SlideShare una empresa de Scribd logo
1 de 8
Earned Value Management
FAISAL HUSAINI
M.Arch. (Building Services)
Jamia Millia Islamia, New Delhi
Earned value management (EVM) is a methodology that
combines scope, schedule, and resource measurements to
assess project performance and progress. It is a commonly
used method of performance measurement for projects. It
integrates the scope baseline with the cost baseline, along
with the schedule baseline, to form the performance
baseline, which helps the project management team
assess and measure project performance and progress.
Tools and Techniques: Earned Value Management
Earned Value Terminology
1. Planned Value (PV): Planned value (PV) is the
authorized budget assigned to scheduled work. The relationship analysis of EV,
PV and AC:
2. Budget at Completion (BAC): Based on your original
baselined plan, what you planned to spend to
complete the entire project. Think of it as the Planned
Value of the entire project.
3. Actual Cost (AC): Based on your current progress to
date, what did you actually spend by this time.
4. Earned Value (EV): The value of the work actually
performed to date. Based on your original baselined
plan AND the activities you've actually completed to
date, what you should have spent to complete those
activities.
PV and AC:
1. Earned Value = Planned
Value on schedule
2. Earned Value = Actual
Cost on budget
3. Earned Value < Planned
Value behind schedule
4. Earned Value < Actual
Cost over budget
5. Earned Value > Planned
Value ahead of schedule
6. Earned Value > Actual
Cost under budget
PROBLEM: to construct a wall of 1000 bricks
• Planned cost: 50000 Rs
• Planned Time: 10 Days
• 800 bricks were Laid after 10 Days
• Using 45000 Rs
Budget at Completion (BAC): 50000 Rs
Planned Value (PV): 50000 Rs
Actual Cost (AC): 45000 Rs
Earned Value (EV): 40000 Rs
We can conclude
EV < PV behind schedule
EV < AC over budget
Try a problem on: Earned Value Management
EV < AC over budget
Variances from the approved baseline will be monitored:
Once we've determined our PV, AC, and EV, we can now perform some calculations to tell
us about the performance of our project in terms of schedule and cost.
The first set of calculations are variances:
Cost Variance: CV = EV - AC
The Cost Variance (CV) is "the amount of budget deficit or surplus at a given point in time,
expressed as the difference between the Earned Value and the Actual Cost." CV is the
difference between the Actual Cost of work done and the Earned Value of work done.
Schedule Variance: SV = EV - PV
Tools and Techniques: Earned Value Management
Cost and Schedule Variances
Schedule Variance: SV = EV - PV
The Schedule Variance (SV) is the difference between the Planned (baseline) Value of work
done and the Earned Value of work done.
Negative variances are bad. If the CV or SV are negative, this means that we are over
budget or behind schedule, respectively.
PROBLEM: to construct a wall of 1000 bricks
• Planned cost: 50000 Rs
• Planned Time: 10 Days
• 800 bricks were Laid after 10 Days
• Using 45000 Rs
Budget at Completion (BAC): 50000 Rs
Planned Value (PV): 50000 Rs
Actual Cost (AC): 45000 Rs
Earned Value (EV): 40000 Rs
SOLUTION:
• Cost Variance:
CV = EV-AC
CV = 40000-45000
= -5000 (Over Budget)
• Schedule Variance:
SV = EV – PV
SV = 40000-50000
= -10000 (Behind Schedule)
Cost Performance Index: CPI = EV ÷ AC
The Cost Performance Index (CPI) tells us how efficient we are at managing our budget.
CPI =1.0 On Budget
CPI >1.0 Under Budget
CPI <1.0 Over Budget
Schedule Performance Index: SPI = EV ÷ PV
The Schedule Performance Index (SPI) tells us how efficient we are at managing our
schedule.
SPI =1.0 On Schedule
SPI >1.0 Ahead of Schedule
Tools and Techniques: Earned Value Management
Cost and Schedule Performance Indices (CPI & SPI)
SPI >1.0 Ahead of Schedule
SPI <1.0 Behind Schedule
PROBLEM: to construct a wall of 1000 bricks
• Planned cost: 50000 Rs
• Planned Time: 10 Days
• 800 bricks were Laid after 10 Days
• Using 45000 Rs
Budget at Completion (BAC): 50000 Rs
Planned Value (PV): 50000 Rs
Actual Cost (AC): 45000 Rs
Earned Value (EV): 40000 Rs
SOLUTION:
• Cost Performance Index (CPI):
CPI = EV/AC
CV = 40000/45000
= 0.9 (Over Budget)
• Schedule Performance Index (SPI) :
SPI = EV / PV
SPI = 40000/50000
= 0.8 (Behind Schedule)
The final calculations we can make with Earned Value are for our Estimate to Complete
(ETC) and Estimate at Completion (EAC). These calculations tell us how much money we will
spend to complete (finish) our project assuming we continue our project at the same
performance level we are currently operating.
Estimate to Complete: ETC = (BAC - EV) ÷ CPI
Estimate to Complete: (ETC) will tell us how much money is required to complete the
remaining work on our project.
Estimate at Completion: EAC = AC + ETC
Estimate at Completion (EAC) will tell us the total amount of money we will spend to
Tools and Techniques: Earned Value Management
Estimate to Complete / Estimate at Completion
Estimate at Completion (EAC) will tell us the total amount of money we will spend to
complete the entire project based on our performance to date.
PROBLEM: to construct a wall of 1000 bricks
• Planned cost: 50000 Rs
• Planned Time: 10 Days
• 800 bricks were Laid after 10 Days
• Using 45000 Rs
Budget at Completion (BAC): 50000 Rs
Planned Value (PV): 50000 Rs
Actual Cost (AC): 45000 Rs
Earned Value (EV): 40000 Rs
SOLUTION:
• Estimate to Complete (ETC):
ETC = (BAC - EV) ÷ CPI
ETC = (50000-40000)/0.9
= 11111 Rs
• Estimate at Complete (EAC) :
EAC = AC + ETC
EAC = 45000+11111
= 56111 Rs
Tools and Techniques: Earned Value Management
Earned Value over Time
The goal of Project control is "comparing actual performance with planned performance,
analyzing variances, assessing trends to effect process improvements, evaluating possible
alternatives, and recommending appropriate corrective action as needed.“
CORRECTIVE MEASURE FOR COST PERFORMANCE:
Project Manager will consider:
• Adjust resource levels or resources to ensure the proper skills are being utilized.
• Evaluate scope of work to ensure no "out of scope" work has found its way into the project
(i.e. Scope Creep).
• Evaluate new risks and determine response strategies.
Tools and Techniques: Earned Value Management
• Evaluate new risks and determine response strategies.
• Ensure issues are promptly reviewed and closed.
• Using less expensive resources than planned in order to recover some budget decline.
• Adjusting the time frame to complete the work.
• use less expensive resources (note that this may impact the schedule performance).
• Ensuring your plan is optimized for resources, and no new resources are regularly joining
the team and dragging down productivity.
• Implementing productivity improvement ideas offered by the project team.

Más contenido relacionado

La actualidad más candente

EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
Fahad Ali
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
Paul King
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
Shenin Hassan
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
constructioninside
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
harwoodr
 

La actualidad más candente (20)

Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Earned value
Earned valueEarned value
Earned value
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
3 pm3 c_4%20-%20control%20accounts%20and%20the%20distributed%20budget
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 

Similar a Earned value management

Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
AsBali1
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 

Similar a Earned value management (20)

Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
Project managment 6 (a)
Project managment 6 (a)Project managment 6 (a)
Project managment 6 (a)
 
EarnedValue.ppt
EarnedValue.pptEarnedValue.ppt
EarnedValue.ppt
 

Último

Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 

Último (20)

Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for Learning
 

Earned value management

  • 1. Earned Value Management FAISAL HUSAINI M.Arch. (Building Services) Jamia Millia Islamia, New Delhi
  • 2. Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. It is a commonly used method of performance measurement for projects. It integrates the scope baseline with the cost baseline, along with the schedule baseline, to form the performance baseline, which helps the project management team assess and measure project performance and progress. Tools and Techniques: Earned Value Management Earned Value Terminology 1. Planned Value (PV): Planned value (PV) is the authorized budget assigned to scheduled work. The relationship analysis of EV, PV and AC: 2. Budget at Completion (BAC): Based on your original baselined plan, what you planned to spend to complete the entire project. Think of it as the Planned Value of the entire project. 3. Actual Cost (AC): Based on your current progress to date, what did you actually spend by this time. 4. Earned Value (EV): The value of the work actually performed to date. Based on your original baselined plan AND the activities you've actually completed to date, what you should have spent to complete those activities. PV and AC: 1. Earned Value = Planned Value on schedule 2. Earned Value = Actual Cost on budget 3. Earned Value < Planned Value behind schedule 4. Earned Value < Actual Cost over budget 5. Earned Value > Planned Value ahead of schedule 6. Earned Value > Actual Cost under budget
  • 3. PROBLEM: to construct a wall of 1000 bricks • Planned cost: 50000 Rs • Planned Time: 10 Days • 800 bricks were Laid after 10 Days • Using 45000 Rs Budget at Completion (BAC): 50000 Rs Planned Value (PV): 50000 Rs Actual Cost (AC): 45000 Rs Earned Value (EV): 40000 Rs We can conclude EV < PV behind schedule EV < AC over budget Try a problem on: Earned Value Management EV < AC over budget
  • 4. Variances from the approved baseline will be monitored: Once we've determined our PV, AC, and EV, we can now perform some calculations to tell us about the performance of our project in terms of schedule and cost. The first set of calculations are variances: Cost Variance: CV = EV - AC The Cost Variance (CV) is "the amount of budget deficit or surplus at a given point in time, expressed as the difference between the Earned Value and the Actual Cost." CV is the difference between the Actual Cost of work done and the Earned Value of work done. Schedule Variance: SV = EV - PV Tools and Techniques: Earned Value Management Cost and Schedule Variances Schedule Variance: SV = EV - PV The Schedule Variance (SV) is the difference between the Planned (baseline) Value of work done and the Earned Value of work done. Negative variances are bad. If the CV or SV are negative, this means that we are over budget or behind schedule, respectively. PROBLEM: to construct a wall of 1000 bricks • Planned cost: 50000 Rs • Planned Time: 10 Days • 800 bricks were Laid after 10 Days • Using 45000 Rs Budget at Completion (BAC): 50000 Rs Planned Value (PV): 50000 Rs Actual Cost (AC): 45000 Rs Earned Value (EV): 40000 Rs SOLUTION: • Cost Variance: CV = EV-AC CV = 40000-45000 = -5000 (Over Budget) • Schedule Variance: SV = EV – PV SV = 40000-50000 = -10000 (Behind Schedule)
  • 5. Cost Performance Index: CPI = EV ÷ AC The Cost Performance Index (CPI) tells us how efficient we are at managing our budget. CPI =1.0 On Budget CPI >1.0 Under Budget CPI <1.0 Over Budget Schedule Performance Index: SPI = EV ÷ PV The Schedule Performance Index (SPI) tells us how efficient we are at managing our schedule. SPI =1.0 On Schedule SPI >1.0 Ahead of Schedule Tools and Techniques: Earned Value Management Cost and Schedule Performance Indices (CPI & SPI) SPI >1.0 Ahead of Schedule SPI <1.0 Behind Schedule PROBLEM: to construct a wall of 1000 bricks • Planned cost: 50000 Rs • Planned Time: 10 Days • 800 bricks were Laid after 10 Days • Using 45000 Rs Budget at Completion (BAC): 50000 Rs Planned Value (PV): 50000 Rs Actual Cost (AC): 45000 Rs Earned Value (EV): 40000 Rs SOLUTION: • Cost Performance Index (CPI): CPI = EV/AC CV = 40000/45000 = 0.9 (Over Budget) • Schedule Performance Index (SPI) : SPI = EV / PV SPI = 40000/50000 = 0.8 (Behind Schedule)
  • 6. The final calculations we can make with Earned Value are for our Estimate to Complete (ETC) and Estimate at Completion (EAC). These calculations tell us how much money we will spend to complete (finish) our project assuming we continue our project at the same performance level we are currently operating. Estimate to Complete: ETC = (BAC - EV) ÷ CPI Estimate to Complete: (ETC) will tell us how much money is required to complete the remaining work on our project. Estimate at Completion: EAC = AC + ETC Estimate at Completion (EAC) will tell us the total amount of money we will spend to Tools and Techniques: Earned Value Management Estimate to Complete / Estimate at Completion Estimate at Completion (EAC) will tell us the total amount of money we will spend to complete the entire project based on our performance to date. PROBLEM: to construct a wall of 1000 bricks • Planned cost: 50000 Rs • Planned Time: 10 Days • 800 bricks were Laid after 10 Days • Using 45000 Rs Budget at Completion (BAC): 50000 Rs Planned Value (PV): 50000 Rs Actual Cost (AC): 45000 Rs Earned Value (EV): 40000 Rs SOLUTION: • Estimate to Complete (ETC): ETC = (BAC - EV) ÷ CPI ETC = (50000-40000)/0.9 = 11111 Rs • Estimate at Complete (EAC) : EAC = AC + ETC EAC = 45000+11111 = 56111 Rs
  • 7. Tools and Techniques: Earned Value Management Earned Value over Time
  • 8. The goal of Project control is "comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed.“ CORRECTIVE MEASURE FOR COST PERFORMANCE: Project Manager will consider: • Adjust resource levels or resources to ensure the proper skills are being utilized. • Evaluate scope of work to ensure no "out of scope" work has found its way into the project (i.e. Scope Creep). • Evaluate new risks and determine response strategies. Tools and Techniques: Earned Value Management • Evaluate new risks and determine response strategies. • Ensure issues are promptly reviewed and closed. • Using less expensive resources than planned in order to recover some budget decline. • Adjusting the time frame to complete the work. • use less expensive resources (note that this may impact the schedule performance). • Ensuring your plan is optimized for resources, and no new resources are regularly joining the team and dragging down productivity. • Implementing productivity improvement ideas offered by the project team.