SlideShare una empresa de Scribd logo
1 de 13
Descargar para leer sin conexión
Adjudication : tips, traps and tactics
05 May 2015
Ben Worthington, Senior Associate
ben.worthington@olswang.com | + 44 20 7067 3541
www.olswang.com2
Adjudication
The Basics
• Compulsory dispute resolution procedure
• Right to refer a dispute at any time / Binding on an
interim basis
• Anatomy of a typical adjudication:
• Crystallisation
• Notice of Adjudication
• Appointment of the Adjudicator
• Referral (within 7 days from Notice)
• Response
• Reply / further submissions
• Meeting / site visit
• Decision (28 / 42 days or agreement)
“The need to have the "right"
answer has been subordinated
to the need to have an answer
quickly. The scheme was not
enacted in order to provide
definitive answers to complex
questions.”
Chadwick LJ in Carillion
Construction Ltd v Devenport Royal
Dockyard Ltd (CA) (2005)
www.olswang.com3
Ambushes
How to spring them
• Decision not unenforceable simply because dispute is
complex or there is a large volume of material: see
CSK Electrical Contractors Ltd v Kingwood Electrical
Services Ltd (2015) and Dorchester Hotel Limited v
Vivid Interiors Limited (2009)
• An “ambush” does not amount to procedural
unfairness – see Twintec Ltd v Volkerfitzpatrick Ltd
(2014)
• A dispute does not arise unless and until it emerges
that the claim is not admitted : AMEC Civil
Engineering Ltd v SoS for Transport (2004)
• Put arguments to the other side before referring the
dispute to adjudication
• Consider the timing of the adjudication carefully
• Only include material that is necessary to prove your
case
“The plain fact is that
adjudication is a rough and
ready process because it has to
be carried out within a very
strict timetable. That often
causes particular pressure for
the responding party. That is, I
am afraid, a fact of
adjudication life; it is inherent
in the whole process.”
Twintec Ltd v Volkerfitzpatrick Ltd
(2014)
Ambushes
How to break them
• Contract drafting issues:
• Prescribe detail required in contractor’s (or sub-contractor’s) payment applications
• Provide contractual timescales for considering applications
• Ensure adjudication clauses provide adequate timescales for responding in
adjudications
• Use clauses which seek to prevent disputes arising?
• Do not reject claims outright / play for time. But see St Austell Printing Company Ltd v
Dawnus Construction Holdings Ltd (2015) –
• “crystallisation may require no more than the service of a claim by the claiming party
and subsequent inactivity for a further short period by the responding party”.
• if supporting documentation is missing that goes to the level of assessment not whether
there is a dispute
www.constructiveblog.com4
Ambushes
How to break them
• Warning signs
• Formal delay notices
• Letters that are legalistic in tone
• Correspondence that adopts the terminology of a dispute
• Consider whether adequate commercial staff available
• Ensure there is a protocol in place for reacting to adjudication notices
• Prepare now
• If the adjudication starts:
• Ask adjudicator for more time
• Reserve position on jurisdiction if extension is not given
• Highlight prejudice
www.constructiveblog.com5
www.olswang.com6
The adjudicator and the adjudication
rules
Playing by the rules
Approaches to incorporation of rules
• Remain silent – the Scheme applies
• Use bespoke rules
• Incorporate rules by reference, but be careful :
• Adjudication procedure goes to heart of the
adjudicator’s jurisdiction: Twintec (2014)
• Adjudicator followed wrong rules: Ecovision
Systems Ltd v Vinci Construction UK Ltd (2015)
Choosing between the rules
• Parties’ costs
• Adjudicator’s fees
• Jurisdiction
“… an adjudicator has no
jurisdiction to determine
whether he has jurisdiction… a
choice between two sets of
adjudication provisions will
amount to such a
determination if the choice
makes a material difference as
to how he should be
appointed.”
Ecovision Systems Ltd v Vinci
Construction UK Ltd (2015)
The adjudicator and the adjudication
rules
Getting the right person
• Naming the adjudicator
• Seeking to agree an appointment
• Appointment by an Adjudicator Nominating Body
• No external controls over ANBs
• There is a Fee
• Party fills in a form which asks for details of the dispute
• Key considerations :
• Expertise
• Experience
• Conflicts
• Fees
• Reputation
www.constructiveblog.com7
The adjudicator and the adjudication
rules
Influencing the nomination process
Filling in the nomination form
• Eurocom Ltd v Siemens PLC (2014) : fraudulent misrepresentation goes to the heart of the
validity of the appointment
• CSK Electrical Contractors Ltd v Kingwood Electrical Services Ltd (2015) : “There may be
circumstances in which a stated preference could amount to a misrepresentation…”
Representations to the nominating body
• London Borough of Camden v Makers UK Ltd (2009) :
• No implied term that a party would not seek to influence the ANB’s decision
• Contact with the adjudicator did not give rise to apparent bias
• Lanes Group v Galliford Try (2011) : referring party could let first notice lapse
Pre – appointment contact
• Paice & Anor v MJ Harding (t/a Mj Harding Contractors) (2015) :
• Telephone conversation between claimant and adjudicator’s office manager should
have been disclosed
www.constructiveblog.com8
The Notice of Adjudication
How to describe the dispute
• Do not define the dispute too narrowly – “or such other sum as the adjudicator finds to be
due”
• Make sure the definition of the dispute is focused : St Austell Printing Company Ltd v
Dawnus Construction Holdings Ltd (2015)
• Note that it is difficult to limit the scope of the referral :
• Pilon Ltd v Breyer Group plc (2010) : adjudicator should have considered the
employer's set-off defence
• Wales And West Utilities Ltd v PPS Pipeline Systems GmbH (2014) : A responding
party may raise any factual or legal defence to the dispute referred to adjudication
www.constructiveblog.com9
Jurisdiction
When to challenge the adjudicator’s
jurisdiction
A party faced with an invalid appointment might:
• Seek an injunction / declaration
• Twintec : “If it is clear that an adjudicator's appointment is invalid… no useful purpose would be
served by allowing an adjudication to proceed… “
• MW High Tech Projects UK Ltd v Haase Environmental Consulting GmbH (2015): Court gave
declaration regarding the correct interpretation of a professional appointment
• Refuse to participate
• Participate but reserve position on jurisdiction
• Reserve rights generally at the outset : Bothma v Mayhaven Healthcare Ltd (2007)
• Be careful to avoid giving the adjudicator jurisdiction
• Raise specific challenges as soon as possible : AT Stannard Ltd v Tobutt (2014)
www.constructiveblog.com10
Receiving the decision
Timing
• The adjudicator must reach his decision within 28 days of the dispute being referred to him
• This period can be extended by 14 days if the referring party agrees
• The parties can agree to a longer timescale
• Case law is unclear as to whether a late decision is enforceable, it seems that:
• An adjudicator is bound to reach his decision within 28 days (or the agreed extended
time)
• A decision not reached within 28 days (or as agreed) will probably be a nullity
• A decision reached within time, but communicated after that period, will be valid
provided it can be shown it was delivered forthwith
• A party who does not agree an extension of time must make this clear : KNN Colburn LLP v
GD City Holdings Ltd (2013)
www.constructiveblog.com11
Receiving the decision
Identifying and correcting errors
• All construction contracts must include a written provision giving the adjudicator the right to
correct a typographical or clerical error in his decision
• Check the provisions – the Scheme provides that any correction must be made within five
days of the date the decision was delivered to the parties
• Parties can agree a different period
• Act quickly
• Be clear as to what you want the adjudicator to correct : see PP Construction Ltd v
Geoffrey Osborne Ltd (2015)
• If you dispute the adjudicator’s jurisdiction, tread carefully - asking for a correction may be
constructed as a waiver of any challenge : Laker Vent Engineering Ltd v Jacobs E&C Ltd
(2014), “With some hesitation I have come to the conclusion that a party can still rely on the
general reservation of jurisdiction and apply under the slip rule or make payment.”
• Do not pay without a specific reservation : Wales & West Utilities Limited v PPS Pipelines
Systems GmbH (2014)
www.constructiveblog.com12
Any questions?

Más contenido relacionado

La actualidad más candente

UK Adjudicators 2021 London Adjudication & Arbitration Conference pack
UK Adjudicators 2021 London Adjudication & Arbitration Conference packUK Adjudicators 2021 London Adjudication & Arbitration Conference pack
UK Adjudicators 2021 London Adjudication & Arbitration Conference pack
Sean Gibbs DipArb, FCIARB, FCIOB, FRICS, MICE
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute Resolution
Justin DeMerchant
 
p13 Property_Journal_July_August_2015
p13 Property_Journal_July_August_2015p13 Property_Journal_July_August_2015
p13 Property_Journal_July_August_2015
Elizabeth Repper
 
Construction Contract Dispute Resolution
Construction Contract Dispute ResolutionConstruction Contract Dispute Resolution
Construction Contract Dispute Resolution
rcnewcomer
 
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONSAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
Oluwaseyi Bamigboye
 

La actualidad más candente (19)

UK Adjudicators 2021 London Adjudication & Arbitration Conference pack
UK Adjudicators 2021 London Adjudication & Arbitration Conference packUK Adjudicators 2021 London Adjudication & Arbitration Conference pack
UK Adjudicators 2021 London Adjudication & Arbitration Conference pack
 
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Robert Hunt
Robert HuntRobert Hunt
Robert Hunt
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute Resolution
 
Meet the Adjudicator
Meet the Adjudicator Meet the Adjudicator
Meet the Adjudicator
 
Drafting Mediation Pledges, Mediation Clauses and Hybrid Clauses
Drafting Mediation Pledges, Mediation Clauses and Hybrid ClausesDrafting Mediation Pledges, Mediation Clauses and Hybrid Clauses
Drafting Mediation Pledges, Mediation Clauses and Hybrid Clauses
 
p13 Property_Journal_July_August_2015
p13 Property_Journal_July_August_2015p13 Property_Journal_July_August_2015
p13 Property_Journal_July_August_2015
 
Construction Contract Dispute Resolution
Construction Contract Dispute ResolutionConstruction Contract Dispute Resolution
Construction Contract Dispute Resolution
 
Bpe Presentation On Changes To The Construction Act 2010 V7 1 Final Read Only
Bpe Presentation On Changes To The Construction Act 2010 V7 1 Final Read OnlyBpe Presentation On Changes To The Construction Act 2010 V7 1 Final Read Only
Bpe Presentation On Changes To The Construction Act 2010 V7 1 Final Read Only
 
Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...
Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...
Project Controls Expo, 18th Nov 2014 - "CONSTRUCTION ACCELERATION— A GLOBAL T...
 
Construction disputes
Construction disputesConstruction disputes
Construction disputes
 
City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...
 
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATIONSAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
SAVING TIME AND COSTS IN COMMERCIAL ARBITRATION
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
 
Resolving Complex Delay Claims
Resolving Complex Delay ClaimsResolving Complex Delay Claims
Resolving Complex Delay Claims
 
Letters of Intent
Letters of IntentLetters of Intent
Letters of Intent
 
The Principle of Cost Follows the event in Commercial Arbitration
The Principle of Cost Follows the event in Commercial ArbitrationThe Principle of Cost Follows the event in Commercial Arbitration
The Principle of Cost Follows the event in Commercial Arbitration
 
VAT Listed Building Relief 2011
VAT Listed Building Relief 2011VAT Listed Building Relief 2011
VAT Listed Building Relief 2011
 

Destacado

Fitopatologia in ambito bonsai - seconda parte
Fitopatologia in ambito bonsai - seconda parteFitopatologia in ambito bonsai - seconda parte
Fitopatologia in ambito bonsai - seconda parte
bonsai italia
 
前端Mvc探讨及实践
前端Mvc探讨及实践前端Mvc探讨及实践
前端Mvc探讨及实践
taobao.com
 
N E W S T U D Y O F B H A G A V A D G I T A D E C 22 D R S H R I N I W...
N E W  S T U D Y  O F  B H A G A V A D  G I T A  D E C 22  D R  S H R I N I W...N E W  S T U D Y  O F  B H A G A V A D  G I T A  D E C 22  D R  S H R I N I W...
N E W S T U D Y O F B H A G A V A D G I T A D E C 22 D R S H R I N I W...
shriniwaskashalikar
 
N E W S T U D Y O F G I T A N O V 30 D R
N E W  S T U D Y  O F  G I T A  N O V 30  D RN E W  S T U D Y  O F  G I T A  N O V 30  D R
N E W S T U D Y O F G I T A N O V 30 D R
shriniwaskashalikar
 
Direct and reported speech
Direct and reported speechDirect and reported speech
Direct and reported speech
Eunice Rivera
 
Happy New Year Dr. Shriniwas Janardan Kashalikar
Happy New Year Dr. Shriniwas Janardan KashalikarHappy New Year Dr. Shriniwas Janardan Kashalikar
Happy New Year Dr. Shriniwas Janardan Kashalikar
shriniwaskashalikar
 
Bernat, Berta, Carla, Santino, Pere S
Bernat, Berta, Carla, Santino, Pere SBernat, Berta, Carla, Santino, Pere S
Bernat, Berta, Carla, Santino, Pere S
sbolader
 
刘平川:【用户行为分析】Marmot实践
刘平川:【用户行为分析】Marmot实践刘平川:【用户行为分析】Marmot实践
刘平川:【用户行为分析】Marmot实践
taobao.com
 

Destacado (20)

Fitopatologia in ambito bonsai - seconda parte
Fitopatologia in ambito bonsai - seconda parteFitopatologia in ambito bonsai - seconda parte
Fitopatologia in ambito bonsai - seconda parte
 
W H E R E I S Z E R O D R
W H E R E  I S  Z E R O  D RW H E R E  I S  Z E R O  D R
W H E R E I S Z E R O D R
 
創意設計
創意設計創意設計
創意設計
 
金雞獨立
金雞獨立金雞獨立
金雞獨立
 
R E V O L U T I O N D R
R E V O L U T I O N  D RR E V O L U T I O N  D R
R E V O L U T I O N D R
 
CIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of Talk
CIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of TalkCIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of Talk
CIOB Complex Projects Contract 2013 - 25 April 2013 - Transcript of Talk
 
371 free electricity from the sky
371   free electricity from the sky371   free electricity from the sky
371 free electricity from the sky
 
前端Mvc探讨及实践
前端Mvc探讨及实践前端Mvc探讨及实践
前端Mvc探讨及实践
 
N E W S T U D Y O F B H A G A V A D G I T A D E C 22 D R S H R I N I W...
N E W  S T U D Y  O F  B H A G A V A D  G I T A  D E C 22  D R  S H R I N I W...N E W  S T U D Y  O F  B H A G A V A D  G I T A  D E C 22  D R  S H R I N I W...
N E W S T U D Y O F B H A G A V A D G I T A D E C 22 D R S H R I N I W...
 
N E W S T U D Y O F G I T A N O V 30 D R
N E W  S T U D Y  O F  G I T A  N O V 30  D RN E W  S T U D Y  O F  G I T A  N O V 30  D R
N E W S T U D Y O F G I T A N O V 30 D R
 
Direct and reported speech
Direct and reported speechDirect and reported speech
Direct and reported speech
 
AdminStudio Suite - Simplified Chinese
AdminStudio Suite - Simplified ChineseAdminStudio Suite - Simplified Chinese
AdminStudio Suite - Simplified Chinese
 
Happy New Year Dr. Shriniwas Janardan Kashalikar
Happy New Year Dr. Shriniwas Janardan KashalikarHappy New Year Dr. Shriniwas Janardan Kashalikar
Happy New Year Dr. Shriniwas Janardan Kashalikar
 
ライセンス状態スナップショットサービス
ライセンス状態スナップショットサービスライセンス状態スナップショットサービス
ライセンス状態スナップショットサービス
 
Bernat, Berta, Carla, Santino, Pere S
Bernat, Berta, Carla, Santino, Pere SBernat, Berta, Carla, Santino, Pere S
Bernat, Berta, Carla, Santino, Pere S
 
21st Century Construction Toolkit - Olswang LLP
21st Century Construction Toolkit - Olswang LLP21st Century Construction Toolkit - Olswang LLP
21st Century Construction Toolkit - Olswang LLP
 
Monetizing Engagement
Monetizing EngagementMonetizing Engagement
Monetizing Engagement
 
11 25-2011-seo-rankings-report
11 25-2011-seo-rankings-report11 25-2011-seo-rankings-report
11 25-2011-seo-rankings-report
 
刘平川:【用户行为分析】Marmot实践
刘平川:【用户行为分析】Marmot实践刘平川:【用户行为分析】Marmot实践
刘平川:【用户行为分析】Marmot实践
 
Ranking analysis-12-20-2011-1
Ranking analysis-12-20-2011-1Ranking analysis-12-20-2011-1
Ranking analysis-12-20-2011-1
 

Similar a Adjudication: Tips, Traps and Tactics

Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Francis Ho
 
20091118 Construction Life cycle completion
20091118 Construction Life cycle completion20091118 Construction Life cycle completion
20091118 Construction Life cycle completion
raymond_wan2005
 

Similar a Adjudication: Tips, Traps and Tactics (20)

Terminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightTerminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it Right
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
Building Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane Neave
Building Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane NeaveBuilding Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane Neave
Building Act, Code, Consenting and Failed Repairs - Dr Duncan Webb Lane Neave
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
 
20091118 Construction Life cycle completion
20091118 Construction Life cycle completion20091118 Construction Life cycle completion
20091118 Construction Life cycle completion
 
Ceca Caselaw
Ceca Caselaw Ceca Caselaw
Ceca Caselaw
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
 
A Little Light Relief? A summary of the post-Mitchell landscape
A Little Light Relief? A summary of the post-Mitchell landscapeA Little Light Relief? A summary of the post-Mitchell landscape
A Little Light Relief? A summary of the post-Mitchell landscape
 
Patrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution BoardsPatrick O'Sullivan Dispute Resolution Boards
Patrick O'Sullivan Dispute Resolution Boards
 
The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..
 
Public sector breakfast club, January 2017 - Exeter
Public sector breakfast club, January 2017 - ExeterPublic sector breakfast club, January 2017 - Exeter
Public sector breakfast club, January 2017 - Exeter
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
 
Top 10 Developments in Employment, Labour & Human Rights Law
Top 10 Developments in Employment, Labour & Human Rights LawTop 10 Developments in Employment, Labour & Human Rights Law
Top 10 Developments in Employment, Labour & Human Rights Law
 
Litigation leeds 5
Litigation   leeds 5Litigation   leeds 5
Litigation leeds 5
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
Public sector planning club - October 2017, Nottingham
Public sector planning club - October 2017, NottinghamPublic sector planning club - October 2017, Nottingham
Public sector planning club - October 2017, Nottingham
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Public sector breakfast club, Exeter - July 2016
Public sector breakfast club, Exeter - July 2016Public sector breakfast club, Exeter - July 2016
Public sector breakfast club, Exeter - July 2016
 

Más de Francis Ho

Olswang Construction Law Masterclass: Project Risks for Developers and Funder...
Olswang Construction Law Masterclass: Project Risks for Developers and Funder...Olswang Construction Law Masterclass: Project Risks for Developers and Funder...
Olswang Construction Law Masterclass: Project Risks for Developers and Funder...
Francis Ho
 
Arbitration Anyone - 2014 Olswang Construction Law Conference
Arbitration Anyone - 2014 Olswang Construction Law ConferenceArbitration Anyone - 2014 Olswang Construction Law Conference
Arbitration Anyone - 2014 Olswang Construction Law Conference
Francis Ho
 

Más de Francis Ho (18)

COP26: Eating for the Planet
COP26: Eating for the PlanetCOP26: Eating for the Planet
COP26: Eating for the Planet
 
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
 
How will Brexit impact on Construction?
How will Brexit impact on Construction?How will Brexit impact on Construction?
How will Brexit impact on Construction?
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
 
The Management of Complex Contracts
The Management of Complex ContractsThe Management of Complex Contracts
The Management of Complex Contracts
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering Effectively
 
Contractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKContractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UK
 
Introductory Note on International Construction Contracts
Introductory Note on International Construction ContractsIntroductory Note on International Construction Contracts
Introductory Note on International Construction Contracts
 
Works Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceWorks Insurance and Latent Defects Insurance
Works Insurance and Latent Defects Insurance
 
Third Party Rights and Why They Matter
Third Party Rights and Why They MatterThird Party Rights and Why They Matter
Third Party Rights and Why They Matter
 
A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015
 
Olswang 2nd Annual Construction Law Conference
Olswang 2nd Annual Construction Law ConferenceOlswang 2nd Annual Construction Law Conference
Olswang 2nd Annual Construction Law Conference
 
Olswang 3rd Annual Construction Law Conference
Olswang 3rd Annual Construction Law ConferenceOlswang 3rd Annual Construction Law Conference
Olswang 3rd Annual Construction Law Conference
 
ACA-ACE Framework Alliance Contract - 25 February 2016
ACA-ACE Framework Alliance Contract - 25 February 2016ACA-ACE Framework Alliance Contract - 25 February 2016
ACA-ACE Framework Alliance Contract - 25 February 2016
 
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBETalk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
 
Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...
Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...
Update on Construction Insurance, Bonds and Guarantees - Francis Ho - Olswang...
 
Olswang Construction Law Masterclass: Project Risks for Developers and Funder...
Olswang Construction Law Masterclass: Project Risks for Developers and Funder...Olswang Construction Law Masterclass: Project Risks for Developers and Funder...
Olswang Construction Law Masterclass: Project Risks for Developers and Funder...
 
Arbitration Anyone - 2014 Olswang Construction Law Conference
Arbitration Anyone - 2014 Olswang Construction Law ConferenceArbitration Anyone - 2014 Olswang Construction Law Conference
Arbitration Anyone - 2014 Olswang Construction Law Conference
 

Último

Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
asmaqueen5
 
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
asmaqueen5
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
delhi24hrs1
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
ApartmentWala1
 
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor PresentationMEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ - Mainstreet Equity Corp.
 
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
asmaqueen5
 
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
ApartmentWala1
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
delhi24hrs1
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
ApartmentWala1
 

Último (20)

Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
 
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
Kalpataru Exquisite Wakad Pune  E-Brochure.pdfKalpataru Exquisite Wakad Pune  E-Brochure.pdf
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
 
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
 
construction material procurement in India
construction material procurement in Indiaconstruction material procurement in India
construction material procurement in India
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
 
Eldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdfEldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdf
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
 
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor PresentationMEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
 
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
 
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdfThe Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
 
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
 
Ganga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdfGanga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdf
 
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdfVanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
 
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living SpacesKohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
 
Bridge & Elliot Ladner Floor Plans May 2024.pdf
Bridge & Elliot Ladner Floor Plans May 2024.pdfBridge & Elliot Ladner Floor Plans May 2024.pdf
Bridge & Elliot Ladner Floor Plans May 2024.pdf
 
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
 
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WI
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WIRetail Space for Lease - 1221 W. Main St., Sun Prairie, WI
Retail Space for Lease - 1221 W. Main St., Sun Prairie, WI
 
Madhugiri Boucher Managed Farmland (knx)
Madhugiri Boucher Managed Farmland (knx)Madhugiri Boucher Managed Farmland (knx)
Madhugiri Boucher Managed Farmland (knx)
 

Adjudication: Tips, Traps and Tactics

  • 1. Adjudication : tips, traps and tactics 05 May 2015 Ben Worthington, Senior Associate ben.worthington@olswang.com | + 44 20 7067 3541
  • 2. www.olswang.com2 Adjudication The Basics • Compulsory dispute resolution procedure • Right to refer a dispute at any time / Binding on an interim basis • Anatomy of a typical adjudication: • Crystallisation • Notice of Adjudication • Appointment of the Adjudicator • Referral (within 7 days from Notice) • Response • Reply / further submissions • Meeting / site visit • Decision (28 / 42 days or agreement) “The need to have the "right" answer has been subordinated to the need to have an answer quickly. The scheme was not enacted in order to provide definitive answers to complex questions.” Chadwick LJ in Carillion Construction Ltd v Devenport Royal Dockyard Ltd (CA) (2005)
  • 3. www.olswang.com3 Ambushes How to spring them • Decision not unenforceable simply because dispute is complex or there is a large volume of material: see CSK Electrical Contractors Ltd v Kingwood Electrical Services Ltd (2015) and Dorchester Hotel Limited v Vivid Interiors Limited (2009) • An “ambush” does not amount to procedural unfairness – see Twintec Ltd v Volkerfitzpatrick Ltd (2014) • A dispute does not arise unless and until it emerges that the claim is not admitted : AMEC Civil Engineering Ltd v SoS for Transport (2004) • Put arguments to the other side before referring the dispute to adjudication • Consider the timing of the adjudication carefully • Only include material that is necessary to prove your case “The plain fact is that adjudication is a rough and ready process because it has to be carried out within a very strict timetable. That often causes particular pressure for the responding party. That is, I am afraid, a fact of adjudication life; it is inherent in the whole process.” Twintec Ltd v Volkerfitzpatrick Ltd (2014)
  • 4. Ambushes How to break them • Contract drafting issues: • Prescribe detail required in contractor’s (or sub-contractor’s) payment applications • Provide contractual timescales for considering applications • Ensure adjudication clauses provide adequate timescales for responding in adjudications • Use clauses which seek to prevent disputes arising? • Do not reject claims outright / play for time. But see St Austell Printing Company Ltd v Dawnus Construction Holdings Ltd (2015) – • “crystallisation may require no more than the service of a claim by the claiming party and subsequent inactivity for a further short period by the responding party”. • if supporting documentation is missing that goes to the level of assessment not whether there is a dispute www.constructiveblog.com4
  • 5. Ambushes How to break them • Warning signs • Formal delay notices • Letters that are legalistic in tone • Correspondence that adopts the terminology of a dispute • Consider whether adequate commercial staff available • Ensure there is a protocol in place for reacting to adjudication notices • Prepare now • If the adjudication starts: • Ask adjudicator for more time • Reserve position on jurisdiction if extension is not given • Highlight prejudice www.constructiveblog.com5
  • 6. www.olswang.com6 The adjudicator and the adjudication rules Playing by the rules Approaches to incorporation of rules • Remain silent – the Scheme applies • Use bespoke rules • Incorporate rules by reference, but be careful : • Adjudication procedure goes to heart of the adjudicator’s jurisdiction: Twintec (2014) • Adjudicator followed wrong rules: Ecovision Systems Ltd v Vinci Construction UK Ltd (2015) Choosing between the rules • Parties’ costs • Adjudicator’s fees • Jurisdiction “… an adjudicator has no jurisdiction to determine whether he has jurisdiction… a choice between two sets of adjudication provisions will amount to such a determination if the choice makes a material difference as to how he should be appointed.” Ecovision Systems Ltd v Vinci Construction UK Ltd (2015)
  • 7. The adjudicator and the adjudication rules Getting the right person • Naming the adjudicator • Seeking to agree an appointment • Appointment by an Adjudicator Nominating Body • No external controls over ANBs • There is a Fee • Party fills in a form which asks for details of the dispute • Key considerations : • Expertise • Experience • Conflicts • Fees • Reputation www.constructiveblog.com7
  • 8. The adjudicator and the adjudication rules Influencing the nomination process Filling in the nomination form • Eurocom Ltd v Siemens PLC (2014) : fraudulent misrepresentation goes to the heart of the validity of the appointment • CSK Electrical Contractors Ltd v Kingwood Electrical Services Ltd (2015) : “There may be circumstances in which a stated preference could amount to a misrepresentation…” Representations to the nominating body • London Borough of Camden v Makers UK Ltd (2009) : • No implied term that a party would not seek to influence the ANB’s decision • Contact with the adjudicator did not give rise to apparent bias • Lanes Group v Galliford Try (2011) : referring party could let first notice lapse Pre – appointment contact • Paice & Anor v MJ Harding (t/a Mj Harding Contractors) (2015) : • Telephone conversation between claimant and adjudicator’s office manager should have been disclosed www.constructiveblog.com8
  • 9. The Notice of Adjudication How to describe the dispute • Do not define the dispute too narrowly – “or such other sum as the adjudicator finds to be due” • Make sure the definition of the dispute is focused : St Austell Printing Company Ltd v Dawnus Construction Holdings Ltd (2015) • Note that it is difficult to limit the scope of the referral : • Pilon Ltd v Breyer Group plc (2010) : adjudicator should have considered the employer's set-off defence • Wales And West Utilities Ltd v PPS Pipeline Systems GmbH (2014) : A responding party may raise any factual or legal defence to the dispute referred to adjudication www.constructiveblog.com9
  • 10. Jurisdiction When to challenge the adjudicator’s jurisdiction A party faced with an invalid appointment might: • Seek an injunction / declaration • Twintec : “If it is clear that an adjudicator's appointment is invalid… no useful purpose would be served by allowing an adjudication to proceed… “ • MW High Tech Projects UK Ltd v Haase Environmental Consulting GmbH (2015): Court gave declaration regarding the correct interpretation of a professional appointment • Refuse to participate • Participate but reserve position on jurisdiction • Reserve rights generally at the outset : Bothma v Mayhaven Healthcare Ltd (2007) • Be careful to avoid giving the adjudicator jurisdiction • Raise specific challenges as soon as possible : AT Stannard Ltd v Tobutt (2014) www.constructiveblog.com10
  • 11. Receiving the decision Timing • The adjudicator must reach his decision within 28 days of the dispute being referred to him • This period can be extended by 14 days if the referring party agrees • The parties can agree to a longer timescale • Case law is unclear as to whether a late decision is enforceable, it seems that: • An adjudicator is bound to reach his decision within 28 days (or the agreed extended time) • A decision not reached within 28 days (or as agreed) will probably be a nullity • A decision reached within time, but communicated after that period, will be valid provided it can be shown it was delivered forthwith • A party who does not agree an extension of time must make this clear : KNN Colburn LLP v GD City Holdings Ltd (2013) www.constructiveblog.com11
  • 12. Receiving the decision Identifying and correcting errors • All construction contracts must include a written provision giving the adjudicator the right to correct a typographical or clerical error in his decision • Check the provisions – the Scheme provides that any correction must be made within five days of the date the decision was delivered to the parties • Parties can agree a different period • Act quickly • Be clear as to what you want the adjudicator to correct : see PP Construction Ltd v Geoffrey Osborne Ltd (2015) • If you dispute the adjudicator’s jurisdiction, tread carefully - asking for a correction may be constructed as a waiver of any challenge : Laker Vent Engineering Ltd v Jacobs E&C Ltd (2014), “With some hesitation I have come to the conclusion that a party can still rely on the general reservation of jurisdiction and apply under the slip rule or make payment.” • Do not pay without a specific reservation : Wales & West Utilities Limited v PPS Pipelines Systems GmbH (2014) www.constructiveblog.com12