Rework Reduction
Through the Use of
Construction Lean Improvement Program (CLIP)
a Case Study in New Australian Embassy in Jakarta (AEJ) -
Leighton Contractors Indonesia & Total Bangun Persada
Joint Operation
Firdaus Basbeth
DMB Student of University of Padjadjaran Bandung
QIK 2014 International Conference
Ascot House Melbourne February 21 2014
Construction Traditional Measure
(Result Based)
▫ Costs
▫ Schedule
▫ Meeting code
Construction Lean Improvement
Program
• Result and Process Based Measurement
▫ Costs
▫ Schedule
▫ Meeting code
▫ Cycle time
▫ Rework
▫ Waste
LEAN
RIGHT THE FIRST TIME
Chancery and Staff Residence, Jakarta
Project Description
The project is Total plot area 40,000m2, total covered floor area 50,106m2 of
which 43,500m2 is building and 6,600m2 is pergola and parking. The scope of
work includes Partial Design, Engineering, • Procurement, Testing and
Inspection, Construction a Compound, consisting of:
o Basement, plus 5 floor chancery building of approximately 26,700m2,
o Head of Mission residence,
o 32 number staff residences,
o Swimming pool,
o Recreation facilities,
o Guard houses,
o Ancillary service buildings,
o Landscaping,
o Security walls,
o All associated works in accordance with drawings, specifications.
The construction duration is 36 months until 2016. It is still ongoing and under
close monitoring by project management.
INTRODUCTION
• Construction traditional measure (Result Based)
vs Performance Measurement System (Process
Based)
• Construction Lean Improvement Program
▫ Lean Thinking
▫ Seven Waste
▫ 5S
▫ Labor Competency Issue
▫ First Inspection Method
LITERATURE REVIEW
Reference Topics and quote
Saad Sarhan and Andrew Fox,
(University of Plymouth, UK)
(2012) ‘Performance
measurement in the UK
construction industry and its
role in supporting the
application of lean construction
concepts’, Australasian Journal
of Construction Economics and
Building, 13 (1) 23-35
Benefits could be achieved from adopting the
lean construction (LC) approach (Arbulu and
Zabelle, 2006). However, the application of
lean principles to construction has not been
successful due to the failure to use
appropriate process performance
measurement systems (PMS).
LITERATURE REVIEW
Reference Topics and quote
Alarcon and Serpell, 1996 Results-based performance preferences
measured in projects, specifically costs and
schedule, are not appropriate for continuous
improvement because they are not effective in
identifying the root-causes of quality and
productivity losses.
Professionals and managers in the
construction industry still have a tendency to
measure performance in terms of time, cost
and meeting code, as opposed to process
performance measures (e.g. cycle time,
Rework, waste)
LITERATURE REVIEW
Reference Topics and quote
Henny Pratiwi, M. Faiqun Niam,
2012.
is said that 62% of construction labors in
Indonesia is an unskilled labors
Koskela (1992) (Garnett et al.,
1998; Mossman, 2009a).
Lean thinking is a philosophy based on the
concepts of lean production, when applied to
construction, it could lead to improved
performance.
(Garnett et al., 1998; Senaratne
and Wijesiri, 2008).
Proposed the need to review construction
production as a combination of conversion
and flow processes to remove waste, when
traditional thinking of construction was only
focusing on conversion activities and ignoring
flow and value considerations
LITERATURE REVIEW
Reference Topics and quote
FACTORS INFLUENCING
CONSTRUCTION PRODUCTIVITY
IN THE INDONESIAN CONTEXT
Sugiharto ALWI
Senior Lecturer
School of Graduate Studies
Construction Management Program,
Proceedings of the Eastern Asia
Society for Transportation Studies,
Vol.4, October, 2003
The majority of the Indonesian construction labour
force are self-employed, and are often farmers from
rural areas. They are low skilled, earn low wages,
and hence are less effective (Kaming et al., 1997).
These young workers enter the pool of construction
workers, for it is the only industry that can provide
employment for those without any qualifications. It
is reported that approximately 86% skilled workers
in Indonesia are informally trained by a senior
craftsman
Henny Pratiwi, M. Faiqun Niam,
2012.
62% of construction labors in Indonesia is an
unskilled labors
Lean Thinking
Lean thinking is a philosophy based on the
concepts of lean production.
Lean is focused on the achievement of three key
outcomes:
1. Maximizing value from the view of the
customer
2. Eliminating waste (non-value adding
processes)
3. Creating smooth and reliable flow of activity.
Benefit
Tangible benefits
•Productivity 16 – 40 %↑
•Refurb lead time 25%↓
•Pre-construction lead time (time between client approval and start of
works on-site) ↓
•48%
Intangible benefits
•Best practice set-up, methods introduced, operation & organization
improvements,
•waste reduction, delays & disruptions reduced, snags reduced,
communications
•improved, Team dynamics improved, partnering benefits, skills
transfer in the industry
Seven Type of Waste
1. Defect
2. Over Production
3. Transportation
4. Waiting
5. Over Processing
6. Motion
7. Inventory
Seven Type of Waste
1. Defect
2. Over Production
3. Transportation
4. Waiting
5. Over Processing
6. Motion
7. Inventory
Implementation Strategy
1. 5S
2. Measuring and Monitoring the Performance of
• NCR
• Rework
• Waste
3. The First Inspection System
4. A Solid and updated QA Plan
5. Recruitment based on labor competency plus
continual training.
5S
Strategy for creating a well organized, smoothly flowing
process. It has been applied in the shop with great success.
Masaaki Imai says, “If one is not doing 5S, one is not doing
lean.”
Benefits of 5S
• Increases organization and efficiency
• Avoids wasted motion
• Increases safety
• Eliminates unnecessary inventory
• Offers improvements at an inexpensive cost
METHOD
The research is a Case Study in Leighton
Contractors Indonesia in New Australian Embassy
Project (2013 – 2016)
Primary and Secondary Data are gathered using
both qualitative and quantitative approaches, and
interview
RESULT
Total NCR and Root cause
RESULT
The Root cause
RESULT
Total NCR in Two Different Area
RESULT
Total NCR in Chancery
DISCUSSION
• In the construction industry, defect or rework is a challenge that
affects the productivity of a project. Additional resources are
required ie: labor, materials, and energy beyond what is budgeted
had the work been done right the first time – not to mentioned
potential risk with respect to quality and safety.
• The New Australian Embassy Project has in place and continually
updates their Quality Plan. Improvement activities can be seen from
the frequency of Non Conformance Report.(Rework required.)
Training to up skill labor to LCI standards, Internal Quality Audits,
and increased management attention has been a focus the last 6
months.
DISCUSSION
• The New Autralian Embassy in Jakarta (AEJ) implemented the First
Inspector System (FIS) – by putting full responsibility of the quality
of product delivered to the supervisor and foreman, so by the time
the quality inspector come to check the work, the variation from
specification will be the minimum. The results have seen the non-
conformance reports reduce by 57%. The saving for the project is
USD$20,000 or Rupiah 240mil.
DISCUSSION
• The Construction Lean Improvement Program Works in Chancery
Area in the Project. Suggestion to be Implemented in some others
construction areas in the Project, with the additional strategy of : 5S,
First Inspector System, Performance Monitoring (Process Based)
Continual Training on the Labor to maintaining quality of the
product.
• Buy in from Project Manager and its implementation strategy need
to be in the first place – stated in Quality Plan.
DISCUSSION
Rework / NCR Reduction in CLIP include the following
processes:
•Rework tracking and main cause classification: detecting and
identifying the rework that occurs and captured, investigate the causes
in a database that used collaboratively by the client, contractors and
designer.
•Corrective action : developing options and actions that will bring
about changes in the project management system with the goal of
eliminating the root cause and reducing construction rework
•Evaluation of the effectiveness of the corrective action taken.
33
Thank youThank you

Más contenido relacionado

La actualidad más candente

Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11PMA Consultants
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve Satish Yadavalli
 
Lean Six Sigma Awareness Handouts
Lean Six Sigma Awareness HandoutsLean Six Sigma Awareness Handouts
Lean Six Sigma Awareness Handoutsguest0981f4
 
Quality awareness
Quality awarenessQuality awareness
Quality awarenesssmcci
 
Purposes of pigging
Purposes of piggingPurposes of pigging
Purposes of piggingAzharMahmud4
 
Kaizen in Everyday Life
Kaizen in Everyday LifeKaizen in Everyday Life
Kaizen in Everyday LifeYogesh Vaghani
 
Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)DEEPAK SAHOO
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedureGerard B. Hawkins
 

La actualidad más candente (20)

Project quality management
Project quality managementProject quality management
Project quality management
 
Project management professional (pmi) study guide
Project management professional (pmi) study guideProject management professional (pmi) study guide
Project management professional (pmi) study guide
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
TPM: Quality Maintenance (Hinshitsu Hozen)
TPM: Quality Maintenance (Hinshitsu Hozen)TPM: Quality Maintenance (Hinshitsu Hozen)
TPM: Quality Maintenance (Hinshitsu Hozen)
 
Lean Six Sigma Awareness Handouts
Lean Six Sigma Awareness HandoutsLean Six Sigma Awareness Handouts
Lean Six Sigma Awareness Handouts
 
[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)
 
Kaizen
KaizenKaizen
Kaizen
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
Quality awareness
Quality awarenessQuality awareness
Quality awareness
 
Purposes of pigging
Purposes of piggingPurposes of pigging
Purposes of pigging
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Lean principles
Lean principlesLean principles
Lean principles
 
TPM: Focused Improvement (Kobetsu Kaizen) Poster
TPM: Focused Improvement (Kobetsu Kaizen) PosterTPM: Focused Improvement (Kobetsu Kaizen) Poster
TPM: Focused Improvement (Kobetsu Kaizen) Poster
 
Kaizen in Everyday Life
Kaizen in Everyday LifeKaizen in Everyday Life
Kaizen in Everyday Life
 
What is Lean manufacturing?
What is Lean manufacturing?What is Lean manufacturing?
What is Lean manufacturing?
 
Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)Failure Mode Effect Analysis (FMEA)
Failure Mode Effect Analysis (FMEA)
 
Project Management - Introduction
Project Management - IntroductionProject Management - Introduction
Project Management - Introduction
 
Piping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning ProcedurePiping and Vessels Flushing and Cleaning Procedure
Piping and Vessels Flushing and Cleaning Procedure
 
Olga Software
Olga SoftwareOlga Software
Olga Software
 

Destacado

Docker architecture rework case study
Docker  architecture rework case studyDocker  architecture rework case study
Docker architecture rework case studydchaffiol
 
Participatory Multi-Hazard Disaster Risk Reduction Project in Armenia
Participatory Multi-Hazard Disaster Risk Reduction Project in ArmeniaParticipatory Multi-Hazard Disaster Risk Reduction Project in Armenia
Participatory Multi-Hazard Disaster Risk Reduction Project in ArmeniaSupportToCommunities
 
Supporting a Continuous Process Improvement Model With A Cost-Effective Data ...
Supporting a Continuous Process Improvement Model With A Cost-Effective Data ...Supporting a Continuous Process Improvement Model With A Cost-Effective Data ...
Supporting a Continuous Process Improvement Model With A Cost-Effective Data ...Juan Negrin, M.A., PMP
 
Agile Continuous improvement
Agile Continuous improvementAgile Continuous improvement
Agile Continuous improvementWafi Mohtaseb
 
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )John French
 
Measuring Process Maturity: The Business Process Maturity Model
Measuring Process Maturity: The Business Process Maturity ModelMeasuring Process Maturity: The Business Process Maturity Model
Measuring Process Maturity: The Business Process Maturity ModelNathaniel Palmer
 
Performance Improvement Roadmap V4
Performance Improvement Roadmap V4Performance Improvement Roadmap V4
Performance Improvement Roadmap V4mulcahymike
 
Lean Construction Webinar
Lean Construction WebinarLean Construction Webinar
Lean Construction WebinarBMGI India
 
lean construction and integrated project delivery
lean construction and integrated project delivery lean construction and integrated project delivery
lean construction and integrated project delivery Mahendra Bhuva
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 

Destacado (12)

Docker architecture rework case study
Docker  architecture rework case studyDocker  architecture rework case study
Docker architecture rework case study
 
Participatory Multi-Hazard Disaster Risk Reduction Project in Armenia
Participatory Multi-Hazard Disaster Risk Reduction Project in ArmeniaParticipatory Multi-Hazard Disaster Risk Reduction Project in Armenia
Participatory Multi-Hazard Disaster Risk Reduction Project in Armenia
 
Supporting a Continuous Process Improvement Model With A Cost-Effective Data ...
Supporting a Continuous Process Improvement Model With A Cost-Effective Data ...Supporting a Continuous Process Improvement Model With A Cost-Effective Data ...
Supporting a Continuous Process Improvement Model With A Cost-Effective Data ...
 
Agile Continuous improvement
Agile Continuous improvementAgile Continuous improvement
Agile Continuous improvement
 
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )
 
Measuring Process Maturity: The Business Process Maturity Model
Measuring Process Maturity: The Business Process Maturity ModelMeasuring Process Maturity: The Business Process Maturity Model
Measuring Process Maturity: The Business Process Maturity Model
 
Performance Improvement Roadmap V4
Performance Improvement Roadmap V4Performance Improvement Roadmap V4
Performance Improvement Roadmap V4
 
Lean Construction Webinar
Lean Construction WebinarLean Construction Webinar
Lean Construction Webinar
 
Lean construction
Lean constructionLean construction
Lean construction
 
lean construction and integrated project delivery
lean construction and integrated project delivery lean construction and integrated project delivery
lean construction and integrated project delivery
 
Building Information Modeling (BIM)
Building Information Modeling (BIM)Building Information Modeling (BIM)
Building Information Modeling (BIM)
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 

Similar a Rework Reduction in Construction Project

Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...IRJET Journal
 
Going & seeing in construction
Going & seeing in constructionGoing & seeing in construction
Going & seeing in constructionKartikeya Pandey
 
Construction Management in Developing Countries, Lecture 8
Construction Management in Developing Countries, Lecture 8Construction Management in Developing Countries, Lecture 8
Construction Management in Developing Countries, Lecture 8Hari Krishna Shrestha
 
Lean Principles and Project Mapping Application to Project Processes. Submitted
Lean Principles and Project Mapping Application to Project Processes. SubmittedLean Principles and Project Mapping Application to Project Processes. Submitted
Lean Principles and Project Mapping Application to Project Processes. SubmittedOlufemi Isaac Akinjiyan
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET Journal
 
construction quality improvement- Presentation
construction quality improvement- Presentationconstruction quality improvement- Presentation
construction quality improvement- PresentationManjunatha L.R
 
karthigairaj Process control andTechnical service resume
karthigairaj Process control andTechnical service resumekarthigairaj Process control andTechnical service resume
karthigairaj Process control andTechnical service resumeKarthigairaj Kandan
 

Similar a Rework Reduction in Construction Project (20)

Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
 
Cve presentation slide
Cve presentation slideCve presentation slide
Cve presentation slide
 
Lean construction
Lean constructionLean construction
Lean construction
 
Going & seeing in construction
Going & seeing in constructionGoing & seeing in construction
Going & seeing in construction
 
PART- 2: Engineering Project Management
PART- 2: Engineering Project Management PART- 2: Engineering Project Management
PART- 2: Engineering Project Management
 
Ramanjan resume s
Ramanjan resume sRamanjan resume s
Ramanjan resume s
 
My resume (1)
My resume  (1)My resume  (1)
My resume (1)
 
KENA PRE.pptx
KENA PRE.pptxKENA PRE.pptx
KENA PRE.pptx
 
Construction Management in Developing Countries, Lecture 8
Construction Management in Developing Countries, Lecture 8Construction Management in Developing Countries, Lecture 8
Construction Management in Developing Countries, Lecture 8
 
Resume
ResumeResume
Resume
 
Lean Principles and Project Mapping Application to Project Processes. Submitted
Lean Principles and Project Mapping Application to Project Processes. SubmittedLean Principles and Project Mapping Application to Project Processes. Submitted
Lean Principles and Project Mapping Application to Project Processes. Submitted
 
CPI_MOM_KBR_20110909_v1
CPI_MOM_KBR_20110909_v1CPI_MOM_KBR_20110909_v1
CPI_MOM_KBR_20110909_v1
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
vinayaktiwari (1)
vinayaktiwari (1)vinayaktiwari (1)
vinayaktiwari (1)
 
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
 
construction quality improvement- Presentation
construction quality improvement- Presentationconstruction quality improvement- Presentation
construction quality improvement- Presentation
 
Project Cost.pptx
Project Cost.pptxProject Cost.pptx
Project Cost.pptx
 
17 1st review
17 1st review17 1st review
17 1st review
 
karthigairaj Process control andTechnical service resume
karthigairaj Process control andTechnical service resumekarthigairaj Process control andTechnical service resume
karthigairaj Process control andTechnical service resume
 

Más de Dr. Firdaus Basbeth

Más de Dr. Firdaus Basbeth (8)

Session 5 Moderating and Mediation
Session 5 Moderating and MediationSession 5 Moderating and Mediation
Session 5 Moderating and Mediation
 
Session 4 Structural Model Evaluation
Session 4 Structural Model Evaluation Session 4 Structural Model Evaluation
Session 4 Structural Model Evaluation
 
Session 3 MEASUREMENT MODEL EVALUATION
Session 3 MEASUREMENT MODEL EVALUATIONSession 3 MEASUREMENT MODEL EVALUATION
Session 3 MEASUREMENT MODEL EVALUATION
 
Session 2
Session 2Session 2
Session 2
 
Session 1
Session 1Session 1
Session 1
 
2. opportunity identification
2. opportunity identification2. opportunity identification
2. opportunity identification
 
Topic 1
Topic 1Topic 1
Topic 1
 
The Changing Role of Quality Professional
The Changing Role of Quality ProfessionalThe Changing Role of Quality Professional
The Changing Role of Quality Professional
 

Último

Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 

Último (20)

Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 

Rework Reduction in Construction Project

  • 1. Rework Reduction Through the Use of Construction Lean Improvement Program (CLIP) a Case Study in New Australian Embassy in Jakarta (AEJ) - Leighton Contractors Indonesia & Total Bangun Persada Joint Operation Firdaus Basbeth DMB Student of University of Padjadjaran Bandung QIK 2014 International Conference Ascot House Melbourne February 21 2014
  • 2.
  • 3. Construction Traditional Measure (Result Based) ▫ Costs ▫ Schedule ▫ Meeting code
  • 4. Construction Lean Improvement Program • Result and Process Based Measurement ▫ Costs ▫ Schedule ▫ Meeting code ▫ Cycle time ▫ Rework ▫ Waste LEAN RIGHT THE FIRST TIME
  • 5. Chancery and Staff Residence, Jakarta Project Description The project is Total plot area 40,000m2, total covered floor area 50,106m2 of which 43,500m2 is building and 6,600m2 is pergola and parking. The scope of work includes Partial Design, Engineering, • Procurement, Testing and Inspection, Construction a Compound, consisting of: o Basement, plus 5 floor chancery building of approximately 26,700m2, o Head of Mission residence, o 32 number staff residences, o Swimming pool, o Recreation facilities, o Guard houses, o Ancillary service buildings, o Landscaping, o Security walls, o All associated works in accordance with drawings, specifications. The construction duration is 36 months until 2016. It is still ongoing and under close monitoring by project management.
  • 6. INTRODUCTION • Construction traditional measure (Result Based) vs Performance Measurement System (Process Based) • Construction Lean Improvement Program ▫ Lean Thinking ▫ Seven Waste ▫ 5S ▫ Labor Competency Issue ▫ First Inspection Method
  • 7. LITERATURE REVIEW Reference Topics and quote Saad Sarhan and Andrew Fox, (University of Plymouth, UK) (2012) ‘Performance measurement in the UK construction industry and its role in supporting the application of lean construction concepts’, Australasian Journal of Construction Economics and Building, 13 (1) 23-35 Benefits could be achieved from adopting the lean construction (LC) approach (Arbulu and Zabelle, 2006). However, the application of lean principles to construction has not been successful due to the failure to use appropriate process performance measurement systems (PMS).
  • 8. LITERATURE REVIEW Reference Topics and quote Alarcon and Serpell, 1996 Results-based performance preferences measured in projects, specifically costs and schedule, are not appropriate for continuous improvement because they are not effective in identifying the root-causes of quality and productivity losses. Professionals and managers in the construction industry still have a tendency to measure performance in terms of time, cost and meeting code, as opposed to process performance measures (e.g. cycle time, Rework, waste)
  • 9. LITERATURE REVIEW Reference Topics and quote Henny Pratiwi, M. Faiqun Niam, 2012. is said that 62% of construction labors in Indonesia is an unskilled labors Koskela (1992) (Garnett et al., 1998; Mossman, 2009a). Lean thinking is a philosophy based on the concepts of lean production, when applied to construction, it could lead to improved performance. (Garnett et al., 1998; Senaratne and Wijesiri, 2008). Proposed the need to review construction production as a combination of conversion and flow processes to remove waste, when traditional thinking of construction was only focusing on conversion activities and ignoring flow and value considerations
  • 10. LITERATURE REVIEW Reference Topics and quote FACTORS INFLUENCING CONSTRUCTION PRODUCTIVITY IN THE INDONESIAN CONTEXT Sugiharto ALWI Senior Lecturer School of Graduate Studies Construction Management Program, Proceedings of the Eastern Asia Society for Transportation Studies, Vol.4, October, 2003 The majority of the Indonesian construction labour force are self-employed, and are often farmers from rural areas. They are low skilled, earn low wages, and hence are less effective (Kaming et al., 1997). These young workers enter the pool of construction workers, for it is the only industry that can provide employment for those without any qualifications. It is reported that approximately 86% skilled workers in Indonesia are informally trained by a senior craftsman Henny Pratiwi, M. Faiqun Niam, 2012. 62% of construction labors in Indonesia is an unskilled labors
  • 11. Lean Thinking Lean thinking is a philosophy based on the concepts of lean production. Lean is focused on the achievement of three key outcomes: 1. Maximizing value from the view of the customer 2. Eliminating waste (non-value adding processes) 3. Creating smooth and reliable flow of activity.
  • 12. Benefit Tangible benefits •Productivity 16 – 40 %↑ •Refurb lead time 25%↓ •Pre-construction lead time (time between client approval and start of works on-site) ↓ •48% Intangible benefits •Best practice set-up, methods introduced, operation & organization improvements, •waste reduction, delays & disruptions reduced, snags reduced, communications •improved, Team dynamics improved, partnering benefits, skills transfer in the industry
  • 13. Seven Type of Waste 1. Defect 2. Over Production 3. Transportation 4. Waiting 5. Over Processing 6. Motion 7. Inventory
  • 14. Seven Type of Waste 1. Defect 2. Over Production 3. Transportation 4. Waiting 5. Over Processing 6. Motion 7. Inventory
  • 15. Implementation Strategy 1. 5S 2. Measuring and Monitoring the Performance of • NCR • Rework • Waste 3. The First Inspection System 4. A Solid and updated QA Plan 5. Recruitment based on labor competency plus continual training.
  • 16. 5S Strategy for creating a well organized, smoothly flowing process. It has been applied in the shop with great success. Masaaki Imai says, “If one is not doing 5S, one is not doing lean.”
  • 17. Benefits of 5S • Increases organization and efficiency • Avoids wasted motion • Increases safety • Eliminates unnecessary inventory • Offers improvements at an inexpensive cost
  • 18. METHOD The research is a Case Study in Leighton Contractors Indonesia in New Australian Embassy Project (2013 – 2016) Primary and Secondary Data are gathered using both qualitative and quantitative approaches, and interview
  • 19. RESULT Total NCR and Root cause
  • 21. RESULT Total NCR in Two Different Area
  • 23. DISCUSSION • In the construction industry, defect or rework is a challenge that affects the productivity of a project. Additional resources are required ie: labor, materials, and energy beyond what is budgeted had the work been done right the first time – not to mentioned potential risk with respect to quality and safety. • The New Australian Embassy Project has in place and continually updates their Quality Plan. Improvement activities can be seen from the frequency of Non Conformance Report.(Rework required.) Training to up skill labor to LCI standards, Internal Quality Audits, and increased management attention has been a focus the last 6 months.
  • 24. DISCUSSION • The New Autralian Embassy in Jakarta (AEJ) implemented the First Inspector System (FIS) – by putting full responsibility of the quality of product delivered to the supervisor and foreman, so by the time the quality inspector come to check the work, the variation from specification will be the minimum. The results have seen the non- conformance reports reduce by 57%. The saving for the project is USD$20,000 or Rupiah 240mil.
  • 25. DISCUSSION • The Construction Lean Improvement Program Works in Chancery Area in the Project. Suggestion to be Implemented in some others construction areas in the Project, with the additional strategy of : 5S, First Inspector System, Performance Monitoring (Process Based) Continual Training on the Labor to maintaining quality of the product. • Buy in from Project Manager and its implementation strategy need to be in the first place – stated in Quality Plan.
  • 26. DISCUSSION Rework / NCR Reduction in CLIP include the following processes: •Rework tracking and main cause classification: detecting and identifying the rework that occurs and captured, investigate the causes in a database that used collaboratively by the client, contractors and designer. •Corrective action : developing options and actions that will bring about changes in the project management system with the goal of eliminating the root cause and reducing construction rework •Evaluation of the effectiveness of the corrective action taken.
  • 27.
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.