)
• Further design on lower segment of stream in coordination
with property owners
• Abandoned well determination
• Expecting design completion early in 2019
30
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Communication
– Comments for this plan version due June 15th
• Provide them directly to Project Manager (Meghan)
• Provide them to community representatives (Gus, et al.)
– Refinements of plan sets as we move forward will refine this
concept, do not expect major changes except in the lower portion
of the stream
– All refinements will be continued to be reviewed by Project Team
and regulatory organizations (e.g. History Commission, Army Corps
of Engineers)
– All refinements will be posted in Sharefile for review
– Continue to provide comments and suggestions
– Planned Next Community Meeting – just before construction
31
Hollin Hills Stream Restoration
DPWES Stormwater Planning Division
Contact Information
Design
Meghan Fellows – Project Manager
703-324-5807
Meghan.Fellows@fairfaxcounty.gov
Fairfax County Stormwater Planning Division
12000 Government Center Parkway
Suite 449
Fairfax, Virginia 22035
www.fairfaxcounty.gov/publicworks/stormwater
To request this information in an alternate format call 703-324-5500, TTY 711
Presentation Website
32
Hollin Hills Stream Restoration

Más contenido relacionado

La actualidad más candente

Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
 
Piney Run at Lake Werowance Stream Restoration Project Oct 2019
Piney Run at Lake Werowance Stream Restoration Project Oct 2019Piney Run at Lake Werowance Stream Restoration Project Oct 2019
Piney Run at Lake Werowance Stream Restoration Project Oct 2019Fairfax County
 
Peyton Run POD Presentation_5_12_21
 Peyton Run POD Presentation_5_12_21 Peyton Run POD Presentation_5_12_21
Peyton Run POD Presentation_5_12_21Fairfax County
 
Piney Run at Lake Werowance Stream Restoration Project
Piney Run at Lake Werowance Stream Restoration ProjectPiney Run at Lake Werowance Stream Restoration Project
Piney Run at Lake Werowance Stream Restoration ProjectFairfax County
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design ReviewFairfax County
 
Lorton Landfill Closure Status Update 3 13-18 SCF mtg
Lorton Landfill Closure Status Update 3 13-18 SCF mtgLorton Landfill Closure Status Update 3 13-18 SCF mtg
Lorton Landfill Closure Status Update 3 13-18 SCF mtgFairfax County
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Fairfax County
 
Sunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectSunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectFairfax County
 
Oakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitOakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitFairfax County
 
Introduction to Biohabitats presentation public meeting number one 02 11-21
Introduction to Biohabitats presentation public meeting number one 02 11-21Introduction to Biohabitats presentation public meeting number one 02 11-21
Introduction to Biohabitats presentation public meeting number one 02 11-21Fairfax County
 
Crook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationCrook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationFairfax County
 
Crestmont circle outfall restoration
Crestmont circle outfall restorationCrestmont circle outfall restoration
Crestmont circle outfall restorationFairfax County
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Fairfax County
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveFairfax County
 
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
 
Accotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationAccotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationFairfax County
 
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
 
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020Cameron Run Tributary at La Vista Drive Stream Restoration June 2020
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020Fairfax County
 
Long Branch Central Watershed Management Area 03-03-2021
Long Branch Central Watershed Management Area 03-03-2021Long Branch Central Watershed Management Area 03-03-2021
Long Branch Central Watershed Management Area 03-03-2021Fairfax County
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Fairfax County
 

La actualidad más candente (20)

Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration Project
 
Piney Run at Lake Werowance Stream Restoration Project Oct 2019
Piney Run at Lake Werowance Stream Restoration Project Oct 2019Piney Run at Lake Werowance Stream Restoration Project Oct 2019
Piney Run at Lake Werowance Stream Restoration Project Oct 2019
 
Peyton Run POD Presentation_5_12_21
 Peyton Run POD Presentation_5_12_21 Peyton Run POD Presentation_5_12_21
Peyton Run POD Presentation_5_12_21
 
Piney Run at Lake Werowance Stream Restoration Project
Piney Run at Lake Werowance Stream Restoration ProjectPiney Run at Lake Werowance Stream Restoration Project
Piney Run at Lake Werowance Stream Restoration Project
 
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood  Stormwater Improvement Preliminary Design ReviewTucker Avenue Neighborhood  Stormwater Improvement Preliminary Design Review
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design Review
 
Lorton Landfill Closure Status Update 3 13-18 SCF mtg
Lorton Landfill Closure Status Update 3 13-18 SCF mtgLorton Landfill Closure Status Update 3 13-18 SCF mtg
Lorton Landfill Closure Status Update 3 13-18 SCF mtg
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
 
Sunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectSunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement Project
 
Oakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitOakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality Retrofit
 
Introduction to Biohabitats presentation public meeting number one 02 11-21
Introduction to Biohabitats presentation public meeting number one 02 11-21Introduction to Biohabitats presentation public meeting number one 02 11-21
Introduction to Biohabitats presentation public meeting number one 02 11-21
 
Crook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationCrook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream Restoration
 
Crestmont circle outfall restoration
Crestmont circle outfall restorationCrestmont circle outfall restoration
Crestmont circle outfall restoration
 
Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014Crosspointe Pond Retrofit 2014
Crosspointe Pond Retrofit 2014
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
 
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017
 
Accotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream RestorationAccotink Tributary at Oakford Drive Stream Restoration
Accotink Tributary at Oakford Drive Stream Restoration
 
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...
 
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020Cameron Run Tributary at La Vista Drive Stream Restoration June 2020
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020
 
Long Branch Central Watershed Management Area 03-03-2021
Long Branch Central Watershed Management Area 03-03-2021Long Branch Central Watershed Management Area 03-03-2021
Long Branch Central Watershed Management Area 03-03-2021
 
Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1Integrated Sewer Metering Project 1
Integrated Sewer Metering Project 1
 

Similar a Paul Spring Branch Stream Restoration Project Community Meeting

Paul Spring at Hollin Hills Stream Restoration Community Meeting 8-27-2019
Paul Spring at Hollin Hills Stream Restoration Community Meeting 8-27-2019Paul Spring at Hollin Hills Stream Restoration Community Meeting 8-27-2019
Paul Spring at Hollin Hills Stream Restoration Community Meeting 8-27-2019Fairfax County
 
Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021
Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021
Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021Fairfax County
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectFairfax County
 
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Fairfax County
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectFairfax County
 
Piney Run Tributary at Lamplighter Way
Piney Run Tributary at Lamplighter WayPiney Run Tributary at Lamplighter Way
Piney Run Tributary at Lamplighter WayFairfax County
 
Leigh Meadow and Towlston Basin Kickoff Presentation Jan 2018
Leigh Meadow and Towlston Basin Kickoff Presentation Jan 2018Leigh Meadow and Towlston Basin Kickoff Presentation Jan 2018
Leigh Meadow and Towlston Basin Kickoff Presentation Jan 2018Fairfax County
 
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Fairfax County
 
Crook Branch at Mantua Elementary School Stream Restoration
Crook Branch at Mantua Elementary School Stream RestorationCrook Branch at Mantua Elementary School Stream Restoration
Crook Branch at Mantua Elementary School Stream RestorationFairfax County
 
Dead Run Segment One Stream Restoration Project
Dead Run Segment One Stream Restoration ProjectDead Run Segment One Stream Restoration Project
Dead Run Segment One Stream Restoration ProjectFairfax County
 
Dead Run Stream Restoration Project Meeting: Feb. 18, 2015
Dead Run Stream Restoration Project Meeting: Feb. 18, 2015Dead Run Stream Restoration Project Meeting: Feb. 18, 2015
Dead Run Stream Restoration Project Meeting: Feb. 18, 2015Fairfax County
 
SMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxSMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxJohnathanSHill
 
SMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxSMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxJohnathanSHill
 
Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead HavenSWCNabi
 
Banks Property Stream Restoration (DC9218)
Banks Property Stream Restoration (DC9218)Banks Property Stream Restoration (DC9218)
Banks Property Stream Restoration (DC9218)Fairfax County
 
Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015Fairfax County
 
Dead Run Stream Restoration May 2014
Dead Run Stream Restoration May 2014Dead Run Stream Restoration May 2014
Dead Run Stream Restoration May 2014Fairfax County
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationFairfax County
 
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Fairfax County
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Fairfax County
 

Similar a Paul Spring Branch Stream Restoration Project Community Meeting (20)

Paul Spring at Hollin Hills Stream Restoration Community Meeting 8-27-2019
Paul Spring at Hollin Hills Stream Restoration Community Meeting 8-27-2019Paul Spring at Hollin Hills Stream Restoration Community Meeting 8-27-2019
Paul Spring at Hollin Hills Stream Restoration Community Meeting 8-27-2019
 
Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021
Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021
Rocky Run Tributary at Hickory Hollow Lane Stream Restoration Feb. 2021
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
 
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
Bullneck Run at Spring Hill Rec Center Stream Restoration Project June 2014
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
 
Piney Run Tributary at Lamplighter Way
Piney Run Tributary at Lamplighter WayPiney Run Tributary at Lamplighter Way
Piney Run Tributary at Lamplighter Way
 
Leigh Meadow and Towlston Basin Kickoff Presentation Jan 2018
Leigh Meadow and Towlston Basin Kickoff Presentation Jan 2018Leigh Meadow and Towlston Basin Kickoff Presentation Jan 2018
Leigh Meadow and Towlston Basin Kickoff Presentation Jan 2018
 
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
 
Crook Branch at Mantua Elementary School Stream Restoration
Crook Branch at Mantua Elementary School Stream RestorationCrook Branch at Mantua Elementary School Stream Restoration
Crook Branch at Mantua Elementary School Stream Restoration
 
Dead Run Segment One Stream Restoration Project
Dead Run Segment One Stream Restoration ProjectDead Run Segment One Stream Restoration Project
Dead Run Segment One Stream Restoration Project
 
Dead Run Stream Restoration Project Meeting: Feb. 18, 2015
Dead Run Stream Restoration Project Meeting: Feb. 18, 2015Dead Run Stream Restoration Project Meeting: Feb. 18, 2015
Dead Run Stream Restoration Project Meeting: Feb. 18, 2015
 
SMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxSMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptx
 
SMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptxSMP_FinalPublicMeeting_FINAL_083022.pptx
SMP_FinalPublicMeeting_FINAL_083022.pptx
 
Steelhead Haven
Steelhead HavenSteelhead Haven
Steelhead Haven
 
Banks Property Stream Restoration (DC9218)
Banks Property Stream Restoration (DC9218)Banks Property Stream Restoration (DC9218)
Banks Property Stream Restoration (DC9218)
 
Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015Dead Run Stream Restoration Public meeting February 18, 2015
Dead Run Stream Restoration Public meeting February 18, 2015
 
Dead Run Stream Restoration May 2014
Dead Run Stream Restoration May 2014Dead Run Stream Restoration May 2014
Dead Run Stream Restoration May 2014
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...
 
Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014Dead Run Stream Restoration Public Meeting April 23, 2014
Dead Run Stream Restoration Public Meeting April 23, 2014
 

Más de Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

Más de Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Último

VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...SUHANI PANDEY
 
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756dollysharma2066
 
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp NumberHot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Numberkumarajju5765
 
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
CSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayCSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayGeorgeDiamandis11
 
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...rajputriyana310
 
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...SUHANI PANDEY
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Book Sex Workers Available Pune Call Girls Khadki 6297143586 Call Hot Indian...
Book Sex Workers Available Pune Call Girls Khadki  6297143586 Call Hot Indian...Book Sex Workers Available Pune Call Girls Khadki  6297143586 Call Hot Indian...
Book Sex Workers Available Pune Call Girls Khadki 6297143586 Call Hot Indian...Call Girls in Nagpur High Profile
 
Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...
Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...
Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...Escorts Call Girls
 
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...SUHANI PANDEY
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...MOHANI PANDEY
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...ranjana rawat
 
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...SUHANI PANDEY
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Standkumarajju5765
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...SUHANI PANDEY
 

Último (20)

VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
 
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
 
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp NumberHot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
Hot Call Girls 🫤 Malviya Nagar ➡️ 9711199171 ➡️ Delhi 🫦 Whatsapp Number
 
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
 
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
(INDIRA) Call Girl Katra Call Now 8617697112 Katra Escorts 24x7
 
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Magarpatta Call Me 7737669865 Budget Friendly No Advance Booking
 
CSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting DayCSR_Module5_Green Earth Initiative, Tree Planting Day
CSR_Module5_Green Earth Initiative, Tree Planting Day
 
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
Call Girls In Bloom Boutique | GK-1 ☎ 9990224454 High Class Delhi NCR 24 Hour...
 
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
 
Book Sex Workers Available Pune Call Girls Khadki 6297143586 Call Hot Indian...
Book Sex Workers Available Pune Call Girls Khadki  6297143586 Call Hot Indian...Book Sex Workers Available Pune Call Girls Khadki  6297143586 Call Hot Indian...
Book Sex Workers Available Pune Call Girls Khadki 6297143586 Call Hot Indian...
 
Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...
Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...Cheap Call Girls  in Dubai %(+971524965298 )#  Dubai Call Girl Service By Rus...
Cheap Call Girls in Dubai %(+971524965298 )# Dubai Call Girl Service By Rus...
 
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
Call Girls Service Pune ₹7.5k Pick Up & Drop With Cash Payment 8005736733 Cal...
 
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Valsad 7001035870 Whatsapp Number, 24/07 Booking
 
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
 
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
 
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night StandHot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
Hot Call Girls |Delhi |Preet Vihar ☎ 9711199171 Book Your One night Stand
 
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
VVIP Pune Call Girls Moshi WhatSapp Number 8005736733 With Elite Staff And Re...
 

Paul Spring Branch Stream Restoration Project Community Meeting

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! June 12, 2018 Community Meeting Sherwood Regional Library Paul Spring Branch Segment 1 @ Hollin Hills Stream Restoration Project Little Hunting Creek Watershed Plan Implementation
  • 2. DPWES Stormwater Planning Division Design Team • Design Team includes: – Members of the Hollin Hills Civic Association – Members of the Hollin Hills community – County staff: Project Manager, Construction Manager, Wastewater, Urban Forester, Stormwater Ecologist – Design Engineers: Stantec – History Commission – Northern Virginia Soil and Water Conservation District 2 Hollin Hills Stream Restoration
  • 3. DPWES Stormwater Planning Division Meeting Outline 3 • Status and General Schedule • Site Location and Project Limits • Existing Conditions • Design Goals • Proposed Alignment and Access • Example Projects • Q&A Hollin Hills Stream Restoration
  • 4. DPWES Stormwater Planning Division Status and General Schedule • Data Collection (Completed) • Stream Restoration Design Process (In progress) – Pre-Concept Plan Development (Completed) – Concept (35%) Design Plan Development (Completed) – Field Walk (Completed) – Obtaining Easements (In progress) – Preliminary (65%) Design Plan Development (After easement) – Final Design Plan Development (After 65%) – Construction Documents (After final design and permits) 4 Hollin Hills Stream Restoration
  • 5. DPWES Stormwater Planning Division Status and General Schedule (continued) • Construction (± 12 months) – Construction date dependent on future funding – Bidding and Contract Award – Community Meeting – Construction Begins 5 Hollin Hills Stream Restoration
  • 6. DPWES Stormwater Planning Division Project Limits 6 Storm Drainage and Floodplain Easement, pending Hollin Hills Stream Restoration
  • 7. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Existing Conditions Storm Sewer Outfall 7
  • 8. DPWES Stormwater Planning Division Existing Conditions Eroding Banks 8 Hollin Hills Stream Restoration
  • 9. DPWES Stormwater Planning Division Existing Conditions Eroding Banks 9 Hollin Hills Stream Restoration
  • 10. DPWES Stormwater Planning Division Existing Conditions Path Flooding 10 Hollin Hills Stream Restoration
  • 11. 11 Existing Conditions Undermined Trees DPWES Stormwater Planning Division Hollin Hills Stream Restoration Erosion undermines tree. Tree becomes unstable and pulls out bank.
  • 12. 12 Existing Infrastructure DPWES Stormwater Planning Division Hollin Hills Stream Restoration Road downstream Sanitary sewer
  • 13. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Design Goals 13 What are the design goals? • Stabilize 1600 LF of stream and storm sewer outfall • Reduce excess sediment from being transported downstream • Reduce excess nutrients from entering the waterway • This concept estimates saving at least 103 lb/yr TP and 223.6 lb/yr TN from waterway • Improve aesthetics • Reduce hazards (steep, eroding banks) • Reconnect stream to floodplain • Improve riparian buffers • Protect valuable infrastructure
  • 14. DPWES Stormwater Planning Division Hollin Hills Stream Restoration Example In-Stream Structures 14 Reinforced Bed Rock Steps Boulder Riffle
  • 15. DPWES Stormwater Planning Division Hollin Hills Stream Restoration Stream Bank Reinforcement 15 Native Vegetation In-Stream Log SillToe-Slope Protection
  • 16. DPWES Stormwater Planning Division Hollin Hills Stream Restoration Stormwater Pipe 16 Drop Structure Flared End Section
  • 17. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Design 17 Upper Middle Lower
  • 18. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Design – Proposed Alignment (Upper) 18 • Hand-work • Minimum disturbance • Minimizing tree removal
  • 19. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Design – Proposed Alignment (Middle) 19 • Follow the existing alignment, grading the banks to remove instability • Add storm sewer pipe and drop structures to connect storm sewer to main channel • Add stabilization structures above and below confluence
  • 20. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Design – Proposed Alignment (Lower, private property) 20 • Lower alignment includes work on private property • Several alignment options, dependent on easements • All will have positive drainage
  • 21. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Design – Proposed Alignment (Lower, HHCA) 21 • Lower portion to shift alignment • Construction staging area/access • Abandoned Well
  • 22. DPWES Stormwater Planning Division Hoolin Hills Stream Restoration Pre-Restoration 22
  • 23. DPWES Stormwater Planning Division Hollin Hills Stream Restoration Post-restoration 23
  • 24. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Design – Tree Preservation 24 • Surveyed 293 Trees • This plan would remove 42 trees 12” or greater • Up to 30 of these trees could be reused on site Brush Habitat Large Log Habitat
  • 25. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Design – Proposed Alignment (Lower) 25 • Option 1: Stop project upstream • Does not address path flooding • Does not address bank erosion
  • 26. Hollin Hills Stream Restoration DPWES Stormwater Planning Division Design – Proposed Alignment (Lower) 26 • Option 2: Re-align stream (example only, not yet designed) • Adds to construction timeline • Large disturbance footprint
  • 27. Hollin Hills Stream Restoration DPWES Stormwater Planning Division 27 Construction Example Pre-Construction 6 months post-Construction
  • 28. 28DPWES Stormwater Planning Division Hollin Hills Stream Restoration Examples – Quander Road Outfall Pre-Construction 6 months post-Construction
  • 29. Pre-Construction Construction Post Construction After plant establishmentPost-Construction Hollin Hills Stream Restoration DPWES Stormwater Planning Division Examples – Big Rocky Run Tributary 29
  • 30. DPWES Stormwater Planning Division Highlights & Next Steps • Stream project requested by the community as storm sewer erosion is degrading • Evaluation and design will improve the stream condition and prevent further degradation • Civic Association will provide easements to access property • Extensive replanting and non-native invasive control will be incorporated in later design phases • Ecological monitoring to take place in June (informs replanting & management goals) • Further design on lower segment of stream in coordination with property owners • Abandoned well determination • Expecting design completion early in 2019 30 Hollin Hills Stream Restoration
  • 31. DPWES Stormwater Planning Division Communication – Comments for this plan version due June 15th • Provide them directly to Project Manager (Meghan) • Provide them to community representatives (Gus, et al.) – Refinements of plan sets as we move forward will refine this concept, do not expect major changes except in the lower portion of the stream – All refinements will be continued to be reviewed by Project Team and regulatory organizations (e.g. History Commission, Army Corps of Engineers) – All refinements will be posted in Sharefile for review – Continue to provide comments and suggestions – Planned Next Community Meeting – just before construction 31 Hollin Hills Stream Restoration
  • 32. DPWES Stormwater Planning Division Contact Information Design Meghan Fellows – Project Manager 703-324-5807 Meghan.Fellows@fairfaxcounty.gov Fairfax County Stormwater Planning Division 12000 Government Center Parkway Suite 449 Fairfax, Virginia 22035 www.fairfaxcounty.gov/publicworks/stormwater To request this information in an alternate format call 703-324-5500, TTY 711 Presentation Website 32 Hollin Hills Stream Restoration

Notas del editor

  1. Construction: FY2018 = July 2018
  2. Construction: FY2018 = July 2018
  3. Construction: FY2018 = July 2018
  4. Construction: FY2018 = July 2018
  5. Construction: FY2018 = July 2018